Check List For Above Falseceiling 1
Check List For Above Falseceiling 1
Check List For Above Falseceiling 1
13 Ensure Drain Zone control Valve Installed with Proper Slope and connected to the
Shaft Header
14 Ensure Zone control Valve Install with correct Direction connected with the Header
Pipes In Shafts.
15 Ensure Civil Opening is don arround the FPS Lines in FPS Shafts
Clearance given for false ceiling work by FPS team
From: BSL Through : SPCPL MEP Through : SPCPL Civil Through : TCE
HVAC SYSTEM
1 Check the supports are fixed as per the specified distance
2 Ensure all duct's hanging supports are in vertical condition
3 Ensure that all duct's are laid as per drawing
4 Verify the all branch connection are done as per the approved drawing
5 Ensure that all VCD,FD,VAV installation works are completed
a Fire damper Installtion and ceiling fire damper without airgaps
b Enusre VCD installation/Provision
Ensure VAV Installation for Installation later date if any materials not
c avilablity.
CHECKLIST FOR COMMENCEMENT OF FALSE CEILING (ON COMPLETION OF FIRST FIX OF FPS/HV
ELECTRICAL SYSTEM
1 Ensure that raceway, tray & Conduit are laid as per the drawing power
2 Ensure raceway / tray supports are in vertical condition
3 Ensure raceway / tray clamp support should be approved colour
4 Ensure ceiling power socket for other (Third Party power)services work are completed
5 Ensure raceway, tray,Earthing & back box connection with conduit is done with check
nut
6 Ensure all wall / partition crossing / connection works completed properly
7 Ensure point wiring drop work completed
8 Ensure the cable dressing are properly done
9 Ensure that identification done for above false ceiling power points
10 Ensure the cable dressing are properly done
11 Ensure that raceway, tray & Conduit are laid as per the drawing DATA/WIFI
CHECKLIST FOR COMMENCEMENT OF FALSE CEILING (ON COMPLETION OF FIRST FIX OF FPS/HV
12 Ensure that raceway, tray & Conduit are laid as per the drawing /AV Requirements
Ensure that raceway, tray & Conduit are laid as per the drawing /IBMS Requirements
13
14 Ensure all wall / partition crossing / connection works completed Fire Selent properly
15 Ensure The Lighting Circuits/Sensors works complted as per the approved Drawings
Ensure that Lighting Trunking Supports ,Trunkings installed as per the approved
16 drawings.
Clearance given for false ceiling work by Electrical team
From: MICRON Through : SPCPL MEP Through : SPCPL Civil Through : TCE
IBMS SYSTEM
1 Ensure that FAS/PA/ACS Cables,cable tray & conduit are installed as per the drawings
2 Ensure that back box fixing completed at ceiling for FAS /PA
3 Ensure thatFAS/PA/ACS cable drop work completed
4 Ensure CCTV provision had been completed
5 Ensure ACS control provision had been completed
6 Ensure third party BMS cabling Connectivity works
Clearance given for false ceiling work by IBMS team
From: IBMS Through : SPCPL MEP Through : SPCPL Civil Through : TCE
CHECKLIST FOR COMMENCEMENT OF FALSE CEILING (ON COMPLETION OF FIRST FIX OF FPS/HV
13 Ensure Drain Zone control Valve Installed with Proper Slope and connected to the
Shaft Header
14 Ensure Zone control Valve Install with correct Direction connected with the Header
Pipes In Shafts.
15 Ensure Civil Opening is don arround the FPS Lines in FPS Shafts
Clearance given for false ceiling work by FPS team
From: BSL Through : SPCPL MEP Through : SPCPL Civil Through : TCE
HVAC SYSTEM
1 Check the supports are fixed as per the specified distance
2 Ensure all duct's hanging supports are in vertical condition
3 Ensure that all duct's are laid as per drawing
4 Verify the all branch connection are done as per the approved drawing
5 Ensure that all VCD,FD,VAV installation works are completed
a Fire damper Installtion and ceiling fire damper without airgaps
b Enusre VCD installation/Provision
Ensure VAV Installation for Installation later date if any materials not
c avilablity.
CHECKLIST FOR COMMENCEMENT OF FALSE CEILING (ON COMPLETION OF FIRST FIX OF FPS/HV
ELECTRICAL SYSTEM
1 Ensure that raceway, tray & Conduit are laid as per the drawing power
2 Ensure raceway / tray supports are in vertical condition
3 Ensure raceway / tray clamp support should be approved colour
4 Ensure ceiling power socket for other (Third Party power)services work are completed
5 Ensure raceway, tray,Earthing & back box connection with conduit is done with check
nut
6 Ensure all wall / partition crossing / connection works completed properly
7 Ensure point wiring drop work completed
8 Ensure the cable dressing are properly done
9 Ensure that identification done for above false ceiling power points
10 Ensure the cable dressing are properly done
11 Ensure that raceway, tray & Conduit are laid as per the drawing DATA/WIFI
CHECKLIST FOR COMMENCEMENT OF FALSE CEILING (ON COMPLETION OF FIRST FIX OF FPS/HV
12 Ensure that raceway, tray & Conduit are laid as per the drawing /AV Requirements
Ensure that raceway, tray & Conduit are laid as per the drawing /IBMS Requirements
13
14 Ensure all wall / partition crossing / connection works completed Fire Selent properly
15 Ensure The Lighting Circuits/Sensors works complted as per the approved Drawings
Ensure that Lighting Trunking Supports ,Trunkings installed as per the approved
16 drawings.
Clearance given for false ceiling work by Electrical team
From: MICRON Through : SPCPL MEP Through : SPCPL Civil Through : TCE
IBMS SYSTEM
1 Ensure that FAS/PA/ACS Cables,cable tray & conduit are installed as per the drawings
2 Ensure that back box fixing completed at ceiling for FAS /PA
3 Ensure thatFAS/PA/ACS cable drop work completed
4 Ensure CCTV provision had been completed
5 Ensure ACS control provision had been completed
6 Ensure third party BMS cabling Connectivity works
Clearance given for false ceiling work by IBMS team
From: IBMS Through : SPCPL MEP Through : SPCPL Civil Through : TCE