Case Study Ninl Techno Smile
Case Study Ninl Techno Smile
Case Study Ninl Techno Smile
CONCEPTS
(CCQC - 2019)
CASE STUDY
QC GROUP NAME – TECHNO SMILE
INTRODUCTION OF ORGANIZATION
NEELACHAL ISPAT NIGAM LIMITED:
I
1.
TITLE OF CASE STUDY: --
COKE OVEN GAS RESISTANCE ACROSS PRIMARY GAS COOLER IS
HIGH.
Shri A.K.Rout.
Coordinator:
Asst. General Manager, TQM.
Facilitator Narayana Prasad Mishra.
Sr.Manager, CO & BPP.
Team Leader S.K.Mohanta
K. C. Sahoo
D. P. Dash
A. K. Bera
C. R. Palei
1. Introduction of organization I
2. Brief History of QC II
3 Index III
III
STEP-1:- IDENTIFICATION OF PROBLEM
List of problems identified
[Through Brainstorming]
LIST OF PROBLEMS
Sr. No NO OF PROBLEMS IDENTIFIED CAT.
1. Decreasing of the effectiveness of oil skimmer. A
2. Frequent damage of cooling tower fans of contaminated pump house. B
3. Disposal problem of treated water of BOD Plant. A
4. Removal of sludge from tar storage tank . A
5. Damage of shaft, pinion and wheel of aerators in BOD Plant. B
6. Abnormal heating of gear box of de-nitrification agitator in BOD Plant. B
7. High NH3,TDS, content in treated water which is undesirable for using A
SGP and PCM.
8. Problem after loading in wagon only with 2nos pump. C
9. Pit pump foot valve gets jamming frequently. A
10. High shock load given to the bacteria in BOD Plant. A
11. Slate conveyor frequent damaging.. A
12. ETP insulator not working in GCP. A
13. Requirement of new ammonium sulphate storage shed in the off season. C
14. Level indicator for caustic lye storage tank. B
15. High ammonia, oil and grease content in the inlet of BOD Plant. A
16. Bucket elevator belt conveyor moving off center. A
17. Hand railing & structure damage at BOD Plant. A
18. Dozing pump getting chocked and not lifting. A
19. PGC cooling tower strippers getting damaged. B
20. Pit tank top cover getting damaged in F L Pump House. A
21. Colour problem of effluent and treated water in BOD Plant. C
22. Problem of maintaining ph in ammonia column. A
23. Auto weigh machine in asp is not working. B
24. Frequent jamming of y-1 conveyor chute in A S P. A
25. Gland leakage of solar oil pump in N.S. A
26. Settling tank-2 gate valve under break down in BOD Plant. A
27. Supply of flushing liquor during power failure to battery. C
28. High condensate from NS. B
29. Disposal problem of ETP wash water. A
30. Frequent break down / damage of hot air fan in ASP. A
31. Pin hole leakage in decanter no.-1. A
32. Decanter top inspection holes cover getting damaged. B
33. Dozing pump pipe lines getting damaged. A
34. Lifting arrangement of equipments no available in BOD Plant. A
35. Damage of power cables of pump no. 9 a & 9 b in BOD Plant. A
01
Sr. No NO OF PROBLEMS IDENTIFIED CAT.
36. Maintaining of desired suction of exhauster during instrument panel A
power failure.
37. Frequent break down of scrubber pump in ASP. A
38. Contamination of storm water and effluent water during rain. A
39. Irregular dispatch of ammonium sulphate fertilizer. B
40. Improper condensate removal system from N S area. A
41. Frequent break down of s / d valves of compressor. A
42. Coal tar is not settling properly in the settling tank of FGC. A
43. Rain water block aging in the tar storage tank area. A
44. Temp. is not maintaining properly in the tar storage tank - 40b. A
45. High gland leakage from DAF in BOD Plant. A
46. Drive inner wheel not working properly in BOD Plant. A
47. Dewatering valve not functioning properly in BOD Plant. A
48. Equalizing pump 2- b having abnormal sound. A
49. Combined pump7- a having regular gland leakage at BOD Plant. A
50. Air blower discharge line duct having leakage in BOD Plant. B
51. No on- spot testing provision of ph at ASP. A
52. No level measuring instrument for hot water tank. B
53. Regeneration of rich solar oil is not carried out. A
54. Corrosion problem of structure in ASP. A
55. Break down of vibrator in ASP. A
56. Retrieval of tar and oil from BOD Plant . A
57. Modification of excess flushing liquor discharge line to maintain A
intermediate f/l tank level.
58. Maintaining inlet flow of effluent water after DAF more than 20 m3/hr. A
59. Frequent choking of submersible pump suction line of neutralizing pit in ASP. A
60. C o gas resistance across primary gas cooler is high A
61. Malfunctioning of tar flow meter in FGC. A
62. Malfunctioning of tar flow meter in PGC. A
63. Arrangement for hoisting device in effluent A
collection pump house for maintenance work.
‘A’ CATEGORY-The Circle with in their control and capacity to solve this type of
problems.
C TYPE,
B TYPE,
4, 6%
11, 18% A TYPE
A TYPE, B TYPE
48, 76%
C TYPE
Pie chart
03
STEP-2:-SELECTION OF PROBLEM
After categorization of problem ,an in-depth study was done on various aspects of A- category
problems, which are again sub-categorized as IMPORTANT, URGFNCY, FEASIBILTY and
ENIVRONMENT. Our group conducted a number of brainstorming sessions and identified 20 nos.
Problems associated with IMPORTANT category, 12 nos. Problems associated with URGFNCY
category, 05 nos. Problems associated with FEASIBILTY category & 11 nos. Problems associated
with ENVIRONMENT category. They are tabulated below as I- IMPORTANT category, U-
URGFNCY category, F- FEASIBILTY category and E- ENVIRONMENT category.
04
05
41 RAIN WATER BLOCKAGING IN THE TAR STORAGE TANK AREA. √
06
With feeling the importance of “URGENCY TYPE” problems, so all members of our QC team are
interested to take this related problems for rating first.
M1 = S. K. MAHANTA
M2 = K. C. SAHOO
M3 = J. B. GIRI
M4 = A. K. BERA
M5 = D. P. DASH
M6 = C.R.PALEI
RATING POINTS - 1 TO 10
SL.
‘U’ CATEGORY PROBLEMS M1 M2 M3 M4 M5 M6 TOTAL
NO.
07
SL.
“U” CATEGORY PROBLEMS M1 M2 M3 M4 M5 M6 TOTAL
NO.
08
QC NAME : DEPT:-CO & BPP HOD:-G.N.SAHOO
GROUP MEMBERS:-
TECHNO SMILE FACILITATOR:-N.P.MISHRA
S.K ,MOHANTA(LEADER)
K.C. SAHOO
PROJECT NAME REASON FOR SELECTION :- GOT HIGHEST
D.P.DASH
:COKE OVEN GAS RATTING BY ALL MEMBERS.
J.B. GIRI
RESISTANCE
A.K.BERA
ACROSS PGC IS
C.R.PALEI
HIGH.
PRESENTATION TH RD
PROJECT NO : 2 STARTING DATE : 13 MARCH 2019 COMPLETION DATE : 03 JULY 2019
MEETING DAY:
MEETING TIME : 03:00 PM TO 04:00 PM
WEDNES DAY
ST PLA
EP
NO Activity Weeks NN
. ED
1 2 3 4 5 6 7 8 9
1 1 1 1 1 1 1 1
0 1 2 3 4 5 6 7
Defining the
3 problem. 2
Analysis of the
4 1
problem.
Identification of
5 Causes. 2
7 Data Analysis. 2
Developing
8 solution. 2
Foreseeing
9 probable 1
resistances.
Trial
10 implementation. 4
Regular
11 implementation. 1
Follow-up/
12 Review. 1
09
STEP-3:-DEFINING THE PROBLEM
Primary gas cooler(PGC) is meant for the primary cooling of coke oven gas(CO GAS), received from the
coke oven battery at 80°C and cools up to 35° C approximately.
For the cooling purpose of the CO gas, there is arrangement of water circulating tubes inside the PGC,
where the hot CO gas is cooled, when passed between the cooling tubes. Here the cooling tubes are acts
as heat exchanger and heat transfer is carried out from CO gas to water cooling tubes to decrease the
CO gas temperature.
Also there is an additional arrangement of hot crude coal tar flushing on the top and middle of the PGC
to absorb the naphthalene content from the CO gas and to clean the outer surface of the cooling tubes
for the better travel of CO gas across the PGC.
Having all these arrangement, still it is not able to maintain the CO gas resistance across the PGC within
the limit (i.e. ≤ 100 mm W c) 10
ACTUAL FIGURE OF PRIMARY C O GAS COOLER. DIAGRAM OF PRIMARY C O GAS COOLER.
11
IMPACT OF THE PROBLEM
EXHAUSTER LOAD INCREASE
EXHAUSTER HUNTING
STEP : 4
HOW IS THE PROBLEM ? EXHAUSTER OPERATION HAMPERED DUE TO RISE IN RESISTANCE ACROSS
THE PGC.
12
DATA COLLECTION:
DATA HAS BEEN COLLECTED FROM EXHAUSTER HOUSE LOG BOOK TO KNOW THE RESISTANCE OF PRIMARY
GAS COOLER FROM 01/01/2019 TO 28/02/2019.
STEP : 5
IDENTIFICATION OF CAUSES BY CAUSE & EFFECT DIAGRAM
To draw cause and effect diagram we have done brainstorming, to find out all the possible causes influencing the effect.
We have organized the causes in to Sub-cause and Sub- sub -cause.
14
CATEGORY CAUSES SUB-CAUSES
1. Negligence. 1. Lack of Alertness
2. Unskillfullness
MAN
2. Non-Following of the Proper Operational 1.Lack of knowledge
Procedure. 2.over confidence
1. Damage of cooling pipes 1.Corrosion in pipes & any
internal damage inside PGC.
2.Gas flow meter malfunctioning 1.Gauge may choked
3.Scaling on outer surface of the cooling tubes. 1.Unsepareted inherent sludge
mixed tar flushing to PGC.
2.Foreign material from CO gas
may deposited on the surface of
the tubes
3. Corrosion on pipes.
4.Tar flushing temperature gauge malfunctioning 1. Faulty or sub –standard
gauge.
MACHINE 5.Tar pressure gauge malfunctioning 1. Faulty or sub – standard
pressure gauge used.
6.Tar flushing pump failure 1. Mechanical fault.
STEP- 6
If any reason scaling occurred on outer surface of the cooling tubes , the
gaps between the bundles of tubes becomes reduced. As a result Coke
How this Problem Occur? Oven gas is not able to pass successively across the primary gas cooler
which causes rise of resistance in PGC.
After analyzing the main cause by 5W & 1H method we found that the root cause is
Data collected from 01/01/2019 to28/02/2019 from Exhauster House log book.
READING OF READING OF
RESISTANCE
SL CO GAS AT IN CO GAS AT
ACROSS PGC REASON OF REDUCTION IN
. LET OF PGC OUT LET OF
N
DATE SHIFT IN mmWc(ALL GAPS BETWEEN THE BUNDLES
in mmWc. (ALL PGC in mmWc.
O. VALUES ARE OF COOLING TUBES.
VALUES ARE (ALL VALUES
IN + VE)
IN – VE) ARE IN – VE)
PARETO ANALYSIS
It is cleared from the data analysis that the below mentioned factors are most
responsible for Reduction in gaps between the bundles of cooling tubes
19
No. FACTORS RESPONSIBLE FOR. CODE FREQUENCY OF CONTRIBUTION(%)
REDUCTION IN GAPS BETWEEN THE OCCURANCES In IND
BUNDLES OF COOLING TUBES nos.
SETTING TARGET
20
STEP -8
DEVELOPING SOLUTION
Sl. Accepted /
Alternative Effect Solution
No. Rejected
By this arrangement
Install a tar filter scaling due to tar
This will restrict the
along with a sludge on outer
4 sludge and foreign Accepted
strainer in tar surface of the cooling
material .
pump delivery line. tubes can be
avoided.
21
DEVELOPING SOLUTION
BEFORE Q.C . (PREVIOUS SYSTEM)
Earlier tar flushing to PGC was carried out only by using a tar pump, no
tar cleaning apparatus was utilized . So the sludge content in tar,
directly enters to PGC ,which causes quick scale formation over the
cooling tubes. Hence it obstacle to pass the CO gas successively. As a
result the resistance increases across the PGC.
DEVELOPING SOLUTION
AFTER Q.C. (MODIFIED SYSTEM)
Keeping in view on the above problem our Q.C team made brainstorming.
Hence propose to install a filter along with a strainer arrangement at the
delivery line of the tar flushing pump.
This will restrict the sludge and any other foreign substance mixed with tar
during tar flushing PGC. As a result only clean tar can be used for flushing
purpose.
22
ACTION PLAN FOR IMPLEMENTATION
We have prepared time bound and responsibility share ,action plan to
implement our solution effectively within time limit.
TIME PERIOD
SL. TH
ACTION RESPONSIBILITY (08 MAY 2019 TO
NO. ST
21 MAY 2019 )
S. K. MOHANTA &
2 ARRANGEMENT OF MATERIALS. 5 DAYS
J. B. GIRI
A. K. BERA &
FABRICATION AND
3 C.R.PALEI 4 DAYS
ERECTION.
STEP – 9
FORESEEING PROBABLE RESISTANCE
It is human nature ,that changes are not easily acceptable to the people . Before implementation
of our idea, “ the new modified system for ” reduction of resistance across PGC ”, our q. C. Members
has listed all the probable resistances that to be faced and done brainstorming to find out the
ways to overcome the resistances
Proper co-ordination to operation Discussion was carried out with operation &
1
and maintenance staff. maintenance staff for proper co-ordination.
Handover of existing tar flushing Operation & maintenance staff are convinced for
2 pipe line and pump for new modification & we decided to carry out the work
modification. in a quick manner .
Adoptability of the new system Our Q. C. Team talked to every operator ,also
5
by operators. demo operation was given .
23
STEP :10 TRIAL IMPLEMENTATION AND
CHECKING PERFERMANCE
Trial implementation has been done from dt. 29th may 2019 to 25th june 2019
Sizeable and appropriate data indicating period of trial and findings for implementation of
our solution we have prepared chart as shown in table to indicate period of trials and
findings.
24
25
STEP :11 REGULAR IMPLEMENTATION
Regular implementation of the modified system was started on dt.26th
June 2019 and found running in a excellent way till now .
26
BENEFITS
1 COST OF CO GAS / m3/ hr. (AT NO. OF OVEN PUSHING OF 75/ DAY) @gas Rs. 16,00,000.00
discharge 320m3/hr including crude coal tar & ammonium sulphate &
naphthalene =
IMPLEMENTATION DETAILS.
1 M.S. PIPE OF DIA .100mm. (10 mtr. @Rs600/mtr.) 10 x Rs600= Rs . 6,000 .00
27
INTANGIABLE BENEFITS
1. Ability to motivate our co-workers towards positive thinking.
2. Problem analysis skill developed.
3. Self satisfaction increased.
4. Mutual understanding improved.
5. Positive attitude towards work.
6. Enthusiasm towards our work improved.
STEP 12
FOLLOW UP AND REVIEW
After doing our project , it was our pleasure about completion of it but
it was the time to review it. For this our team collected data of co gas
resistance across PGC and prepared a need based check list to sustain the
process improvement.
28
STANDARDISATION
All the modification have been approved and issued as per
REF. BPP/MECH/OPER/A1/7694
29
TOOLS & TECHNIQUES APPLIED
Brain Storming.
Milestone Chart.
Flow Diagram.
Data Collection.
Cause And Effect Diagram.
Pareto Diagram.
Rating Method.
Bar Chart.
4w & 1h Method / 5w & 1h Method.
ACKNOWLEDGEMENT
31