A 88 PCSCM
A 88 PCSCM
A 88 PCSCM
BENGALURU
Agenda for the 88th Meeting of Protection Coordination
Sub-Committee of SRPC to be held on 18th December, 2019
1. Introduction
3. Grid Occurrences
3.1 Grid Disturbances (GD), Grid Incidences (GI), trippings due to failure of Auto-reclosing
(A/R) and mal-operation of PLCC equipment that occurred during the period October -
November, 2019, given at Annexure-I, would be discussed in the PCSC meeting.
(a) Single line diagram of the station with switching devices, CT, PT and relay details.
(b) Cause of the tripping & Remedial Action taken
(c) Relay setting details
3.2 In compliance of Regulations 5.2 (r) of IEGC, the Constituents are required to furnish
the following information in respect of Grid Occurrences within 24 hr. of occurrence
of the same to SRLDC/ SRPC:
Agenda for the 88th Meeting of PCSC scheduled to be held on 18th December, 2019 Page 1
constituents in forthcoming PCSC.
As per the schedule the Protection audit of 19 substations scheduled in the month of
October and 33 substations scheduled in the month of November were successfully
completed. All officers nominated for audit in the month of December are requested
to take necessary measures for smooth conduct of audit. All coordinating Officers of
audits are also requested to ensure that filled in audit formats reach the concerned
audit team with a copy marked to SRPC well in advance.
During Protection audit of some stations it has been noted that in spite of enabling
Autoreclosure in many lines at 220kV and above, they have been kept in non-auto
mode. Constituents are requested to furnish status of implementation of A/R on all
lines at 220kV and above clearly indicatating whether A/R is in service or enabled in
non-auto mode.
Agenda for the 88th Meeting of PCSC scheduled to be held on 18th December, 2019 Page 2
6. Updating of Protection Audit format
As per the Guidelines of CEA/MOP, it has been decided to conduct the PCSC meetings on
monthly basis. It is requested that Agenda Items for the PCSC meetings, if any, may please
be sent latest by 5th working day of the month to SRPC Secretariat to compile and circulate
the same so as to have fruitful discussions in the PCSC meetings.
The tentative date of 89th meeting of PCSC is 13th& 14th February 2019.
*****
Agenda for the 88th Meeting of PCSC scheduled to be held on 18th December, 2019 Page 3
Grid Occurrences - 88
For all tripping events involving failure of substation equipment, Constituents are requested to
kindly furnish the SLD or equivalent pictorial representation showing (i) Location of the fault,
and (ii) Bus-bar arrangement/ Configuration of feeders and other connected equipment with
proper CB positions (OPEN/ CLOSE) at the time of occurrence of the fault.
Sl.
Details of Event Date &Time Reason Category
No.
Line tripped at Julurpadu end on
operation of DT receipt. At
Tripping of 400kV
08-09-2019 at Manuguru end, along with the
1 Julurpadu – GI-2
14:50 Hr. line station transformer#1 and bus
Manuguru Line-1
reactor also got tripped and the
same needs review.
Line tripped at Nunna end only on
operation of Zone-2 distance
protection. It was further
Tripping of 220kV 27-09-2019 at
2 mentioned in the report that there GI-1
KTPS-Nunna 14:41 Hr.
was bus fault at KTPS end. Non
operation of protection at KTPS
end needs review
Grid Occurrences to be discussed in the 88thMeeting of PCSC scheduled to be held on 18th December, 2019 1/7
02-10-2019 at
05:47 Hr.
03-10-2019 at
08:00 Hr.
09-10-2019 at On all the days line tripped on
Tripping of 230kV 12:29 Hr. single line to ground fault.
3 GI-1
Kudankulam - TTPS 13-10-2019 at Frequent tripping of the line may
04:49 Hr. be due to tree clearance issues.
21-10-2019 at
06:19 Hr.
31-10-2019 at
10:34 Hr.
400/220kV ICT-3 at Hoody
Tripping of tripped on mal-operation of PRD
04-10-2019 at
4 400/220kV ICT-3 at (Pressure Relief Device) relay. As GI-2
22:50 Hr.
Hoody reported PRD had not acted
physically.
400kV UPCL-Hassan line-2
tripped on DEF protection.
During the same time 220kV
UPCL-Kemar line-1 and 2 also
Complete loss of
06-10-2019 at tripped at remote ends resulting in
5 supply at 400kV GI-2
16:59 Hr. complete loss of supply at 400kV
UPCL station.
UPCL station. Units at UPCL
were under RSD and 400kV
UPCL-Hassan line-1 was not in
service in the antecedent.
ICT#2 at Talaguppa got tripped
Tripping of 07-10-2019 at
due to suspected mal-operation of
6 400/220kV ICT-2 at 18:52 Hr. GI-2
LV side backup over current
Talaguppa. and 19:18 Hr.
relay.
09-10-2019 at
00:40 Hr.
14-10-2019 at
01:45 Hr.
24-10-2019 at
00:26 Hr.
24-10-2019 at
23:51 Hr. Line tripped on operation of OV
29-10-2019 at St-1 protection at Mysore end and
Tripping of 400kV
22:58 Hr. DT received at Neelamangala
7 Nelamangala – GI-2
05-11-2019 at end. From DR of Mysore end, R-
Mysore line-2
02:00 Hr. phase voltage is lower as
07-11-2019 at compared to other two phases
01:54 Hr.
08-11-2019 at
00:57 Hr.
10-11-2019 at
16:05 Hr.
15-11-2019 at
03:02 Hr.
Tripping of Bus-1 at Triggering incident was insulator
220kV Ghanapur 09-10-2019 at flashover in 220kV Ghanapur –
8 GI-1
station of 01:17 Hr. Pocharam feeder. 220kV bus bar
TSTRANSCO protection of Bus-1 acted due to
Grid Occurrences to be discussed in the 88thMeeting of PCSC scheduled to be held on 18th December, 2019 2/7
operation of breaker failure relay.
Tripping of 400kV JSW – 11-10-2019 Line tripped at BPS end only on receipt of DT
1
BPS Line-2 at 15:04 hr. from JSW end.
Tripping of 400kV Warangal- 15-10-2019 Line tripped at Bhoopalapally end only. Line was
2
Bhopalapally line-2 at 22:50 Hr. holding at Warangal end.
Triggering incident was Y phase to B phase fault
in the line. At Chillakallu end, as per the report
submitted it is mentioned that Zone-1 distance
Tripping of 220kV 17-10-2019 protection operated. However, DR is not available
3
Chillakallu Suryapet line-1 at 13:30 Hr. to verify the same. At Suryapet end, Zone-2
distance protection operated and carrier was not
received. Failure of carrier aided protection at
Suryapet end needs review.
Line tripped on operation of overvoltage stage-1
Tripping of 400kV Warangal- 21-10-2019 protection at Bhoopalapally end. However DT
4
Bhoopalapally line-2 at 03:07 Hr. was not received at Warangal end. Line did not
trip at Warangal end.
Tripping of 400kV Kolar 29-10-2019 Line tripped only at Kolar end on DT receive
5
Hoody line-1 at 23:53 Hr. from Hoody end. Suspected PLCC mal operation.
Tripping of 400kV Lines tripped at Kayathar end only due to direct
06-11-2019
6 Thennampatty – Kayathar trip received. Lines were holding at Thennampatty
at 06:08 Hr.
Line-1&2 end.
Grid Occurrences to be discussed in the 88thMeeting of PCSC scheduled to be held on 18th December, 2019 6/7
V. Frequent tripping of following line during October 2019 and November 2019:
Frequent faults observed in the line. PCSC forum may be briefed the reason for frequent
tripping and remedial actions taken.
Grid Occurrences to be discussed in the 88thMeeting of PCSC scheduled to be held on 18th December, 2019 7/7
Annexure-II
Status of Pending Implementation of PCSC Recommendations as on 29.11.2019 (up to 87th Meeting)
Meeting Details of Event Date & Time Reason PCSC Recommendations Utility responsible for Status of Implementation of PCSC Recommendations Remarks Latest Status
No / Implementation (To be filled up by the Constituent)
Index
Multi-Utilities
34/I/6 400/220 kV ICT-1 & 2 at 16-07-2014 As reported directional over current relay of ICT’s 1. Bus bar protection shall be provided by asset KPTCL/ KPTCL Mail dated 27-05-2015: Pending
Munirabad operated due to snapping of line jumper in 220kV owner ( i.e KPTCL). PGCIL (SR-I) 1. KPTCL has taken action to provide bus bar protection to 220kV buses. --- Pending (with KPTCL)
Lingapur line. 2. Over current relay Settings of ICTs to be reviewed by PGCIL.
2. Settings for main distance protection & --- Pending
Overcurrent protection shall be examined and 3. --- Pending
reviewed. KPTCL Mail dated 29-07-2015:
1. Initial Tendering stage. --- Pending
3. Time synchronization of the Substation shall be 2. --- Pending
ensured. 3. --- Pending
APTRANSCO informed that they would be able to implement LDP from their &
APGENCO side by April, 2018.
In this regard, PCSC forum made it clear that the recommendation is about providing
LDP as both Main-I & Main-II relays on all stated lines in Nellore Complex, ans
Page 1 of 45
Annexure-II
PGCIL (SR-I) mail dated 20.06.2018:
PGCI(SR1) procuring LDP relays for retrofitting of Main-1&2 distance relays.
Tenders are invited from bidders & tender floated. Technical bid opening in this
week.
Page 2 of 45
Annexure-II
APTRANSCO Mail Dated 25.09.2018:
ABB make LDP relays for Main-1 protection were delivered earlier and schneider
make LDP relays for Main-2 protection are delivered in this week.
PGCIL-SR1:
Retrofitting works completed in NPS-NCC-1&2, NPS-Nellore-1&2 Main-1 relay,
NPS-TPCIL-1&2 lines completed.
Confirmation for retrofitting of Main-2 relay in NPS-Nellore-1&2 lines to be
received from SRPC. Presently both lines are bypassed at Nellore Bus-1&2 and
connected to Tiruvalam SS by closing Tie CBs at Nellore end. Now lines are long
lines as 400kV NPS-Tiruvalam-1&2. The same was discussed in 84th PCSC meeting.
SRPC has to give concurrence.
Page 3 of 45
Annexure-II
66/ II/ 10 Tripping of 400/ 220 kV 11-06-2017 Triggering incident was failure of 220 kV 1. NTPC to disable high-set of DEFR on the 220 kV NTPC-Ramagundam/ NTPC mail dated 07.12.2017: Pending
ICT’s – 3 & 4 at at 19:46hrs B-phase LA in ICT-3 LV extension feeder (220KV lines emanating from their Ramagundam STPS. TSTRANSCO 1. High set DEFR on 220 KV lines is disabled ----Completed
Ramagundam STPS line-2) at Malayalapalli substation 2. ---- Pending
2. NTPC/ TSTRANSCO to provide Line Differential
Protection (with or without pilot) on 220 kV Review Meeting dated 19.12.2017:
Ramagundam – Malayalapalli lines – 1 & 2 & 3. TSTRANSCO informed that the works are under progress, and are targeted to be
completed in 3 months time.
Page 4 of 45
Annexure-II
69/I/2 Complete outage of 400kV 30-10-2017 at 400kV TPCIL - Nellore line-1 got tripped at TPCIL 1. TPCIL to configure DEF protection such that it TPCIL/ Review Meeting dated 19.12.2017: Pending
TPCIL station 21:37 hrs end during failure of LA of Station Transformer-2 at remains in blocked condition as long as Distance PGCIL (SR-I) PGCIL (SR-I) informed that they are waiting for written confirmation from TPCIL to
TPCIL. Running Units at TPCIL got tripped due to loss Protection is active, and becomes active only when complete procurement of LDP relays. To this, PCSC forum asked TPCIL to submit
of evacuating line. 400kV TPCIL - Nellore PS line-2 distance protection does not pickup. written confirmation to PGCIL (SR-I) by 29.12.2017. PGCIL (SR-I) assured that
was under emergency shutdown with receipt of above confirmation from TPCIL by Dec, 2017, they would be able to
2.PGCIL (SR-I) to ensure healthiness of Carrier complete the work by February, 2018.
communication, and the set PUP mode of carrier aided
scheme operates reliably on TPCIL lines 1 & 2. APTRANSCO informed that they would be able to implement LDP from their &
APGENCO side by April, 2018.
In this regard, PCSC forum made it clear that the recommendation is about providing
LDP as both Main-I & Main-II relays on all stated lines in Nellore Complex, ans
asked all stakeholders to ensure & comply with the same.
69/III/3 Tripping of 400 kV 02-10-2017 at Line tripped on B-ph to ground fault. A/R was 1) PGCIL (SR-I) and APTRANSCO to provide for APTRANSCO/ APTRANSCO maild ated 30.01.2018: Pending [with
Kurnool(PG) – Kurnool(AP) 02:03 hrs unsuccessful at both Kurnool (AP) and Kurnool (PG) Line Differential Protection as both the Main PGCIL (SR-I) 1. Pending... PGCIL (SR-I)]
line-2 ends. protections on 400 kV Kurnool (AP) – Kurnool (PG)
lines 1 & 2 lines. 2.A/R scheme on 400kV Kurnool (PGCIL) feeder-2 will be checked after getting LC.
2) APTRANSCO to furnish an action taken report APTRANSCO maild ated 24.04.2018 & 24.05.2018 & 26.06.2018:
w.r.t. resolving A/R non-operation at Kurnool-AP end 1. Pending...
for the subject trippings and configure EL for capturing
PDR operation at their 400 kV Kurnool-AP SS. 2. B Ph auxilaryMail
APTRANSCO trip relay
Datedis found defective. The same is to be replaced by M/S
18.12.2018:
1) Bays and lines pertains to PGCIL .
2) ---Completed.
PGCIL (SR-I) mail dated 20.12.2018:
1) PO placed on M/s GE & TD India Ltd on 24.09.2018. Supply of relays will be
completed by Jan'2019.
APTRANSCO MAIL DATED 22.01.2019:
Pending [with PGCIL (SR-I)]
Page 5 of 45
Annexure-II
69/III/7 Tripping of 220 kV 12-10-2017 at Line tripped on B-Ph to earth fault. A/R was successful KPTCL and APTRANSCO to sort out issues relating APTRANSCO/ KPTCL APTRANSCO maild ated 15.12.2017: Pending
Ragulapadu – Alipura line 01:30 hrs at Regulapadu and breakers at Alipura end got tripped. to incongruence in denoting R, Y, B phases of the APTRANSCO would extend support and requirements if any ,for the rectification [with KPTCL ]
electric supply on their respective sides. proposed by KPTCL.
Review Meeting dated 19.12.2017:
It was noted that the original Gooty - Lingapur line got LILOed at BTPS, Alipura,
and Ragulapadu. It was also noted that Phase Discrepancy is being observed in
Ragulapadu - Alipira section only. When enquired about the same, KPTCL informed
that they would examine the issue in detail, and would inform the action lan proposed
by next PCSC-71 meeting. On this, APTRANSCO was also asked to render all help
required from their side to KPTCL.
76/II/9 Tripping of 230 kV 13-06-2018 at Y-phase to earth fault occurred in line. At 230 kV 1) TANTRANSCO to provide double-bus operation at TANTRANSCO/ 1) TANTRANSCO Mail dated 29.08.2018 & 11.09.2018: Pending [with
Thiruvalam - Chittoor line 18:55hrs Tiruvalam end, breaker was under lockout leading to their 230 kV Thiruvalam SS. APTRANSCO Material supplied and work to be taken up ---Pending TANTRANSCO]
operation of LBB protection. 2) APTRANSCO Mail dated 24.09.2018:
2) APTRANSCO to replace the existing static relays The static relays were replaced with Numerical relay on all 220 kV feeders at 220 kV
with suitable numerical relays for various line SS chittoor.---Completed
protections at their 220 kV Chittoor SS.
TANTRANSCO Mail dated 11.12.2018:
Due to space constraint, the equipments could not be erected.
Page 6 of 45
will be taken. Time upto Sep 2019
78/I/2 Complete outage of 220 kV 17-09-2018 at 220kV lines connected to Nagjheri PH got tripped due 1. SLDC/KPTCL to be pro-active in issuing necessary KPCL/ KPTCL KPTCL mail dated 19.12.2018: Pending
Nagjheri PH and 220/110 kV 14:37hrs to successive transient faults. Running Units #3 and #4 directions that help in expeditious restoration of the 3). Nagzari-Bidnal PLCC link is healthy --- Completed.
Ambewadi Substation. at Nagjheri got tripped on over frequency protection tripped lines based on the prevailing conditions and 1.--- Pending
operation due to loss of evacuating lines resulting in grid security. 2. --- Pending
complete outage of 220 kV Nagjheri. 220 kV Nagjheri
being the only source to 220kV Ambewadi station, 2.KPCL to implement A/R enabled on all 220 kV lines Review Meeting on 20.12.2018:
since 220kV Ambewadi Narendra line 1&2 were under emanating from their 220 kV Nagjheri PH, with the 1. & 3. Completed
shutdown during antecedent condition, tripping of help of KPTCL, by December, 2018. In the event of 2. Pending
Units at 220 kV Nagjheri resulted in the loss of supply non-amenability of the existing PZ1000 relays in
to 220 kV Ambewadi SS. providing A/R feature, KPCL shall take steps to KPCL mail dated 24-12-2018:
retrofit them with suitable relays that support A/R. 1) --- Completed
3. KPTCL to restore PLCC carrier communication on 2) Proposal will be taken up for replacement of existing PZ1000 relays with new
220 kV Nagjheri – Bidnal line at the earliest version Numerical Line protection relays having IEC61850 shortly, after availing
necessary admnistrative approval...Pending
3) Completed
2. Letter addressed to site to take up the proposal for replacement of PZ1000 line
distance relays.
KPCL mail dated 23.03.2019:
1). COMPLETED
2) Proposal will be taken up for replacement of existing PZ1000 relays with new
version Numerical Line protection relays having IEC61850. Prepration of
specification is under progress.
3) COMPLETED
Reviewmail
KPCL Meeting
datedon16.07.2019:
27.06.2019:
1) & 3) Completed
2) Replacement of existing PZ1000 relays with new version Numerical Line
protection relays having IEC61850 is included in PSDF Phase-II DPR. Approval of
NLDC for DPR is awaited. However, administrative approval for issue of NIT for
replacement of existing PZ1000 relays with new version Numerical Line protection
relays having IEC61850 obtained. Preparation of technical specification is under
progress.
Page 7 of 45
progress.
Annexure-II
78/II/16 Multiple trippings at 220kV 31-08-2018 Triggering incident was B-E fault in 220 kV Nagjheri - 1)KPTCL to examine the reasons for tripping of more KPTCL/ KPCL Review Meeting on 20.12.2018: Pending
Nagjheri PH at 11:49 hrs Ambewadi line-1. As per the information received, than one Unit (Units – 3 & 6) on SPS operation at 1. KPTCL I formed that SPS scheme finalisation shall be completed in one month
after tripping of 220 kV Naghjeri - Ambewadi line-1, Nagjheri PH during subject trippings, and furnish a time --- Pending
220 kV Naghjeri Ambewadi line#2 got overloaded. report on the same along with remedial action taken to
This resulted in the tripping of Nagjheri Generating PCSC forum. KPCL mail dated 24-12-2018:
Units #3 and 6 on SPS operation. At the same time, 2) Time delay of operation is not changed. However, the external NCT is used for
Unit #2 got tripped on REF operation. 2)KPCL to employ a suitable time delay of 50 – 60 REF protection against earlier internal NCT for REF, to avoid tripping due to
msec in operation of REF protection for the GT of Unit- malopration --- Completed.
2 at their Nagjheri PH.
KPCL mail dated 23.01.2019:
1) It shall be reviewd and Implemented by KPCL in coordination with KPTCL.
2)....Completed.
83/I/1 Complete outage of 230kV 11-03-2019 Triggering incident was Y-phase CT blast in 230kV 1. TANTRANSCO is recommended to submit action TANTRANSCO TANTRANSCO MAIL DATED 13.06.2019: Pending[PGCIL-
Veeranam substation of at 00:55Hrs Tirunelvelli (Abhishekpatty) – Veeranam Ckt-1. plan to provide Multi-Bus operation/ Hybrid breakers 1.Provision of bus coupler breaker is not feasible due to space constaint. SR-II]
TANTRANSCO 230kV Trirunelvelli – Veeranam Ckt-1 and 2 tripped. at 230kV Veeranam SS with clear timelines.
Two faults were observed from the PMU plot. During 2. TANTRANSCO to revise the distance zone settings 2&3. Tirunelveli end maintained by PGCIL.
Page 8 of 45
Annexure-II
83/I/6 Complete outage of 220kV 10-04-2019 Y and B-phase earth isolator switch blades of 220kV 1. KPTCL is recommended to revise the SPS at KPTCL/ KPCL KPCL mail dated 25.06.2019: Pending
Hubli substation of KPTCL at 18:09Hrs Hubli-Bidnal ckt-1, got closed due to failure of locking Nagjheri, (to accommodate a new condition with high 2) Carrier aided protection is enabled on all 220kV lines emanating from NPH
and 220kV mechanism during heavy wind and rain flow and low time delay) in consultation with SRPC ___Completed
Nagjheri Power station of conditionsresulting in bus fault. Bus bar protection and SRLDC.
KPCL operated and all connected elements tripped. There was 2. KPCL in coordination with KPTCL is recommended Review Meeting on 27.06.2019:
complete loss of supply at 220kV Hubli station since to provide at least one main protection as carrier aided 1. KPTCL informed that Nagjheri SPS has to be studied in the event of configuration
the station was on single bus operation. At thesame three zone distance protection on the 220kV lines changes and outcome of the same will be intimated soon
time, 220kV Nagjheri-Ambewadi ckt-1 and 220kV emanating from Nagjheri GS.
Nagjheri – Bidnal tripped on overcurrent KPCL mail dated 16.07.2019 & 30.10.2019:
protection. Since 220kV Nagjheri – Ambewadi ckt-2 1. under progress
and 220kV Nagjheri-Kodasalli ckt-1 &2 wereunder 2. Completed
shutdown in the antecedent due to maintenance,
running units #1,4,5 and 6 tripped due to
loss of evacuating lines. This resulted in complete loss
of supply at 220kv Nagjheri station.
83/II/9 Tripping of 400 kV 10-03-2019 at Line tripped on operation of overvoltage stage-1 PGCIL (SR-II) to submit action plan regarding PGCIL (SR-II)/ KPTCL PGCIL (SR-I) mail dated 07.06.2019: Pending
GUTTUR - NARENDRA -1 18:03hrs protection at Guttur end and DT received at Narendra replacement of CT’s for 400Kv Guttur Narendra line - Line belongs to PGCIL(SR-2)
end. Voltages at Guttur end: Vr-254kV, Vy-252kV, 1 at Guttur end. PGCIL (SR-II) to sort out the time
Vb-246kV. As per voltage grading, 400kV Guttur sync issues in DR and EL at Narendra end. Review meeting on 27.06.2019:
Narendra line-2 should trip first. PGCIL(SR-II) informed that R & Y ph CVT replaced on 25.05.2019. Time
syncronisation has to be attended by KPTCL.
83/II/17 Tripping of 400kV 23-03-2019 at Feeder tripped due to severe tracking on line insulator 1. APGENCO to inform PCSC forum the following: APGENCO/ APTRANSCO mail dated 19.06.2019: Pending [ with
Krishnapatnam – Nellore ckt- 04:41 hrs stacks. Status of A/R in 400kV Krishnapattnam – Nellore APTRANSCO 3. Line Insulator stacks were replaced with SRC insulators at location Nos.4,5,6 for APGENCO]
1 line-1 at Krishnapattanam end, if A/R is not enabled Krishanpatnam-1 on 26/03/2019 and Krishanpatnam-2 on 27/03/2019.--------------
APGENCO shall implement 1-ph ‘lead-follow’ A/R Completed.
scheme at Krishnapattanam.
The reason for tripping of Unit-2, along with the line Review Meeting on 27.06.2019:
tripping on 24.03.2019. 1. APGENCO representative did not attend the meeting. APGENCO is requested to
2. APGENCO in consultation with APTRANSCO to furnish the status at the earliest.
explore the possibility of providing Line Differential
Protection (LDP) for the line.
3. APTRANSCO is recommended to replace the
insulators of the line with polymer insulators.
24-03-2019 at
02:32 hrs
25-03-2019 at
01:19 hrs
84/I/1 Complete outage of 230kV 18-05-2019 at Triggering incident was Y phase to Earth fault in 220 1.TANTRANSCO may take immediate measures to TANGEDCO/ TANTRANSCO mail dated 26.07.2019: Pending
NCTPS Generating Station 04:39 hr. kV NCTPS Tondiarpet line-2. Due to mal-operation of attend the problem in LBB wiring that is extending trip TANTRANSCO 1 & 2.Inbuilt LBB function will be enabled in the new distance relays.
of TANGEDCO LBB protection (of Tondiarpet line-2) at NCTPS end, during A/R within one month. 3. will be ensured.
all the connected elements of bus zone-3 got tripped. 2. TANTRANSCO is recommended to send a detailed 4.230kV Kilpauk was operated radially for avoid overloading in the adjacent feeders
Due to loss of evacuating lines, running units at report regarding the A/R status (availability due to cable fault in the area.Normally all feeders are operated as grid feeders.
NCTPS unit#1 and 2 got tripped. /enabling)on all lines emanating from 230kV NCTPS
GS and enable A/R in all lines emanating from 230kV
NCTPS GS.
3.TANGEDCO in coordination with TANTRANSCO
may take definite measures to ensure time
synchronization of all relays with GPS signal at
NCTPS end and remote ends at the earliest.
4. It was also suggested that possibility of backing
down of generation, in the event of unavailability of
many feeders, in particular when radial feeders only
are in service, may be looked at.
Page 9 of 45
Annexure-II
84/I/2 Complete outage of 230kV 19-05-2019 at 230kV lines connected to NCTPS got tripped due to 1. TANGEDCO in coordination with TANTRANSCO TANGEDCO/ TANTRANSCO mail dated 26.07.2019: Pending
NCTPS Generating Station 22:44 hr. fault in lines. Running units#1,2 and 3 at 230kV to take definite measures to ensure time TANTRANSCO 2& 3.wedge connector have been provided in order to avoid jumbercut.
of TANGEDCO NCTPS also got tripped due to loss of evacuating lines. synchronization of all relays with GPS signal at 4. Replacement of porcelain insulators by polymer insulatos in all 230kV & 400kV
NCTPS end and remote ends at the earliest. feeders in North Chennai area has been completed
2.The PCSC noted frequent jumper cut/conductor snap
instances in the area, of late; accordingly, it was
suggested to have adequate condition monitoring and
preventive maintenance measures.
3.TANTRANSCO to communicate
(i) the schedule of replacement of balance porcelain
84/II/4 Tripping of 230kV Sulurupet- 11-04-2019 at Triggering incident was B-N fault in 230kV 1.TANTRANSCO to check the resistive and reactive TANTRANSCO/ APTRANSCO mail dated 30.07.2019: Pending [ with
Gumudipoondi line 16:05 hr. Gummudipoondi-NCTPS line. 230kV Sulurupet - reach settings of 230kV Gummudipoondi-NCTPS line APTRANSCO 2. GPS not available at 220KV Sullurpet SS.Manually set the timing on 29/07/2019 - TANTRANSCO]
Gummudipoondi line tripped on operation of zone-2 at Gummidipoondi end. - Completed
distance protection at Sulurpet end and reverse zone 2. APTRANSCO to ensure time synchronization of
protection at Gummudipoondi end. DR and EL at Sulurupet end. Also in coordination with TANTRANSCO mail dated 26.07.2019:
TANTRANSCO sort out the time synchronization 1. & 3. Will be reviewed
issue in 230kV Sulurupet-Gumudipoondi line.
3. TANTRANSCO to check the SOTF settings at
Gummidipoondi end for 230kV Gummudipoondi-
NCTPS line .
84/II/19 Tripping of 400/220 kV ICT- 03-05-2019 at ICT-1 Tripped on operation of APTRANSCO 220 kV 1. PGCIL (SR-I) to submit the high set settings of PGCIL (SR-I)/ APTRANSCO mail dated 30.07.2019: Pending [ with
1 atCuddapah 23:39 hr. Bus Bar relay (96 trip relay). Fault reported in 220 kV ICT’s at Cuddapah. Since the static relay in which APTRANSCO 2. The 220KV GE make B90 type Bus Bar relays tested on 23/07/19 and found PGCIL (Sr-1)
Cudappah-Renigunta line high set is enabled has no provision to provide time healthy. The report submitted vide mail dated 29.07.2019 - Completed
delay, ICT high set shall be enabled from numeric
relay and sufficient time delay shall be provided for PGCIL (Sr-1) maild ated 31.10.2019:
highset operation. Kadapa ICTs DOC&EF adopted settings are attached for your review.
2.APTRANSCO to check the Busbar operation at 220
kV Cuddapah SS and submit a report regarding the
same.
3. PGCIl (SR-I) to inform the methodology adopted for
calculating high set settings of ICT’s. Also due to
changes in system configuration at Cuddapah in recent
84/II/22 Tripping of 400kV 09-05-2019 at Line tripped on mal-operation of Reactor differential TSTRANSCO in coordination with PGCIL (SR-I) to TSTRANSCO/ PGCIL TSTRANSCO mail dated 30.10.2019: Pending [with
Khammam-Mamidapalli line- 02:40 hr. protection and DT sent to Khammam. ensure time synchronization of relays at Mamidapalli (SR-I) GPS time synhronization work at 400kV Mamidipally will be done by December, TSTRANSCO]
1 end with Khammam end in 6 months’ time. 2019.
84/II/29 Frequent tripping of 220 kV 01-05-2019 at B-N FAULT It was noted that no representative of APGENCO APGENCO/ Yet to be informed Pending
KTPS –Lower Sileru line 16:04 hr. B-N FAULT attended the meeting. TSGENCO
04-05-2019 at B-N FAULT For the subject line, the following shall be carried out
14:48 hr. B-N FAULT by TSGENCO in co-ordination with APGENCO:
05-05-2019 at R-N FAULT (i) End-to-end communication for DT/ permissive &
11:29 hr. R-B FAULT other signals may be ensured by testing at boththe
06-05-2019 at R-B FAULT ends.
13:14 hr. B-N FAULT (ii) Healthiness of PLCC system components
85/II/3 Tripping of 400kV Kurnool- 17-05-2019 at line tripped only at Srisailam end on Zone-3 distance1. TSGENCO is recommended to modify the PSL TSGENCO/ APTRANSCO maild ated 03.10.2019: Pending [with
Srisailam line 14:10 hrs protection operation during Y phase to B phase fault in
logic (Srisailam end to trip for faults occurring in Zone- APTRANSCO 1. Pending with TSGENCO TSGENCO]
220kV NarnoorSomayajulapalli line-1 2 and Zone-3 with respective time delays except for 2. GPS synchronisation is not avialable at Somayajulapalli SS. Time in relays is
PUR scheme if adopted ) in 1 month time to avoid manually set on 29/08/19. - Completed
occurrence of any such unwarranted trippings in future.
85/II/14 Tripping of 230kV Theni- 29-05-2019 at 3 phase to earth fault occurred in line. Tripped on For the subject line, the following shall be carried out TANTRANSCO/ Yet to be informed Pending
Sabarigiri line 18:39 hrs ground over current protection 67N at Sabarigiri and by TANTRANSCO in coordination with KSEBL: KSEBL
Zone-2 at Theni end. (i) End-to-end testing for DT/ permissive & other
signals may be ensured by testing at both the ends.
(ii) Healthiness of PLCC system components (
85/II/17 400 kV Ghani – Narnoor line- 30-05-2019 at Triggering incident was Y-ph to B-ph fault in the 1. APTRANSCO is recommended to sort out the issues APTRANSCO/ PGCIL APTRANSCO maild ated 03.10.2019: Pending [ with
1, 400 KV Jamalamadugu- 00:48 hrs 400kV NarnoorJammalamadugu line-1 & 2 due to with their distance protection relay (7SA522) which (SR-1) 1).The distance relay(7SA522) was thoroughly tested in all zones duly availing LC on PGCIL (Sr-1)
Kurnool line-1, 765/400 kV falling of Y-ph CVT jumper on B-ph during heavy maloperated and caused unwarranted tripping of 400KV Ghani-Narnnor line-1 on 31.07.2019 and relay found healthy. The time
ICT-1&2 at Kurnool wind. At the same time, 400kV GhaniNarnoor tripped 400kV Ghani – Narnoor line-1. The time synchronization of main-1&2 relays at Ghani end adjusted and are in coincident with
only at Ghani end on operation of Zone-1 distance synchronization of relays at Ghani end also shall be GPS. - COmpleted
protection. 765/400 kV ICT-1 & 2 at Kurnool PG also ensured.
got tripped on HV side Directional Overcurrent (DOC) 2.PGCIL (Sr-1) is recommended to submit a detailed 2. Pending
protection. report regarding operation of ICT Buchholz relay for
through fault conditions along-with remedial measures PGCIL(Sr-1) mail dated 31.10.2019:
suggested by OEM. Rectification by OEM is planned in this month. The same will be completed by 1st
week of Sep-2019.
Page 10 of 45
Annexure-II
85/II/20 Tripping of 220kV Idukki- 05-06-2019 at Triggering incident was R-Y-Earth fault in the For the subject line, the following shall be carried out KSEBL/ Yet to be informed Pending
Udumalpet line 15:13 hrs line. Carrier aided protection not operated at by TANTRANSCO in coordination with KSEBL: TANTRANSCO
Udumalpet end. (iii) End-to-end testing for DT/ permissive & other
signals may be ensured by testing at both the ends.
(iv) Healthiness of PLCC system components (
hardware and software) at both the ends shall be
85/II/26 Tripping of 400kV Vemagiri- 14-06-2019 at Line-1 tripped on Y-Phase to earth fault due to Y- 1. APTRANSCO is recommended to submit APTRANSCO/ GMR APTRANSCO maild ated 03.10.2019: Pending (with
GMR line-1&2 09:33 hrs Phase LA failure at Vemagiri end. Line-2 tripped at Equipment failure report (LA failure) to CEA. 1. Equipment (LA failure) Failure report submitted to CEA on 12.07.19. GMR)
GMR end only 2.GMR is recommended to submit a report regarding ---Completed
tripping of 400kV Vemagiri-GMR line-2 at GMR end 2. Pending
along-with the related tripping files.
85/II/32 220kV Lower Sileru-KTPS 02-06-2019 R-phase to earth fault occurred in line. Auto-reclose ATRANSCO in coordination with TSTRANSCO to APTRANSCO/ APTRANSCO maild ated 03.10.2019: Pending (with
line at 15:30 hrs was successful at Lower sileru end. A/r is not enabled ensure frequent patrolling and proper maintenance of TSTRANSCO 1. Thorough patrolling has been conducted on the line upto APTRANSCO TSTRANSCO)
at KTPS. ROW by attending all tree clearance issues. juridiction(60KM). All the fault distances of this incident falls in TSTRANSCO
juridiction. (Total line length:146.5Km)
85/IV/5 Tripping of 400kV Warangal- 08-06-2019 at 400kV Warangal-Bhoopalapalli line-1 line tripped For the subject line, the following shall be carried out TSGENCO/ TSTRANSCO mail dated 30.10.2019 Pending
Bhoopalapalli line-1 1:35 hrs only at Boopalappalli end on OV st-1 protection by TSTRANSCO in coordination with TSGENCO TSTRANSCO New PLCC panels are alloted for 400kV Warangal-Bhoopalpalli-1 line and waiting
&BoopalppalliChandlapur operation and DT was not sent to Warangal end due to (i)End-to-end testing for DT/ permissive & other for PGCIL to give permission for erection and commissioning of the same at their
line-1 failure of both PLCC channels. 400kV signals may be ensured by testing at both the ends. end.
BoopalppalliChandlapur line-1 tripped at Boopalpalli (ii)Healthiness of PLCC system components (
end due to DT Receive hardware and software) at both the ends shall be
86/II/7 Tripping of 220 kV KTPS - 8-7-2019 at Line tripped on B-phase to earth fault. As per FIR, checked
For the and faulty
subject components
line, shallshall
the following be repaired/
be carried out APGENCO/ Yet to be informed Pending
Lower Sileru-1 10:45 hrs there was zone-2 operation at KTPS by APGENCO in coordination with TSGENCO: TSGENCO
i. End-to-end testing for DT/ permissive& other signals
may be ensured by testing at both the ends.
ii. Healthiness of PLCC system components (hardware
and software) at both the ends shall be checked and
faulty components shall be repaired/ replaced .
87/II/3 Tripping of 220 kV KTPS-Lower 15-08-2019 at 13;04 Frequent Line tripping due to transient fault in R & Y phase APTRANSCO and TSTRANSCO are requested to take APTRANSCO/ Yet to be informed Pending
Sileru line-1 hr.; necessary actions to ensure proper tree clearances and right of TSTRANSCO
20-08-2019 at 11:23 way for the subject line.
hr.;
26-08-2019 at 13:43
hr.;
28-08-2019 at 11:17
hr.
Page 11 of 45
Annexure-II
87/III/1 Tripping of 230 KV-Neyveli TS 17-08-2019 at B phase to Earth fault in the line. At Neyveli end A/R not NLCIL and PED to submit a report regarding failure of A/R NLCIL / PED Yet to be informed Pending
II - Karaikal line-1 00:28hr. operated. and the reason for the same
Andhra Pradesh
Page 12 of 45
Annexure-II
57/II/9 Tripping of 400 kV Nellore 18-07-2016 Triggering incident was snapping of Y phase conductor APGENCO to furnish a report on the remedial action APGENCO Review Meeting dated 19.12.2017: Pending
(PG) - NPS line-1, 400 kV at 19:05 hrs in 400kV Nellore (PG) - NPS line-1. Distance relay at implemented w.r.t. overreaching of Krishnapatnam end It was noted that no APGENCO representative had come to attend the meeting.
Krishnapatnam-Nellore (AP) Krishnapatnam end over-reached in Zone-1, and distance relays during the tripping of 400 kV Nellore
lines -1&2 and 400kV NPS - resulted in tripping of 400kV Krishnapatnam – Nellore (PG) - NPS line-1 APGENCO Mail dated 19.12.2017:
MEPL line (AP) lines - 1&2 from Krishnapatnam end. Distance Procurement of relays is under progress
relay at MEPL over-reached and resulted in tripping of
MEPL-NPS line from MEPL end. Review Meeting dated 20.12.2018:
APGENCO representatives had not come to attend the meeting.
83/III/8 Tripping of 400 kV VTPS - 24-03-2019 at Feeder tripped on Y -N Fault. Auto reclose operated at APGENCO is recommended to submit a detailed APGENCO Review Meeting on 27.06.2019: Pending
Nellore 12:46hrs Nellore end but not operated at VTPS end. report regarding the reason for A/R being kept 1. APGENCO representative did not attend the meeting. APGENCO is requested to
disabled and the Remedial Measure taken for the same. furnish the status at the earliest.
86/II/1 Tripping of 400 kV 01-07-2019 Line tripped on operation of over voltage stg-1 1. APGENCO to configure both OVR start and trip APGENCO Yet to be informed Pending
Krishnapatnam-Nellore-1 at 03:40 hrs, protection at Krishnapatnam and direct trip was signal in DR or EL.
03-07-2019 received at Nellore. The Y –phase CVT voltage at 2. APGENCO in coordination with APTRANSCO to
at 3:42 hrs, Krishnapatnam end was observed to be 8 to 10 kV sort out the time sync issues between Krishnapattanam
19-07-2019 higher than the R & B phase voltages and Nellore.
at 2:25 hrs, 21-07-
2019
at 2:27 hrs, 28-07-
2019
86/II/10 Outage of Bus-2 at 400 kV 18-07-2019 Bus bar protection of 400 kV Bus-2 operated due to APGENCO to revise the CT circuit supervision circuit APGENCO Yet to be informed Pending
RYTPP station of at 3:30 hrs malfunctioning of CT supervisory circuit. All elements monitoring and tripping of Busbar at RYTPP.
APGENCO connected to Bus-2 tripped
86/II/15 Tripping of 400 kV 01-08-2019 at Triggering incident was R phase to Y phase fault in the APGENCO to submit OEM report regarding mal- APGENCO Yet to be informed Pending
Krishnapatnam-Nellore line- 21:49 hr. line. Unit -2 of SDSTPS also got tripped during the operation of GT differential relay of Unit-2 at
1 and Unit -2 of incident. Krishnapattanam.
Krishnapatnam
87/I/1 Complete outage of 220 kV 23/08/2019 at Malopertion of Bus-1 and Bus-2 bus bar protection 1. APGENCO to ensure that shift engineers and APGENCO Yet to be informed Pending
Lower Sileru GS of 18:52 hr. lead to tripping of all connected elements at 220 kV operators strictly adhere to operational procedure.
APGENCO Lower Sileru resulting in complete loss of supply at 2. APGENCO may explore the possibility of providing
220 kV Lower Sileru station. proper interlock between Buscoupler and isolator (i.e.,
In the event of an element connected to one bus
through respective bus isolator the interlock is intended
to disallow closing of other Bus isolator if Bus coupler
is in open condition).
Page 13 of 45
Annexure-II
86/I/3 Complete outage of 220 08-08-2019 at Triggering incident was failure of Y-ph LA of 220 kV 1. APTRANSCO to submit equipment failure report to APTRANSCO APTRANSCO mail dated 29.10.2019: Pending
kV/132kV Paravada SS of 11:34 hrs Paravada- VSS (Vizag Switching Station) line at CEA,in respect of the failed Lightning arrester, and to 1. Equipment failure report to CEA in respect of the failed Lightning arrester will be
APTRANSCO Paravada end. ensure healthiness of Lightning arresters in other sent soon, and healthiness of Lightning arresters in other phases are already checked
phases. on 08-08-2019.
2. APTRANSCO shall also regularly perform third 2. Third harmonic current measurement (THRC) kit not available with
harmonic current measurement (THRC) and APTRANSCO. Measurement of LA stack temperature to monitor healthiness of all
measurement of LA stack temperature to monitor LA’s is done every month along with other equipment and this month testing is
healthiness of LA’s. scheduled on 02-11-2019 . --Completed
86/II/19 Tripping of 400 kV 5-08-2019 at Triggering incident was failure of R-phase LA in 400 APTRANSCO to implement line differential protection APTRANSCO APTRANSCO mail dated 29.10.2019:
Simhadiri-Kalpakka line- 13:37 hr. kV Kalpakka-Asupaka line. for 400 kV Simhadri- Kalpakka line immediately and The line differential protection was enabled in 400 kV kalapaka PGCIL(Gajuwaka) I
1,2&3; 400 kVKalpakka- required OFC/OPGW may be arranged within a week & II feeders, 400 kV kalapaka HNPCL I & II feeders. LC was programmed on
Asupaka line-1 &400 15.10.2019, 17.10.2019 and 18.10.2019 for testing and enabling the differential
kVKalpakka-Gazuwaka line- feature in 400 kV Kalapaka Simhadri-2,3, &, 4 feeders. clearance for testing was not
2 accorded from M/s NTPC. As and when the clearance is accorded from M/s NTPC
the differential feature will be enabled in 400 kv kalapaka Simhadri-2,3&4.
87/1/2 Complete Outage of 220 kV 28/08/2019 a. Bus-1 and Bus-2 Bus Bar Protection operated due to 1. APTRANSCO to investigate whether ageing or tension led APTRANSCO Yet to be informed Pending
at 15:3 snapping of R-phase dropper jumper at 220 kV VSS r to failure of R-Phase dropper from Jack bus to bridge which
Vizag Switching Station and
esulting in the tripping of all the connected elements. b. 400 led to complete outage of 220 kV VSS and Parawada.
220 kV Parawada SS of
kV/220 kV ICT#1 and 2 at Gazuwaka also got tripped during 2. Healthiness of other jumpers at 220 kV VSS shall
APTRANSCO this event. be ensured and a report shall be furnished to SRPC.
c.220 kV Paravada SS was radially fed from 220 kV VSS APTRANSCO to submit Thermovision scanning reports of
during antecedent conditions. 220 kV VSS during past 6 months and ensure time sync at
220 kV VSS.
87/III/3 Tripping of 400 kV 22-08-2019 at 4:00 B-phase to earth fault occurred in line. Auto-reclose was 1. APTRANSCO to submit a report after checking A/R APTRANSCO Yet to be informed Pending
Maheshwaram-Narnoor line hr. successful at Mahshwaram and A/R not operated at Narnoor operation.
2. APTRANSCO to configure OVR start in EL.
Page 14 of 45
Annexure-II
Telangana
82/II/1 Tripping of 400kV KTPS VI- 05-01-2019 Line tripped at KTPS VI end due to suspected mal- 1) TSGENCO to configure OVR_start and TSGENCO TSGENCO mail dated 24.06.2019: Pending
KTPS VII at 10:17hrs operation of over-voltage protection. Line was in OVR_tripin EL at KTPS-VI end and sent a report after The issue is referred to M/s BHEL ( EPC vendor ) and the study on feasibility for
service from KTPS VII., BUS CVT secondary R completion of works related to DT communication providing the communication with the existing available system is under process and
PHASE got grounded at KTPS VI channel between KTPS-VI and KTPS-VII will be completed during the availability of next shutdown.
84/II/28 Frequent tripping of 220 kV 05-04-2019 at In 155thOCC meeting of SRPC, APTRANSCO 1. TSGENCO to check the non-operation of carrier TSGENCO Yet to be informed Pending
KTPS –Nunna line 12:55 hr. B-N informed that the tripping was due to clearance issues aided trip, when fault is detected at KTPS end in Z-2
FAULT in the ROW caused by mango tree. It was cleared and and carrier is also received, and submit a report
15-04-2019 at issue was rectified. However, frequent tripping of line regarding the same.
13:20 hr. Y-N is still persistent. 2. TSGENCO and APTRANSCO to ensure that
FAULT ROW is cleared periodically.
87/II/5 Tripping of 220 KV-Srisailam 16-04-2019at at
18-08-2019 4:23 3.APTRANSCO
Suspected mal-operation of Main-2 distance protection relay at TSGENCO & the
to carry out TSGENCO may
following for consider
tripping raising TSGENCO
of the Yet to be informed Pending
Right Bank-Nagarjunsagar TS-1 hr.; Nagarjunsagar TS-1. Line was holding from Srisailam right subject line:
05-09-2019 at 13:50 bank. 1.Check the SOTF settings and breaker contacts. 2.SOTF
hr auto-initiation shall be kept off (in settings).
3.Submit a disturbance recorded file after changing the DR
time scale to capture 500msec pre fault and 2 sec post fault
events.
84/II/1 Tripping of 400kV Srisailam- 06-04-2019 at 400kV Mamidapally Dindi line-1 tripped on R-phase 1.TSTRANSCO to ensure time synchronization of DR TSTRANSCO TSTRANSCO MAIL DATED 30.10.2019: Pending
Dindi line-1 and 400kV 17:39 hr. to earth fault. 400kV Srisailam-Dindi line-1 tripped on and EL at Mamidapalli end and Dindi end. Also in 1. GPS time synhronization work at 400kV Mamidipally will be done by December,
Mamidapalli-Dindi line-1 operation of cable differential protection at Srisailam coordination with TSGENCO sort out the time 2019.
and direct trip was sent to Dindi. synchronization issue in 400kV Srisailam – Dindi line- 2. A/R dead time is maintained as 1 sec at all stations.
1. 2.TSTRANSCO to ensure that A/R dead-time
is maintained as 1 sec uniformly at all Stations.
84/II/14 Tripping of 400/220 kV ICT- 22-04-2019 at ICT#2 and 3 got tripped on suspected mal-operation of 1 .TSTRANSCO to ensure directional settings for ICT TSTRANSCO TSTRANSCO MAIL DATED30.10.2019: Pending
2 and 3 at Dichipalli 17:22 hr. LV earth fault relay during fault in 220 kV Dichpally- earth fault protection and to ensure coordination 1. The problem was with the CT wiring and directionality issue is rectified. -----
Substation Medaram feeder between line and ICT DEF protection. Completed
2.TSTRANSCO to investigate the reason for non- 2. The bus bar relay was static relay and is being replaced with numerical relay
operation of LBB protection of 220 kVDichpally- (Micom P741) which is available at site.
Medaram line while breaker lockout at Dichipalli SS 3. Monitoring of CBs is done regularly. --Completed
occurred.
3. TSTRANSCO to perform condition monitoring of
CB’s regularly to ensure sufficient air pressure for
proper CB operation.
Page 15 of 45
Annexure-II
84/II/27 Multiple tripping at 220 kV 27-05-2019 at Triggering incident was failure of B-phase CT of bus 1.TSTRANSCO is recommended to submit TSTRANSCO TSTRANSCO MAIL DATED30.10.2019: Pending
Ghanapur station 02:04 hr. coupler of Bus-2. Bus bar protection of 220 kV Bus-2 Equipment failure report to CEA regarding the blast 1. Informed our transmission wing to submit the Equipment failure report to CEA.
operated resulting in tripping of all elements connected CT. 2. All the existing old CTs are replaced with new one.
to Bus-2. 2.TSTRANSCO to inform if any old CTs exist in
Ghanapur SS and ensure healthiness of the same to
87/II/15 Tripping of 400/220 kV ICT-3 05-09-2019 at Triggering incident was R phase to Earth fault in 220 kV TSTRANSCO to check the transformer bushing CT to ensure TSTRANSCO Yet to be informed Pending
AT Mahbubnagar 12:41 hr. Veltoor-Shapur solar line. ICT#3 at Veltoor got tripped on identical characteristics for CT’s is all phases and submit a
REF protection and the same needs review. report regarding the same.
Page 16 of 45
Annexure-II
Karnataka
46/II/21 Trippings at 220kV Raichur 07-06-2015 at 1. KPCL to check the operation of anti-pumping relay KPCL Mail received on 21-10-2015: Pending
TPS 01:35 hrs on 220 kV side and keep it in healthy condition. 1) Anti-pumping contactors of all the nine 220KV Lines are in circuit and tested
periodically during AOH works of lines along with other protections.
2. KPCL to provide manual reset to the 220 kV side 2) Completed.
master trip relay. 3) Possibility to use both the 220kV buses as main bus under normal operation is
under review.
3. KPCL to use both the 220 kV buses as main buses Mail recieved on 23-11-2015:
under normal operation, and should go for single bus 1) Completed
operation only during emergencies. 3) Two bus operation for 220kV buses : In place of existing CT switching relays,
High speed manual heavy duty change over switch of sufficient current capacity will
be retrofitted to all feeders at 220kV station and same will be operated manually
during changeover of feeder by one bus to the other and this arrangement may
facilitate to put both buses in service. Time required for this retrofit is around 90days
. However, this work will be taken up only after retrofitting of electromagnetic relays
with numerical relays for Main-2 protection of all 220kV lines, for which work is in
progress.
Status received vide mail dated 10-07-2017:
1) --- Completed.
2) --- Completed.
3) Two Bus operation for 220kV bus is being carried out whenever required.
However scheme for tripping of one bus during LBB/fault and maintaining the other
bus intact by tripping B/C breaker will be taken up in R&M works. --- Pending
Status received vide KPCL mail dated 14.12.2017:
3) DPR for implementation of Two Bus operation for 220kV bus system has been
prepared and proposal is placed for funds from PSDF. After the approval of the DPR,
the work is proposed to be taken up.
54/II/9 Tripping of 400kV Raichur 13-04-2016 at Y-ph Pole of Tie-breaker of Unit-4 at RTPS failed. 1.KPCL to undertake the following remedial measures KPCL Status received vide KPCL mail dated 10.07.2017: Pending
TPS 21:12 hrs Unit-4 got tripped on operation of Generator to avoid breaker flashovers: 1. (ii) Hot line water washing stopped and off line water washing is carried out
Bus-2 Differential, Reverse power & LBB protection. (i) Replacing all porcelain insulators with composite whenever the 400 KV Unit or line is under tripped condition / Shutdown condition. ---
Operation of LBB protection led to tripping of BUS-2 insulators Completed
at RTPS (ii) Carrying out hot-line water washing of all 1. (iii) Silicon coating for Unit#8 main & tie breakers carried out in Sep'16 and same
insulators on regular basis. is under observation. Till today in order and good condition. For remaining breakers,
(iii) Applying Room Temperature Vulcanizing (RTV) since it is big order, approval for the same is under process. --- Pending
Silicone high voltage insulator coatings to all bus-
connected ceramic insulators of equipment like CT,
Page 17 of 45
PT, CB, Isolators etc.
Annexure-II
Operation of LBB protection led to tripping of BUS-2 insulators
at RTPS (ii) Carrying out hot-line water washing of all
insulators on regular basis.
(iii) Applying Room Temperature Vulcanizing (RTV)
Silicone high voltage insulator coatings to all bus- Review Meeting dated 19.12.2017:
connected ceramic insulators of equipment like CT, 1 (iii) As upgradation of 400kV switchyard equip's to be taken under PSDF funds,
PT, CB, Isolators etc. Silicon rubber coating for breakers is deffered till then. --- Pending
2.KPCL to take steps to provide dedicated breaker 2. Replacement by Num relay for Units - 5,6 & 7 completed in the month of Oct-
flashover protection to all breakers at Raichur TPS at 2017. Main-I is Seimens make and Main-II is ABB make. --- Pending
the earliest.
KPCL mail dated 19.01.2018:
2. Replacement of Numerical relays for Units-5, 6 & 7 have been completed.
Referred to OEM for providing the Breaker flashover protection for all the breakers.
2) Reply is awaiting from OEM to implement the Breaker flash over protection in the
Numerical relays in 400KV station. & Being discussed with other utilities.
It is requested to furnish Necessary logic and settings to implement the breaker
flashover protection
2) Reply is awaiting from OEM to implement the Breaker flash over protection in the
Review meeting on 27.06.2019:
SRPC informed that referenc of necessary logic and settings to implement the breaker
flashover protection will be shared soon.
Page 18 of 45
Annexure-II
54/II/13 Tripping of Units at 220 kV 15-04-2016 at During testing of retrofitted distance protection in In view of the availability of two buses along with KPCL Status received vide KPCL mail dated 10.07.2017 & 14.12.2017: Pending Timeline?
Raichur TPS 15:36 hrs 400kV Raichur-2 feeder, LBB protection trip DC got healthy bus-coupler at 220 kV RTPS, KPCL is Two Bus operation for 220kV bus is being carried out whenever required. However
extended to Bus trip. This resulted in tripping of 220kV recommended to put in service the double-bus scheme for tripping of one bus during LBB/fault and maintaining the other bus intact
bus at RTPS and all connected 220 kV elements. Unit- operation at 220 kV RTPS by suitably distributing by tripping B/C breaker will be taken up in R&M works.
4 which is connected to 400 kV Bus got tripped due to loads within 15 days.
tripping of Station Utility Transformer that is Review Meeting dated 19.12.2017:
connected 220 kV bus 3) KPCL informed that DPR for implementation of Two Bus operation for 220kV bus
system has been prepared and proposal is placed for funds from PSDF. After the
approval of the DPR, the work is proposed to be taken up. Time frame requested is 2
yrs.
Page 19 of 45
Annexure-II
58/I/3 Complete outage of 220 kV 06-09-2016 LBB of 220kV Kodasalli breaker at Kadra end got 1) KPCL to check settings of LBB protection in all KPCL Status received vide KPCL mail dated 14.06.2017: Pending
(GD) Kadra power station of at 14:40 hrs operated which resulted in tripping of Bus at Kadra relays from which it was implemented, and ensure that 1. All logics checked and found normal. LBB timing checked and found 200msec as
KPCL and in turn led to tripping of all elements their configuration, logic, and timing are in order at per KPTCL MRT recommendation. - Completed
their 220 kV Kadra PH. 2. Work Under Progress ---- Pending
3. New GPS System commissioned along with new numerical and synchronised with
2) KPCL to furnish details regarding the existing LT GPS system - Complied
auxiliary supply arrangement at their 220 kV Kadra 4. Work Under Progress ---- Pending
PH, and take steps to provide a suitable Auto-Main- Status received vide mail dated 14.12.2017:
Fail (AMF) panel for DG set to effect its auto-starting 1),3),4) Completed
in case of failure of LT supply. 2. Auto Start of DG set is taken up --- Pending
3) KPCL to ensure time-sync of all relays (DR’s & Review Meeting dated 19.12.2017:
EL’s) with GPS at their 220 kV Kadra PH. 2. KPCL informed that for AMF of DG, Scheme prepared & material procurement
under process. The AMF scheme will be implemented in January 2018. --- Pending
4) KPCL to provide stand-alone Event Logger at their 3. The GPS system commissioned on Nov 2016 & all the numarical relay time
220 kV Nagjheri PH. synchronised with GPS ---- Completed
Page 20 of 45
Annexure-II
69/II/8 Tripping of 220 kV Kaiga- 06-10-2017 at While de-synchronising of Unit-2, B-phase pole of KPCL to take steps to replace the existing static KPCL Status received vide mail dated 25.07.2018: Pending
Kadra line-1 22:22 hrs GCB did not open and pole descrepancy relay protection relays for Generator Units and Generating Numerical Generator protection relay replacement proposed to be taken up alongwith
operated. Hence all 220KV lines CB hand tripped. Transformers (GT’s) with suitable Numerical relays at SCADA work.
their 220 kV Kadra PH. KPCL mail dated 20.12.2018:
Will be taken up along with SCADA work. NIT to be issued on Jan-2019
Review Meeting on 21.12.2018:
KPCL informed that Tender for the work would be floated by March, 2019, and work
would be completed in 1 year.
KPCL mail dated 23.01.2019:
Tender for the work would be floated by February-2019 and work would be
completed in 1 year.
72/I/4 Complete outage of 220kV 01-02-2018 High resistance fault occurred in 110kV Sedam- KPCL to disable GFC protection on all lines KPCL Review Meeting on 21.12.2018 Pending
Sedam, Shahapur, Shahabad, at 17:46 hrs Chittapur line near Sedam end. Line DEF operated and emanating from their generating stations. KPCL informed that compliance w.r.t. Implementing the recommendation would be
Kapanoor, Humnabad and backup OC protection of 100MVA transformer furnished soon.
Halabarga Stations of operated at Sedam end. But line breaker and
KPTCL transformer HV breaker didn’t open due to problem in KPCL mail dated 23.03.2019:
trip circuit. This resulted in cascade tripping of 'GFC protection will be disabled in all lines in coordination with M/s.KPTCL
upstream feeders and power supply was lost to six
220kV stations of KPTCL. KPCL mail dated 10.05.2019 & 25.06.2019:
Letter addressed to CE, RT, KPTCL dated: 10.04.2019 to disable GFC protection
in all 220kV lines . Reply is awaited.
73/I/5 Complete outage of 220kV 15-03-2018 at There was Y-phase to ground fault on 220 kV Varahi - KPCL to take steps to put double-bus operation into KPCL Status received vide mail dated 25.07.2018: Pending
Varahi power station 22:36 hrs Shimoga line-2. Consequent to persisting fault in ‘Y’ service at their 220 kV Varahi PH. Under Implementation.
phase, the breaker failure protection operated resulting
in operation of 220KV bus bar protection at Varahi, KPCL mail dated 20.12.2018 & 23.01.2019 & 23.03.2019:
tripping all the connected lines and Varahi running Retrofitting of 220kV Bus Isolators is under progress. Proposed to be in service after
units. April-2019
78/I/1 Complete Outage of 220 kV 24-08-2018 at Due to suspected mal-operation of 220KV bus bar 1. KPCL to take steps to put double-bus operation into KPCL KPCL mail dated 20.12.2018 & 23.01.2019: Pending
Varahi UGPH. 11:00 hrs protection at Varahi, all the connected lines and Varahi service at their 220 kV Varahi UGPH by December, 1. Retrofitting of 220kV Bus Isolators is under progress. Proposed to be in service
running Units got tripped. (6 nos 220kV lines and 4 2018. after April-2019 --- Pending
nos Varahi generating station running Units). This 2. ---- Completed.
resulted in complete outage of 220kV Varahi UGPH 2. KPCL to employ correct operational practices like
keeping DC fuses of B/C CB intact during bus KPCL mail dated 23.03.2019:
changeover works, disabling back-up protections of 1) Retrofitting of 220kV Bus Isolators is under progress. Proposed to be in service
B/C CB during bus changeover works & enabling after April-2019
them with proper settings only when it is used as Main-
82/I/3 Complete Outage of 220kV 04-02-2019 at During de-synchronising of Kadra unit#2, R-pole CB of the grid
1) KPCL elements.
to ensure that DR and EL for all events are KPCL KPCL mail dated 10.05.2019:
10.03.2019: Pending
Kadra Power House of 20:19 hrs didn’t open due to struck breaker condition. Pole made available. If Static relays with no DR are present 1) Preparation of technical specification is completed. Tender will be floated during
KPCL & 220kV Karwar SS Discrepancy operated. All the connected 220kV lines in Station, standalone Disturbance recorder and Event 3rd week of May- 2019 for control & protection system along with SCADA.
of KPTCL at Kadra end were hand tripped. logger should be provided. 2) English Electric make static type relay is used for NPS protection system at Unit
2) KPCL to investigate the operation of Negative no.2. The detailed report shall be furnished shortly.
sequence relay and report to SRPC since the operation
of Negative sequence relay due to stuck breaker KPCL mail dated 25.06.2019:
condition is not proper as per protection philisophy 1) Preparation of technical specification is completed. Tender will be floated during
1st week of July 2019 for control & protection system along with SCADA.
2) Existing relays are English Electric Static type
@ GT -2
KPCL side,
mail Unit 16.07.2019:
dated breaker opened at 3MW, HV side current is
1) Tender published on 21.06.2019. Time line for completion of Work is Dec-2020.
2) Completed.
Page 21 of 45
Annexure-II
86/II/5 Tripping of 400 kV Raichur 03-07-2019 Line tripped on operation of overvoltage stage-1 1. KPCL to check the voltages of all three phases KPCL Yet to be informed Pending
TPS - Bellary TPS line at 4:39 hr. protection at Bellary TPS end and DT received at during trippings other than Overvoltage related
08-07-2019 Raichur TPS end. From BTPS end. Difference in phase trippings by triggering dummy DR’s. Tandelta and
at 5:20 hr. voltages observed from BTPS end DR (Vr-259kV, Vy- capacitance testing of CVT’s to be performed if
245kV and Vb-238kV) difference in voltages persist. If the results are found
violating standard values, then the CVT’s shall be
86/I/6 Tripping of 400 kV BTPS- 08-07-2019 Line tripped on operation of overvoltage stage-1 1. KPCL to check the voltages of all three phases KPCL Yet to be informed Pending
JSW line at 2:43hrs protection at Bellary TPS end and DT received at during trippings other than Overvoltage related
JSW. Difference in phase voltages observed at Bellary trippings by triggering dummy DR’s. Tandelta and
TPS from DR (Vr-241kV, Vy-257kV and Vb-225kV) capacitance testing of CVT’s to be performed if
difference in voltages persist. If the results are found
violating standard values, then the CVT’s shall be
replaced.
2. KPCL to adopt OVR 2018 gradings at BTPS end,
since tripping is not as per the grading.
87/I/3 Complete Outage of 220kV 29-09-2019 at 11:31 a. Single line to ground fault occurred in 220kV Kemar – KPCL to check A/R functionality for all lines emanating from KPCL Yet to be informed Pending
Kemar, MSEZ, hrs Varahi line-2 due to R-phase insulator flashover and the line 220 kV Varahi GS and submit a report regarding the same.
tripped on Zone-1 distance protection. Simultaneously, 220kV
Puttur&Kavoor stations of
Kemar – Varahi line-1 tripped at Kemar end only.
KPTCL b. 220kV Kemar –Varahi line-3 tripped due to overloading.
This resulted in complete loss of supply at 220kV Kemar since
all the three source feeders tripped.
c. In addition there was complete loss of supply at 220kV
MSEZ, 220kV Kavoor and 220kV Puttur stations since these
stations were radially fed from 220kV Kemar station.
40/I/1 GD-1 at 220kV Ambewadi 22-12-2014 Triggering incident was B-phase to earth fault in 1. Till the completion of R&M works for bus bar and KPTCL Mail received on 28-04-2015: Pending
Station of KPTCL at 21:22 hrs 220kV Ambewadi- Nagzari line-1. B-pole of breaker LBB protection, KPTCL shall explore the possibility 1. In view of operating 220kV Ambewadi SS in split bus mode, action is being taken
did not open at Ambewadi end. LBB protection not of having split bus operation at Ambewadi and submit up by KPTCL. Problem in the 220kV bus coupler breaker is attended and isolator
available at Ambewadi end. All elements tripped on the details of the same to PCSC forum. overhauling work is under progress. Spilt bus operation at Ambewadi will be made
Zone-2 from remote ends. possible at the earliest. --- Pending
2. KPTCL shall provide the details of the tripping of
Supa hydro station connected downstream from 110 2. ICT Protection system at Ambewadi and trippings occured at Supa GS during the
kV bus. instance is checked up and remedial measures already furnished in this regard.
KPTCL Mail dated 16.12.2017 & Review Meeting dated 19.12.2017:
1. Recommended works at Ambewadi have not been taken up due to various problems
faced due to poor response from the turn key agency M/s ERL. A site meeting is
planned during this month to discuss about further plan of action for attending SRPC
recommendations pertaining to the Sub station.
The issue was discussed in the review meeting. Considering the importance of the
substation and delay in executing the works, it was decided to escalate all pending
41/I/4 Complete outage at 220kV 27-01-2015 at R-Phase to ground fault occurred on 220kV Sedam- 1. KPTCL to provide Bus bar and LBB KPTCL issuesreceived
Mail relating to
onAmbewadi SS to KPTCL top Management for early completion.
28-04-2015: Pending 1. Status?
Sedam Substation of KPTCL 8.00 hrs Shahpur line. Fault not cleared from Sedam end due to protections for 220 kV bus at Sedam S/s. Procurement of Bus bar and LBB protection is in the final tendering stage. 2. Action
(GD-1) stuck-breaker condition. While the Sedam- Sahapur is being taken to restore the carrier protection for 220kV Sedam-Tandoor line. AR
line tripped from Shahapur end in Zone-1, the other 2. KPTCL to implement A/R feature on 220 kV will be enabled.
220 kv lines from Sedam tripped at remote ends in Sedam-Tandur inter-state line. Mail received on 29-07-2015:
Zone-2. This caused complete outage of 220kV Sedam 1. Procurement of Bus bar and LBB protection is in the final tendering stage.
substation. 2. Action is being taken to restore the carrier protection for 220kV Sedam-Tandoor
line. AR will be enabled after restoration of PLCC.
KPTCL mail received on 23-01-2016:
1. Bus bar protection panels pocured and erected at Sedam. Wiring , testing
,commissioning is being taken up.Planned to complete by April 2016.
2. Action is being taken to restore the carrier protection for 220kV Sedam-Tandoor
line. AR will be enabled after restoration of PLCC.
KPTCL Mail recieved dated 22-11-2017:
1 & 2). Bus Bar Protection panel and required Wave traps are supplied under R&U.
Wave trap to be commisioned in Tandoor line and PLCC to be restored.Once PLCC
is restored AR will be enabled. The Wave traps required are supplied under R&U
project and the same is to be commisioned at Sedam end for restoration of PLCC.
Page 22 of 45
Annexure-II
KPTCL Mail dated 16.12.2017:
1 & 2) Replacement of Bus Bar Protection is included under R&U project. Awarded
to M/s GE Ltd. Panels have alredy been supplied by the Agency. The work will be
taken up on top priority.
Page 23 of 45
Annexure-II
42/I/1 Complete outage of 220kV 15-02-2015 Fault occurred in 220kV Sedam-Shahpur line 1. KPTCL to provide Bus Bar protection and LBB KPTCL Mail received on 27-05-2015: Pending
Sedam substation of KPTCL at 14:24 hrs protection at Sedam S/s and furnish the status of their 1. Bus Bar protection will be provded under R&U.
implementation to PCSC forum. 2. A/R yet to be enabled.
Mail received on 29-07-2015:
2. KPTCL to implement A/R feature on 220 kV Sedam- 1. Procurement of Bus bar and LBB protection is in the final tendering stage.
Tandur inter-state line. 2. Action is being taken to restore the carrier protection for 220kV Sedam-Tandoor
line. AR will be enabled after restoration of PLCC.
KPTCL Mail Recieved dated 22-11-2017:
Bus Bar Protection panel and required Wave traps are supplied under R&U. Wave
trap to be commisioned in Tandoor line and PLCC to be restored.Once PLCC is
restored AR will be enabled.
KPTCL Mail dated 16.12.2017:
Review meeting on 27.06.2019:
1. Timeline - September 2019
2. Completed
42/I/2 Complete outage of 220 kV 12-03-2015 at Fault in 220kV Ambewadi-Nagjheri line-2 1. KPTCL shall provide A/R feature on Ambewadi – KPTCL Mail received on 29-07-2015: Pending
(GD) Ambewadi substation of 7:51 hrs Ponda 220 kV D/C inter-state line. 1. Procurement of Bus bar and LBB protection is in the final tendering stage.
KPTCL 2. Action is being taken to restore the carrier protection for 220kV Sedam-Tandoor
2. Till the completion of R&M works for bus bar and line. AR will be enabled after restoration of PLCC.
LBB protection, KPTCL shall explore the possibility
of having split bus operation at Ambewadi and submit KPTCL Mail Recieved dated 22-11-2017 & 16.12.2017:
the details of the same to PCSC forum. 1.Enabling the AR feature was discussed during PCSC meetings and since Ambewadi-
Ponda and Ambewadi-Xeldom lines are radial lines, it was decided that enabling AR
is not required. To clear the faults in the abovelines early, the timings of the Zone 2
KPTCL mail dated 20.12.2018:
The protection issues pertaining to Ambewadi was appraised to the management
and proposal for construction of new GIS SUb stations has been approved by KPTCL
management. Further as per SRPC directions and in view of attending protection audit
recommendations pertaining to Ambewadi SS without linking with new Station
proposal, action has been taken to include the works in extended scope of R&U
project awarded to M/s GE T&D India Limited. Addition materials required are yet to
be supplied by M/s GE. work expecnted to be completed in 5 months.
Page 24 of 45
Annexure-II
48/I/3 Outage of 220kV Ambewadi 30-09-2015 at 220kV Ambewadi-Nagjheri line-2 tripped on B-phase KPTCL to fast-track providing A/R on all 220 kV KPTCL KPTCL mail received on 23-01-2016: Pending Status?
station in Karnataka 10:41 hrs to earth fault. This resulted in loss of supply to 220kV lines emanating from Ambewadi SS to prevent Station Will be complied in a months time.
Ambewadi bus. 220kV Ambewadi-Ponda line-1&2 shut-down on temporary faults. KPTCL Mail Recieved dated 22-11-2017:
were hand tripped after deenergization of bus at Enabling the AR feature was discussed during PCSC meetings and since Ambewadi-
Ambewadi. Ponda and Ambewadi-Xeldom lines are radial lines, it was decided that enabling AR
is not required. To clear the faults in the abovelines early, the timings of the Zone 2
was reduced to 150mS and the Back Up EFR timings have been reducedto 150mS.
KPTCL Mail dated 16.12.2017:
Enabling the AR feature was discussed during PCSC meetings and since Ambewadi-
Ponda and Ambewadi-Xeldom lines are radial lines, it was decided that enabling AR
is not required. To clear the faults in the abovelines early, the timings of the Zone 2
was reduced to 150mS and the Back Up EFR timings have been reduced to 150mS.
In view of the above, it is requested to drop the issue from this list.
KPTCL mail dated 20.12.2018:
The protection issues pertaining to Ambewadi was appraised to the management
and proposal for construction of new GIS SUb stations has been approved by KPTCL
Page 25 of 45
Annexure-II
52/I/3 Complete outage of 220 kV 22-02-2016 at 220kV Bus Bar protection operated during failure of R KPTCL to operate 220 kV Shimoga on multi-bus KPTCL KPTCL Mail received dated 25-04-2017: Pending
Shimoga substation 15:03 hrs phase CT in DVG-2 line bay. operation under normal conditions, and put it on single- Replacement of existing BBP by new BBP with 4 zone protection is being taken up
bus operation only under emergency conditions. under R&U.
KPTCL Mail Recieved dated 22-11-2017:
GE Ltd has already supplied the necessary Bus Bar protection panels for replacement
of the existing static type BBP by new numerical BBP with 4 zone protection under
R&U project. The work of commissioning the same will be taken up shortly.
57/II/1 Tripping of 220 kV Chikkodi- 01-07-2016 at Triggering incident was failure of B-ph PT of 220kV 1.KPTCL to take steps to provide busbar protection at KPTCL KPTCL Mail Recieved dated 22-11-2017: Pending
Mudshingi and 220 kV 03:03 hrs Bus-2 (western bus) at 220KV Chikkodi substation. their 220 kV Chikkodi inter-regional substation, and 1. The necessary Bus Bar protection panels are already supplied to Chikkodi under
Chikkodi-Talandage lines 220KV Chikodi- Belgaum-I line tripped on DEFR furnish a time-line for the same. R&U project. Presently R&U works at sub stations subjected to audit are taken up.
(Inst), 220KV Chikkodi-Kudachi line tripped on After completion of PAR works, the baove works are planned.
Distance protection and also 100MVA transformer-2 2.KPTCL to review distance protection settings for --- Pending
tripped on E/F protection. 220 kV Chikkodi – Kudachi line. 2. --- Pending
3. --- Pending
KPTCL mail dated 20.12.2018:
3.KPTCL to furnish equipment failure report of the
1). Bus Bar Protection work is included under R&U. work expected to be completed
current incident to PSE&TD Division of CEA with a
in 3 months ---- Pending
copy marked to SRPC.
2). Major equipment failure reports are being sent to CEA regularly ----
Completed.
Page 26 of 45
Annexure-II
62/II/3 Tripping of 220 kV Bus 2 09-01-2017 Failure of R-phase CT of 220/ 66 kV transformer-2 at 1. KPTCL to provide Busbar protection at their 220 KPTCL KPTCL mail received dated 25.04.2017: Pending
and connected elements at 23:06 hrs 220kV Hoody end resulted in a bus fault in 220kV Bus- kV Hoody SS at the earliest. Numerical BBP is being provided under R&M works.
(220kV HAL #1 and 2, 2. Fault was cleared by backup protection of ICT's
400/220 kV ICT- 1, 2 and (220kV lines were being radially operated) due to 2. KPTCL to furnish an Equipment Failure Report on KPTCL Mail Recieved dated 22-11-2017:
220/66 kV ICT-2) at absence of busbar protection CT failure to CEA with a copy marked to SRPC. 1. Numerical Bus Bar protection panels have already been supplied as a part of R&M
KPTCL mail dated 20.12.2018:
400/220 kV Hoody
1). The R&M work of 220kV Hoody SS is under progress and expected to be
substation of KPTCL (Load
comleted before the end of August 2019. Providing Bus Bar Protection to 220kV
loss : 590 MW)
buses is a part of R&M work at Hoody ----- Pending
62/II/5 Tripping of 220 kV South 20-01-2017 at Triggering incident was fault in 66 kV Somanahalli - KPTCL to provide numerical Busbar Protection at KPTCL KPTCL mail received dated 25.04.2017: Pending
Bus and connected elements 14:34 hrs Bannerghatta line and fault was cleared by operation of their 220 kV Somanahalli SS at the earliest. Numerical BBP is being provided under R&M works
(220kV HSR, 220kV Back-up OCR at Somanahalli end.
Nagnathpura, 220 kV KPTCL Mail Recieved dated 22-11-2017:
Harohalli, 220 kV Tesing & Commissioning of numerical BBP at Somanahalli is under progress. There
Subramanyapura, 220 kV was some technical issue wth BBP scheme supplied to Somanahally which is being
Tataguni, 220 kV Mallur and finalised in consultation with OEM SIFANG. Numerical BBP will be commissioned
74/I/2 400/220kVoutage
Complete ICT-2ofand
2203)kV
at 02-04-2018 at Loss of supply occurred to 220 kV Ambewadi station 1). KPTCL to review operation of SPS at NPH for KPTCL at Somanahally
KPTCL within20.12.2018:
mail dated a month's time. Pending
Ambewadi station 13:46hrs due to tripping of 220kV Nagzhari-Ambewadi line-2 proper functionality and changed network conditions 1). To be reviewed. Expected to be completed in 1 month.---- Pending
(Source) from Nagzhari power station. After bus dead, (reduction of generation with tripping of evacuating
Ambewadi-Ponda lines – 1 & 2 were hand-tripped. In lines) and put it into service at the earliest. 2), Being followed ----- Pending
antecedent conditions, 220kV Ambewadi - Nagjheri
ckt-1, 220kV Ambewadi-Narendra Ckt-1 &2 were out 2). KPTCL to furnish equipment failure report of the Review meeting on 27.06.2019:
of service. current incident (R-phase CT in Nagjheri – 1 bay at 1. Nagjheri SPS shall be studied in view of changed system configuration
Ambewadi SS) to PSE&TD Division of CEA with a 2. Completed
copy marked to SRPC.
74/II15 Multiple Trippings at 21-04-2018 at Triggering incident was fault in 220 kV Davanagare - KPTCL to put double-bus operation at their 220 kV KPTCL KPTCL mail dated 20.12.2018: Pending
400/220kV Guttur station 12:50 hrs Shimoga line. Bus bar protection operated at Guttur Guttur substations by attending to Bus-2 CVT Bus-2 CVT problem is attended. However due to breaker replacement works, 220kV
resulting in tripping of all the connected elements. 220 problem. side operated in single bus mode.
kV Guttur was on single bus operation due to CVT
problem in Bus-2. Review Meeting dated 20.12.2018:
KPTCL informed that double-bus operation at their 220 kV Guttur would be provided
within two months.
79/III/9 Tripping of 400 kV JSWEL 29-09-2018 R-phase to earth fault occurred in line. Auto-reclose KPTCL to furnish a detailed report on tripping event KPTCL Review Meeting on 21.12.2018: Pending
–Guttur line at 11:30 hrs was not attempted at JSWEL due to DT receive. At bringing out reasons for DT sending from Guttur end KPTCL was aksed to furnish status of implementation of the recommendation given
Guttur end auto-reclose could not be validated with to JSWEL on 400 kV Guttur - JSWEL line along with at the earliest.
DR/EL. remedial action taken to PCSC forum.
Review meeting on 27.06.2019:
report will be submitted by KPTCL
80/II/7 Tripping of 400 kV JSWEL- 17-10-2018 at Triggering incident was R-phase to earth fault in line. KPTCL to examine the reasons for sending of DT from KPTCL Review meeting on 27.06.2019: Pending
Guttur line 02:04 Hrs At Guttur end there was operation of pole discrepancy Guttur end to JSWEL end, and furnish an action taken report will be submitted by KPTCL
and resulted on tripping of Y & B pole after a duration report including remedial measures taken to rectify the
of 2 seconds from the occurrence of fault. FIR, DR & same.
EL of Guttur end were not furnished.
82/I/4 Complete Outage of 220kV 06-02-2019 at Fault occurred while test charging of 220kV KPTCL to investigate the reason for non-tripping of KPTCL Review meeting on 27.06.2019: Pending
Ambewadi Station of 14:51hrs Ambewadi – Nagjheri Line -2 from Ambewadi end. 220kV Ambewadi - Nagjheri line-2 on operation of report will be submitted by KPTCL
KPTCL Suspected stuck breaker condition at Ambewadi end) SOTF and submit a report regarding the same to
led to clearing of fault by tripping of remote end SRPC. Also KPTCL to take necessary measures in
breaker in Zone-2. LBB protection is not active at order to ensure healthiness of breaker before
82/I/8 Complete outage of 220kV 20-02-2019 at 220kV
As Ambewadi
informed station.Suspected delayed clearance
by KPTCL, testcharging
1) KPTCL isofrecommended
any line. to furnish detailed report KPTCL Review meeting on 27.06.2019: Pending
Alipura substation 12:45 hrs of fault in 220 kV BTPS-Lingapur line from BTPS end regarding spurious operation of DEF at Alipur SSand report will be submitted by KPTCL
resulted in tripping of lines from Alipura S/s. check the directionality of DEF on all lines.
2) KPTCL is requested to share the revised zone
settings for Distance protection at BTPS end.
Page 27 of 45
Annexure-II
82/II/12 Tripping of 400kV Kaiga- 07-02-2019 Line-1 tripped due to insulator flashover. Line-2 KPTCL is recommended to take necessary measures to KPTCL Review meeting on 27.06.2019: Pending
Guttur line-1&2 at 11:49 hrs tripped due to zone-3 operation at Kaiga and Direct ensure that Main-I and Main-II at Guttur end shall be KPTCL informed that the recommendation has been included as part of R & M work.
trip receive at Guttur of different types (make and model) coherent with the Timeline will be informed
general protection philosophy followed in SR region.
84/II/12 Tripping of 400kV DHONI 18-04-2019 at Triggering incident was failure of B-ph CB of 400kV 1. KPTCL to send equipment failure report, KPTCL Yet to be informed Pending
GUTTUR line- 1 18:59 hr. Dhoni-Guttur line at Dhoni end. This resulted in the corresponding to the failed CB at Dhoni SS, to CEA.
operation of LBB of bus-1 and DT was sent to Guttur 2. KPTCL to ensure time synchronization at Guttur
end end.
84/II/24 Tripping of 400/220 kV ICT- 13-05-2019 at ICT-3 tripped on operation of 59N neutral KPTCL to inform PCSC forum regarding the changes KPTCL Yet to be informed Pending
1&3 at Hoody Substation 15:35 hr. displacement relay. ICT-1 tripped on OCR. implemented in Hoody ICT SPS and to ensure time
synchronization of relays at Hoody SS.
85/I/4 Tripping of 220kV Sedam-RTPS 14-06-2019 Tripped on Directional Earth Fault indications in Main- 1. KPTCL is recommended to enable A/R on all lines KPTCL Yet to be informed Pending
line-1&2 and 220kV Sedam- at 02:00 hrs 2 relay at Tandur end for fault at Raichur end. Sedam emanating from 220kV Sedam SS.
Tandur line end details not furnished. 2.KPTCL is recommended to commission BBP at
220kV Sedam SS immediately.
85/II/5 Tripping of 400/220 kV ICT-3 at 19-05-2019 As per FIR, ICT-3 got tripped on operation of High Set 1. KPTCL is recommended to enable auto-reclosure KPTCL Yet to be informed Pending
Nelamangala substation at 16:11 hrs Over current trip on 400kV side on all lines emanating from 400/ 220kv Neelamangala
SS and to ensure time synchronization of relays at
Neelamangala SS.
85/II/11 Tripping of 400kV Hoody- 25-05-2019 Line tripped at Hoody end only and was holding from KPTCL is recommended to check the spurious KPTCL Yet to be informed Pending
Yelahanka line-1 at 20:41 hrs Yelahanka. operation of SOTF protection at Hoody SS and submit
a report to SRPC regarding the same .
85/II/12 Tripping of 400/220 kV ICT-1at 26-05-2019 LV side of 400kV/220kV 315MVA ICT#1 Guttur got 1. KPTCL is recommended to submit a report to SRPC KPTCL Yet to be informed Pending
Guttur Substation at 10:00 hrs tripped due to CB lockout (B phase)because of low after the CB pressure leakage problem is attended by
SF6 gas in the CB OEM.
2.. KPTCL to ensure that during recharging of Circuit
breakers, cylinders with Non-return valve only are
used to prevent sudden pressure drop in Circuit
breakers.
85/II/22 Tripping of 400kV Dhoni- 06-06-2019 Line got tripped at Dhoni end. From DR Zone-3 start, KPTCL is recommended to submit a report regarding KPTCL Yet to be informed Pending
Munirabad line at 02:01 hrs PSB and A/r block was observed. PSB maloperation along-with the RM suggested by
OEM. Proper legends shall be ensured for digital
signals at Doni end.
Page 28 of 45
Annexure-II
85/II/27 Tripping of 400/220kV ICT-2 at 16-06-2019 ICT-2 got tripped on operation of over-flux protection KPTCL is recommended to adopt v/f settings as per KPTCL Yet to be informed Pending
Hoody substation at 19:20 hrs manufacture suggested curve.
v/f setting for alarm: 1.1 time Vnominal; Time delay
10 seconds;
v/f trip setting : v/f is 1.2 time Vnominal;Time delay
60 seconds
85/II/29 Tripping of 400kV Hiriyur- 22-06-2019 at 400kV Hiryur-Nelamangala line-1 : 'Y' phase bushing KPTCL is recommended to submit equipment failure KPTCL Yet to be informed Pending
Nelamangala line-1 and 400kV 04:06hrs of Hiriyur line-1 reactor failed at Nelamangala end report to CEA regarding the reactor bushing failure
Gooty-Nelamangala line resuting in a R-Y phase fault. Direct trip was sent to and also to sort out time synchronization issues of
Hiryur. 400kV Hiriyur-Nelamangala line.
85/II/30 Tripping of 400/220kV ICT-1&2 24-06-2019 400/220kV ICT-1&2 at Munirabad end got tripped due KPTCL is recommended to submit equipment failure KPTCL Yet to be informed Pending
at Munirabad substation at 20:50 hrs to operation of High set of backup earth fault relay report to CEA regarding the CT and PT failure.
during failure of Y phase CT in 220kV Munirabad-
Kalyani steel feeder at Kalyani steel end
86/II/9 Tripping of 400 kV 15-07-2019 line tripped on operation of OV st-1 protection at KPTCL to configure both OVR start and OVR trip in DR or EL KPTCL KPTCL mail dated 30.10.2019: Pending
Neelamangala-Mysore line-2 at 2:02 hr Neelamangala end and DT was received at Mysore end. DR of at 400 kV Neelamangala SS. Time sync issues at 400 kV DR triggering has been done for OVR stage-1 operation in Mysore-2 line . GPS time
Nelamangala end was not available for validation of OV Neelamangala SS shall also be sorted out immediately. synchronisation of Power Grid bays will be taken up along with panel replacement work
protection operation envisaged under R&M.
OVR_start also to be configured.
Page 29 of 45
Annexure-II
49/I/3 Complete outage of 220kV 29.10.2015 at 220kV Nagjheri-Ambewadi line-1 tripped at 13:33 hrs 1. KPCL to provide A/R on all 220 kV lines emanating KPCL/ KPTCL KPTCL Mail Recieved dated 22-11-2017: Pending
Ambewadi Substation of 14:34 hrs due to B phase to earth fault. Ambewadi was radially from Nagjheri PH. 1. coordination of KPCL has been requested for enabling AR lines terminated to
KPTCL fed from Nagjheri power station through 220kV Nagajari.
Nagjheri-Ambewadi line-2. Tripping of this line 2. KPTCL to provide A/R on all 220 kV lines 2. AR will be enabled at Ambewadi end for lines other than Ponda and Xeldom lines
caused 220kV Bus shut down at Ambewadi and emanating from Ambewadi SS. during retrofitting of Back Up protection by Distance protection relay at Ambewadi.
remaining lines and transformers were hand tripped
KPTCL Mail dadted 16.12.2017 & Review Meeting dated 19.12.2017:
1. KPTCL informed that Coordination of KPCL has been requested for enabling AR
lines terminated to Nagajari.
--- Pending
2. KPTCL informed that AR would be enabled at Ambewadi end for lines other than
Ponda and Xeldom lines during retrofitting of Back Up protection by Distance
protection relay at Ambewadi. -- Pending
Page 30 of 45
Annexure-II
53/I/3 Complete outage of 220kV 18-03-2016 at Ambewadi Narendra line-2 tripped on fault and 220kV 1. KPCL to furnish a report on the reasons for Unit-6 KPCL/ KPTCL KPTCL Mail received dated 28-06-2016: Pending
Ambewadi station of 14:40 hrs ambewadi Narendra line-1 tripped due to over-loading. tripping at Nagjheri PH. Modifications to be carried in Nagzari SPS logic is submitted to SRLDC/SRPC for
KPTCL and 220kV Nagjheri Running Units at Nagjheri also tripped during the event verification and approval
of KPCL due to tripping of evacuating lines 2. KPCL/ KPTCL to modify suitably the SPS at
Nagjheri Power House such that it would also factor in Status received vide KPCL mail dated 14.06.2017:
the over loading of Ambewadi-Narendra lines. 1. Tripped since there was evacuation problem and there were only two lines NA-1
and NA-2 ---- Completed
3. KPCL to put 220 kV Kodasalli - Nagjheri D/C lines 2. Will be reviewed in consultation with EE(RT), KPTCL, Hubli. --- Pending
into service if more than 200 MW generation from 3. Both the lines are in charged condition. --- Completed.
Kali Complex (with Nagheri Contribution not less than
50 MW) is ensured on sustained basis. KPTCL Mail Recieved dated 22-11-2017:
2. Proposed revision in existing SPS scheme is already submitted to SRLDC/SRPC.,
yet to be discussed and approved by the SRPC forum. --- Pending
Tamil Nadu
Page 31 of 45
Annexure-II
62/II/7 Tripping of running Units & 25-01-2017 at Failure of Bus Section-I Y-ph CT resulted in operation 1. TANGEDCO to replace existing Check-Zone relay TANGEDCO TANGEDCO mail dated 15.04.2017: Pending Status?
230kV feeders at Tuticorin 22:36 hrs of bus-bar protection for Bus Sections -I & II. Running with a new one possessing required performance. 1) New Relay is tested and ready for replacement.Now all 5 units are in service.The
TPS of TANGEDCO Units#1, 4 and 5, 230 kV Kayathar, 230kV relay will be replaced when lesser units are in service. --- Pending
Kudankulam, 230kV Sterlite, Station Transformer-1, 2 2. TANGEDCO to take steps to provide numerical 2.a)Steps are taken to renovate & mordernization of all the control panel into
(Gen Loss: 640 MW) & 3 got tripped during the incident. Unit – 2 & 3 were busbar protection at their 220 kV Tuticorin TPS. Numerical based control panels. --- Pending
not in service. TANGEDCO may also explore providing dual CT’s 2.b) Since 230 KV indoor switchyard has no spare space providing dual CT`s is not
(on either side) for all B/S breaakers at the time of fessible. -- Completed
commissioning of numerical BBP, if there were no 3) Procurement of EL & DR is under progress. --- Pending
space constraints.
TANGEDCO mail dated 26.04.2017:
3. TANGEDCO to take steps to provide for standalone 1) Check zone New Relay is replaced on 17.04.2017 -- Completed.
Event Logger (EL) and standalone Disturbance 2. --- Pending
Recorder (DR) with automatic downloading facility to 3. --- Pending
a centralized server.
TANGEDCO mail dated 13.12.2017:
2).P & C wing gives clearance to TTPS to procure the Bus bar protection relays and
protection relays and SER / DR system vide
Lr.CE/P&C/SE/D/EEPC4/AEE3/F.TECH/D.27/17 Dated: 05.10.2017. To get
administrative approval budgetary offer has bar protection relay from various
companies ----Pending
3). SRPC vide Lr: SRPC/SE- III/CEA/2017/6450/DT:27.10.2017 gives features of
SER/DR. Budgetary offer will be called for SER / DR having above features. ---
Penidng
50/I/3 Complete outage of 230kV 21-12-2015 at Busbar protection got operated for a fault in 230kV TANTRANSCO to examine the feasibility of TANTRANSCO TANTRANSCO Mail received on 19-02-2016 and 24-03-2016: Pending
Mywadi station of 6:28 hrs Mywadi-Anaikadavu line providing two main-zone operation for bus bar Revision of Bus Bar Protection setting was carried out. The stabilizing voltage
TANTRANSCO protection by exploring various alternatives like setting was raised from 410 to 450 volts. After completing the necessary test, the bus
replacing existing bus-coupler CB with a hybrid bus- bar protection put in to service on 29.12.2015.
coupler CB that comes with inbuilt CT, replacing Mail Received on 27-04-2016 ,16-06-2016,25-07-2016 & 24-09-2016:
existing BBP relay with another suitable relay that Revision of Bus Bar Protection setting was carried out. After completing the
supports two main-zone operation, and implement the necessary test, the bus bar protection put in to service on 29.12.2015.
same. Mail received on 10-11-2016 & 20.12.2016:
Provision of Bus Coupler bay arrangement was included in the Upgradation works
proposed and the same was sanctioned by MoP through PSDF.
Numerical relay allotted and being commissioned.
Mail received on 20-02-2017:
Numerical BBP relay was commissioned on 02.02.2017
Status received vide mail dated 18-09-2017 & 31-20-2017:
Numerical BBP relay was commissioned on 02.02.2017. Provision of CT in Bus
Coupler bay is arranged and zone segregation will be provided.
Status received vid email dated 12-12-2017:
Numerical BBP relay was commissioned on 02.02.2017. Provision of CT in Bus
Coupler bay has been allotted. Zone segregation will be provided after commissioning
of CT.
Review Meeting dated 19.12.2017:
TANTRANSCO informed that the recommendation would be complied with by
Page 32 of 45
Annexure-II
Status received vid email dated 11-12-2018:
Civil work completed & CT will be commissioned after strengthening Bus .2
conductor jumpers.Awaiting Bus LC Time line before January 2019.
55/I/1 Complete outage of 230 kV 12-05-2016 at Flashover of Auto Transformer- 2 HV TANTRANSCO to take steps to provide double-bus TANTRANSCO Mail recieved on 25-07-2016 & 24-09-2016: Pending
(GD) Gummidipoondi Station of 12:15 hrs B-phase Isolator supporting insulator of 230kV operation at their 230 kV Gummidipoondi SS. TANTRANSCO: Auto Transformer-2 HV side Bus isolator 'C'-phase support
TANTRANSCO Southern Bus occurred at Gummidipoondi station. At insulator of 230kV Southern Bus was replaced and Bus Bar Protection scheme was
the time of fault, Bus bar protection relay was not in restored on 12.05.2016.
service for pre-commissioning testing of Auto Status received vide mails received on 10-11-2016 & 20.12.2016 & 12.04.2017
Transformer-2. All feeders got tripped due to operation & 01.06.2017 & 15-06-2017 & 04.08.2017 & 18.09.2017:
of zone-2 protection from remote ends. CT is not available in the Bus Coupler bay for zone segregation. CT latch relay is to
be provided for all bays for zone segregation.
Page 33 of 45
Annexure-II
58 Different type and Make of distance protection relays to be provided for Main-I & Main-II protection for 230kV feeders at 400 kV Sunguvarchathiram & 230 kV TANTRANSCO The issue was discussed in PCSC-58 meeting held on 18.10.2016, when PCSC forum Pending
Sunguvarchathiram Substation [Carry-Over from Protection Audit Recommendations] agreed to de-link the implementation of the Item from the scope of Protection Audit
Recommendations (PAR), and pursue it as part of PCSC Recommendations.
Status received vide mails dated 10.01.2017 & 12.04.2017 & 01.06.2017 &15-06-
2017 & 04.08.2017 & 18.09.2017 & 31-10-2017& 12-12-2017:
Different make Relays will be provided for Main-I & II relays at Sunguvarchatram
end in a phased manner.
58/II/17 Multiple tripping at 230 kV 14-09-2016 at Bus Bar Protection (Zone-2) of 230 kV Bus-B got 1. TANTRANSCO to check the healthiness of BBP TANTRANSCO Mail received on 10-11-2016 & 20.12.2016: Pending
Alamathy Station 11:13Hrs operated at Alamathy Station during fault in 230 kV relay by conducting stability test, and take appropriate 1. The Bus Bar Protection scheme will be tested for healthiness including the CT
Alamathy-Korattur feeder. remedial action like increasing voltage settings, circuits.
ensuring the healthiness of CT’s, using CT’s with 2. High impedance BBP relay will be replaced by Numerical relay.
similar characteristics (equal saturation effects & Status received vide mails dated 10.01.2017 & 12.04.2017 & 01.06.2017 & 15-06-
equal winding resistances) etc. at their 230 kV 2017:
Alamathy SS. 1. The Bus Bar Protection scheme was tested for healthiness including the CT
circuits. AREVA make CTs in Alamathy SS are having different kneepoint voltage
2. TANTRANSCO to replace the existing high- for the cores. CT cores of higher knee point voltage has been choosen for BBP in
impedance BBP relay with its low-impedance/ 230kV Korattur, 230kV OPG-1 & 230kV OPG-2 feeders on 29.11.2016. ----
numerical variant so as to accommodate variation in Completed.
CT characteristics at their 230 kV Alamathy SS.
2. High impedance BBP relay will be replaced by Numerical relay. --- Pending,
Status received vide mails dated 04.08.2017 & 18.09.2017 & 31-10-2017 & 12-
12-2017.
1. ---- Completed
2. High impedance BBP relay will be replaced by Numerical relay. --- Pending
15-09-2016 at Bus Bar Protection (Zone1) of 230kV Bus-A got
Review Meeting dated 19.12.2017:
22:14 hrs operated at Alamathy Station during fault in 230 kV
2) TANTRANSCO informed that Numerical BBP would be provided by April, 2018
Alamathy-OPG-1 feeder.
--- Pending
TANTRANSCO mail received on 25-01-2018:
1. --- Complied.
2. High impedance BBP relay will be replaced by Numerical relay. Timeline: April-
2018.
Page 34 of 45
Annexure-II
TANTRANSCO MAIL DATED 11-12-2018:
Numerical BBP relay to procured. Timeline: Sep-2019.
Page 35 of 45
Annexure-II
64/1/4 Complete outage of North 26-03-2017 Tripping of evacuating lines due to fault led to tripping 1. TANTRANSCO to take steps to complete insulator TANTRANSCO Status received vide mails dated 04.08.2017 & 18.09.2017 & 31-10-2017: Pending
Chennai TPS STG-1 at 23:14hrs of running Unit at NCTPS Stg-1 replacement works on the 230 kV lines owned by them 1. All the Porcelain insulators were replaced with Polymer insulators in 230kV
in NCTPS area within 6 months. NCTPS-I - Tondiarpet feeders - 1 & 2.
---- Completed
2. TANTRANSCO to take steps to implement A/R on 2. AR will be implemented on all 230kV lines emanating from NCTPS-I. --- Pending
all 230 kV lines emanating from NCTPS-I at the
earliest. Status received vid email dated 12-12-2017:
1. Completed
2. The scheme needs modification to enable AR, since AR was not envisaged for this
station during commissioning. AR will be implemented on all 230kV lines emanating
from NCTPS-I within six months. --- Pending
77/II/9 Multiple trippings at TANTRANSCO to refer the issue of selective tripping TANTRANSCO mail dated 11.09.2018: Pending
400 kV Manali Substation of 400 kV side breakers, and non-tripping of 230 kV OEM will be referred
side breakers due to operation of Densimeters on low
pressure in the instant case to their OEM, and share Review Meeting on 21.12.2018:
OEM’s advice/ remedy in this regard. TANTRANSCO was asked to update the status.
Page 36 of 45
Annexure-II
79/I/3 Complete outage of 230 kV 05-10-2018 at Bus-1 got tripped at 230 kV Thiruvalam substation due TANTRANSCO to take steps to implement multi-bus, TANTRANSCO TANTRANSCO MAIL DATED 11-12-2018: Pending
Thiruvalam Substation 14:32 hrs to spurious LBB relay (independent) operation of multi-zone operation (Double-bus operation) at their Due to space constraint, the equipments could not be erected.
230kV Thiruvalam Chittoor line. 230kV Thiruvalam 230 kV Thiruvalam SS by December, 2018. Review Meeting on 21.12.2018:
substation was under single bus operation; hence It was noted that the station was on a single (Main) bus and there was not even
operation of LBB protection resulted in tripping of all transfer bus. In view of the importance of 230 kV Thiruvalam SS, TANTRANSCO
connected elements resulting in the complete outage was asked to take steps to provide dobule-bus operation at their 230 kV Tiruvalam
SS.
82/I/1 Complete outage of 400kV 28-01-2019 Failure of ‘R-phase’ HV side Current transformer (CT) 1) TANTRANSCO to ensure proper legends for DR TANTRANSCO TANTRANSCO MAIL DATED 13.06.2019: Pending
Sriperumbudur station at 01:15 Hrs of 315MVA 400/230kV ICT-3 at 400kV Digital signals and all required events(including CB 1. At present Duobias relay avaiable I/O configuration could not be carried out.after
Sriperumbudur substation (400kV TANTRANSCO status, Type of protection operated) are captured in changing the relay Digital signals will be configured
switchyard). Event logger. 2.COMPLIED
2) TANTRANSCO to extend BBP trip from BusBar 3.Provision of Numerical BBP relay covered under R&M work. Tender under
relay to 86A (with source-1 DC) in addition to 86B progress.
(with source-2 DC), or to provide Common trip relay 4.out of 30 CTs, 21 No CTs have been replaced with new one.
96 with redundant DC supply.
3) TANTRANSCO to inform the action plan with Review meeting on 27.06.2019:
timelines for providing Numerical BBP at 1. , 3. Timeline requested upto July 2020.
Sriperumbdur SS . 2. Complied
4) TANTRANSCO to check the healthiness of all 4. Timeline requested upto September 2019.
CT’s in the stationand submit a report regarding the
same to SRPC to prevent any such occurrence in
future. TANTRANSCO mail dated 18.07.2019:
1. At present Duobias relay avaiable I/O configuration could not be carried out.after
changing the relay Digital signals will be configured
2.COMPLIED
3.Provision of Numerical BBP relay covered under R&M work. Tender under
progress.
4.out of 30 CTs, 21 No CTs have been replaced with new one.
85/II/1 Tripping of 400/230kV 13-05-2019 at ICT-3 got tripped on the activation of HV REF 1. TANTRANCO is recommended to sort out the TANTRANSCO TANTRANSCO mail dated 11.11.2019: Pending
MANALI ICT-3 2:42 hrs protection. During test charging of 110 kV Manali- malfunctioning of ICT Ref protection in consultation 1. The issue was addressed to OEM reply awaited.
ETPS -1 , the 110 kV ETPS -1 got tripped on the with OEM and submit a detailed report regarding the 2. Uniform Labelling of Digital signal will be ensured.
activation of Back up relay and Distance relay failed to same in 1 month time.
act 2. TANTRANSCO is recommended to ensure proper
labelling of all digital signals in Disturbance recorders
of lines and ICTs at Manali SS.
85/III/6 400 KV Thiruvelam – Palavadi 28-05-2019 at 18:04 B-phase to earth fault. A/r attempt could not be validated. TANTRANSCO is recommended to check sending of DT from TANTRANSCO TANTRANSCO mail dated 11.11.2019: Pending
line-1 hrs Palvadi end during 3-ph trip at Palvadi. The time Extension of DT signal for the tripping was suceessful.
synchronization issues between Thiruvalem and Palvadi shall
also be rectified.
85/IV/6 Tripping of 400kV Kayathar- 10-06-2019 at 12:22 Line-1 & 2 tripped at Kanarpatty end due to spurious DT sent TANTRANSCO is recommended to submit a report regarding TANTRANSCO TANTRANSCO mail dated 11.11.2019: Pending
Kanarpatty line-1 & 2 hrs from kayathar end. Feeder did not trip at Kayathar end the problem with PLCC panel at Kayathar along-with OEM suggested that Zener diode is to be provided to enhance the threshold voltage
Remedial Measures suggested by OEM.
86/II/22 Tripping of 400/110 kV Kamuthi 10-08-2019 ICT tripped due to operation of 110 kV Bus bar protection TANTRANSCO to regularly carry out thermovision scanning TANTRANSCO TANTRANSCO mail dated 11.11.2019: Pending
ICT-3 at 11:00 hr. in the switchyard to identify weak links, if any. TANTRANSCO informed that it will be done.
Page 37 of 45
Annexure-II
87/II/7 Outage of 230 kV Bus-1 at 19-08-2019 at 12:28 Triggering incident was jumper cut of 230 kV Madurai- 1.TANTRANSCO to submit a report regarding non-operation TRANTRANSCO Yet to be informed Pending
400/230 kV Madurai station of hr. Ranganathapuram feeder. Bus bar protection of Bus-1 of A/R at Renganathapuram and to change the digital signal
TANTRANSCO operated resulting in tripping of all elements connected to legend from carrier fail to carrier healthy.
230 kV bus-1. 2. TANTRANSCO to configure digital signals corresponding
to CB status in DR and sort out time synchronization issues at
230 kV Checkanurani SS.
87/II/18 Multiple Tripping at 230kV 10-09-2019 at 13:24 Triggering incident was B phase to Earth fault in 230 kV 1.TANTRANSCO to submit a report regarding non-operation TANTRANSCO Yet to be informed Pending
Checkanurani S/s of hr. Checkanurani - Renganathapuram line. Persistent fault current of A/R at Renganathapuram and to change the digital signal
TANTRANSCO resulted in the operation of LBB protection and all the legend from carrier fail to carrier healthy.
elements connected at Bus-1 got tripped since 230 kV 2.TANTRANSCO to configure digital signals corresponding
Checkanurani-Renganathapuram line was connected at Bus-1 to CB status in DR and sort out time synchronization issues at
during antecedent conditions 230 kV Checkanurani SS
87/IV/3 Tripping of 230 kV KKNPP – 02-10-2019 / at Line tripped at KTPS VII end due to DT received from KTPS The PCSC recommended the following: TANTRANSCO Yet to be informed Pending
TTPS line 05:47 hr. VI end. Line was holding from KTPS VI end. 1. TANTRANSCO to carryout PID (Puncture Insulator
Deposit) testing of insulators to ensure healthiness of the
03-10-2019 at same.
08:00 hr. TANTRANSCO to measures clearance between phase to
phase and phase to earth at all locations.
09-10-2019 at 2. TANTRANSCO to carry out frequent Hotline washing
12.29 hr and measures such as bird guards and colour flags to scare
away birds to limit faults caused by birds.
13-10-2019 at 3. TANTRANSCO to furnish the findings by December
04.49 hr. 2019.
21-10-2019 at
06:19 hr.
Page 38 of 45
Annexure-II
PED
Kerala
58/I/1 Complete outage of 220 kV 23-08-2016 Triggering incident was conductor snapping in 110 kV KSEB to take steps to provide the following at their KSEB KSEB Mail received vide dated 17.01.2017: Pending 1. Time-frame?
(GD) Kalamassery Substation at 11:20 hrs Kalamassery- Kaloor feeder 220/ 110 kV Kalamassery SS: 1. 110 kV bus bar protection progressing ----Pending
1. Busbar protection at 110 kV level 2. Connection of 220kV earth mat and 110 kV plate earthing system completed.----
Completed
2. Connecting 220 kV and 110 kV sides on to a 3. Redundancy of 110V DC system in progress. Complete independent redundancy is
common earthmat not practical for the time being. 48 V DC redundancy was already there. ----
Pending
3. Redundant DC supply for both protection (220 V) 4. Instead of stand alone event logger, SCADA system of 110 kV feeder is expected
and communication (48 V) applications Status received vide mail dated 12-12-2017:
1. Detailed engineering of the scheme has been completed. Material procurement is in
4. Stand-alone Event Logger progress. ---Pending
2.,3. ---- Completed
4. The SOE and DR are available with time stamping from the numerical relays.
Hence stand alone event logger is not necessary ----- Completed
Page 39 of 45
Annexure-II
80/II/5 Multiple trippings at 220 kV 15-10-2018 at Triggering incident was Y-phase to ground fault in KSEBL to take steps to replace the existing static KSEBL Status received vide mail dated 11-12-2018: Pending
Madakathra station 08:57 Hrs 220kV Madakathra – Palakkad_KL (Ellapully) line (high impedance type) 220 kV BBP with numerical In progress
due to flashover of pilot insulator string. Auto-reclose Busbar protection at their 220 kV Madakathara SS.
was successful at Madakathra end. At the same time
bus differential relay Zone-C mal-operated resulting in Status received vide mail dated 19.03.2019:
tripping of all elements connected to the bus. Status as on 18.03.2019: Estimate sanctioned by CE(Transmission North ) and have
prepared the technical specifications.Tendering procedures are yet to get started.
82/I/5 Complete Outage of 220kV 08-02-2019 at Complete outage of 220kV Brahmapuram SS occurred 1) KSEBL to furnish detailed report regarding the KSEBL Status received vide mail dated 03.05.2019: Pending
Bhramapuram substation of 10:28 hrs due to suspected mal operation of Bus Bar protection. healthiness of BBP operation at 220kV Brahmapuram 1) Detailed report sent on 02.05.2019…..Completed.
KSEB after testing of the same on 12th April 2019. 2) As reported earlier in this regard, the permanent solution to this problem is to
2) KSEBL to submit the action plan regarding replace the existing high impedance static relay with a low impedance numerical
(i) Replacing of the Static High impedance BBP relay. The station authorities have already initiated action to implement the same by
(using CRM relays) with Numerical BBP. June 2020.
(ii) Replacement of CRM relays and relays with no
Disturbance recording facilitites.
84/I/3 Complete outage of 220 kV 27-05-2019 at Triggering incident was three phase to earth fault in 1.KSEBL may develop proper operational code for KSEBL KSEBL mail dated 30.07.2019: Pending
Edamon SS of KSEB 12:30 hr. 220 kV Edamon Bus 1 and 2. Bus 1 and 2 Bus bar procedures to be followed while performing operations 1. proper operrational code is avilalable in 220kV SS Edamon
protection operated resulting in the tripping of all in switchyard and sensitize their operators to reduce 2. All 220KV relays of Edamon substation are synchronized with GPS clock . Out of
connected elements. operational errors. 2.ksEBL to ensure time this, 3 relays are having hardware issues with time synchronisation switch . This
synchronization of relays at 220 kV Edamon SS. problem will be resolved by August 2019 itself.
87/II/14 Tripping of 400/220 kV ICT-3 at 29-08-2019 at 16:32 ICT-3 got tripped during testing of busbar protection KSEBL to submit a report after providing separate breaker KSEBL Yet to be informed Pending
Trichur hr failure relays for ICT-3 and sorting out the time
synchronization issues of relays at 400 kV Madakkathara SS.
82/II/6 Tripping of 400/220 kV ICT- 27-01-2019 ICT-1 at Khammam tripped on operation of IV side PGCIL (SR-I) to immediately take necessary actions PGCIL (SR-I) Review meeting on 27.06.2019:
1 at Khammam at 14:33hrs non directional Over-current high set during failure of to raise the Highset pick up current setting as per PGCIL (SR-I) informed that the ICT high set settings have been sent by mail
L.A in 220kV Khammam (Budhidampadu)-Suryapet protection standards since unwarranted tripping of ICT
line-2 for fault on 220kV line compromises the reliability of
Power system. In any case the transformer protection
should not encroach into protection zone of nearby
protection element. Pending
Page 40 of 45
Annexure-II
85/II/8 Tripping of 765/400kV ICT- 21-05-2019 at ICT 1 and 2 got tripped due to maloperation of PGCIL (SR-I) is recommended to submit a detailed PGCIL (SR-I) Yet to be informed Pending
1 and 2 at Kurnool 18:11 hrs Bucholz relays during the charging of 400KV Kurnool- report regarding operation of Buchholz relay of 765/
substation Nanoor line 1 which tripped on SOTF 400kV ICT 1& 2 during through fault after
consultation with OEM along-with the remedial
measures taken to prevent occurrence of any such
incidence in future.
85/II/16 Tripping of 400kV Tumkur- 29-05-2019 at Lines tripped due to Y-N & Y-B phase to earth fault PGCIL (SR-2) is recommended to submit Equipment PGCIL (SR-II) Yet to be informed Pending
Bidadi line-1&2, 400kV 6:11 hrs failure report to CEA regarding the failed LA.
Tumkur-Cuddapah line-2,
400kV Tumkur-Pavagada
line-2
85/II/18 Tripping of 765/400kV ICT- 02-06-2019 at ICT-2 got tripped on operation of Back up directional PGCIL (SR-1) is requested to check the operation of PGCIL (SR-I) Yet to be informed Pending
2 at Kurnool 17:41 hrs over current due to through fault (Y-B phase fault). ICT HV side High set O/C protection for through fault
and submit a report regarding the same.
86/II/23 Tripping of 400/220 kV ICT- 12-08-2019 ICT’s got tripped due to operation of 220 kV Bus bar 1. PGCIL (SR-1) to ensure that segregation of ICTs on PGCIl (SR-I) Yet to be informed Pending
1,2,3&4 at N.P.Kunta at 12:08 hr. protection both buses so that in the event of one bus failure RE
evacuation is not affected.
2. PGCIL (SR-1) to ensure that whenever any line is
under outage the respective bus isolator is kept open
(along with line side isolator) or enable dead zone
protection for BBP.
3. PGCIL to recommended to share relay settings to
86/IIV/1 Tripping of 400 kV Nellore- 01-07-2019 at Direct trip received at both ends. SRPC/SRLDC.
PGCIL (SR-1) to configure OVR start and OVR trip PGCIl (SR-I) Yet to be informed Pending
Sriperambadur line-2 03:40 hrs; signal in DR or EL at 400 kV Nellore PS.
28-07-2019 at
3:20 hrs
80/II/9 Tripping of 400/220 kV ICT- 26-10-2018 at 400/220 kV ICT-2 at Bengaluru (Sonamahalli) tripped PGCIL (SR-II) to configure DR’s & EL’s all PGCIL (SR-II) Review meetinmg on 27.06.2019: Pending
2 at Bangalore (Somanahalli) 12:10 Hrs due to operation of LV side over flux protection which protection relays at their 400/ 220 kV Somanahally SS PGCIL (SR-II) was asked to furnish the status of implementation of the
in turn was due to suspected 220 kV CVT problem. for all mandated protections and signals. recommendation at the earliest.
84/II/2 Tripping of 400kV 07-04-2019 at Line tripped on operation of over voltage stage-1 1. PGCIL (SR-II) to configure OVR start and OVR PGCIL (SR-II) Yet to be informed Pending
Somanahalli-Dharmapuri 18:02 hr. protection at Somanahalli. Somanahalli end DR: Vr- trip signal in Event logger to facilitate verification of
line-2 240kV, Vy-253kV, Vb-241kV. Y-phase voltage was adopted OVR grading.
higher than R and B phase 2.PGCIL (SR-II) to ensure time synchronization of
DR and EL at Somanahalli end and Dharmapuri end.
85/III/7 Tripping of 400kV Pugalur- 31-05-2019 at R-phase to earth fault occurred in line. Auto-reclose PGCIL (SR-2) is recommended to ensure proper PGCIL (SR-II) Yet to be informed Pending
Karaikudi line-1 17:44 hrs was successful at Karaikudi, At Pugalur end there was condition monitoring of their CB’s such as sufficient
3-phase trip air pressure.
Page 41 of 45
Annexure-II
86/II/3 Tripping of 400 kV Guttur- 01-07-2019 Line tripped on operation of over voltage stg-1 PGCIL (SR-2) to configure OVR start and OVR trip PGCIL (SR-II) Yet to be informed Pending
Hiryur line-1 at 18:02 hrs; protection at Guttur and direct trip was received at signals in DR or EL of 400 kV Guttur-Hiryur line-1
02-07-2019 Hiryur. However, over-voltage stg-1 operation could
at 1:20 hrs not be validated from DR of Guttur end as the volatges
were less than O/V pick up
86/II/18 Tripping of 400/230kV 4-08-2019 at Udumalpet ICT-3 HV side and LV side CB tripped due PGCIL (SR-2) to ensure healthiness of Bus CVT at PGCIL (SR-II) Yet to be informed Pending
Udumalpet ICT-3 10:34 hr. to operation of Over-flux relay at LV side. 230kV Udumalpet SS.
87/II/2 Tripping of 400/ 230 kV ICT-3 at 15-08-2019 at 6:57 ICT-3 got tripped due to operation of Oil surge relay. PGCIL (SR-2) to submit a report regarding operation of PGCIL (SR-2) Yet to be informed Pending
Karaikudy hr. Differential trip during OSR operation that led to tripping of
ICT-3 at Karaikudi.
Others
Page 42 of 45
Annexure-II
54/I/1 Complete outage of 230 kV 02-04-2016 at B-phase CT failure occurred in 230 kV S.P.Koil - 1.MAPS to furnish a detailed report on the tripping of NPCIL (MAPS) Status revided vide MAPS mail dated 06.12.2016; Pending
S.P.Koil Station of 17:08 hrs MAPS line-1. Busbar protection got operated at SP Koil – MAPS lines 1 & 2 at MAPS end with focus 1. The settings given by M/s TANTRANSCO were adopted for Main –I & Main- II
TANTRANSCO SP.Koil station. All elements except 230kV Oragadam on the correctness of the settings of Main-I & Main-II relays for both the lines. The same settings were verified to be same. Subsequently
and 230kV Kalivandapattu got tripped at 230kV relays (for primary & back-up protections) on both the calibrated was done and no drift was observed. --- Completed
S.P.Koil station. ‘Y’ phase CT and support insulators lines.
also got damaged. 2. From May 2016 onwards, the DR, EL and trip report are being sent by mail to
2.MAPS to take steps to provide down-loading facility SRLDC, Bengaluru by MAPS. --- Completed
69/I/1 Complete outage of 400kV 25-10-2017 at 400 kV TPCIL-Nellore PS line-1 got tripped from TPCIL to configure DEF protection such that it TPCIL Review Meeting on 21.12.2018: Pending
TPCIL station 19:33 hrs TPCIL end during fault in 400kV Nellore-Nellore PS remains in blocked condition as long as Distance It was noted that no TPCIL representatives had come to attend the meeting
line-2. Running units at TPCIL got tripped due to loss Protection is active, and becomes active only when
of evacuating line. 400kV Nellore PG - Nellore PS line- distance protection does not pickup. Review meetinmg on 27.06.2019:
2 and 400kV TPCIL - Nellore PS line-1 were under No representative from the utility attended meeting and it is requested to submit status
shutdown. regrading the recommendation at athe earliest.
Page 43 of 45
Annexure-II
78/II/2 Tripping of 400 kV Neyveli 01-08-2018 Triggering incident was failure of R-ph tension 1. NLCIL to furnish a report along with a suitable NLCIL Review Meeting on 21.12.2018: Pending
TS2Exp -Pugalur line at 11:56 hrs insulator string/ flashover in 400 kV Bus-1 at NLC SLD on the tripping event explaining the observed NLCIL was asked to furnish the status of implementation of the recommendation
TS2Exp end. Busbar protection had operated resulting discrepancies [DPR, Z1 operation, instantaneous given at the earliest.
in tripping of all main breakers connected to 400kV operation of OVR-II operation], and remedial action
Bus-1 at Neyveli TS2 Exp. In 400kV NLC TS2Exp - taken to attend the same. Review meetinmg on 27.06.2019:
Pugalur line, fault was sensed in Zone-1, R-N at 2. NLCIL to configure DR’s & EL’s of all protection No representative from the utility attended meeting and it is requested to submit status
Pugalur end resulting in a single phase trip. Direct Trip relays at their NLC TS-IIExp station for all mandated regrading the recommendation at athe earliest.
was received at Pugalur end due to operation of over protections & signals.
voltage Stg-2 at NLC TS2Exp.
79/II/8 Tripping of 400 kV NLC TS- 10-09-2018 at Line tripped on B-N fault. Auto-reclose was not NLCIL to furnish a detailed report on tripping event NLCIL Review Meeting on 21.12.2018: Pending
2 (Exp) – Pugalur line 20:57 hrs attempted at Pugalur end due to DT receipt from NLC explaining the observed discrepancies , and proper NLCIL was asked to furnish the status of implementation of the recommendation
TS2Exp end. At NLC TS2Exp end, V>2 trip was reasons for tripping of the line considering both the given at the earliest.
observed in DR. Analog voltages recorded in DR were Main-relays including remedial action taken w.r.t.
observed to be less than that required for O/V Stage-II healthiness/ replacement of Main protection relays on Review meetinmg on 27.06.2019:
operation. 400 kV NLC TS2Exp–Pugalur line. it is requested to submit status regrading the recommendation at athe earliest.
80/II/17 Tripping of 400 kV Nellore 14-11-2018 at Y- ph to earth fault occurred in line due to snapping of SGPL to examine the reasons for no-operation / failure SGPL Review meetinmg on 27.06.2019: Pending
PS – SGPL line-1 20:20 hrs GIS to Air bushing conductor at SGPL switchyard. of Auto-reclosure from their end for the subject No representative from the utility attended meeting and it is requested to submit status
The conductor got grounded such that the fault was tripping, and furnish an action taken report detailing regrading the recommendation at athe earliest.
being fed by NPS bus and there was earth fault and remedial measures taken to PCSC forum.
broken conductor start at SGPL end. NPS end got
tripped in Zone-2 due to non-receipt of carrier resulting
in a 3-ph trip at NPS. After 500ms, earth fault
occurred at SGPL end resulting in Zone-1 operation
and 3 phase trip. A/R was not attempted at SGPL end
80/III/6 Tripping of 400 kV Neyvelli 07-11-2018 at 400 kV Neyvelli TS2Exp - Pugalur tripped on NLCIL to furnish a detailed report on the reasons for NLCIL Review meetinmg on 27.06.2019: Pending
TS2 (Exp) - Pugalur line 05:50 Hrs B-phase to ground fault due to DPR, Z1 operation. A/R non-operation for the subject tripping at their No representative from the utility attended meeting and it is requested to submit status
Auto-reclose was successful at Pugalur end and the NLCTS2Exp station including remedial measures regrading the recommendation at athe earliest.
line tripped at Neyveli TS2Exp end only. Auto-reclose taken to PCSC forum.
83/III/1 Tripping of 220 kV 24-02-2019 at Line tripped on B-phase to earth fault. Auto-reclose It was noted that no representative of NTPC attended NTPC (KYKLM) Review meeting on 27.06.2019: Pending
Kayamkulam –Punnapura-2 03:05hrs was successful at Punnapura. A/r was not attempted at the meeting. No representative from the utility attended meeting and it is requested to submit status
Kayamkulam and there was pole discrepancy operation NTPC (Kayamkulam) to furnish detailed report regrading the recommendation at athe earliest.
resulting in tripping of R and Y pole of CB. regarding failure of Auto-reclosure at Kayamkulam
end for Kayamkulam –Punnapura line-2. NTPC mail dated 13.05.2019:
Trip report for Tripping of 220 kV Kayamkulam –Punnapura-2 submitted , but for
submitting detailed report for Auto-reclosure at Kayamkulam end not operating for
83/III/2 Tripping of 220 kV 05-03-2019 at 220kV Kayamkulam-Punnapura -2 tripped on Zone-1 It was noted that no representative of NTPC attended NTPC (KYKLM) Kayamkulam
Review meeting –Punnapura line-2 , half day shutdown of Kayamkulam –Punnapura
on 27.06.2019: Pending
Kayamkulam –Punnapura-2 00:30hrs distance protection due to R-N fault. Auto reclose the meeting. No representative from the utility attended meeting and it is requested to submit status
operated and successful at Punnapara end but didnot NTPC (Kayamkulam) to furnish detailed report regrading the recommendation at athe earliest.
operate at Kayamkulam end. regarding failure of Auto-reclosure at Kayamkulam
end for Kayamkulam –Punnapura line-2. NTPC mail dated 13.05.2019:
Trip report for Tripping of 220 kV Kayamkulam –Punnapura-2 submitted , but for
submitting detailed report for Auto-reclosure at Kayamkulam end not operating for
Kayamkulam –Punnapura line-2 , half day shutdown of Kayamkulam –Punnapura
line is required to check reason for failure . May please approve half day outage of
84/I/5 Complete outage of 400kV 05-06-2019at 18:51Triggering
hr. 1. NLCILTransformer)
incident was failure of Y-phase CT of GT-1 (Generator to check the healthiness of R & B phBus-1
at 400kV NLC1EXP. CT ofBus
NLCIL Kayamkulam
bar protection operated resulting
NLCIL in the–Punnapura
mail dated
tripping line and intimate
09.07.2019:
of NLC1EXP us atleast
U#1 and 400kVone day in advance.
NLC1EXP- Nagapattinam line Pending
NLC1 Unit-1 at NLC TS1(Exp) and if found unhealthy AT TS2 Side Siemens 7SA52 & Micromho relay are used for distance protection.
Expansion(NLC1EXP) replace the same alongwith replacement of Y-ph CT. During the incident Micromho has sensed the CT blast as a Zone-1 fault and tripped
CT replacement plan and timeframe shall be informed the feeder. Adt signal was send to TS1 Exp end. The relay will be tested during the
to SRPC. next shut down.
2.NLCIL in coordination with PGCIL(SR-II) to
resolve the time syncronisation issues in 230kV NLC
TS1(Exp) – Nagapattinam line.
3. NLCIL was also requested to investigate the reason
84/II/20 Tripping of 400kV Neyveli 400kV/230kV
07-05-2019 at 20:56 hr. ICT-1 got tripped on Differential of
1. unwarranted DT sentthetoearth
NLCIL to measure NLCresistance
TS1 (Exp)ofend from NLCIL
Neyveli NLCIL mail dated 09.07.2019: Pending
TS2- Neyveli TS-I (EXP) protection due to failure of R phase bushing on the HV TS-2 SS and submit the same to PCSC forum. NLCIL 1) The earth pit resistance of the ICT1 LA was measured as follows.
and 400/230 kV ICT-1 side. For 400kV Neyveli TS2- Neyveli TS-I (EXP), R to check the healthiness of LAs of ICTs and confirm 400 kV side was measured on29-03-19
atNeyvli pole breaker at TS1Expgot tripped. TS2 End breaker proper earthing. Rphase - 0.61 ῼ , Y phase - 0.76ῼ , B phase - 0.58 ῼ
tripped on trip command received from TS1 EXP 2.It is also recommended to furnish a report on 230 kV side was measured on 29-03-2019
adequacy of ground wire shielding of switchyard. Rphase - 0.47 ῼ , Y phase - 0.86ῼ , B phase - 0.68ῼ
3. NLCIL to ensure Time synchronization of relays at The resistive leakage current for the LA's was also measured and the readings are as
Neyveli TS-2 SS. follows.
400kV side was measured on 29-03-2019 and the values are as follows .
R phase - 73 μA , Y phase 90 μA , B phase - 92 μA .
Page 44 of 45
230kV side was measured on 22-03-2019 and the values are as follows
R phase - 238 μA , Y phase - 330 μA , B phase 401 μA.
After the incident on 07-05-19 the resistive leaksge current was again measured on
adequacy of ground wire shielding of switchyard. Rphase - 0.47 ῼ , Y phase - 0.86ῼ , B phase - 0.68ῼ
Annexure-II
3. NLCIL to ensure Time synchronization of relays at The resistive leakage current for the LA's was also measured and the readings are as
Neyveli TS-2 SS. follows.
400kV side was measured on 29-03-2019 and the values are as follows .
R phase - 73 μA , Y phase 90 μA , B phase - 92 μA .
230kV side was measured on 22-03-2019 and the values are as follows
R phase - 238 μA , Y phase - 330 μA , B phase 401 μA.
After the incident on 07-05-19 the resistive leaksge current was again measured on
13-05-2019 and the values are as follows.
400kV Side
R phase - 91 μA , Y phase - 116 μA , B phase - 105 μA
230 kV side
R phase - 297 μA , Y phase - 318 μA , B phase - 385 μA
85/II/19 Tripping of 400kV JSW- 02-06-2019 at Line tripped due to OV St-1 protection operation at JSWEL is recommended to monitor the B-ph CVT of JSWEL 2)
YetTime
to besynchronization
informed of one series of relays completed. The time synchronization Pending
Guttur line 18:17 hrs JSW end and DT was sent to Guttur end. At Guttur 400kV JSWEL-Guttur line (due to lower B-ph voltage
end B ph voltage was observed to be lesser comparing compared to other two phases). The same shall be
to R ph and Y ph(Vr-249kV, Vy-255kV and Vb- replaced if the issue persists.
230kV).
85/II/21 Tripping of 400kV JSW - 05-06-2019 at Y-phase to earth fault occurred in 400kV Kaiga-Guttur 1. NPCIL (KGS) is recommended to identify the issue NPCIL (KGS) Yet to be informed Pending
Guttur line and 400 kV 18:27 hrs line-2. A/r was successful at Guttur end. At Kaiga end related to unsuccessful A/R attempt of 400kV Kaiga –
Kaiga - Guttur line-2 A/r was not attempted and breakers got tripped due to Guttur line and non-opening of R-pole CB. It is
operation of Pole discrepancy (1.65 Sec). 400kV JSW- recommended to check the healthiness of all breakers
Guttur line tripped on operation of over-voltage at including breaker timing.
Guttur and direct trip was received at JSW. From DR 2. Time synchronization of DR and EL at Kaiga end
of Guttur, it is observed that there was swell in R & Y shall be ensured.
phase voltage for few cycles
85/III/14 Tripping of 400kV Kaiga- 16-06-2019 at R-phase to earth fault. Auto-reclose attempt at Guttur 1. NPCIL (KGS) is recommended to identify the issue NPCIL (KGS) Yet to be informed Pending
Guttur line-2 19:20 hrs end was not successful as fault was persistent in related to unsuccessful A/R attempt of 400kV Kaiga –
nature. Attempt for A/r could not be established from Guttur line and non-opening of R-pole CB. It is
Kaiga end EL recommended to check the healthiness of all breakers
including breaker timing.
2. Time synchronization of DR and EL at Kaiga end
shall be ensured.
85/IV/7 Tripping of 400kV 11-06-2019 at Line tripped due to Direct Trip receive at Ramadugu Singareni STPP is recommended to submit a detailed Singareni TPP Yet to be informed Pending
Ramadugu-Singareni line 08:24 hrs end report regarding sending of DT from singareni end that
resulted in tripping of 400kV Ramadugu-Singareni
line.
86/III/2 Tripping of Kaiga-Gutur line 22-07-2019 at Line tripped on B-phase to earth fault. Line did not NPCIL (KGS) to ensure time sync between DR and NPCIL Yet to be informed Pending
-2 17:47hr. auto-reclose. EL at Kaiga end.
87/III/4 Tripping of 400 kV Kaiga- 06-09-2019 at 4:33 Line tripped on Zone-1 distance protection operation due to R- NPCIL (KGS) to review A/R scheme at Kaiga GS. As per NLCIL (KGS) Yet to be informed Pending
Narendra line-2 hr. phase to Y phase fault. At Kaiga end line auto-reclosed. A/R logic, any phase to earth fault detection should lead to
opening of the faulted phase and reclosing after dead time.
But during dead time if any subsequent fault occurs it should
block A/R and 3-ph trip should be extended.
Page 45 of 45
Annexure-III
Pending Remedial Measures/ Actions taken for the Critical Tripping Incidents (as on 27.11.2019)
Sl.No. Element Name Outage date/time Revival date/time Reason for outage Sender/ Receiver Remedial Measures/ Actions taken Remarks
DC LEAKAGE AT
400KV-SURYAPET-KETHIREDDYPALLY-1 03-09-2019/14:42:00 03-09-2019/18:08:00 TSTRANSCO To-be-discussed
1 KETHIREDDYPALLY
Due to interlocking
HVDC 500KV KOLAR_DC Pole 04-09-2019/17:02:00 04-09-2019/17:41:00 condition of DC circuit PGCIl (SR-II) To-be-discussed
2 breakers
3 400KV-NELAMANGALA-TALGUPPA-1 08-09-2019/11:50:00 DISTANCE PROTECTION KPTCL To-be-discussed
400KV-ILFS-NAGAPATTNAM_PS-2 09-09-2019/13:41:00 09-09-2019/16:26:00 Earth Fault ILFS/ PGCIL (SR-2) To-be-discussed
4
Page 1 of 8
Annexure-III
Page 2 of 8
Annexure-III
43
220KV-KOTHAGUDEM_TPS- TRIPPED DUE TO B-N LINE
11-10-2019/09:41:00 TSGENCO/ APGENCO To-be-discussed
44 LOWER_SILERU-1 FAULT
400KV-RAMADUGU-GAJWEL-1 11-10-2019/19:05:00 11-10-2019/19:28:00 TRIPPED ON R-N FAULT TSTRANSCO To-be-discussed
45
APTRANSCO : Feeder tripped on R-
Phase to ground, Zone-1 fault. AR
220KV-KOTHAGUDEM_TPS-NUNNA_AP-1 12-10-2019/01:18:00 12-10-2019/01:29:00 Y-N FAULT TSGENCO/ APTRANSCO Pending with TSGENCO
successful and line was holding from
46 Nunna end.
47 400KV-TALGUPPA-HASSAN-1 12-10-2019/02:23:00 TRIPPED ON R-N FAULT KPTCL/ PGCIL (SR-2) To-be-discussed
220KV-SRISAILAM_RIGHT_BANK-
12-10-2019/12:32:00 12-10-2019/13:14:00 DISTANCE PROTECTION APGENCO/ PGCIL (SR-1) To-be-discussed
48 NAGARJUNSAGAR
Page 3 of 8
Annexure-III
Page 4 of 8
Annexure-III
Page 5 of 8
Annexure-III
220KV-KOTHAGUDEM_TPS- TRIPPED ON SINGLE PHASE
01-11-2019/11:08:00 01-11-2019/17:10:00 TSGENCO/ APGENCO To-be-discussed
86 LOWER_SILERU-1 TO GND FAULT
220KV-KOTHAGUDEM_TPS_V- TRIPPED ON SINGLE PHASE
01-11-2019/11:16:00 01-11-2019/12:26:00 TSGENCO/ APGENCO To-be-discussed
87 LOWER_SILERU TO GND FAULT
220KV-THENI-MOOZIYAR-1 01-11-2019/11:59:00 01-11-2019/12:29:00 TRIPPED ON B-N FAULT KSEBL/ TANTRANSCO To-be-discussed
88
220KV-KOTHAGUDEM_TPS_V-
02-11-2019/17:34:00 02-11-2019/18:15:00 TRIPPED ON R-N FAULT TSGENCO/ APGENCO To-be-discussed
89 LOWER_SILE ..
91
Page 6 of 8
Annexure-III
TRIPPED DUE TO B-N LINE
400KV-BHOOPALAPALLY-CHANDALAPUR-2 06-11-2019/14:06:00 16-11-2019/19:07:00 TSGENCO/ TSTRANSCO To-be-discussed
98 FAULT
TRIPPED DUE TO CT
400KV-KALPAKKA-SIMHADRI_STG1-3 06-11-2019/22:06:00 APTRANSCO/ NTPC (SHM) To-be-discussed
99 PROBLEM
400KV-HINDUJA-KV_KOTA-1 06-11-2019/11:33:00 06-11-2019/16:10:00 TRIPPED ON R-N FAULT HNPCL/ APTRANSCO To-be-discussed
100
230KV-KUDANKULAM-TTPS 17-11-2019/11:08:00 17-11-2019/11:50:00 TRIPPED ON R-N FAULT NPCIL (KKNPP)/ TANTRANSCO To-be-discussed
119
Page 7 of 8
Annexure-III
400KV-GOOTY-NARNOOR-1 22-11-2019/16:46:00 22-11-2019/17:05:00 PLCC MAL OPERATION PGCIL (SR-1)/ APTRANSCO To-be-discussed
126
Page 8 of 8