Sap Wipro National Grid Complaint PDF

Download as pdf or txt
Download as pdf or txt
You are on page 1of 39

Case 1:17-cv-06997-CBA-RER Document 1 Filed 11/30/17 Page 1 of 35 PageID #: 1

UNITED STATES DISTRICT COURT


EASTERN DISTRICT OF NEW YORK

NATIONAL GRID USA SERVICE


COMPANY, INC.,
Civil Action No. 1:17-cv-6997
Plaintiff,

v. COMPLAINT

WIPRO LIMITED, JURY TRIAL DEMANDED

Defendant.

Plaintiff National Grid USA Service Company, Inc. (“National Grid”), for its complaint

against Defendant Wipro Limited (“Wipro”), alleges as follows:

PRELIMINARY STATEMENT

1. This action arises from the fraud, breaches of contract and other misconduct of

defendant Wipro, a multinational global software consulting firm, in connection with its failure

to properly design, configure, test and implement a company-wide enterprise resource planning

(“ERP”) software system for National Grid, a leading U.S. electric and gas utility.1 Despite

touting its extensive experience and being paid more than $140 million for its work, Wipro

botched the implementation, delivering a system that was of virtually no value to National Grid.

2. In 2008, National Grid commenced a strategic initiative, known as the U.S.

Foundation Program (“USFP” or “Project”), to upgrade the back-office computer systems that

run its financial, human resources (“HR”), and supply chain and procurement operations. The

1
“National Grid” is a trade name for a multinational organization consisting of U.K. and U.S. affiliated companies
that provides gas and electric services in the U.K. and U.S. (Massachusetts, New York and Rhode Island). The SAP
implementation at issue was not limited to National Grid USA Service Company, Inc., but all of its U.S.-based
affiliates.
Case 1:17-cv-06997-CBA-RER Document 1 Filed 11/30/17 Page 2 of 35 PageID #: 2

new computer platform was to run on SAP, a leading ERP software solution that is intended to

integrate and automate a company’s core business functions.

3. National Grid engaged several vendors to work on USFP. Deloitte Consulting

LLP (“Deloitte”) served as the original Lead Implementation Partner, Project Manager and

Systems Integrator from late 2009 to June 2010. In June 2010, Deloitte was replaced by Ernst &

Young LLP (“EY”),2 which was the Lead Implementation Partner and Project Manager through

and after the go-live of the new SAP system, and by Wipro, which was the Systems Integrator

through and after go-live. SAP America, Inc. served in an advisory role regarding certain

aspects of the Project.

4. Soon after the Project began in late 2009, National Grid considered engaging an

off-shore partner to provide technical support to Deloitte during USFP’s blueprint and design

phase. To that end, National Grid, which had virtually no personnel with SAP experience, issued

a Request for Proposal (“RFP”) to consulting firm candidates to determine which firm would be

able to provide the most appropriately skilled and experienced consultants for the Project.

5. In its February 17, 2010 response to National Grid’s RFP (the “RFP Response”),

Wipro misrepresented its skills and experience in order to induce National Grid into hiring

Wipro for the Project. Among other things, Wipro misrepresented its (i) ability to furnish

National Grid with appropriately experienced and skilled consultants; (ii) experience with U.S.

utility companies; and (iii) ability to leverage the knowledge and best practices it had acquired

from working on back-office and front-office SAP implementations (respectively, the “MySAP”

and “GDFO” projects) for National Grid’s U.K. affiliates (“National Grid U.K.”).

2
Pursuant to applicable contracts, National Grid cannot assert claims against EY in court.

2
Case 1:17-cv-06997-CBA-RER Document 1 Filed 11/30/17 Page 3 of 35 PageID #: 3

6. Wipro’s representations were knowingly or recklessly false when made. As

Wipro knew or should have known, it had neither the ability nor intent to assign appropriately

experienced and skilled consultants to the Project because, contrary to its assertion in its RFP

Response that it had “long-running partnerships with . . . 20 of the top 50 investor-owned utilities

in North America,” it in fact had virtually no experience implementing an SAP platform for a

U.S.-regulated utility. Wipro also knew or should have known that its ability to meaningfully

leverage its work from MySAP and GDFO – two U.K.-based projects – on the U.S.-based USFP

was highly circumscribed because of the critical differences between the core business processes

of National Grid and National Grid U.K. Indeed, the different regulatory schemes and union

rules in the U.S. and the U.K. rendered Wipro’s work for National Grid U.K. of limited value on

the U.S.-based USFP.

7. In reliance on Wipro’s representations in the RFP, National Grid hired Wipro for

USFP, initially as its Offshore Development Center (“ODC”) partner. By spring 2010, in

continuing reliance on Wipro’s representations, National Grid gave Wipro a substantially larger

role on USFP, making Wipro the Systems Integrator.

8. Reflecting how crucial it was that Wipro staff the Project with appropriately

skilled and experienced consultants, the parties’ agreement contained a series of unusually

detailed and stringent express warranties. For example, Wipro agreed to: (i) exercise “the

degree of skill, care, professional judgment, prudence and foresight which would be expected

from the top 25% of companies who are expert[s] and experienced in conducting the same type

of undertaking that provides the same or similar services as those Services;” and (ii) provide

consultants that were “suitably qualified, skilled, honest, experienced and trained in the work

which they are to perform.” As set forth in detail below, Wipro breached those warranties and

3
Case 1:17-cv-06997-CBA-RER Document 1 Filed 11/30/17 Page 4 of 35 PageID #: 4

other contract obligations. In fact, its work was marred by significant performance failures

through every Project phase.

9. Staffing. Wipro’s consultants lacked the requisite skills, experience and expertise

concerning SAP software, industry standards of care and the U.S. utility industry, including with

respect to the applicable regulatory requirements and union rules.

10. Design. Wipro’s system design was fundamentally flawed. Among other things,

Wipro failed to apply industry standards of care and gather and understand sufficient information

about National Grid’s U.S. business requirements to prepare appropriate functional and technical

specifications to support National Grid’s requirements.

11. Build and Configuration. Wipro helped design and build an overly complex SAP

solution that was not configured pursuant to industry standards of care. Rather than taking

advantage of certain design and configuration options available within the out-of-the-box SAP

software to minimize system complexity and reduce risk, Wipro’s inexperienced consultants

engaged in excessive customization of the base SAP system. Wipro’s configuration and

programming errors led to crippling post-go-live problems.

12. Testing. Wipro’s testing of the system was deficient, as Wipro failed to identify

system defects that caused many of the post-go-live problems. Wipro failed to follow standard

testing protocol, including the design and development of testing scripts that would detect bugs

in the system, identify and track defects, functionality gaps and other design flaws. Rather than

conducting robust testing of those business scenarios most likely to cause post-go-live problems,

Wipro engaged in truncated testing that produced artificially positive results.

13. Data Conversion. Wipro failed to correctly convert National Grid’s data into the

SAP system. Wipro did not convert and load National Grid’s legacy data into the new SAP

4
Case 1:17-cv-06997-CBA-RER Document 1 Filed 11/30/17 Page 5 of 35 PageID #: 5

system correctly and, in some instances, entire data files were corrupt and/or contained incorrect

information. Although Wipro should have detected the faulty data during testing, it failed to do

so.

14. Immediately after go-live, defects in the payroll system rendered National Grid

unable to pay its employees accurately or timely. The new SAP system miscalculated time, pay

rates and reimbursements, so that employees were paid too little, too much or nothing at all.

Payroll defects also snarled tax and 401(k) withholdings, union dues, benefits, pensions, and

court-ordered garnishments. When National Grid turned to Wipro for desperately needed post-

go-live assistance, Wipro was unable to remediate key system defects, ultimately admitting it

could not solve the payroll problems its inept consultants had caused. Wipro eventually had to

turn the system over to another vendor that was able to fix the problems.

15. National Grid also faced critical system issues with respect to accounts payable

and procure-to-pay functionality, particularly its ability to make payments to vendors and its

ability to reconcile cashed checks. Meanwhile, with respect to supply chain functions, system

defects devastated National Grid’s procurement, inventory and vendor payment processes. Two

months after go-live, National Grid’s backlog of unpaid supplier invoices exceeded 15,000, and

its inventory record-keeping was in shambles.

16. In the face of these payroll and supply chain problems, National Grid’s auditor

could not sign off on National Grid’s financial statements. Whereas National Grid typically

performed its monthly financial close in four days with its legacy systems, on the new SAP

system it took National Grid approximately 43 days to close its financial statements, heightening

regulatory and financial risks. Indeed, as a result of SAP system defects, National Grid was

5
Case 1:17-cv-06997-CBA-RER Document 1 Filed 11/30/17 Page 6 of 35 PageID #: 6

unable to produce crucial accounting reports, forced to seek multiple extensions, and denied the

ability to enter into routine, short-term borrowing arrangements by federal regulators.

17. In order to stabilize the system, meet its regulatory reporting requirements and

resolve its pervasive payroll, supply chain and financial reporting problems, National Grid had to

engage hundreds of additional resources from multiple vendors at a cost of hundreds of millions

of dollars. Even with these additional resources, it took more than two years for the SAP system

to be fully stabilized. In many instances, functional and technical specifications had to be

completely re-written and entire SAP modules had to be re-built or abandoned. In the meantime,

National Grid was unable to submit required reports on time, was forced to seek extensions of its

payroll and tax reporting obligations, was the subject of investigations by multiple state

Attorneys General, was subject to scathing negative press reports, and was forced to pay a

$12 million settlement to its employees.

18. Compounding the post-go-live problems was Wipro’s failure to adhere to

standard industry practices that require documentation of Project test results and defects.

19. Through this action,3 National Grid seeks to recover from Wipro the

approximately $140 million in fees it paid to Wipro (consisting of approximately $71 million

paid to Wipro during the Project and another approximately $69 million paid to Wipro after go-

live), and hundreds of millions of dollars in fees it paid to other vendors for post-go-live

stabilization and remediation work.

3
On October 28, 2015, National Grid and Wipro executed a Tolling Agreement to toll and suspend all applicable
statutes of limitation concerning National Grid’s potential claims against Wipro arising out of Wipro’s work on
USFP. To extend the tolling period, the parties executed a series of Tolling Agreement amendments, the last of
which was executed on October 12, 2017. The Tolling Agreement expired on November 30, 2017.

6
Case 1:17-cv-06997-CBA-RER Document 1 Filed 11/30/17 Page 7 of 35 PageID #: 7

PARTIES

20. Plaintiff National Grid is a Massachusetts corporation with its principal place of

business located at 40 Sylvan Road, Waltham, Massachusetts 02451. It is a U.S. subsidiary of

National Grid plc, a multinational electricity and gas utility company headquartered in the United

Kingdom.

21. Defendant Wipro is an Indian corporation with its principal place of business in

Bangalore, India. It is a global information technology, consulting and outsourcing company.

JURISDICTION AND VENUE

22. This Court has jurisdiction over the subject matter of this action pursuant to

28 U.S.C. § 1332 because there is complete diversity of citizenship between the parties and

because the amount in controversy exceeds $75,000, exclusive of interest and costs.

23. Venue in this Court is proper pursuant to 28 U.S.C. § 1391 and Section 12, Clause

66.3 of the parties’ Master Services Agreement (“MSA”), which states, in pertinent part, that

“each party hereby irrevocably and unconditionally submits, for itself and its property, to the

nonexclusive jurisdiction of, and venue in, any New York State Court or federal court of the

United States of America sitting in the Southern or Eastern District of New York and any

appellate court from any court thereof, with regard to any claim or matter arising in relation to

this Agreement.”

FACTUAL BACKGROUND

A. National Grid’s Global Operations

24. National Grid plc is an international electricity and gas company based in the

U.K. with operations there and in the northeastern U.S. The company plays a vital role in

connecting millions of people safely, reliably and efficiently to the energy they use through

7
Case 1:17-cv-06997-CBA-RER Document 1 Filed 11/30/17 Page 8 of 35 PageID #: 8

National Grid’s distribution and transmission utility networks. National Grid U.K. and U.S.

employ approximately 10,000 and 17,000 people, respectively.

25. National Grid U.K. owns a high-voltage electricity transmission system in

England and Wales, and operates the system across Great Britain. It also owns and operates a

high pressure gas transmission system in Great Britain. National Grid U.K.’s distribution

networks deliver gas to approximately 11 million consumers, or approximately one quarter of

Great Britain.

26. In the U.S., National Grid owns and operates electricity distribution networks in

upstate New York, Massachusetts and Rhode Island. Through these networks, National Grid

serves approximately 3.4 million electricity consumers in New England and upstate New York.

National Grid’s U.S. gas distribution networks provide services to roughly 3.6 million consumers

across the northeastern U.S., located in upstate New York, New York City, Long Island,

Massachusetts and Rhode Island. National Grid also owns over 4,000 megawatts of contracted

electricity generation, providing power to over one million Long Island Power Authority

customers. National Grid’s U.S. operations primarily consist of separate regulated operating

companies such as The Brooklyn Union Gas Company, KeySpan Gas East Corporation, National

Grid Generation LLC, Niagara Mohawk Power Corporation, Nantucket Electric Company,

Massachusetts Electric Company, New England Power Company, Narragansett Electric

Company, Colonial Gas Company, Narragansett Gas Company and Boston/Essex Gas Company.

B. The Different Regulatory Schemes in the U.S. and U.K.


And Their Impact on National Grid’s Business Processes

27. From a financial accounting and management perspective, the core business

processes of National Grid’s U.K. and U.S. operations are markedly different. For example, the

U.K. electricity market is more liberalized, dating back to a privatization trend that began in the

8
Case 1:17-cv-06997-CBA-RER Document 1 Filed 11/30/17 Page 9 of 35 PageID #: 9

1970s, and the regulatory regime in the U.K. – including licensing requirements and oversight by

the Department of Energy and Climate Change and the Department of Enterprise, Trade, and

Investment – imposes substantially fewer regulations on National Grid’s U.K. operations than

American regulators impose on National Grid in the U.S. Moreover, because National Grid’s

U.S. employees are organized by a complex union framework that does not exist in the U.K.,

National Grid’s U.S. business processes must address complicated collective bargaining

procedures and payroll and tax calculations that are not required in the U.K.

28. A majority of National Grid’s U.S. employees are members of multiple unions

and bargaining units, and work under dozens of different negotiated collective bargaining

agreements. Each separate union agreement sets forth different standards for union dues and

employee pay depending on, among other things, region, schedules, overtime and extreme

weather circumstances. These union-related variables are not an issue in the U.K., where the

applicable standards are fixed by law.

29. The U.S. utility industry also is subject to heightened regulation, including with

respect to reporting and rate requirements on both a local and federal basis, as compared to the

U.K. utility industry. Specifically, National Grid’s U.S. operations, involving both its gas and

electricity businesses, are subject to extensive state and federal regulations governing, among

other things, detailed mandatory reporting and pricing requirements. The U.S. electricity sector

is generally subject to federal regulation of interstate transmission and wholesale power sales,

state regulation of retail rates and distribution services, and local regulation of facility siting and

environmental impacts. Federal regulation is handled primarily by the Federal Energy

Regulatory Commission (“FERC”), although the Department of Energy and the Environmental

Protection Agency also play a role. Further, to maintain the reliability of the electric grid in the

9
Case 1:17-cv-06997-CBA-RER Document 1 Filed 11/30/17 Page 10 of 35 PageID #: 10

U.S., entities operating transmission facilities such as National Grid have ongoing compliance

and reporting requirements developed by the North American Electric Reliability Corporation.

Still more reporting requirements are imposed by local agencies in each state.

C. National Grid’s Decision to Implement SAP Software

30. National Grid’s growth in the U.S. resulted from a series of mergers and

acquisitions involving various northeastern U.S. regional utility companies. The most recent and

significant of these transactions occurred in 2008 when National Grid acquired KeySpan and

became the third-largest electric and gas utility in the U.S.

31. Following the KeySpan acquisition, National Grid operated with several business

processes across numerous technology platforms. This complex and cumbersome structure

posed significant technical risk, as several business-critical systems ran on aging infrastructure

platforms, often with limited or decreasing vendor support.

32. National Grid’s multiple business processes resulted in significant constraints and

limitations on its back-office financial management and accounting operations, including:

(i) technical and other risks affecting payroll, accounting closes, local and jurisdictional financial

and regulatory reporting, financial planning and budgeting and group financial analyses and

controls; (ii) misaligned HR hierarchies that required excessive and time-consuming work-

arounds; (iii) technical and other risks to inventory management, accounts payable, procurement

and information systems (“IS”) reporting across several back-office systems; and (iv) outmoded

data analysis methods across all business units that depended on spreadsheets for data

consolidation and reporting, leading to inefficiencies and manual errors.

33. To address and overcome these risks, constraints and limitations, National Grid

decided to integrate its systems onto a single SAP platform through the USFP. At the time,

National Grid U.K. had already completed MySAP to implement SAP for its back-office

10
Case 1:17-cv-06997-CBA-RER Document 1 Filed 11/30/17 Page 11 of 35 PageID #: 11

operations and was working on GDFO to implement an SAP solution to handle its U.K. gas

distribution front-office operations, i.e., its provision of gas services to customers. National Grid

U.K. engaged Wipro as its lead ODC partner on both MySAP and GDFO.

34. The primary back-office functions that were the subject of the USFP included HR

(e.g., payroll, time entry and attendance), supply chain and procurement (e.g., fleet and

management of and payment for internal and external goods and services) and finance

(e.g., planning and financial reporting and closing). These components had been running for

years on multiple systems, such as Oracle and PeopleSoft ERP platforms. In addition, USFP

also encompassed plans to: (i) upgrade several front office work management modules in the

areas of assessment management, scheduling, billing and vendor payments; (ii) upgrade several

legacy front-office solutions, such as PowerPlant (plant accounting system), Maximo (asset

management software), and STORMS (work order management system); and (iii) integrate these

solutions with the new SAP system. In all, USFP was supposed to link together dozens of

different systems, across multiple business processes, into one integrated solution that would

generate substantially enhanced operational efficiencies and data reporting accuracy.

35. In light of its complex functional business requirements related to, among other

things, the regulatory and union environments in which it operates – and because it lacked in-

house SAP implementation expertise and experience – National Grid decided it was imperative

to engage vendors that had the requisite highly specialized skills and experience. More

specifically, National Grid needed to engage partners and advisors with the ability and intention

to staff the Project with consultants who had: (i) sufficient expertise to understand the

regulatory, HR and other requirements applicable to U.S. utility companies; (ii) a mastery of the

SAP solution, and specific SAP modules, at issue on the Project; (iii) the skills, experience and

11
Case 1:17-cv-06997-CBA-RER Document 1 Filed 11/30/17 Page 12 of 35 PageID #: 12

expertise to apply industry standards of care to appropriately design, build and test the SAP

solution to meet National Grid’s functional and technical needs; and (iv) the skills, experience

and expertise required to implement an SAP software implementation of the size and complexity

of the USFP.

D. Wipro Misrepresents its Skills and Experience to National Grid

36. At the outset of the Project in late 2009, National Grid engaged Deloitte to lead

the Project strategy and roadmap work and, ultimately, to be the Lead Implementation Partner,

Project Manager and Systems Integrator.

37. In addition to Deloitte, National Grid considered options to engage an off-shore

partner to provide lead technical assistance during the Project’s blueprint and design phase. In

that regard, on January 26, 2010, National Grid put out a bid for an off-shore partner for USFP

through the RFP, asking candidates to detail their skills, experience and expertise with respect to

SAP implementations, both in general and specifically in the context of the U.S. utilities sector.

The RFP described National Grid’s need for a global transformation of its back-office

functionality to consolidate the company’s finance, HR and supply chain business processes onto

a single SAP platform and thereby enhance efficiencies and financial reporting abilities.

Because of the complex regulatory, HR and other requirements uniquely applicable to U.S.

utilities, National Grid also stressed in the RFP that candidates must have U.S. utility industry

experience.

38. On February 17, 2010, Wipro submitted its RFP Response. In it, Wipro

repeatedly emphasized that it had the ability and intention to provide National Grid with the

necessary and appropriate skills and experience – related to SAP implementations in general, and

U.S. utilities-related SAP implementations in particular – to deliver a successful Project. Wipro

also made specific representations concerning its purported ability to leverage its knowledge of

12
Case 1:17-cv-06997-CBA-RER Document 1 Filed 11/30/17 Page 13 of 35 PageID #: 13

National Grid U.K.’s operations based on the work it had previously performed on MySAP and

GDFO.

39. Specifically, Wipro represented that its expertise in the U.S. utilities’ sphere, its

track record for SAP implementations, and its ability to leverage work product, knowledge, and

best practices it had acquired from MySAP and GDFO, would enable National Grid to

successfully implement the new SAP system.

40. With regard to its expertise and experience with ERP implementations for U.S.

utilities, Wipro made the following representations, excerpted from its RFP Response:

41. Even though Wipro in fact had limited experience performing implementations

for U.S. utilities, more than half of the utility logos that Wipro prominently displayed in its

13
Case 1:17-cv-06997-CBA-RER Document 1 Filed 11/30/17 Page 14 of 35 PageID #: 14

RFP response materials were for U.S. utilities.4 In addition, Wipro represented in its RFP

Response that, among other things:

 It had a “proven track record of delivering SAP programs for [its] global utility
clients” and was “uniquely qualified to partner with National Grid” because
Wipro was National Grid’s ODC partner for MySAP and GDFO;

 It was “committed to staff this engagement with the best and most experienced
resources in all the tracks” and would leverage and maximize the knowledge base
from the U.K. implementations;

 It was uniquely positioned for the Project as a result of its U.K.-based work for
National Grid that would enable Wipro to bring “key learnings and knowledge”
and “best practices” to the Project;

 It had the ability and intention to apply its “comprehensive project delivery
methodology [and] utilize its highly experienced business process improvement
skills/people and deep knowledge of SAP processes/capabilities to ensure that all
[of National Grid’s] business requirements are identified and understood,” and to
apply “industry and SAP best practices.” Wipro also represented that
customizations would “be kept to a minimum in the solution design to ensure
maintainability and standardization;” and

 It had the ability and intention to provide National Grid access to its “Centers of
Excellence” team of purportedly skilled technical experts and consultants.

42. Wipro’s representations were false. First, Wipro knew or should have known that

it did not have the ability and/or intention to staff the Project with sufficient numbers of

consultants who had the appropriate skills and experience related to SAP implementations in

general and SAP implementations in the U.S. utilities sector in particular. Second, Wipro knew

or should have known that its prior work and knowledge gained from MySAP and GDFO had

limited transferability or re-usability in connection with the U.S.-based USFP because there were

4
In particular, the following U.S. utility logos were displayed in the RFP Response section entitled “Wipro’s Track
Record in Utilities Industry”: (i) Aquarion Water Company, based in Connecticut; (ii) Entergy, based in Louisiana;
(iii) PacifiCorp, based in Oregon; (iv) Midwest ISO, based in Indiana; (v) Pinnacle West Capital Corporation, based
in Arizona; (vi) SMECO, based in Maryland; (vii) Vectren, based in Indiana; (viii) California ISO, based in
California; and (ix) AGL Resources, based in Georgia.

14
Case 1:17-cv-06997-CBA-RER Document 1 Filed 11/30/17 Page 15 of 35 PageID #: 15

critical differences between the core business processes of the two National Grid organizations

stemming from the different regulatory schemes and union rules in each country.

43. Based in part on National Grid’s trust and confidence in Wipro arising out of their

prior relationship on the MySAP and GDFO projects, National Grid reasonably relied on

Wipro’s pre-contract misrepresentations and engaged Wipro as its ODC partner for the blueprint

and design phase. Thereafter, in the spring of 2010, National Grid decided to restructure the

vendors on the Project, removing Deloitte and assigning EY as the Lead Implementation Partner

and Project Manager, and Wipro as the Systems Integrator. National Grid made the decision to

expand Wipro’s role and make Wipro the Systems Integrator based in large part on the same

representations Wipro had made in the RFP Response when it was originally hired to be ODC

partner.

E. The Contracts Between National Grid and Wipro

44. The MSA was the first in a series of contracts that Wipro induced through false

representations and omissions. Pursuant to the MSA and accompanying Schedules, Wipro and

National Grid thereafter entered into numerous “Work Packs” that set forth the specific work and

deliverables to be performed by Wipro in each phase of the Project, including work relating to

design, build, testing and stabilization of the new SAP system. The parties also entered into

certain amendments to the Work Packs, known as “Variations.”

45. As detailed below, Wipro agreed to, among other things: (i) support National

Grid during the business design phase by participating in collaboration hub workshops and

preparing functional design documents (Work Packs 5388 and 5389); (ii) prepare configuration

15
Case 1:17-cv-06997-CBA-RER Document 1 Filed 11/30/17 Page 16 of 35 PageID #: 16

documents detailing the system settings and configuration values (Work Packs 5388, 5389,

5491); and (iii) deliver a fully-tested SAP system (Work Packs 5491 and 6107).5

46. In the MSA, Wipro made extensive warranties concerning its ability and intention

to provide National Grid with the necessary and appropriate resources to perform pursuant to

applicable professional standards. Highlighting National Grid’s acute need for appropriately

skilled consultants, Wipro agreed to express warranties in the MSA that are substantially more

stringent and detailed than those found in most ERP-related service agreements.

47. Among other things, Wipro represented and warranted that it would provide

services “to a standard that is at least as high as the then current Good Industry Practice of

performance, quality and timeliness.” (MSA § 2, Clause 4.1(a).) The MSA defined “Good

Industry Practice” as, “in respect of the Services, the exercise of the degree of skill, care,

professional judgment, prudence and foresight which would be expected from the top 25% of

companies who are expert[s] and experienced in conducting the same type of undertaking that

provides the same or similar services as those Services.” (MSA § 1.)

48. Wipro further represented and warranted that it would (i) ensure that its

consultants on the Project were “suitably qualified, skilled, honest, experienced and trained in the

work which they are to perform” (MSA § 5, Clause 27.3(b)); (ii) provide work “fit for its

purpose, free from design, coding and configuration errors,” and in conformance with SAP

specifications (MSA § 4, Clause 23.1); and (iii) perform all testing with “experienced, careful

and competent” personnel to ensure that the SAP system would comply with all specifications

(MSA § 6, Clause 34.1). Importantly, the MSA places the burden upon Wipro to conduct due

diligence and inquire as to the “accuracy and adequacy of any information supplied to it by or on

5
Cited herein are only some of the most critical Work Packs.

16
Case 1:17-cv-06997-CBA-RER Document 1 Filed 11/30/17 Page 17 of 35 PageID #: 17

behalf of National Grid” – no such requirement applies to National Grid with regard to

information supplied by Wipro. (MSA § 2, Clause 7.1(a).) Furthermore, Wipro specifically

acknowledged that it was aware that National Grid was relying upon its “expertise as an

experienced provider” of the services it was contracted to provide and further warranted that “all

information, representations and statements [it] communicated (whether in writing or

otherwise) . . . arising out of [its RFP Response] [were] true, complete and accurate in all

respects.” (MSA § 2, Clause 7.2; id. § 4, Clause 23.2(b).)

F. Wipro’s Performance Failures as Systems Integrator

49. Having induced National Grid into retaining it as Systems Integrator, Wipro’s

work on the Project over the following two years was marred by egregious performance failures.

Among other things, Wipro failed to: (i) staff the Project with qualified and experienced

consultants; (ii) properly design the system; (iii) properly build and configure the system;

(iv) adequately test the system; and (v) adequately convert National Grid’s data to the SAP

system. Wipro’s performance failures breached the MSA and numerous Work Packs, and

demonstrated the extent to which many of its pre-contract representations were false.

i. Wipro’s Failure to Staff the Project with Qualified Consultants

50. Underlying Wipro’s failures as Systems Integrator was its failure to meet one of

its core contractual obligations: providing National Grid with appropriately skilled and

experienced consultants. The consultants Wipro assigned to the Project were often incompetent,

inexperienced and/or incapable of managing an SAP implementation of the Project’s size and

scope.

51. Wipro’s consultants lacked the requisite skills, experience and expertise

concerning SAP software, industry standards of care and the U.S. utility industry, including with

respect to the applicable regulatory requirements and union rules. Directly contrary to its

17
Case 1:17-cv-06997-CBA-RER Document 1 Filed 11/30/17 Page 18 of 35 PageID #: 18

representations in its RFP Response, Wipro had virtually no experience at the time implementing

an SAP platform for utilities regulated in the U.S.

52. In many instances, Wipro failed to provide any consultants at all, much less those

who were sufficiently skilled and experienced. For example, during crucial Project phases,

Wipro’s team had vacancies in positions as vital as Program Director, Solution Architect and

Track Leads for Finance and HR. Wipro consultants also lacked a basic understanding of critical

Project areas, such as benefits, warehouse and inventory management, business planning or

budgeting consolidations, and accounts payable, requiring National Grid to demand stronger

resources. Wipro’s lack of appropriately skilled personnel became so acute that it had to hire

contractors to fill essential Project team roles.

53. In some instances, Wipro inexplicably reassigned crucial consultants off the

Project and onto engagements for other clients. The revolving door of Wipro consultants

severely disrupted the Project by depriving National Grid of Wipro personnel who had

familiarity with National Grid’s business processes and had prior involvement on the Project,

resulting in incomplete and ineffective training of replacement consultants, delays in project

tasks and inferior work product.

ii. Wipro’s Failures During the Design Phase

54. During the design phase of the Project, Wipro worked on, among other things:

(i) identifying and recording National Grid’s existing business processes, and formulating a

design for future business processes; (ii) identifying, mapping, and preparing functional and

technical specifications for the required interfaces between the SAP system and National Grid’s

other software systems that passed data to, and received data from, the SAP system; (iii) the

functional design of SAP Business Intelligence (“BI”); and (iv) generating other specifications,

business process flows, and related design documents.

18
Case 1:17-cv-06997-CBA-RER Document 1 Filed 11/30/17 Page 19 of 35 PageID #: 19

55. Wipro’s work with respect to the design of the system was deficient on almost

every level. For example, Wipro failed to gather and understand sufficient information about

National Grid’s U.S. business requirements to prepare appropriate functional and technical

specifications to support National Grid’s requirements. Contrary to its pre-contract

representations, Wipro’s U.K.-related work was not an applicable or appropriate design template

for the U.S. based utilities USFP. And not only did Wipro fail to successfully leverage its U.K.

experience, but it also failed to understand National Grid’s legacy systems so that it could

effectively leverage those processes that assimilated best with the new SAP system. Ultimately,

the fundamental failures in Wipro’s approach to the design of National Grid’s SAP system were

reflected in a host of design defects that became clear only after the system’s disastrous go-live,

as discussed further below.

iii. Wipro’s Failure to Properly Build and Configure the System

56. Wipro was also responsible for the build and configuration of National Grid’s

system, including the preparation of configuration documents detailing the system settings and

configuration values that would enable the SAP solution to support National Grid’s business

requirements. However, as a result of Wipro’s inability to adequately staff the Project, and its

general lack of knowledge of U.S. utilities and necessary understanding of National Grid’s

business processes, Wipro failed to provide the required deliverables.

57. Rather than build a system that accommodated National Grid’s required business

processes and avoided unnecessary changes, Wipro built an overly complex SAP solution that

was not configured pursuant to industry standards of care for an SAP implementation of the

Project’s size and complexity, and that did not efficiently, or in certain instances did not at all,

address National Grid’s actual and necessary business processes.

19
Case 1:17-cv-06997-CBA-RER Document 1 Filed 11/30/17 Page 20 of 35 PageID #: 20

58. Further, Wipro failed to understand the end-to-end National Grid processes, and

thus failed to advise on the ramifications changes it made in one area of the system might have

on another. Instead, abandoning its contractual responsibilities, Wipro defaulted to the role of

“builder,” and, even there, failed miserably. For example, Wipro’s coding work was deficient

and failed to conform to industry standards of care, including development standards related to

SAP’s programming language known as Advanced Business Application Programming

(“ABAP”). Among other things, Wipro’s coding: (i) lacked modularization such that its code

was not reusable elsewhere in the system, leading to inconsistencies in the code, difficulties in

maintaining the system, coding errors and a lack of traceability; (ii) lacked inline documentation,

reducing transparency and making it difficult to identify and resolve defects in the code; (iii) was

developed with an incorrect technical approach, resulting in increased maintenance expenses;

and (iv) did not account for a variety of different conditions and scenarios, leading to more

defects in the system.

iv. Wipro’s Failure to Adequately Test the System

59. Wipro also failed to adequately test the SAP system prior to system go-live. The

testing phase of any ERP implementation is critical, as it presents the opportunity to identify and

remedy any inherent design, configuration, programming or interface defects before the system

goes live – that is, before such inherent technical defects can cause substantial damage to an

organization or its customers.

60. Wipro was responsible for conducting much of the testing on the SAP system,

including build and unit testing (to determine whether the system configuration accurately met

business requirements), technical coding, preparation of most test plans, cases and scripts, and

configuration and maintenance of testing tools. (Work Packs 5491 and 6107.) Moreover, as

with all Project phases, the MSA required that Wipro perform its testing work with “experienced,

20
Case 1:17-cv-06997-CBA-RER Document 1 Filed 11/30/17 Page 21 of 35 PageID #: 21

careful and competent” personnel to ensure that the SAP system would comply with all

specifications. (MSA § 6, Clause 34.1.) But Wipro failed to do so, and Wipro’s testing of the

SAP system before it went live was deficient. By failing to advise on the industry standard

protocols and instead conducting minimal testing, Wipro ensured artificially positive results that

provided a misleading validation of the SAP system’s ability to accurately process payroll,

procurement and finance transactions, thereby allowing the problems that existed in the system

to go undetected.

v. Wipro Did Not Correctly Convert National Grid’s Data for the SAP System

61. Data conversion is the process by which data is converted from the legacy system

to the SAP system. Data conversion is a critical phase in any ERP project because if the data is

not converted correctly, the new SAP system will process incorrect file information resulting in

processing errors or other incorrect outputs from the SAP system.

62. On the USFP, Wipro failed to fulfill its responsibilities during the data extraction

process, including determining what data needed to be extracted from National Grid’s legacy

systems and converting and loading that data into the new SAP system. As was discovered after

go-live, in many instances Wipro did not convert and load National Grid’s legacy data into the

new SAP system correctly, sometimes loading entire data files that were corrupt. In other

instances, Wipro failed to follow best practices by moving through data conversion phases

without first resolving key errors that arose during prior phases of the conversion process.

Wipro’s data conversion failures led to a number of post-go-live problems for National Grid, and

required that National Grid spend substantial amounts of time and resources on “data cleansing”

after the system went live.

21
Case 1:17-cv-06997-CBA-RER Document 1 Filed 11/30/17 Page 22 of 35 PageID #: 22

G. Wipro’s Performance Failures and Related Misconduct


Inflict Massive Damages on National Grid

63. Immediately following go-live and for months thereafter, National Grid was

crippled by post-go-live problems caused by inherent design, configuration and testing failures in

the SAP system built by Wipro – defects that Wipro should have identified had it, among other

things, conducted appropriate testing. Specifically, inherent technical defects in the new SAP

system rendered National Grid unable to operate its core functions relating to payroll, supply

chain and procurement, accounts payable, and financial close and reporting. Wipro’s failures

caused National Grid to suffer hundreds of millions of dollars in damages.

i. Payroll

64. The first series of payrolls processed after go-live were plagued by errors. As an

initial matter, payroll programs that took a few hours to run on National Grid’s legacy payroll

systems took weeks to run on the new SAP system (in part due to the flawed design of National

Grid’s SAP in-house cash module). And, as a result of system defects, employees could not

access payroll-related web portals at peak times. Employees attempting to log into these portals

– the primary gateways for payroll entry and time approval – were met with error messages.

65. The payroll system itself was riddled with defects, as payroll amounts were

wrong, causing harm to National Grid and its employees. National Grid was not able to pay its

employees on time and in accurate amounts, as employees were underpaid, overpaid or not paid

at all. National Grid’s union workforce was overpaid by approximately $8 million, a loss that

National Grid ultimately had to absorb. The system was incorrectly computing essential

information, including tax, benefit and pension deductions, union dues, and 401(k) and

garnishment withholdings, some of which deduct amounts from employees’ pay pursuant to

court-ordered obligations.

22
Case 1:17-cv-06997-CBA-RER Document 1 Filed 11/30/17 Page 23 of 35 PageID #: 23

66. There were also significant issues with the live checks and direct deposits that

were issued to employees. For example, live checks were incorrectly mailed by overnight mail,

costing exorbitant amounts in overnight shipping expenses. On the other hand, paychecks that

should have been deposited into live checking accounts were deposited into employees’

previously replaced or closed checking or savings accounts. In addition, many employees

received checks that either did not belong to them or were made in the wrong amount.

67. In addition, the defective SAP system could not process employees’ Form W-2s.

National Grid was forced to request a 30-day extension from the IRS for W-2 filings in order to

generate W-2s for numerous employees. National Grid was also forced to outsource the

production and delivery of such statements.

68. Wipro’s flawed build and configuration with respect to role-to-position mapping

and organizational hierarchy prevented National Grid users from being able to access the new

SAP system. For example, at the time of go-live, National Grid supervisors did not have the

ability to delete payroll or to run reports, and approvals for purchases of materials, sick, vacation

and/or overtime pay were being incorrectly sent to managers for approval related to employees

that they did not know or supervise.

69. In the face of these payroll issues, National Grid was forced to engage numerous

vendors to identify the root causes of the problems, respond to the overwhelming employee

payroll inquiries and help to develop a remediation plan. It took over two years to stabilize the

system and remediate the SAP system’s inherent payroll-related design, configuration and

programming defects.

23
Case 1:17-cv-06997-CBA-RER Document 1 Filed 11/30/17 Page 24 of 35 PageID #: 24

ii. Supply Chain and Procurement

70. System defects also permeated the supply chain and procurement applications of

the new SAP system. Within weeks after go-live, the SAP system could not properly run

National Grid’s business processes for paying vendors. By January 2013, the backlog of unpaid

invoices exceeded 15,000, caused in part by data corruption that generated inaccurate vendor

invoices.

71. Unable to obtain the supplies it needed to service its customers and run its

operations, National Grid had to prematurely pay vendors, in estimated amounts, to ensure that

they would continue to supply National Grid with required materials. These pre-payments

resulted in reconciliation problems when National Grid had to subsequently determine amounts

that were advanced to vendors in excess of what was actually owed. In other instances, National

Grid unknowingly paid vendors for the same invoice multiple times, which took extensive

research and effort to uncover and correct.

72. National Grid also faced critical issues with respect to its ability to pay the

vendors who supplied its warehouses. Months after go-live, National Grid’s ability to process

pay cycles to make payments to vendors, as well as its ability to reconcile cashed checks, were

crippled by SAP system errors.

73. Moreover, after go-live, the SAP system was unable to detect whether or not a

check sent to a vendor or customer had been cashed. As a result, a cash reconciliation team had

to be formed to contact banks to determine whether checks were actually cashed or not. This

encashment problem forced National Grid to write-off approximately $3 million on

approximately 40,000 checks that were cashed or voided in error.

24
Case 1:17-cv-06997-CBA-RER Document 1 Filed 11/30/17 Page 25 of 35 PageID #: 25

iii. Financial Close and Reporting

74. As a public utility, National Grid’s financial statements are subject to intense

scrutiny by various regulators. As a result, National Grid’s financial close processes – its ability

to generate timely and accurate financial statements within a reasonable period of time after the

month has ended – are central to its viability as an ongoing concern. In addition, like any

organization, National Grid depends on timely and accurate financial statements to appropriately

service its customers, manage its workforce, make informed decisions about its operations, and

fund those operations through borrowing and other financial transactions. Some of the debt and

other financial instruments on which National Grid relies to fund its operations explicitly require

timely and accurate financial statements.

75. Following go-live, National Grid experienced extreme delays in its financial close

and reporting processes, which jeopardized its ability to carry out each of the functions discussed

above. For months, neither National Grid nor its auditors could rely on the integrity of the data

generated by its new SAP accounting management systems. National Grid was therefore forced

to repeatedly delay issuing critical financial and regulatory reports (both state and federal)

regarding its financial status, drawing penalties from its regulators and jeopardizing its relations

with lenders.

76. The financial close delays after go-live were stunning: whereas National Grid

typically performed its monthly financial close in 4 working days, the first financial close after

go-live took 43 working days. These delays were caused by (among other things): (i) the

instability and defects in the SAP system; (ii) inaccurate data conversion and lack of data

capacity; (iii) defective application interfaces; and (iv) the cascading effects of the payroll and

supply chain issues described above.

25
Case 1:17-cv-06997-CBA-RER Document 1 Filed 11/30/17 Page 26 of 35 PageID #: 26

77. Nor could National Grid take advantage of certain attributes of the SAP solution

that are designed to enhance an organization’s financial close and reporting capabilities. The

system’s flawed mapping and related design defects prevented National Grid from benefitting

from the SAP FERC module, which addresses unique accounting requirements set by FERC for

public utilities like National Grid. For more than a year after go-live, National Grid was unable

to use the SAP FERC module to process the extensive financial reports it must regularly provide

to FERC, and the company was forced to seek numerous extensions from its regulators. FERC

also denied National Grid the ability to engage in short-term borrowing from banks due to the

company’s inability to file FERC financial reports. The problems with the SAP FERC module

should have been readily evident during testing, but Wipro never tested the module and none of

the problems were discovered until after go-live.

H. Stabilization and Remediation

78. To deal with the numerous post-go-live problems, National Grid launched the

USFP Stabilization Program and was forced to engage hundreds of third-party vendors to fix the

system problems caused by and/or missed as a product of Wipro’s performance and testing

failures. Specifically, teams were assembled in major areas affected by the SAP implementation

to address specific system issues.

79. The first priority of the company’s stabilization efforts was to ensure that it was

compliant with its obligations, including: (i) paying employees accurately and timely; (ii) paying

outside vendors accurately and timely; and (iii) providing legal, regulatory and other reports to

external stakeholders that were accurate and timely.

80. To address the numerous payroll issues, among other things, a Payroll

Improvement Team consisting of internal personnel and vendor partner experts was quickly

deployed and had to work seven days a week in order to respond to employee issues and

26
Case 1:17-cv-06997-CBA-RER Document 1 Filed 11/30/17 Page 27 of 35 PageID #: 27

questions. The Transaction Delivery Center, which provided employee services, also had to

remain open seven days a week with extended hours from early November 2012 through mid-

February 2013. Additionally, payroll clinics in 53 field locations across National Grid’s U.S.

footprint had to be established, and significant additional time entry training was provided to

employees.

81. National Grid also implemented several programs to assist employees who were

affected by the payroll issues and were not receiving paychecks. A cash advance debit card

program of up to $2,000 per employee was made available to all affected employees. Those

employees whose court-mandated payments were affected or who had urgent issues were

provided with immediate financial assistance. A large portion of the money that was distributed

through this program resulted in overpayments to employees that were never recouped.

82. Another stabilization priority was to enable National Grid to be self-sufficient in

operating the new SAP system, while being able to realize the benefits it was supposed to

deliver, without significant reliance on external support. By September 2013, the continuing

efforts to stabilize the new SAP system cost approximately $30 million per month, totaling over

$300 million. As of August 2013, there were still approximately 321 external resources

contracted, and full SAP stabilization was not achieved until approximately September 2014.

I. Wipro Admits its Performance Failures on USFP

83. National Grid leads were dismayed by Wipro’s slow and poor performance

following the disastrous go-live. Wipro consultants themselves even acknowledged that that they

could not fix crucial issues with the new system. As a result of Wipro’s shortcoming in BI

reporting, finance, and payroll, National Grid was forced to turn to other vendor consultants from

SAP and Deloitte (who returned to the Project after go-live to identify and fix problems) to

27
Case 1:17-cv-06997-CBA-RER Document 1 Filed 11/30/17 Page 28 of 35 PageID #: 28

resolve system defects. In many instances, functional and technical specifications had to be re-

written and SAP modules had to be re-built.

84. As the post-go-live problems intensified, key Wipro consultants, who worked on

National Grid’s system pre-go-live and who had gained institutional knowledge about National

Grid’s business processes, were taken off the Project to work for other clients. When National

Grid leadership demanded that Wipro bring certain of such consultants back, Wipro

acknowledged that it made significant errors, and further admitted that Wipro’s USFP

consultants lacked the requisite experience and expertise required to successfully implement the

Project. Nevertheless, despite Wipro’s incompetence following go-live, National Grid was

required to keep Wipro in place since Wipro alone had full access to the SAP system and was

integral to maintenance of the system moving forward.

85. After go-live, National Grid was also forced to undergo significant re-testing of

its system. Even after National Grid was crippled by its defect-riddled SAP system, and after

certain remediations were complete, Wipro’s tests were still reporting that the system was

operating smoothly. However, when other consultants tested the same processes, they were

finding significantly different results and numerous defects. For example, when Deloitte re-

tested Wipro’s test scripts, it uncovered twice the number of defects in the areas of procurement

and supply chain. Nor were these additional defects minor: for example, when re-testing certain

test scripts, Deloitte uncovered an $8,000 receipt that was recorded in the system as an

$880 million receipt – an error that Wipro somehow never detected. Deloitte continued to re-test

Wipro’s test scripts through several other system releases that were necessary to fix the system

issues. With each additional release, Deloitte’s results were the same: it uncovered many

28
Case 1:17-cv-06997-CBA-RER Document 1 Filed 11/30/17 Page 29 of 35 PageID #: 29

system defects that Wipro failed to uncover, even though Wipro had reported all of its original

test results as “passing” or “adequate.”

J. National Grid’s Damages

86. National Grid suffered significant damages as a result of Wipro’s misconduct,

including hundreds of millions of dollars in vendor fees paid post-go-live (of which

approximately $69 million were paid to Wipro).

CAUSES OF ACTION

FIRST CAUSE OF ACTION


(Fraudulent Inducement)

87. National Grid incorporates by reference all of the preceding paragraphs as if fully

set forth herein.

88. As set forth above, Wipro made numerous pre-contract misrepresentations of

material facts, and failed to disclose material facts to National Grid regarding, among other

things, Wipro’s purported abilities, skills, experience, expertise, consultants, qualifications,

credentials and ability to perform and provide services in connection with the USFP. Such

representations were false, and Wipro knew, or recklessly disregarded, that such statements were

false at the time they were made.

89. Specifically, in its February 17, 2010 response to National Grid’s RFP, Wipro

misrepresented its skills and experience in order to induce National Grid into hiring Wipro as its

ODC partner on the Project. Wipro also misrepresented its experience with U.S. utility

companies and its ability to leverage work, knowledge, and best practices it had acquired from

MySAP and GDFO. In truth, Wipro had limited, or virtually no, experience implementing an

SAP platform for a regulated utility company in the United States.

29
Case 1:17-cv-06997-CBA-RER Document 1 Filed 11/30/17 Page 30 of 35 PageID #: 30

90. Moreover, Wipro’s pre-contractual representations concerning Wipro’s alleged

ability and intent to furnish National Grid with appropriately experienced and skilled consultants

were materially false and misleading. Wipro induced National Grid to hire Wipro by specifically

representing that it had the ability and intent to assign competent resources experienced with the

U.S. utilities industry to the Project. In fact, however, Wipro had neither the ability nor the

intent to assign such personnel to the Project.

91. Wipro made these pre-contractual representations and concealed these material

facts in order to induce National Grid to hire Wipro.

92. National Grid reasonably relied upon Wipro’s misrepresentations in its response

to National Grid’s RFP, which led National Grid to hire Wipro as ODC partner and later give

Wipro a much larger role on the Project as Systems Integrator. Had National Grid known the

truth, it would not have hired Wipro in the first place.

93. As a direct and proximate result of Wipro’s fraud and deceit, National Grid

sustained damages in an amount to be determined by the trier of fact.

WHEREFORE, National Grid prays for relief as set forth below.

SECOND CAUSE OF ACTION


(Breach of Contract)

94. National Grid incorporates by reference all of the preceding paragraphs as if fully

set forth herein.

95. The MSA and related Work Packs are valid, enforceable contracts.

96. National Grid has performed, or has substantially performed, any and all

necessary conditions precedent, dependent obligations, and/or dependent covenants owed under

the MSA and related Work Packs. National Grid is, and has been, entitled to Wipro’s

performance of its obligations under these contracts.

30
Case 1:17-cv-06997-CBA-RER Document 1 Filed 11/30/17 Page 31 of 35 PageID #: 31

97. Wipro unilaterally and materially breached its contractual obligations to National

Grid, including the express terms and covenants and/or implied covenants set forth or implied

within the MSA and related Work Packs, as described above.

98. Wipro’s breaches of contract include, among other things: (i) failure to prepare

adequate and appropriate blueprint and design documents, including functional and technical

specifications pursuant to industry standards of care; (ii) failure to perform appropriate

configuration and programming pursuant to industry standards of care; (iii) failure to apply and

adhere to acceptable industry testing practices and adequately detect and forewarn of problems

with the system to ensure the system’s functionality and stability; and (iv) failure to advise that

the system was not ready to go live.

99. Because Wipro’s breach of its obligations arose from its gross negligence and/or

willful misconduct, National Grid is entitled to indirect, consequential and other damages in

addition to contract damages.

100. As a direct result of Wipro’s breach of the MSA and Work Packs, National Grid

sustained damages in an amount to be determined by the trier of fact.

WHEREFORE, National Grid prays for relief as set forth below.

THIRD CAUSE OF ACTION


(Breach of Express and Implied Warranties)

101. National Grid incorporates by reference all of the preceding paragraphs as if fully

set forth herein.

102. Among other things, Wipro’s utter lack of competence breached the MSA’s

express warranty that Wipro would exercise “the degree of skill, care, professional judgment,

prudence and foresight which would be expected from the top 25% of companies who are

31
Case 1:17-cv-06997-CBA-RER Document 1 Filed 11/30/17 Page 32 of 35 PageID #: 32

expert[s] and experienced in conducting the same type of undertaking that provides the same or

similar services as those Services.” (MSA § 1; id. at § 2, Clause 4.1(a).)

103. Wipro also breached the MSA’s express warranty that it would provide

consultants that were “suitably qualified, skilled, honest, experienced and trained in the work

which they are to perform.” (MSA § 5, Clause 27.3(b).) Despite this warranty, Wipro assigned

consultants to the Project that completely lacked the requisite knowledge and skills to

successfully perform the required services or deliver an SAP system capable of meeting National

Grid’s business requirements.

104. Wipro also materially breached other express and implied warranties contained

within the MSA and Work Packs relating to the quality, performance, cost, design, integration,

testing and/or consulting services it contracted to provide National Grid.

105. As a direct consequence of Wipro’s breaches of express and implied warranties,

National Grid sustained damages in an amount to be determined by the trier of fact.

WHEREFORE, National Grid prays for relief as set forth below.

FOURTH CAUSE OF ACTION


(Negligent Misrepresentation)

106. National Grid incorporates by reference all of the preceding paragraphs as if fully

set forth herein.

107. In order to induce National Grid to enter into the MSA and related Work Packs,

Wipro made numerous false and misleading representations about its ability, skills, experience

and expertise to perform the services requested by National Grid.

108. Wipro made these representations without reasonable grounds for believing they

were true and in a manner not warranted by the information in Wipro’s possession. For example,

Wipro had no reasonable grounds for claiming that it had significant experience with U.S. utility

32
Case 1:17-cv-06997-CBA-RER Document 1 Filed 11/30/17 Page 33 of 35 PageID #: 33

companies such that it could handle an implementation of National Grid’s complexity and

magnitude.

109. Wipro’s negligent misrepresentations were made with the intent that National

Grid rely on them. Indeed, based upon Wipro’s prior work and knowledge that National Grid

trusted Wipro’s abilities, as evidenced by National Grid’s agreement to allow Wipro sole access

to its system and maintenance of the system, Wipro and National Grid had a special relationship

of trust. Further, Wipro alone had knowledge of the fact that its consultants did not have the

requisite experience or expertise to provide the promised services. Aware of National Grid’s

trust in its relationship with Wipro, Wipro made these misrepresentations to induce National

Grid to enter into the MSA and related Work Packs. National Grid reasonably relied on Wipro’s

misrepresentations when it, among other things, entered into the MSA and Work Packs, did not

terminate the MSA and Work Packs, and continued to pay Wipro during the terms of the MSA

and Work Packs.

110. National Grid’s reliance on Wipro’s negligent misrepresentations caused National

Grid to sustain damages in an amount to be determined by the trier of fact.

WHEREFORE, National Grid prays for relief as set forth below.

FIFTH CAUSE OF ACTION


(Violation of GBL Section 349)

111. National Grid incorporates by reference all of the preceding paragraphs as if fully

set forth herein.

112. New York General Business Law (“GBL”) Section 349 prohibits deceptive acts

and practices in the conduct of any business, trade, or commerce or in the furnishing of any

service in this state.

33
Case 1:17-cv-06997-CBA-RER Document 1 Filed 11/30/17 Page 34 of 35 PageID #: 34

113. Wipro violated GBL Section 349 by engaging in deceptive acts and practices in

the conduct of its businesses, including making false representations to National Grid that each

possessed the ability, skills, experience, expertise, resources, qualifications, credentials and

ability to perform and provide services in connection with the design, build and implementation

of the SAP software system, when Wipro knew or should have known that they did not have the

requisite skills, resources, expertise and experience needed.

114. National Grid has suffered actual injury by virtue of Wipro’s unlawful, unfair and

fraudulent acts.

WHEREFORE, National Grid prays for relief as set forth below.

JURY DEMAND

National Grid hereby demands a trial by jury on all issues so triable.

PRAYER FOR RELIEF

WHEREFORE, National Grid respectfully requests that this Court enter judgment

against Wipro, and provide the following relief:

(a) Rescission of the MSA and related Work Packs;

(b) Actual, indirect, economic, consequential and compensatory damages

against Wipro in an amount to be determined at trial;

(c) Restitution of all amounts paid by National Grid to Wipro;

(d) Punitive and/or exemplary damages;

(e) Reasonable and necessary attorney’s fees;

(f) Pre- and post-judgment interest at the maximum rate allowed by law;

(g) All costs of suit; and

34
Case 1:17-cv-06997-CBA-RER Document 1 Filed 11/30/17 Page 35 of 35 PageID #: 35

(h) All such further relief, both general and special, at law or in equity, to

which National Grid may show itself justly to be entitled or as this Court

may deem appropriate.

Dated: November 30, 2017


New York, New York
KASOWITZ BENSON TORRES LLP

By: /s/ Mark P. Ressler


Mark P. Ressler
([email protected])
Kim Conroy
([email protected])
Trevor J. Welch
([email protected])
Gavin D. Schryver
([email protected])

1633 Broadway
New York, New York 10019
Tel. (212) 506-1700

Attorneys for National Grid USA Service Company, Inc.

35
Case 1:17-cv-06997-CBA-RER Document 1-1 Filed 11/30/17 Page 1 of 2 PageID #: 36
JS 44 (Rev. CIVIL COVER SHEET
The JS 44 civil cover sheet and the information contained herein neither replace nor supplement the filing and service of pleadings or other papers as required by law, except as
provided by local rules of court. This form, approved by the Judicial Conference of the United States in September 1974, is required for the use of the Clerk of Court for the
purpose of initiating the civil docket sheet. (SEE INSTRUCTIONS ON NEXT PAGE OF THIS FORM.)

I. (a) PLAINTIFFS DEFENDANTS


NATIONAL GRID USA SERVICE COMPANY, INC. WIPRO LIMITED

(b) County of Residence of First Listed Plaintiff Middlesex County, MA County of Residence of First Listed Defendant Bangalore, India
(EXCEPT IN U.S. PLAINTIFF CASES) (IN U.S. PLAINTIFF CASES ONLY)
NOTE: IN LAND CONDEMNATION CASES, USE THE LOCATION OF
THE TRACT OF LAND INVOLVED.

(c) Attorneys (Firm Name, Address, and Telephone Number) Attorneys (If Known)
Mark P. Ressler
KASOWITZ BENSON TORRES LLP
1633 Broadway, NY, NY 10019 / 212-506-1700
II. BASIS OF JURISDICTION (Place an “X” in One Box Only) III. CITIZENSHIP OF PRINCIPAL PARTIES (Place an “X” in One Box for Plaintiff
(For Diversity Cases Only) and One Box for Defendant)
1 U.S. Government 3 Federal Question PTF DEF PTF DEF
Plaintiff (U.S. Government Not a Party) Citizen of This State 1 1 Incorporated or Principal Place 4 4
of Business In This State

2 U.S. Government 4 Diversity Citizen of Another State 2 2 Incorporated and Principal Place 5 5
Defendant (Indicate Citizenship of Parties in Item III) of Business In Another State

Citizen or Subject of a 3 3 Foreign Nation 6 6


Foreign Country
IV. NATURE OF SUIT (Place an “X” in One Box Only) Click here for: Nature of Suit Code Descriptions.
CONTRACT TORTS FORFEITURE/PENALTY BANKRUPTCY OTHER STATUTES
110 Insurance PERSONAL INJURY PERSONAL INJURY 625 Drug Related Seizure 422 Appeal 28 USC 158 375 False Claims Act
120 Marine 310 Airplane 365 Personal Injury - of Property 21 USC 881 423 Withdrawal 376 Qui Tam (31 USC
130 Miller Act 315 Airplane Product Product Liability 690 Other 28 USC 157 3729(a))
140 Negotiable Instrument Liability 367 Health Care/ 400 State Reapportionment
150 Recovery of Overpayment 320 Assault, Libel & Pharmaceutical PROPERTY RIGHTS 410 Antitrust
& Enforcement of Judgment Slander Personal Injury 820 Copyrights 430 Banks and Banking
151 Medicare Act 330 Federal Employers’ Product Liability 830 Patent 450 Commerce
152 Recovery of Defaulted Liability 368 Asbestos Personal 835 Patent - Abbreviated 460 Deportation
Student Loans 340 Marine Injury Product New Drug Application 470 Racketeer Influenced and
(Excludes Veterans) 345 Marine Product Liability 840 Trademark Corrupt Organizations
153 Recovery of Overpayment Liability PERSONAL PROPERTY LABOR SOCIAL SECURITY 480 Consumer Credit
of Veteran’s Benefits 350 Motor Vehicle 370 Other Fraud 710 Fair Labor Standards 861 HIA (1395ff) 490 Cable/Sat TV
160 Stockholders’ Suits 355 Motor Vehicle 371 Truth in Lending Act 862 Black Lung (923) 850 Securities/Commodities/
190 Other Contract Product Liability 380 Other Personal 720 Labor/Management 863 DIWC/DIWW (405(g)) Exchange
195 Contract Product Liability 360 Other Personal Property Damage Relations 864 SSID Title XVI 890 Other Statutory Actions
196 Franchise Injury 385 Property Damage 740 Railway Labor Act 865 RSI (405(g)) 891 Agricultural Acts
362 Personal Injury - Product Liability 751 Family and Medical 893 Environmental Matters
Medical Malpractice Leave Act 895 Freedom of Information
REAL PROPERTY CIVIL RIGHTS PRISONER PETITIONS 790 Other Labor Litigation FEDERAL TAX SUITS Act
210 Land Condemnation 440 Other Civil Rights Habeas Corpus: 791 Employee Retirement 870 Taxes (U.S. Plaintiff 896 Arbitration
220 Foreclosure 441 Voting 463 Alien Detainee Income Security Act or Defendant) 899 Administrative Procedure
230 Rent Lease & Ejectment 442 Employment 510 Motions to Vacate 871 IRS—Third Party Act/Review or Appeal of
240 Torts to Land 443 Housing/ Sentence 26 USC 7609 Agency Decision
245 Tort Product Liability Accommodations 530 General 950 Constitutionality of
290 All Other Real Property 445 Amer. w/Disabilities - 535 Death Penalty IMMIGRATION State Statutes
Employment Other: 462 Naturalization Application
446 Amer. w/Disabilities - 540 Mandamus & Other 465 Other Immigration
Other 550 Civil Rights Actions
448 Education 555 Prison Condition
560 Civil Detainee -
Conditions of
Confinement
V. ORIGIN (Place an “X” in One Box Only)
1 Original 2 Removed from 3 Remanded from 4 Reinstated or 5 Transferred from 6 Multidistrict 8 Multidistrict
Proceeding State Court Appellate Court Reopened Another District Litigation - Litigation -
(specify) Transfer Direct File
Cite the U.S. Civil Statute under which you are filing (Do not cite jurisdictional statutes unless diversity):
28 U.S. Code 1332
VI. CAUSE OF ACTION Brief description of cause:
Fraud, breach of contract, and other misconduct.
VII. REQUESTED IN CHECK IF THIS IS A CLASS ACTION DEMAND $ CHECK YES only if demanded in complaint:
COMPLAINT: UNDER RULE 23, F.R.Cv.P. To be determined at trial. JURY DEMAND: Yes No
VIII. RELATED CASE(S)
(See instructions):
IF ANY JUDGE DOCKET NUMBER
DATE SIGNATURE OF ATTORNEY OF RECORD
11/30/2017 /s/ Mark P. Ressler
FOR OFFICE USE ONLY

RECEIPT # AMOUNT APPLYING IFP JUDGE MAG. JUDGE


Case 1:17-cv-06997-CBA-RER Document 1-1 Filed 11/30/17 Page 2 of 2 PageID #: 37
CERTIFICATION OF ARBITRATION ELIGIBILITY
Local Arbitration Rule 83.10 provides that with certain exceptions, actions seeking money damages only in an amount not in excess of $150,000,
exclusive of interest and costs, are eligible for compulsory arbitration. The amount of damages is presumed to be below the threshold amount unless a
certification to the contrary is filed.

I, __________________________________________,
Mark P. Ressler counsel for____________________________,
NATIONAL GRID USA SERVICE COMPANY, INC. do hereby certify that the above captioned civil action

is ineligible for compulsory arbitration for the following reason(s):

monetary damages sought are in excess of $150,000, exclusive of interest and costs,

the complaint seeks injunctive relief,

the matter is otherwise ineligible for the following reason

DISCLOSURE STATEMENT - FEDERAL RULES CIVIL PROCEDURE 7.1


Identify any parent corporation and any publicly held corporation that owns 10% or more or its stocks:
Please see the Rule 7.1 Corporate Disclosure Statement on Behalf of National Grid USA Service
Company, Inc., filed concurrently herewith.

RELATED CASE STATEMENT (Section VIII on the Front of this Form)


Please list all cases that are arguably related pursuant to Division of Business Rule 50.3.1 in Section VIII on the front of this form. Rule 50.3.1 (a) provides that “A civil case is “related”
to another civil case for purposes of this guideline when, because of the similarity of facts and legal issues or because the cases arise from the same transactions or events, a
substantial saving of judicial resources is likely to result from assigning both cases to the same judge and magistrate judge.” Rule 50.3.1 (b) provides that “ A civil case shall not be
deemed “related” to another civil case merely because the civil case: (A) involves identical legal issues, or (B) involves the same parties.” Rule 50.3.1 (c) further provides that
“Presumptively, and subject to the power of a judge to determine otherwise pursuant to paragraph (d), civil cases shall not be deemed to be “related” unless both cases are still
pending before the court.”

NY-E DIVISION OF BUSINESS RULE 50.1(d)(2)

1.) Is the civil action being filed in the Eastern District removed from a New York State Court located in Nassau or Suffolk
County? Yes X No

2.) If you answered “no” above:


a) Did the events or omissions giving rise to the claim or claims, or a substantial part thereof, occur in Nassau or Suffolk
County? Yes No

b) Did the events or omissions giving rise to the claim or claims, or a substantial part thereof, occur in the Eastern
District? Yes No

c) If this is a Fair Debt Collection Practice Act case, specify the County in which the offending communication was
received:______________________________.

If your answer to question 2 (b) is “No,” does the defendant (or a majority of the defendants, if there is more than one) reside in Nassau or
Suffolk County, or, in an interpleader action, does the claimant (or a majority of the claimants, if there is more than one) reside in Nassau or
Suffolk County?___________________________________
(Note: A corporation shall be considered a resident of the County in which it has the most significant contacts).

BAR ADMISSION

I am currently admitted in the Eastern District of New York and currently a member in good standing of the bar of this court.

Yes No

Are you currently the subject of any disciplinary action (s) in this or any other state or federal court?

Yes (If yes, please explain No

I certify the accuracy of all information provided above.


/s/ Mark P. Ressler
Signature: ____________________________________________________
Case 1:17-cv-06997-CBA-RER Document 1-2 Filed 11/30/17 Page 1 of 2 PageID #: 38

AO 440 (Rev. 06/12) Summons in a Civil Action

UNITED STATES DISTRICT COURT


for the
Eastern District
__________ of of
District New York
__________

)
)
NATIONAL GRID USA SERVICE COMPANY, INC. )
)
Plaintiff(s) )
)
v. Civil Action No. 1:17-cv-6997
)
)
)
WIPRO LIMITED )
)
Defendant(s) )

SUMMONS IN A CIVIL ACTION

To: (Defendant’s name and address)


Wipro Limited
Doddakannelli Sarjapur Road
Bangalore, Karnataka
560 035 India

A lawsuit has been filed against you.

Within 21 days after service of this summons on you (not counting the day you received it) — or 60 days if you
are the United States or a United States agency, or an officer or employee of the United States described in Fed. R. Civ.
P. 12 (a)(2) or (3) — you must serve on the plaintiff an answer to the attached complaint or a motion under Rule 12 of
the Federal Rules of Civil Procedure. The answer or motion must be served on the plaintiff or plaintiff’s attorney,
whose name and address are:
Mark P. Ressler
KASOWITZ BENSON TORRES LLP
1633 Broadway
New York, New York 10019

If you fail to respond, judgment by default will be entered against you for the relief demanded in the complaint.
You also must file your answer or motion with the court.

CLERK OF COURT

Date: 11/30/2017
Signature of Clerk or Deputy Clerk
Case 1:17-cv-06997-CBA-RER Document 1-2 Filed 11/30/17 Page 2 of 2 PageID #: 39

AO 440 (Rev. 06/12) Summons in a Civil Action (Page 2)

Civil Action No.

PROOF OF SERVICE
(This section should not be filed with the court unless required by Fed. R. Civ. P. 4 (l))

This summons for (name of individual and title, if any)


was received by me on (date) .

I personally served the summons on the individual at (place)


on (date) ; or

I left the summons at the individual’s residence or usual place of abode with (name)
, a person of suitable age and discretion who resides there,
on (date) , and mailed a copy to the individual’s last known address; or

I served the summons on (name of individual) , who is


designated by law to accept service of process on behalf of (name of organization)
on (date) ; or

I returned the summons unexecuted because ; or

Other (specify):
.

My fees are $ for travel and $ for services, for a total of $ 0.00 .

I declare under penalty of perjury that this information is true.

Date:
Server’s signature

Printed name and title

Server’s address

Additional information regarding attempted service, etc:

You might also like