MS SAPT Transformer Testing

The document provides a method statement for testing transformers. It outlines the testing equipment required, manpower needs, detailed work procedures including insulation resistance testing, winding resistance measurement, ratio measurement and high voltage testing. It also describes the risk assessment and necessary personal protective equipment.

Uploaded by

Fareh Khan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
80 views7 pages

MS SAPT Transformer Testing

The document provides a method statement for testing transformers. It outlines the testing equipment required, manpower needs, detailed work procedures including insulation resistance testing, winding resistance measurement, ratio measurement and high voltage testing. It also describes the risk assessment and necessary personal protective equipment.

Uploaded by

Fareh Khan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 7

Page: 1/7

Method Statement for Transformer Testing


Method Statement title. CT Testing at SAPT
Method Statement No. SAPT/2
Revision No. 00
Date of Issue. 2/10/2019

Owner/Client Consultant Primary contractor Contractor/ Job


Performer
Logo:

SAPT HALCROW CHEC

Approved by: Reviewed by: Reviewed by: Prepared by:


Name - Abdul Fareh khan

Designation: Designation: Designation: Designation:


Executive Engineer

Location of Work (as specific as possible)

Site Name: SAPT


Specific Location of task: SAPT Phase II

Description of Work: (Title)


Method Statement for testing of Transformers.

Start of work date 10/10/2019 Expected Duration of work 2 days


Risk prediction completed and reviewed? Yes 
Page: 2/7
Method Statement for Transformer Testing

Table of Contents
1 Introduction ..................................................................................................................... 3
2 Scope .............................................................................................................................. 3
3 Testing Equipment Required ............................................... Error! Bookmark not defined.
4 Method of execution of Activity ......................................................................................... 3
4.1 Manpower Requirement ............................................................................................. 3
4.2 Detailed Work Procedure............................................. Error! Bookmark not defined.
4.3 Risk Assessment........................................................................................................ 6
5 HSE Plan ......................................................................................................................... 6
5.1 Emergency Procedure ................................................................................................ 6
5.2 Personal Protective Equipment .................................................................................... 7
5.3 Responsible Personel ................................................................................................. 7
Page: 3/7
Method Statement for Transformer Testing
1 Introduction
This method statement has been developed to comply with client’s requirements and will serve
as technical guidelines to the testing of Transformer Testing. This method statement will serve
for SAPT Phase II. This method statement is with reference to client’s specifications, quality
procedures and other related standards.

2 Scope
Transformer Testing

3 Test Equipment Required


The following equipment will be used for the scope of work covered under this method of
statement
1- Insulation Tester
2- Turn Ratio Tester
3- Hi-Pot Tester
4- Winding Resistance Tester
5- Three Phase Supply

4 Method for execution of Activity


4.1 Manpower Requirement
1- Testing Engineer
2- Technicians
3- Helpers
All the power tools and testing equipments will be operated by competent persons.
Page: 4/7
Method Statement for Transformer Testing
4.2 Detailed Work Procedure
1- Mechanical Check and Visual Inspection

1. Verify nameplate ratings are in accordance with the approved drawings and specifications.
2. Inspect for physical damage/ defects and mechanical condition.
3. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench
method.
4. Verify earth connections.
5. Labels/Marking Rating Plate Correctness Checks.

2- Insulation Resistance Test

The voltage shall be applied between:


1. Primary to secondary.
2. Secondary to ground.
3. Primary to ground.
Test voltage limits mentioned in table below. The ambient temperature shall be noted down during
test.

Table – Test Voltage Limits


Rated voltage Test voltage
100-1000V AC/DC 1000V DC
>1000 to 5000V 5000V DC

3- Winding Resistance Measurement

Winding Resistance test is to confirm that the measured resistance of HV and LV windings must
match the factory test results; this resistance is measured with a ohm meter.
- Ensure the contacts at the bushing are clean.
- Hold the sensing probes across the conduct between with the contact resistance is to be
measured (Test Current 5A DC)
- Observe the reading and record in the test format.
Page: 5/7
Method Statement for Transformer Testing
4- Ratio Measurement
- Ensure that both the Primary and Secondary windings are not connected to any cables/ Bus bar.
- Ensure that Tap Changer in the lowest tap position.
- Apply three phase supply voltage (415 V AC) across the Primary Termination of the
Transformer.
- Measure the secondary (LV) voltage at the LV Termination, Observe the reading and record the
test format.
- If the tap changer is OFF load type, switch of the power supply and rise on step and apply the
three Phase 415 V AC at primary winding, and measure the voltage at the secondary winding.
- The above step to be carried out until the highest tap.
Alternatively, test is performed with a digital ratio meter which measures the ratio value of the
transformer and simultaneously checks the vector group and the polarity.

5- High Voltage Test

Objective of HV test is to determine the equipment is in proper condition to put in service, after
installation for which it was designed and to give some basis for predicting whether or not that a
healthy condition will remain or if deterioration is underway which can result in abnormally short
life.

Test Instruments Required for HV Test


Calibrated VLF hi-pot test set for switchgear with leakage current indicator and overload protection.

6- Vector Group Checks

- Ensure that both the Primary and Secondary windings are not connected to any cables/Bus Bar.

- Connect the “R” phase of the Primary winding and the “R” phase of the Secondary winding
(Short R phase of primary and secondary termination).

- Apply 3 Phase supply voltage (415 V AC) across the Primary Termination of the Transformer.
Measure the voltage at the both primary and secondary termination at all the phases. Observe
the reading and record in the test format.
Page: 6/7
Method Statement for Transformer Testing
4.3 Risk Assessment
The contractor should control all and not limited to the following listed hazards during the
testing
No. Hazard Control Measure

Use proper and right tool. Use PPE. Inspect and


1 Nails, sharp corners, tools
remove projected nails from formwork after use

2 Equipment hitting working people Trained people, tool box talks on regular basis

Adequate designed (as required) and checked


3 Incorrect formworks
formwork. Use of PPE at the time of execution

4 Dust/ Noise Use PPE, Masks, Earmuffs and goggles


Competent Scaffolds, Barricade area, Warning
5 Fall/ Trip
signs, tool box talks, safety harness
6 Accumulation of gas / water Supervision and continuous monitoring

5 HSE Plan

5.1 Emergency Procedure


 ERP shall be present at site.
 List of site key persons including certified first Aider will be posted in the working area.
 Emergency contact number will be posted in the working area
 Assembly points are displayed on site. Copy of the site plan with assembly point location
attached.
Page: 7/7
Method Statement for Transformer Testing
5.2 Personnel Protective Equipment

What PPE’s must be required?


Mandatory Task Specific

Tick the
check box
for
specifying
the Task
Specific
PPE’S
Safety Safety Reflective Safety Ear Gloves Dust Face Safety Gas
Helmet goggle vest shoe Plugs Mask Shield Harness Mask
         
Specify the names of additional task specific PPE’s (If Required)

5.3 Responsible Personnel

Testing Engineer

Technicians

Helpers