Deliverables

This document provides a typical engineering deliverables list for a zinc oxide manufacturing facility project. It includes deliverables to be provided with the feasibility study, Front End Engineering Design (FEED), and final engineering. Deliverables include process design documents like process flow diagrams, equipment lists and specifications, piping and instrumentation diagrams, site plans, and manuals for commissioning and operation. The actual deliverables list for a specific project may be amended during FEED to reflect project details and scope.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
1K views13 pages

Deliverables

This document provides a typical engineering deliverables list for a zinc oxide manufacturing facility project. It includes deliverables to be provided with the feasibility study, Front End Engineering Design (FEED), and final engineering. Deliverables include process design documents like process flow diagrams, equipment lists and specifications, piping and instrumentation diagrams, site plans, and manuals for commissioning and operation. The actual deliverables list for a specific project may be amended during FEED to reflect project details and scope.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 13

HIGH EFFICIENCY EQUIPMENT FOR FRENCH PROCESS

ZINC OXIDE MANUFACTURING

Detailed Design and Engineering Deliverable List

This listing is a typical engineering deliverables list for a zinc oxide manufacturing facility. The
actual deliverable list will be amended during the FEED process to reflect the actual details and the
proposed scope of the project. In many cases, the documentary requirements are met by issuing a
single document, such as a general arrangement drawing, showing battery limits, utility
connections and utility requirements etc.

P = Deliverables with the feasibility study

F = Deliverables with the FEED (Front End Engineering Design)

D = Final engineering deliverables (the column is omitted except for the P&ID data page)

Unmarked Items are deliverables at the completion of the Engineering Process (EPCM)

◆ Preliminary information

◆ Documentary requirements Complete

Introduction

Description of deliverable P F


Introduction
◆ ◆
Statement of plant production targets and progressive implementation plan
◆ ◆
Site Description

Client supplied data

Project execution plan

Document order and precedence

Master document Index

Engineering unit statement

A. H. Burns Energy Systems Ltd.


562 Main Street East, Hamilton. Ontario. Canada. L8M 1J2
Tel 905 525 6321 www.burnsenergy.ca
Feasibility
Description of deliverable P F


Description of project

Basis of design

Preliminary equipment scope

Shop space requirements

Basic engineering design data

Preliminary site plan

Project codes and standards

Process Design
Description of deliverable P F

P F
Process safety documents

Hazop report (Hazardous Operation)

• Fire hazard report

• Process flow diagrams (PFDs), Utility flow diagrams (UFDs) Heat & material
balance

Process & operational control description

Process equipment list
◆ ◆
Datasheets for main equipment (per equipment list)

• Process design calculations
◆ ◆
• Line list (Process / Mechanical engineering database)
Tie-in schedule
Effluent and emission summary
◆ ◆
Mechanical handling report
◆ ◆
Noise data

Performance guarantees statement

Performance test procedure
Pre-commissioning and commissioning manual
Operating manual
PLANT DESIGN

Description of deliverable D P F

◆ ◆
Hazardous area classification drawings
◆ ◆
Plant block flow diagram
◆ ◆
Process flow diagram
◆ ◆
P&ID Process & Instrument Diagrams based upon ISA2
◆ ◆ ◆
• Equipment list
◆ ◆
• Instrument index

• Instrument specification data sheet template
◆ ◆
• P&ID Symbols, Legends, Specimen Diagrams, Tag Details
◆ ◆
• Typical loop diagram specimens
◆ ◆
• I/O Schedules
◆ ◆ ◆
• Ring water main
◆ ◆ ◆
• Utility system
◆◆
Equipment specifications, Long lead complete, Preliminary for other Items
◆◆
Pipeline sizing; Complete for major process lines

Piping support and stress analysis
◆ ◆
Site Plan

• Equipment layout plan

• Underground layout drawings

• Safety drawings

• Geotechnical survey & reports

• Material selection guide
◆ ◆
Design pressure / Temperature limits
◆ ◆
Utility summary

Fuel, Chemical, Coolant, Hydraulic & Lubricant Summary
◆ ◆
Startup & 2 year operational spares list
PLANT DESIGN PAGE 2

Description of deliverable P F


Feed material flow control Block diagram

Material handing block diagram

• Product conveyor system. Design layout, flow diverters, densification equipment
specifications. Detailed descriptions, general arrangement drawings, detailed
drawings, equipment specifications

• Product storage area. Detailed descriptions, general arrangement drawings,
detailed drawings, equipment specifications

• Product packaging area. Detailed descriptions, general arrangement drawings,
detailed drawings, equipment specifications

• Silo storage system. Detailed descriptions, general arrangement drawings,
detailed drawings, equipment specification

• Silo homogenization systems. Detailed descriptions, general arrangement
drawings, detailed drawings, equipment specification

• Wieight’ometer, weigh scales etc. Detailed descriptions, general arrangement
drawings, detailed drawings, equipment specifications

• Packaging station. Detailed descriptions, General arrangement drawings, detailed
drawings, equipment specifications

Conveyor, Cranes, Mobile equipment, specifications RFQ etc.

Spares inventory control recommendations

• Consumable spares inventory, storage and tracking systems

• Operational spares inventory, storage and tracking systems

Feeds stock Inventory tracking systems descriptions

Product inventory tracking systems descriptions

Maintenance works shop description, recommendations, tooling requirements

Chemical laboratory requirement lists

• Analytical requirements

• Day to day operational requirements

• Shipping and Q.A. requirements, client support etc.
ELECTRICAL DESIGN BUILDING SYSTEMS

Description of deliverable P F


Area key plans for lighting, tray and grounding layouts

Lighting level calculations
Plant and site lighting layouts

Substation layouts

• Plant distribution center switchgear building and equipment layout
U/G duct bank layout
One-line diagram with interlocks, capacities, voltages. currents, impedances,

• 4.16 kV one-line diagrams

• 600 – 460 V one-line diagrams
• Motor control schematics
• Lighting control schematics
Electrical interface block diagram

Installation details

• Duct bank details

• Lighting and distribution panel schedules
• Tray sizing calculations

• Cable tray general arrangement drawing and detailed drawings

• Cable tray penetration details into buildings

Equipment sizing calculations

Emergency load calculations

System studies, Fault levels, Short circuit current, Minimum/Maximum

Motor start effects, system stability
Transformer tap settings
Motor protection settings
ELECTRICAL DESIGN PLANT SYSTEMS

Description of deliverable P F

Equipment drawings including vendor diagrams


• Front & interior panel layout
• Wiring diagram & terminal layout
• 3-Line diagrams
• Manuals
• Maintenance and instruction manuals
• Electronic equipment manuals, Config data, Data sheets with environmental limits
• Fuse ratings
• Circuit breaker settings
• Battery details including amp-hour ratings
• Relay settings
• Spare parts list
Interconnection diagrams
Cable routing schedules
Schematics
• 4 kV schematics
• 600 – 460 V schematics
• 120 V schematics
• 125 V UPS
• MOV control schematics (Voltage suppression devices)
• Lighting control schematics
• Emergency power schematic diagram
PIPELINE & LAYOUT

Description of deliverable P F


Piping general arrangement

Isometric drawings for N-50 and greater

Isometric drawings for pipework underground

Detailed fabrication drawings for N50 and larger



Piping material specification

Standard piping details

Pipework support calculations

Pipework fabrication and Installation specifications

Pressure test procedure
◆ ◆
Special piping requirements
• Material test certificate
• Welding procedures and inspection certificates (Physical testing reports)
• Inspection reports, certification stamps as required
• Nonconformance, remediation, details and reports
Special piping support details

Stress critical line list

Stress analysis specification
Stress reports, images, etc.
Hydrostatic test diagrams (High pressure pipework)

Details of special requirements, heat tracing, explosion risk requirements, damage
protection requirements, insulation, color coding, plastic pipework requirements etc.
PLANT INFRASTRUCTURE

Description of deliverable P F


Building drawings

Site Details; Drainage, Paving, Fencing

Structural details

Pipe rack supports drawings
◆ ◆
Control systems general requirements

Control systems DCS (Distributed Control System)

PLC (Programmable Logic Controller)

SIS (Safety Instrumented System)

Cable routing diagrams

Electrical equipment list including but not limited to

• Mobile equipment recharging stations design, installation drawings, instructions

• Uninterruptable power supplies design, installation drawings, instructions

• Emergency systems, generators, cooling systems etc. design, installation
drawings, instructions.

Electrical equipment data sheets

Electrical load list, load calculations, cable schedules

Area classification diagrams description

FIRE CONTROL AND PREVENTION

Description of deliverable P F
◆ ◆
Statement of design philosophy

Firefighting equipment layout list & requisitions
Gas and fire detection equipment schedule
Fixed extinguishing systems design
Mobile fire-fighting equipment schedule
Safety equipment schedule
MOTORS, INSTRUMENTATION & CONTROLS

Description of deliverable P F

System block diagram
System functionality definition and interface description between systems

MCC Motor Control Center schedules

• Detailed motor list, type, efficiency, inrush current, operating load range

• Motor data sheets, instructions

• Starter details Direct on line, Star/Delta, Soft start, Variable speed

• Interlock list, fail safes condition list, local disconnect I/D list
System graphic displays
Instrumentation drawings

Instrument cable schedule
Instrument cable routing
Instrument air distribution diagram

Instrument design data and engineering calculations

Instrument power and utility requirements
Alarm & trip schedule
Control room layout
Electrical panel and rack layout drawings
Electrical schematics

• One-line power distribution diagram

• Power distribution schedule

• Grounding diagram for instruments and control systems
• Termination schedule/diagram
• Junction box schedule

• Interconnection diagrams
CIVIL & STRUCTURAL DESIGN

Description of deliverable P F


Civil layouts site plan drawings

Civil design criteria

Road layouts and details

Foundation & concrete structure details



Underground services specification

Underground services layout

Earthworks, excavation procedures, filling & compaction requirements

Earthwork grading drawings

Piling specification
Piling layouts, with support capacities, locations, cutoffs, elevations

Reinforced concrete specification

Structural design criteria

Structural steelwork design and specification

Structural steelwork requisitions
Fireproofing schedule if applicable
Indexed design calculations

ARCHETECTURAL DESIGN

Description of deliverable P F


Building specification

Building layout drawing
Building detail drawings
Schedule of finishes
Schedule of doors and windows
PROCUREMENT

Description of deliverable P F

◆ ◆
Long lead item list
◆ ◆
Approved vendor list

FEED contract deliverable list

Key documents

Material requisitions

Requests for quotation RFQ

CONSTRUCTION

Description of deliverable P F

◆ ◆
Land use plan

Infrastructure strategy document

Temporary facility requirements, requisitions and specifications
• Site huts, toilets, washrooms, and temporary offices
• Mobile and hired equipment, (Man lifts, Cranes, Compressors, fork lift truck etc)
• Communications
• Temporary power, Generators, Electrical hooks-ups etc.
• Scaffolding, staging, protective barriers etc
SCOPE OF WORK

Description of deliverable P F

◆ ◆
Introduction

Management plan

Division of responsibility

Interface systems, Services, etc.

Tie-in details, battery limits, lists, diagrams, drawings

COST ESTIMATE Level 3 (-10% / +15%)

Description of deliverable P F


Estimate report

e-file doc, Proposals for major equipment
e-file doc, Proposals for installation packages

Reference drawing list

Cost estimate and project cash flow forecast
This list is based on the list presented on The Project Definition website. This website usefully
contains descriptions and definitions of the various roles and tasks an engineering contractor is
required to perform under an engineering contract. The list presented here has been amended to
reflect the usual engineering deliverables at the time a new zinc oxide plant project is handed over to
a client. The list assumes building and architectural engineering services are part of the engineering
contract, for an EPCM contract, these services will usually be contracted locally.

In some instances, multiple documentary requirements are covered by a single document for
example an electrical diagram will usually provide;

• Line electrical loads


• Fuse details
• Circuit breaker settings
• Circuit loads and voltages
• Transformer tap settings
• Ground cable requirements
• Interconnection cable details
• Terminal rail details
• Panel Layout, Internal Layout, Spare Parts list.

The documentary requirements are important as they provide a consistent user interface, referenced
using the P&ID numbering schedule. Some of these deliverables are noted as preliminary at the end
of the Engineering contract (Column D) as these data will be continually amended during the course
of a project and during operations.

Translation services have been omitted from the list as translations are usually handled during the
preparation of each document. Translation usually requires the assistance of the client to ensure that
the meaning and intent of the document is properly communicated. It is usual that the client or a
translator approved by the client be tasked separately with translation services. As this is large task
for most plant construction projects, translators play an important role.

Third party data sheets and instructions are not always available in the local language. Under our
normal engineering deliverable requirements, third party information will be provided in the available
language. If a document requires translation it will be handled as an extra service under the terms of
the engineering contract. Where possible local language requirements will be specified in the
purchase contract with a third-party vendor.