Manual ATS 7000 Cerrada
Manual ATS 7000 Cerrada
Nameplate
The Transfer Switch nameplate includes data for each
specific 7000 Series ACTS. Use the switch only within the
limits shown on this nameplate. A typical catalog number
is shown on the next page with its elements explained.
TABLE OF CONTENTS
section-page
INSTALLATION . . . . . . . . . . . . . . . . . . . . . . . . 1-1
Mounting and Line Connections . . . . . . . . . 1-1
Auxiliary Circuits and Harness . . . . . . . . . . . 1-2
Engine Starting Contacts . . . . . . . . . . . . . . . 1-2
Functional Test . . . . . . . . . . . . . 1-2, 1-3, 1-4, 1-5
TESTING & SERVICE . . . . . . . . . . . . . . . . . . 2-1
Transfer Test . . . . . . . . . . . . . . . . . . . . . . . . . . 2-1
Preventive Maintenance . . . . . . . . . . . . . . . . 2-1
Disconnecting the Controller . . . . . . . . . . . . 2-1
Manual Load Transfer . . . . . . . . . . . . . . . . . . 2-2
Trouble-Shooting . . . . . . . . . . . . . . . . . . . . . . 2-2
INDEX . . . . . . . . . . . . . . . . . . . . . . . . . back cover
150 – 400 ampere sizes
ASCO POWER TECHNOLOGIES CANADA PO Box 1238, 17 Airport Road, Brantford, Ontario, Canada N3T 5T3
Catalog Number Identification
Typical 7000 Series catalog no. for E–design switched neutral, 3 pole, 400 amp, 480 V, ACTS in Type 1 enclosure:
E 7ACTS C 3 400 N 5 C
design
prefix
letter
Neutral Phase Poles Amperes Voltage Controller Enclosure
A – solid 2 – single Ø 150 1000 A 115 J 400 5 – standard C – type 1
B – switched 3 – three Ø 260 1200 B 120 K 415 5X – if F – type 3R
C – overlapping 400 1600 C 208 L 440 accessories G – type 4
ordered
blank – none 600 2000 D 220 M 460 L – type 12
800 3000 E 230 N 480 blank – open type
field connections
terminal block TB
power
connections Transfer
Control
& lights
Dual
Transfer
Switch
Group 5
Controller
power
connections
1---1
INSTALLATION (continued)
Tighten bolted joints to the torque specified in Table A. Engine Starting Contacts
The engine control contact connections (if used) are
located on the transfer switch. Connect signal wires to
The reliablility of the connection depends appropriate terminals as specified in Table B and shown
on how clean and how tight the joint is. in Figure 1–1.
Table A. Tightening torque values for bolted joints Table B. Engine start connections
(Grade 5 hardware) When normal Terminals on
Bolt Diameter Tightening Torque source fails transfer switch
in inches in foot pounds contact closes TB1 and TB2
1/4 7 contact opens TB1 and TB3
5/16 12
3/8 20
1/2 50
5/8 95
3/4 155
engine start
Controller Ground connections
A grounding wire must be connected to the controller’s on
lower left mounting stud. Because the controller is customer
terminal
mounted on the enclosure door, a conductive strap
block TB
must be used between the enclosure and the door. This
connection provides proper grounding which does not
rely upon the door hinges.
Harnesses
The transfer switch is connected to the left side of the
control panel by a plug-in harness (two plugs).
Auxiliary Circuits
Connect auxiliary circuit wires to appropriate terminals on Figure 1-1. Customer terminal block
the transfer switch. Note the control features that are on the top right side of enclosure.
furnished on this switch. Make the necessary auxiliary
connections by referring to the Wiring Diagram.
Functional Test
The Functional Test consists of three checks: Read all instructions on the Wiring Diagram and labels
affixed to the ACTS. Note the control features that are
S 1 — Manual Operation Test, page 1–3 provided and review their operation before proceeding.
S 2 — Voltage Checks, page 1–4
Continue to 1 – Manual Operation Test on next page.
S 3 — Electrical Operation, page 1–5
1---2
INSTALLATION (continued)
handle
shafts
handle
handle
1 – Manual Operation 1000 through 4000 amp. G–design See Figure 1-5.
Install the hub (with pin) onto the shaft and insert the
A detachable manual operator handle is provided on the
manual firmly into the side hole in the hub. Push in
Transfer Switches for maintenance purposes only.
or pull out hub to engage opposite source contacts.
Manual operation of both CN and CE transfer switches
must be checked before they are operated electrically. 3000 and 4000 amp. F–design See Figure 1-4.
Insert the manual handle into the hole in the weight.
2. Move the handle as shown to manually operate the
Do not manually operate the transfer switch Transfer Switch. The switch should operate smoothly
until both power sources are disconnected: without binding. If it does not, check for shipping
open both circuit breakers. damage or construction debris. Repeat the manual
operation check on the other Transfer Switch.
1. Select the appropriate switch amperage size above
and follow the directions for installing the handle: 3. Return the CN Transfer Switch to the C (closed)
position. Return the CE Transfer Switch to the O
150 through 400 amp. E–design See Figure 1-2. (open) position. Remove manual operator handle and
Insert the manual handle into the hole in the shaft, store it on the Transfer Switch in the place provided.
left side of the operator.
600 and 800 amp. F–design See Figure 1-3.
Attach the manual handle onto the pivot shaft Verify that the maintenance handle has been
removed and stored properly before proceeding!
extension, left side of the operator.
Now continue to 2 – Voltage Checks on next page.
Normal
contacts counterclockwise DOWN clockwise DOWN
OPENS the contacts CLOSES the contacts
Pull out shaft to open Emergency Pull out shaft to close Emergency
contact position source contacts (upper) source contacts (upper)
Push in shaft to open Normal Push in shaft to close Normal
indicators (left side) source contacts (lower) source contacts (lower)
Figure 1-5. 1000 – 4000 ampere G–design transfer switches.
1---3
INSTALLATION (continued)
observe
these lights
GREEN RED
observe operate
these lights this switch
GREEN RED
1---5
SECTION 2 TESTING & SERVICE
TRANSFER TEST DISCONNECTING THE CONTROLLER
Operate the 7000 Series ACTS at least once a month The harness disconnect plugs are furnished for repair
by following the five–step Electrical Operation purposes only and should not have to be unplugged.
Transfer Test procedure on page 1–5. If the controller must be isolated, follow these steps:
S Clean the ACTS enclosure. Brush and vacuum Reconnecting the Plugs
away any excessive dust accumulation. Remove any
moisture with a clean cloth.
Do not unplug the controller
S Check the transfer switch contacts. Remove the until steps 1a or 1b is completed.
transfer switch barriers and check contact condition.
Replace the contacts if they become pitted or worn 1. Observe the position of the transfer switch.
excessively. Reinstall the barriers carefully.
a. If the transfer switch is in the Normal position,
S Maintain transfer switch lubrication. If the first be sure that both normal and emergency
transfer switch is subjected to severe dust or source circuit breakers are open. Second, be
abnormal operating conditions, renew factory sure that the standby engine starting control is
lubrication on all movements and linkages. still in the off position.
Relubricate the solenoid operator if the TS coil is b. If the transfer switch is in the Emergency posi-
replaced. Do not use oil; order lubrication kit tion, first be sure that both normal and emer-
75-100. gency source circuit breakers are open.
S Check all cable connections & retighten them. 2. The two harness plugs and sockets are keyed.
Carefully align the plugs with the sockets and press
straight in until both latches click. Close the door!
REPLACEMENT PARTS 3. Restore the two sources in sequence as follows:
Replacement parts are available in kit form. When a. If the transfer switch is in the Normal position,
ordering parts provide the Serial No., Bill of Material first close the normal source circuit breaker.
No. (BOM), and Catalog No. from the transfer switch Second, close the emergency source circuit
nameplate. Contact your local ASCO Power Technolo- breaker. Third, place the standby engine
gies Sales Office or ASI: starting control in the automatic position.
in United States call 1 800 – 800 – ASCO (2726) b. If the transfer switch is in the Emergency
position, first close the emergency source circuit
breaker. Second close the normal source circuit
breaker.
2---1
TESTING & SERVICE (continued)
MANUAL LOAD TRANSFER 2. Use the maintenance handle to manually operate the
transfer switch to the opposite source. First open the
This procedure will manually transfer the load if the
closed contacts, then close the other contacts. Do not
controller is disconnected.
leave both closed. See Manual Operation on page
1–3.
Do not manually operate the transfer switch 3. Then remove the maintenance handle. See page 1–3.
until both power sources are disconnected
(all conductors deenergized).
Verify that the maintenance handle
1. Deenergize both the normal and emergency source has been removed before proceeding!
conductors (remove fuses or open circuit breakers).
4. If the transfer switch is in the Emergency position
manually start the engine generator and then install
emergency source fuse or close the circuit breaker.
TROUBLE-SHOOTING
Note any optional accessories that may be furnished on
the ACTS and review their operation. Refer to any
separate drawings and/or instructions that may be Hazardous voltage capable of causing
packed with the ACTS. shock, burns, or death is used in this switch.
Do not touch the power or load terminals of
the transfer switch!
2---2
INDEX
A I R
alarm reset, 1–5, 2–2 inspection, 2–1 rating label, cover
auxiliary circuits, 1–2 installation, 1–1 replacement parts, 2–1
C L S
labels,
cable engine start contacts, 1–2 settings
lugs, 1–2 rating, cover see Controller User’s Guide
preparation, 1–2
lights, 1–4, 1–5
catalog number, inside cover
lubrication, 2–1
T
cleaning, 2–1 test, functional, 1–2, 1–3, 1–4, 1–5
closed transition bypass, 1–5, 2–2 M time delays, 2–1
connections maintenance handle, 1–3 see Controller User’s Guide
line, 1–1 Transfer Control selector switch
maintenance, preventive, 2–1
controller, 1–1 Retransfer Delay Bypass, 1–5
manual load transfer, 2–2 Transfer Test, 1–5
disconnecting, 2–1
warning, 2–2
see Controller User’s Guide Transfer Switch Connected To
manual operation, 1–3 Emergency light, 1–5, 2–1
illustration of, 1–3
E warning, 1–3 Transfer Switch Connected To
Normal light, 1–4, 2–1
electrical operation, 1–5
emergency source accepted light, N transfer test, 1–5
1–4 transfer to emergency, 1–5
nameplate, cover
extended parallel time, 2---2 transfer to normal, 1–5, 2–1
normal source accepted light, 1–4
trouble–shooting, 2–2
F O TS locked out, 2---2
failure to synchronize, 2---2 operation
frequency, generator, 2–2 electrical, 1–5
manual, 1–3
V
functional test, 1–2, 1–3, 1–4, 1–5 illustration of, 1–3 voltage checks, 1–4
warning, 1–3 voltage, pickup and dropout settings
G optional accessories see Controller User’s Guide
see Controller User’s Guide
ground, controller, 1–1
H P
harness, 1–1 parts, 2–1
disconnect plugs, 2–1 phase rotation check, 1–4
HELP problem, 2–2
[email protected]
800–800–ASCO