Esmf 04052017 PDF
Esmf 04052017 PDF
Esmf 04052017 PDF
Environment and
Social
Management
Framework for
Power
Transmission and
Distribution
Projects
Andhra Pradesh
October, 2016
Page 1
Table of Contents
Page 2
ANNEXURE 8 – RESETTLEMENT POLICY FRAMEWORK (RPF) 224
ANNEXURE 9 – IMPLEMENTATION ARRANGEMENTS FOR RTFCTLARRA 245
ANNEXURE 10 – IMPLEMENTATION OF RTI ACT 248
ANNEXURE 11 – MINUTES OF DISCLOUSRE WORKSHOPS 250
Page 3
Acronyms and Abbreviations
Page 4
MoU Memorandum of Understanding
MRO Mandal Revenue Officer
MVA The Motor Vehicles Act
NGO Non-Government Organisation
NOC No Objection Certificate
PCB Polychlorinated Biphenyls
PCCF Principal Chief Conservator of Forests
PESO Petroleum and Explosives Safety Organisation
PF Provident Fund
PIUs Project Implementation Unit
PTCC Power & Telecommunication Coordination Committee
R&R Rehabilitation and Resettlement
Right to Fair Compensation and Transparency in Land Acquisition,
RFCTLARRA
Rehabilitation and Resettlement Act
ROW Right of Way
RPF Resettlement Policy Framework
RWAs Resident Welfare Association
SAPIO State Asst. Public Information Officers
SC Scheduled Caste
SE Superintendent Engineer
SF6 Sulfur Hexafluoride
SIA Social Impact Assessment
SPCB State Pollution Control Board
SPIO State Public Information Officer
ST Scheduled Tribe
T&D Transmission and distribution
TPP Tribal People Plan
TPPF Tribal Peoples Planning Framework
ULBs Urban Local Bodies
Page 5
1. Executive Summary
Project Context
Andhra Pradesh is one of the states in the country where the 24x7 Power for All programme
is being implemented. This program was created to ensure 24x7 quality, reliable and
affordable power to all domestic, commercial and industrial consumers within a fixed time
frame. Further, the program also aims to ensure all unconnected households be provided
access to electricity in a phased manner.
The Government of Andhra Pradesh (GoAP), through the Government of India (GoI), has
approached the World Bank for financial and technical support.
Generation Distribution
Regulation Transmission
(APGENCO) (APSPDCL &
(APERC) (APTRANSCO)
(NREDCAP) APEPDCL)
The proposed investments under the World Bank funded project will be implemented by
APTRANSCO, APSPDCL and APEPDCL. These are corporatize entities with their own board.
The details of the investments are provided below:
Page 6
Testing instruments (13 sets);
Purchase of tower spotting software;
Purchase of design licenced software and earthing software;
Trainings
The tentative long list of transmission schemes that have been identified for World Bank
funding are provided below:
Page 7
Sl. Name of the Line
Connected lines District Site Status
No. Sub-station Length
2nd circuit stringing on
132kV DC/SC Line from
40km
220/132kV SS Nagari to
132kV SS Pachikapallam
Erection of 132kV DC
Identification of
radial line from 132/33kV
132kV SS Government land for
7. SS Rayachoti to the 20km YSR
T.Sundupalli the substation is
proposed 132/33kV SS T.
under process
Sundupalli
Request letter
Erection of 132kV DC submitted to Zonal
radial line from 220/132kV Manager, APIIC,
132kV SS
8. SS Chinakampalli to the 30km YSR Kadapa for 15 Acres
Satellite City
proposed 132/33kV SS of land near
Satellite city Vogivemana
University
Package-III
Erection of 132kV DC
radial line from Site available, 5.00
132kV SS 400/220/132kV SS Acres, Sy.No.85/2,
9. 25km Nellore
Kadivedu Manubolu to the Kadivedu(V),
proposed 132/33 kV Chillakuru(M)
Kadivedu substation
Erection of 132kV DC
radial line from 220/132kV
132/33kV SS Site available in
10. SS Kondapalli to the 25km Krishna
Mylavaram existing 33kV SS,
proposed 132 kV
Mylavaram SS
Erection of 132kV DC
radial line from
132kV SS
11. 220/132kV SS Podili to 26km Prakasam Identified Govt. Land
Chinarikatla
the proposed 132/33kV
ChinarikatlaSS
Erection of 132kV DC
radial line from
132kV SS East
12. 220/132kV SS Podili to 21km Prakasam Identified Govt. Land
Gangavaram
the proposed 132/33kV
East Gangavaram SS
Page 8
B) Proposed Investments for APSPDCL and APEPDCL
The tentative distribution schemes identified for World Bank are provided in the following
table. The total investments are estimated to be INR 2490 Cr for APSPDCL and INR 1032
Cr for APEPDCL.
Page 9
Disaster Management, GoAP, about 44% of the state is vulnerable to
tropical storms and related hazards. Placing power lines underground
eliminates their susceptibility to lightning and wind damage
UG cabling would be provided in smart city areas of Visakhapatnam
and Kakinada towns
Distribution New 33/11 kV indoor substations, GIS substations and new 33/11 kV
7
Substations outdoor substations are proposed
TA will be essential for effective implementation of proposed
Technical investments. TA support is required for overall institutional
Assistance development, capacity building and governance improvement as well
8. (TA)/Capacity as some specific areas like strengthening and improving Project
Building Planning and implementation, business processes and accountability
systems, corporate governance and financial management practices
and human resource development
Based on the mitigation and management measures outlined in this ESMF document,
specific Environment and Social Management Plans (ESMP) will be developed for different
components of the World Bank supported investments. These ESMPs will be based on
component specific Environment and Social Impact Assessments (ESIA). In this regard:
An ESMP (including a safety plan) has been prepared for the proposed HVDS projects
that are to be implemented by APEPDCL and APSPDCL. This ESMP will be included in
the bidding documents submitted by the two distribution utilities.
Page 10
For distribution substations, ESIAs will be prepared for a cluster of distribution
substations and the bidding docs will include a resultant ESMP
Methodology
The ESMF has been prepared on the basis of environmental and social assessments which
involved gathering of data through both primary and secondary sources. This included
consultations with key stakeholders as well as desk research. The steps followed in
developing the ESMF are provided below:
Establishment of the social and environment baseline through desk research
Defining the legal / regulatory framework that will influence implementation of the
proposed projects and sub-projects
Identification of the area of influence of the proposed projects
Identification the social and environmental impacts
Defining the mitigation methods to manage the social and environmental impacts
Establishing the grievance redressal mechanism
Defining the monitoring plan to oversee the implementation of social and
environment management and mitigation methods
Preparing the gender action plan (GAP), tribal people planning framework (TPPF)
and the resettlement policy framework (RPF)
Identifying the training requirements at the utility level, for undertaking the social
and environment assessments and implementing the mitigation measures
Providing an estimated budget to undertake the provisions of the ESMF
Describing a process to integrate project affected people’s opinion and concerns in
the environment and social management plans through consultations
Page 11
Andhra Pradesh has a population of 4.94 Cr (4.08% of India’s population) and a population
density of 304 persons per sq. km. There are 126.65 lakh households in the State and the
average size of the household is 3.95. Andhra Pradesh is still largely rural with 70.42% of
the total population living in rural areas and only 29.58% living in urban areas.
Of the total population Scheduled Cates (SC) constitute 17.10% and Scheduled Tribes (ST)
5.33%. Prakasam is the district with the highest SC population (7.88 lakh) while
Vizianagaram has the lowest (2.47 lakh). Visakhapatnam is the district with the largest
concentration of STs with 14.42% of the total ST population, while Kurnool with 2.04
percent has the lowest concentration.
Stakeholder Analysis
The purpose of a stakeholder analysis is to identify the various stakeholder groups that can
affect or can directly/indirectly be affected by project activities. Key stakeholder groups
include: a) Government and regulatory agencies; b) Multilateral agencies such as the World
Bank and Asian Development Bank; c) Power sector utilities in Andhra Pradesh; d) Different
government departments like Revenue Department at state and district level; e) Panchayats
and municipal corporations at the village/city level; f) Public and Private sector companies
like BSNL and Reliance; g) Non-government organisations (NGOs), community based
organisations (CBOs) like resident welfare associations and informal groups like women’s
group, farmer’s group; h) Commercial and residential complexes and communities which
constitute end-beneficiaries; and i) vulnerable groups like women, small farmers,
scheduled tribes and scheduled castes.
The analysis further maps the relationship between the stakeholder groups; defines their
roles, responsibilities and interest in the project; and highlights the key expectations /
concerns these stakeholders have with respect to the planned investments. The key
expectations and issues and concerns that emerged from the stakeholder analysis have
been summarized below:
Environmental Aspects
Ensuring environmentally sensitive and fragile lands are not allotted to the project
and protection of forest land and wildlife habitats
In situations where the use of forest land is unavoidable, ensuring that all relevant
clearances are taken and compensation is paid as per National or State laws.
Ensuring that irrigation canals, tanks, and / or water bodies are not damaged or
polluted in any way by construction activities
Ensuring that water ways are not blocked
Minimization of disturbances during construction including noise and air pollution
Ensuring there is no danger to wildlife and adequate protection in form of fencing
of substations and electrical towers / lines to prevent accidents
Ensuring health and safety of workers during construction and maintenance
Page 12
Social Aspects
Ensuring reliable power supply to end users and minimizing transmission and
distribution losses
Ensuring land and right of way is secured in a transparent and fair manner and that
the minimum required land is used for projects
Ensuring that rehabilitation and resettlement is avoided wherever possible and if
unavoidable is handled as per relevant National / State Policies
Ensuring that the community is consulted
Ensuring that rights of tribal people and other vulnerable groups are protected and
that they participate in the benefits of the project
Ensuring that compensation is paid for temporary damage to land, crops, trees or
structures during construction. The compensation to be paid would differ for
APTRANSCO and the distribution companies and depend on the nature of the sub-
project.
Ensuring adequate compensation for land and tower footing is paid as per
regulations
Ensuring there is minimal disturbance to public during construction due to blocking
of access roads, damage to roads / highways etc.
Ensuring safety of community during construction phase
Ensuring the projects do not cause any disruption to the exiting communication
networks of telecommunication companies, railways and defence
Page 13
Impact on community health and safety due to exposure to electromagnetic
fields, exposure to hazardous material and threat of electric shocks
Impact on workers’ health and safety due to contact with live power lines, working
at height, and exposure to electromagnetic fields and chemicals
Impact on vulnerable population like women, SCs, STs and minorities due to loss
of livelihood, farm land and security issues during the pre-construction and
construction phase
Threat of damage to buildings and artefacts of cultural and historical importance
during the construction phase
Interference with communication channels (including railway signalling, defence
communication and telecommunication services) due to mutual induction with
electric current in live wires
Page 14
endeavour to secure existing government land for their construction. Where government
land is not available, land will be purchased on willing buyer willing seller basis and no
physical or economic displacement of people is envisaged. As neither the proposed
transmission nor proposed distribution projects seem to create any other significant
negative social or environmental impact, the investment can be classified as “Category B”.
The World Bank Operational Polices that need to be considered are OP- 4.01 covering
Environmental Assessment; OP- 4.04 on Natural Habitats; OP- 4.10 for Indigenous Peoples;
OP-4.11 on Physical Cultural Resources (PCR); OP-4.12 dealing with Involuntary
Resettlement; and OP-4.36 related to Forests. Additionally, World Bank Source Book on
Involuntary Resettlement states that for RoW in power transmission projects, local laws
and regulations would determine the constraint on use of land.
The constitutional provisions ensuring social and environmental safeguards are as follows:
Acts/Rule/Policy Objective Applicability to this project
5th Schedule of Provides for the administration and control For approvals and securing
Constitution of Scheduled Areas and Scheduled Tribes. land for sub-projects
(Article 244) (transmission lines and
Article 244(1) and Article 244 (2) of the towers) passing through
constitution of India enables the Scheduled Areas
government to enact separate laws for [As of now, none of the
governance and administration of the tribal proposed projects are
areas. In pursuance of these articles, located in Scheduled Areas]
President of India had asked each of the
state to identify tribal dominated areas.
Areas thus identified by the states were
declared as Fifth schedule areas
73rd Amendment of Enables participation of Panchayat level For any sub-project located
Constitution, 1992 institutions in decision-making and in panchayat area
supporting preparation and implementation
of development schemes.
74th Amendment of Enables participation of Urban local bodies For any sub-project located
Constitution, 1992 like municipalities and municipal in urban area
corporation in decision-making and
supporting preparation and implementation
of development schemes.
Panchayats The provisions of PESA Act extends the For approval of any sub-
(Extension to provisions of Part IX of constitution relating project located in
Scheduled Areas) to Panchayats to the Scheduled Areas. As Scheduled Areas
Act, 1996 per the provisions, every village in Schedule
V areas will have a Gram Sabha which
would approve the plans, programmes and
projects for social and economic
development before any such plans,
programmes and projects are taken up for
implementation at village level.
Page 15
Social Policies:
The social polices applicable to the proposed projects are provided below:
Act / Rules / Policies Applicability
1 The Right to Fair If any involuntary land acquisitions are undertaken to secure land for
Compensation and projects they will fall under the purview of The Right to Fair
Transparency in Compensation and Transparency in Land Acquisition, Rehabilitation and
Land Acquisition, Resettlement Act (RFCTLARRA), 2013. The act puts the onus on the State
Rehabilitation and Government to ensure that there is a legitimate and bona fide public
Resettlement Act purpose which necessitates the acquisition and that the potential
(RFCTLARRA), benefits of the project outweigh the social costs to the affected
2013** populations. The responsibility of the utilities is restricted to selecting the
site for substations and requesting for land to be secured. The
RFCTLARRA, 2013 makes it mandatory for the State Government to carry
out a Social Impact Assessment (SIA) and publicise the findings through
public hearings. Further, the Act outlines the criteria for determining
compensation to be given for the land acquired and requires that
Rehabilitation and Resettlement (R&R) Awards are provided for each
affected family. The awards are also to be made public ensuring
transparency in the process.
Details of compensation and R&R entitlements are provided in the table
below and figure 1 provides an overview of the process to be followed.
2 Andhra Pradesh These rules have been notified by the Government of Andhra Pradesh
Right to Fair in exercise of the powers conferred by Section 109 of the RFCTLARRA,
Compensation and 2013. The rules specify:
Transparency in (i) Process for carrying out the Social Impact Assessments (SIAs)
Land Acquisition, (ii) Institutional Support for SIAs
Rehabilitation and (iii) Other guidelines for carrying out the SIAs
Resettlement Rules, (iv) Process for conducting public hearings
(A.P. RFCTLARRR) (v) Declaration of Awards and Compensation
2014
As per Chapter V Sections 25, 26 and 27 of the A.P. RFCTLARRR 2014,
awards and compensations are in line with the provisions of the
RFCTLARRA, 2013. Section 28, further specifies the following that were
to be notified by the State Government:
(a) The multiplication factor mentioned in RFCTLARRA, 2013 is set at
1.25 for rural areas other than scheduled areas and 1.50 for
scheduled (tribal) areas
(b) The one-time grant to artisan, small traders and certain others is
set at INR 25,000
(c) The payment of compensation shall be made expeditiously
through account payee cheques / electronic mail transfer
3 The Electricity Act, At the national level, the Indian Telegraph Act, 1885 and the Electricity
2003 (With Act, 2003 give the transmission and distribution utilities the authority to
place towers, poles and lines on any land as required. However, Section
Page 16
Act / Rules / Policies Applicability
Amendments in 10 (b) of the Indian Telegraph Act, 1885, clearly states that land for the
2003 & 2007) lines and poles (towers) will not be acquired. Further, Section 67 (3) and
And 68 (5) of the Electricity Act, 2003 require the utilities to minimise damage
The Indian to property in carrying out their works, and to pay full compensation to
Telegraph Act, 1885 all persons interested for any damage sustained by them due to the
works carried out.
The details of compensation paid by the power utilities, in accordance
with these laws, is provided in Annexure 6 – Compensation Plan for
Temporary Damages.
4 Ministry of Power, These guidelines have been formulated for “determining the
Guidelines for compensation towards “damages” as stipulated in Section 67 and 68 of
Payment of the Electricity Act, 2003 read with Section 10 and 16 of the Indian
Compensation Telegraph Act, 1885 which will be in addition to the compensation
Towards Damages in towards normal crop and tree damages”
Regard to Right of According to Section 2 of the Guidelines, compensation will be payable
Way for only for transmission lines supported by a tower base of 66 kV and
Transmission Lines, above, and not for sub-transmission and distribution lines below 66 kV.
2015 However, the Government of Andhra Pradesh has not adopted these
guidelines.
5 Indian Treasure The Act provides for procedures to be followed in case of finding of any
Trove Act, 1878 treasure, archaeological artefacts etc. during excavation. Possibilities of
as amended in such discoveries are quite remote due to limited and shallow
1949 excavations. However, in case of such findings the concerned Utility will
follow the laid down procedure in the Section-4 of Act.
Details of compensation and R&R entitlements as per RFCTLARRA, 2013, are provided in
the table below and figure 1 provides an overview of the process to be followed:
a. Comprehensive Compensation Package
Eligibility for Entitlement Provisons
Affected family. Determination of Compensation:
Page 17
The Scheduled Tribes and other traditional In case of rural areas (other than
forest dwellers who have lost any of their Scheduled Areas) a multiplication factor
forest rights recognized under the Scheduled of 1.25 will be applied
Tribes and Other Traditional Forest Dwellers In case of Scheduled (Tribal) Areas, a
multiplication factor of 1.50 will be
(Recognition of Forest Rights) Act, 2006 due
applied
to acquisition of land or
In case of urban areas, a multiplication
Family whose primary source of livelihood factor of 1.00 will be applied
for three years prior to the acquisition of the
land is dependent on forests or water bodies 3. Value of asset attached to land:
and includes gatherers of forest produce, Building/Trees/Wells/Crop etc. as valued by
hunters, fisher folk and boatmen and such relevant govt. authority
livelihood is affected due to acquisition of
4. Solatium: 100% of total compensation
land; or
A member of the family who has been Total Compensation = Market value of land
assigned land by the State Government or mentioned against (1) X relevant multiplier (2)
the Central Government under any of its + Value of assets (3) + Soaltium (4)
schemes and such land is under acquisition;
(**)As determined by Government of Andhra
or
Pradesh
A family residing on any land in urban areas
for preceding three years or more prior to the
acquisition of the land or whose primary
source of livelihood for three years prior to
the acquisition of the land is affected by the
acquisition of such land
b. R&R Package
S.No Elements of R&R Entitlements Provisons
1. Provision of housing units in case of If a house is lost in rural areas, a
displacement constructed house shall be provided as per
Indira Awas Yojana specifications; or if the
family opts not to take the house, the
equivalent cost of the house may be offered
instead
If a house is lost in urban areas, a
constructed house shall be provided, which
will be no less than 50 sq mts in plinth area;
or if the family opts not to take the house
offered, it shall get a one-time financial
assistance for house construction which
shall not be less than INR 1,50,000 / -
These benefits shall also be extended to
any affected family which is without
homestead land and which has been
residing in the area continuously for not
less than three years preceding the date of
notification of the affected area
Page 18
No family shall be given more than one
house
2. Choice of Annuity or Employment The Appropriate Government shall provide the
following options:
Where jobs are created through the
project, after providing suitable training
and skill development, the Appropriate
Government shall make provision for
employment to at least one member per
affected family in the project or arrange a
job in such other project as maybe
required. The wages for the job shall not
be less than the minimum wages provided
for in any law for the time being in force
Or
Onetime payment of INR 5,00,000 / - per
affected family
Or
Annuity policies that shall pay not less than
INR 2,000 per month per family for twenty
years, with appropriate indexation to the
Consumer Price Index for Agricultural
Labourers
3. Subsistence grant for displaced Each affected family which is displaced form
families for a period of one year the land acquired shall be given a monthly
subsistence allowance equivalent to INR 3,000
per month for a period of year from the date of
award
4. Transportation cost for displaced Each affected family which is displaced shall
families get a onetime financial assistance of INR
50,000 /- as transportation cost for shifting of
the family, building materials, belongings and
cattle
5. Cattle shed / petty shops cost Each affected family having cattle or having a
petty shop shall get onetime financial
assistance of such amount as the Appropriate
Government may specify subject to a
minimum of INR 25,000 /- for the construction
of cattle shed or petty shop
6. Onetime grant to artisan, small traders Each affected family of an artisan, small trader
and certain others or self-employed person or an affected family
which owned non-agricultural land or
commercial, industrial or institutional structure
in the affected area, shall get a one-time
financial assistance of INR 25,000 /-
Page 19
7. Onetime resettlement allowance Each affected family shall be give a onetime
Resettlement Allowance of INR 50,000 /-
8. Stamp duty and registration fee The stamp duty and any other fees payable
for registration of the land or house allotted
to the affected families shall be borne by the
requiring body
The land for house allotted to the affected
family shall be free from all encumbrances
The land or house allotted may be in the
joint names of wife and husband of the
affected family
Special provisions for Scheduled Castes and Scheduled Tribes
In addition to the R&R package, SC/ST families will be entitled to the following additional benefits:
One time financial assistance of INR 50,000 /- per family
Families settled outside the district shall be entitled to an additional 25% R&R benefits
Payment of one third of the compensation amount at very outset
Preference in relocation and resettlement in area in same compact block
Free land for community and social gatherings
In case of displacement, a Development Plan is to be prepared
Continuation of reservation and other Schedule V area benefits from displaced area to
resettlement area
Page 20
Activity Chart for RFCTLARRA, 2013
12 Months
Pre-Notification
9 Months
Government
Pre. Notification
within 1 year of
Finalization of
R&R Scheme
Census Survey & Preparation of R&R Scheme by
12 Months
Administrator under Section 16
Notification
Months
12
Award under Section 30
Disbursement of Compensation and R&R Benefits 3 Months from Com. 6 months for
under Section 38 R&R. (not possible without this)
Page 21
However, it should be noted that as stated earlier, for the proposed transmission and
distribution projects no involuntary acquisition is required for securing land and the
projects will not result in any physical or economic displacement of people.
Environmental Policies:
The Forest (Conservation) Act, 1980 is the main legislation through which the
environmental impacts of transmission projects are managed since the current regulation
does not require an Environmental Impact Assessment for transmission lines. The
legislation requires compensatory afforestation for any forest land diverted for non-forest
use in twice the area diverted with afforestation undertaken by the respective state Forest
Department. A national fund CAMPA has been created for this purpose. In case projects
pass through or are located in designated protected areas, clearances from the Wildlife
Board are also required.
It appears that the constitution of India and several acts ensure protection of project
affected people which are consistent with World Bank policies; hence there is no need to
bridge the gap between protection measures guaranteed under Indian Laws and World
Bank safeguard requirements.
Organisational Arrangements
APTRANSCO has established a corporate cell to implement the Environment and Social
Management Plans (ESMPs). The Environment and Social Management System (ESMS)
cell has the following members:
Page 22
The cell will also deal with redressal of grievances and requests for Public Information.
Details are provided in Table under Section 9.
APSPDCL / APEPDCL
SPDCL and EPDCL have identified an Environment and Social Management member to
manage the potential social and environmental impacts from the proposed projects.
SPDCL: SE/Civil
EPDCL: EE/Civil
The impact management and mitigation framework has been designed in accordance with
applicable National and State laws as well as with international standards for environment
and social impact management. The framework is built on the principle of avoidance,
minimization and mitigation wherein preference is given to avoiding any negative social
impact wherever possible. If it is not possible to avoid negative impacts, utilities will strive
to minimize these impact and take mitigation measures.
The impact management and mitigation framework is provided below:
Page 23
Potential Social Impact Mitigation Methods
proposed route. Only in rare cases, when Government land is
not available, other methods of securing land will be pursued. In
any case, minimal amount of lands are required for substations
(the land required for a 132kV / 33kV substation is approximately
5 acres1). The following steps are to be followed depending on
the method of land acquisition:
i. Transfer of Government land: The Andhra Pradesh Land
Allotment Policy (G.O. Ms. No. 571 issued 14.09.2012)
prescribes that only waste lands will be allotted and
environmentally sensitive / fragile areas such as tank beds,
river, beds, hillocks with afforestation shall not be allotted.
ii. Voluntary donation: In the case of voluntary donation of
land, there should not be any undue pressure on the land
owner / user(s) to transfer ownership of their land and the
donor should be fully aware of the value of the donated land.
iii. Purchase of land on willing buyer and willing seller: This is
done on the basis of negotiated price. These negotiations
shall be carried out in a transparent manner providing the
seller of full information/ provisions of the law of the land.
iv. Involuntary acquisition of land: Involuntary acquisition of
land will be the last resort and be undertaken only when
other methods are not feasible. In the case of involuntary
acquisition, the provisions of RFCTLARRA, 2013 and the A.P.
RFCTLARRR, 2014 shall be applicable.
Note: The land for the proposed investments in APTRANSCO secured
either from the Distribution Utilities (Discom) where they have provided
extra land available in their existing substations to APTRANSCO or
government land has been identified. The status of sites for the proposed
12 substations as on 5th May 2016 is provided below:
1
Reference manuals on construction and operational practices of EHV substations & lines and commercial
and load dispatch operations. Available at: http://www.aptransco.gov.in/transco/images/APTRANSCO-
Technical-reference-book-2011-vol-ii.pdf
Page 24
Potential Social Impact Mitigation Methods
Yet to be identified (proposed 3
through transfer of government
land)
The land requirement for distribution substation is around 0.5 acre which
will be secured through transfer of government land or purchase of land.
Land parcels for this have been identified for the purpose and same will
be secured as and when the sub projects are firmed up.
Restricted use of land and Right of Way (ROW) does require lands for two purposes: (i) one,
concerns regarding right of for tower footing; and (ii) the other, transmission/ distribution
way (RoW) lines (corridor). Unlike in case of substations, for the
construction of transmission towers / distribution poles and the
transmission / distributions lines, there is no permanent loss of
lands. Lands under the tower and/ corridor can continue to be
used. So, ownership of the land remains with the existing owner
and is not transferred to the requesting body.. The utility will
have the right of user only in the property under, over, along,
across in or upon which the lines and poles / towers are placed.
However, Government of India (Ministry of Environment and
Forests- MoEF) mandates the utilities to maintain right of way
corridors as follows:
Voltage Width of RoW* (in meters)
132 kV 27
33 kV 15
11 kV 7
*Width of Right of Way is as per MoEF guidelines dated May 2014
In the width of the RoW, some restrictions are imposed and trees
are cut or pruned to the extent required for preventing electrical
hazards by maintaining the following:
2
Applicable only for transmission towers.
Page 25
Potential Social Impact Mitigation Methods
Damage to trees
Damage to crops
Damage/disturbances to structures
Damage to trees
Damage to crops
Damage/disturbances to structures
Page 26
Potential Social Impact Mitigation Methods
ensured during preparation and implementation of the
project. It will be further ensured that
- Women employed by project are fully informed about
labor rights
- Men and women receive equal pay for equal work
- Construction sites are properly lit and minimize blockage
of access roads to mitigate the concern for security of
women
- Women are fully integrated into any income restoration
activities
In India, as women usually do not have property rights,
ensure that women are informed/consulted before securing
land for project activities
Ensure that women receive compensation for land, RoW
and damage to crops and trees in cases where property
rights are with women
3
Price fixed shall not be less than what the land owner would be entitled to as per AP RFCTLARR Act of 2014.
Page 27
Potential Social Impact Mitigation Methods
extent of the impacts may vary owing to the vulnerable
socio-economic position of these communities. Therefore,
Section 41 of RFCTLARRA, 2013 has special provisions for
people belonging to SCs and STs
As per Section 41 of RFCTLARRA, 2013:
- In cases of involuntary displacement of the Scheduled
Castes families, a Development Plan shall be prepared in
the format prescribed in RFCTLARR. The Development
Plan shall lay down the details of the procedure for
settling land rights due, but not settled and restoring
titles of the Scheduled Castes on the alienated land by
undertaking a special drive together with land
acquisition.
- The resettlement areas predominantly inhabited by the
Scheduled Castes shall get land, to such extent as may
be prescribed by the Appropriate Government free of
cost for community and social gatherings.
- Any alienation of lands belonging to members of the
Scheduled Castes in disregards of the laws and
regulations for the time being in force shall be treated as
null and void.
The environmental issues associated with transmission and distribution (T&D) projects are
manageable since (a) They are mostly localised to Right of Way (ROW); (b) the ‘footprint’
associated with towers is small and (c) there is flexibility in siting facilities within relatively large
host area. The transmission line project may have some adverse effects on natural resources
however, they can be minimized by careful route selection and siting of substations. The
potential environment impacts and the respective management measures are provided below:
Page 28
Potential Environment Impact Mitigation Methods
Clearing of trees with in Right Care must be taken to avoid thick vegetation; towers to be
of Way (ROW) located where vegetation is thin. This will greatly minimize tree
loss and compensation to be paid to tree owners. Clearance for
trees to be cut will be taken from concerned authorities and if
required compensatory afforestation (CA) has to be done in
association with the concerned authorities. Trimming of trees
should be done in consultation with the concerned authorities.
The forest types in the mentioned sections are mostly governed
by Open Forests and Non-forest types thereby minimizing
presence of rare and endangered species.
Aesthetic appeal The route is to be planned to avoid any dense habitation or
forested area. The clearing of trees must be kept to minimum
and clearing of trees must be kept to minimum and wherever
possible, trimming of trees must be adopted vis-à-vis felling of
trees.
Soil and water contamination Follow laid down procedures for safe disposal of used
due to unscientific disposal of transformer oil, lead battery and electrical and electronic
used transformer oil, lead equipment
battery and electrical and
electronic equipment
Global warming due to Proper maintenance of equipment to minimize leakage
Mishandling and leakage of
SF6 gas
Substations related Impacts
Used Transformer Oil As a part of routine maintenance, transformer oil is changed
every 10- 15 years. The removal of the oil is generally carried out
at the central depot. The volume generated is very limited and
at long intervals. Further, it is disposed of centrally through
authorized recycler. Hence, overall no significant adverse
impact is anticipated.
e-Waste The scrapped electrical and electronic waste generated from
routine maintenance activities include damaged components,
electrical fittings & fixtures etc. These are collected centrally and
disposed of through MSTC Limited, a Govt. of India Enterprise.
No significant adverse environmental impacts are anticipated
from handling and storage of the e-waste at the site.
Drainage Congestion Appropriate drainage and sewage network to be provided at the
substations to avoid flooding, land and water pollution. Regular
inspection, cleaning and maintenance of the drainage systems
in and around the site needs to be ensured, especially if
construction works are carried out during the wet season.
Page 29
Grievance Redressal Mechanism
The grievance redressal mechanism (GRM) provides the procedure to address/resolve the
concerns and grievances of people affected by the projects. All the three utilities have three
systematic and robust mechanism for addressing the grievances. The formal arrangements
existing for DISCOMS is quite exhaustive as the framework rests on consultative
mechanisms involving officials as well non-official representation:
Page 30
APTRANSCO’s ROG mechanisms are bit different as they have very little to interact with
the consumers directly. Their interface is chiefly with the people on whose lands towers/
corridors are laid, contractors, labourers, and other departments and utilities. Currently, the
arrangements are as follows:
People with grievances can approach local Divisional Engineer (DE). He is the main
officer to handle any complaints at the local offices.
At the corporate office, ED Planning and HRD is the nodal officer for Grievance Redressal
in APTRANSCO. He is supported by Additional Secretary, APTRANSCO. In case any
grievance is not satisfactorily handled at the DE level, it gets escalated to the corporate
office. For the World Bank Projects, the ESMS cell will support the DE in resolving any
project related grievances before escalation to ED Planning and HRD. Towards enabling
this support, the following supplementary measures are planned: (i) online registration
of complaints; (ii) registration of complaints on toll free numbers; (iii) receipt of
grievances through sub-station advisory as well as district electrical coordination
committees; (iv) receipt of grievances through ITDAs in schedule areas; and (v)
Spandana viz., regional meetings with the CMD.
.
Monitoring Mechanism
This section details out the plan to monitor the implementation of social impact
management and mitigation measures and grievance redressal.
The ESMS cell of the APTRASNCO and the environment and social member of the project
team for discoms has overall responsibility for achieving the environmental and social
performance. They will be responsible for monitoring the ESMF, including monitoring the
implementation of the ESMF and subsequent preparation, implementation and monitoring
of environmental and social safeguards for the sub-projects.
The environmental and social monitoring plan for each project will be integrated with the
construction, operation and maintenance activities and shall be monitored by the ESMS
cell/designated environment and social member on a monthly basis.
The Environment and Social Member (Discoms) and the concerned EE/Civil in field -
covering the jurisdiction of the Transmission Project, concerned DE/Construction in Vidyut
Soudha, looking after the Transmission Project of ESMS cell (APTRANSCO) will also
perform supervision site visits during the construction and operations phases of the sub-
projects to confirm that environmental and social safeguards are being effectively
implemented, and status of the same will be reported periodically in the Site Visit Reports.
Page 31
The quarterly and annual reports on the key steps, outputs and results of the environmental
and social management actions taken to support the implementation of the ESMF and the
sub-projects will be prepared. The Environment and Social Member (corporate members
of ESMS cell (SE / PM / 400 kV / APTRASNCO / VS / Hyderabad, SE / PM / Construction /
APTRANSCO / VS / Hyderabad, EE / Civil / APTRANSCO /VS / Hyderabad) will track the
overall status and any shortcomings in the implementation of the ESMF and of any
circumstances or occurrences that could adversely impact the environmental and social
performance of the project beyond the already anticipated impacts.
Page 32
*Note: Our conservative estimate will be max 10 samples per scheme i.e a longitudinal Transmission line
laying project including receiving station.
1. Management of Social 10,00,000 For crop damages during HVDS work and
Impact Damage to any structure, road, any other
public utility like water pipes etc. during
UG cabling
2. Monitoring Monitoring will be undertaken by
employees and hence no additional cost
3. Training and Capacity 76,000 2-day training covering all aspects
Building 4 resource persons (one each for
ESMF, GAP, TPP, Monitoring). 8,000
per resource person for 2-3 hr session
Trainings will be held at offices of
respective utility so no venue cost
Assuming INR 20,000 for logistics
including travel and food
Page 33
Assuming INR 24000 for travel cost for
resource person
4. GRM (including spend Mechanism in place. INR 1 Cr are
on publicity) allocated for publicity by EPDCL every
year
Total: 10,76,000
The draft ESMF that was created through these consultations was then shared with the
World Bank whose inputs further strengthened the framework.
Consultations were undertaken with the community and vulnerable groups including
farmers, SC and women.
The final draft of the ESMF and related RPF, TPPF and GAP were disclosed on the websites
of the three utilities following which three state level disclosure workshops were held to
solicit feedback from key stakeholders. The participants at these workshops included
representatives of other government departments, academic institutions, members of
NGOS / community based organisations, media and the general public. This document
captures the feedback received and action taken (Chapter 14 and Annexure 11) and has
been updated to include relevant points that arose from these workshops.
Page 34
2. Introduction
2.1 Project Context
The Government of Andhra Pradesh (GoAP) has signed a Memorandum of Understanding
(MoU) with the Government of India (GoI) to launch the ‘Power for All” initiative. The
purpose of the initiative is to ensure 24x7 power supply in the State of Andhra Pradesh
(AP). The key interventions planned under the initiative, to strengthen power transmission
and distribution are:
Adequate power transmission and distribution systems
Interventions for improving operational efficiency and customer satisfaction
The Government of Andhra Pradesh, through the GoI, has approached the World
Bank for financial and technical support. Specifically, the proposed World Bank
investments will be to implement the following initiatives:
Establish new sub-stations
Upgrade existing sub-stations
Lay transmission/distribution lines
Deploy smart grid technologies
The investments will be implemented through the Andhra Pradesh state power utilities –
Transmission Corporation of Andhra Pradesh Limited (APTRANSCO), Andhra Pradesh
Southern Power Distribution Company Limited (APSPDCL) and Andhra Pradesh Eastern
Power Distribution Company Limited (APEPDCL).
A tentative list of twelve schemes were identified for proposed World Bank funding. The
total investments were estimated to be INR 522.11 Cr. The identified investments are for
raising of new 132 kV substations and for erection of 132 kV DC radial line between the
substations. Apart from the above a total investments of INR 166 Cr were identified for the
following:
Constructing Substations and erection of 132 kV radial line
Augmentation of power transformers;
Testing instruments (13 sets);
Tower spotting software;
Design licenced software;
The tentative long list of transmission schemes that have been identified for World Bank
funding are provided below:
Page 35
Sl. Name of the Line
Connected lines District Site Status
No. Sub-station Length
Package-I
Erection of LILO of 132kV
Site available
132/33kV SS Ramachandrapuram - 9.00 East
1. in existing
Mummidivaram Amalapuram to proposed km Godavari
33kV SS,
Mummidivaram
Erection of 132kV DC line for
making LILO of 2nd circuit of
6.86
132kV Kakinada – Yanam line to
km Site available
132kV SS the proposed 132/33 kV East
2. in existing
Gollapalem Gollapalem SS Godavari
33kV SS,
Stringing of 2nd circuit on
42.00
existing 132kV Kakinada –
km
Yanam DC/SC Line
Identification of
Erection of 132kV DC radial line
Government
132/33kV SS at from 220/132kV SS Samarlakota 24.89 East
3. land for the
Jaggampet to the proposed 132/33kV km Godavari
substation is
Jaggampet SS
under process
132kV DC radial line from 132kV
132kV SS Site available
Noonegundlapalli Switching 25.00
4. Kothapalli Chittoor in existing
station to the proposed 132/33 km
(Gudipala) 33kV SS,
kV Kothapalli SS
Package-II
Erection of 132kV DC radial line
from proposed 132/33kV 20.00
Pachikapallam to the proposed km
132kV SS 132/33 kV Penumur SS Identified Govt.
5. Chittoor
Penumur 2nd circuit stringing on 132kV Land
DC/SC Line from 220/132kV SS 40.00
Nagari to 132kV SS km
Pachikapallam
Identification of
Erection of 132kV DC radial line
Government
132kV SS from 132/33kV SS Rayachoti to 20.00
6. YSR land for the
T.Sundupalli the proposed 132/33kV SS T. km
substation is
Sundupalli
under process
Request letter
submitted to
Zonal
Erection of 132kV DC radial line
Manager,
132kV SS from 220/132kV SS 30.00
7. YSR APIIC, Kadapa
Satellite City Chinakampalli to the proposed km
for 15 Acres of
132/33kV SS Satellite city
land near
Vogivemana
University
Page 36
Sl. Name of the Line
Connected lines District Site Status
No. Sub-station Length
Erection of 132kV DC radial line
Site available
132/33kV SS from 220/132kV SS Kondapalli to 25.00
8. Krishna in existing
Mylavaram the proposed 132 kV Mylavaram km
33kV SS,
SS
Package-III
Site available,
Erection of 132kV DC radial line
5.00 Acres,
132kV SS from 400/220/132kV SS 25.00
9. Nellore Sy.No.85/2,
Kadivedu Manubolu to the proposed km
Kadivedu(V),
132/33 kV Kadivedu substation
Chillakuru(M)
Erection of 132kV DC radial line
132kV SS from 220/132kV SS Podili to the 26.00 Identified Govt.
10. Prakasam
Chinarikatla proposed 132/33kV km Land
ChinarikatlaSS
Making LILO of 2nd ckt of 220kV
Bommur – Rampachodavaram 1.00
line to proposed 220/33kV SS km
220/33kV SS East
11. Korukonda Site available
Korukonda Godavari
Stringing of 2nd ckt on existing
67.00
220kV Bommur –
km
Rampachodavaram line
Erection of 132kV DC radial line
132kV SS East from 220/132kV SS Podili to the 21.00 Identified Govt.
12. Prakasam
Gangavaram proposed 132/33kV East km Land
Gangavaram SS
The total investments are estimated to be INR 2490 Cr for APSPDCL and INR 1032 Cr for
APEPDCL. The sub-project components covered under the investments are:
S.No. Component Component Description
HVDS aims at reduction of losses through replacement of the low
High Voltage voltage distribution network (LVDS) with HVDS and installation of
Distribution large number of smaller capacity distribution transformers – 40 KVA,
1. System 25 KVA or 16 KVA in place of higher capacity distribution transformers
(HVDS) – 100 KVA or 63 KVA for supply to agricultural consumers. This system
is best suited to meet the scattered low density loads observed in
rural areas
Energy Replacement of existing pump sets with 5 star BEE rated energy
Efficient efficient pump sets would result in energy conservation and increased
2.
Pump Sets pumping efficiency
Energy efficient pump sets to be installed on pilot basis
Remote
Remote starters/Electric Smart Control Panel would provide facility
3. ON/OFF
ON/OFF operation remotely by using SMS/phone call. This would also
starters:
Page 37
provide protection to the devices due to under voltage, over voltage,
dry run, single phasing etc.
It is proposed to install remote starters for pump sets
A smart meter would record consumption of electric energy in
intervals of an hour or block and communicates information back to
Smart
4. the utility for monitoring and billing. Smart meters enable two-way
Metering
communication between the meter and the central system
Smart meters for urban consumers
The SCADA/DMS System will provide real time monitoring and
control, loss minimization/loss balancing and considerable
improvement in voltage/VAR profiles. It would also facilitate proper
handling of loads while load shedding & restoration, efficient
planning of network for future growth by using proven power system
planning tools
SCADA
5. Scheme consists of installation of Remote Terminal Units (RTU) at
each 33/11 kV substation and integration of these RTUs with
centralized control center to manage the Distribution system of the
town
SCADA to be implemented in balance sub-stations of
Vishakhapatnam and Vijayawada which have not been covered under
R-APDRP/IPDS
AP is exposed to cyclones, storm surges, floods and droughts. Every
two or three years, AP experiences a moderate to severe intensity
UG Cabling cyclone or landfall. According to an estimate by the Dept. Of Disaster
and Covered Management, GoAP, about 44% of the state is vulnerable to tropical
6.
Conductors storms and related hazards. Placing power lines underground
eliminates their susceptibility to lightning and wind damage
It is proposed to provide UG cabling in smart city areas of
Visakhapatnam and Kakinada towns
Distribution New 33/11 kV indoor substations, GIS substations and new 33/11 kV
7
Substations outdoor substations are proposed
TA would be needed for effective implementation of proposed
Technical investments. TA support is required for overall institutional
Assistance development, capacity building and governance improvement as well
8. (TA)/Capacity as some specific areas like strengthening and improving Project
Building Planning and implementation, business processes and accountability
systems, corporate governance and financial management practices
and human resource development
Page 38
2.2 Purpose of ESMF
Currently, the projects and sub-projects under the proposed World Bank investments have
been identified but the final project sites and the alignment of the transmission and
distribution lines will be concluded after detailed design is prepared. Therefore, an
Environment and Social Framework is being developed to manage and mitigate the
potential positive and negative impacts of the proposed projects. The ESMF provides a
procedure for environment and social assessment of projects. It will guide the utilities in
determining the appropriate level of environmental and social assessment required for the
sub-projects and in preparing the necessary environmental and social mitigation measures
for the sub-projects during the pre-construction, construction, operations and maintenance
phases. The objective of ESMF are as follows:
Identify potential social and environmental impacts of the proposed project
activities
Compliance with applicable national and local guidelines
Compliance with World Bank safeguard policies
Minimize the potential adverse impacts and maximize the potential positive
impacts
Lay down the procedure for preparing project/investment specific environment
and social management plan
Based on the mitigation and management measures outlined in this ESMF document,
specific Environment and Social Management Plans (ESMP) will be developed for different
components of the World Bank supported investments. These ESMPs will be based on
component specific Environment and Social Impact Assessments (ESIA). In this regard:
An ESMP (including a safety plan) has been prepared for the proposed HVDS projects
that are to be implemented by APEPDCL and APSPDCL. This ESMP will be included in
the bidding documents submitted by the two distribution utilities.
For distribution substations, ESIAs will be prepared for a cluster of distribution
substations and the bidding docs will include a resultant ESMP
Page 39
3. Socio-Economic Profile of State
History
In 1953, the Andhra State Act was passed creating the State of Andhra which constituted
territories of the Madras State that were predominantly Telugu-speaking. In 1956 the
Telugu-speaking people in the region of the former state of Hyderabad were merged with
the Andhra state to form the combined state of Andhra Pradesh. This was the first Indian
state formed on the basis of linguistic identification. The combined state had 23 districts
with its capital in Hyderabad. Following a prolonged movement for a separate State,
Andhra Pradesh was further bifurcated on 2nd of June 2014, to form the state of Telangana
by passing of the AP State Reorganization Bill. After bifurcation, 10 districts (including the
capital city of Hyderabad) with a combined area of 1,14,840 Sq. Km. and a population of
3.53 Cr people became a part of the new State of Telangana. Andhra Pradesh presently
constitutes 13 districts and has a new capital city of Amravati.
Geographic Profile
The present-day state of Andhra Pradesh, lies between 12°41’ and 22°N latitude and 77°
and 84°40’E longitude and covers an area of 1,62,760 Sq. Km. making it the 8th largest state
in the country. It includes the eastern part of the Deccan Plateau and a sizeable part of the
Eastern Ghats and is bordered by Maharashtra, Chhattisgarh, Telangana and Orissa in the
North, the Bay of Bengal in the East, Tamil Nadu to the South and Karnataka to the West.
The State has the second longest coastline in the country with a length of 974 km and two
major rivers, the Godavari and the Krishna.
Of the total land area, 38.31% of the state’s geographical area is under net area sown (62.35
lakh hectares), 22.51% under forest (36.63 lakh hectares), 8.61 % under current fallow lands
(14.01 lakh hectares), 12.30% under land put to non-agricultural uses (20.02 lakh hectares),
8.30% under barren and uncultivable land (13.51 lakh hectares) and remaining 9.97% is
under other fallow land, cultivable waste lands like permanent pastures and other grazing
lands and land under miscellaneous tree crops and groves not included in net area sown.
Demographic Profile
A.P. is the 10th largest state in India with a population of 4.94 Cr (4.08% of India’s population)
and a population density of 304 persons per sq. km. There are 126.65 lakh households in
the State and the average size of the household is 3.95. A.P. is largely rural with 70.42% of
the population living in rural areas and 29.58% living in urban areas.
Of the total population Scheduled Cates (SC) constitute 17.10% and Scheduled Tribes (ST)
5.33%. Prakasam is the district with the highest SC population (7.88 lakh) while
Vizianagaram has the lowest (2.47 lakh). Visakhapatnam is the district with the largest
concentration of STs with 14.42% of the total ST population, while Kurnool with 2.04% has
the lowest concentration.
Page 40
The growth rate of population has slowed from 11.89% in 2001 to 9.21% in 2011 while the
sex ratio rose from 983 in 2001 to 997 in 2011 (as per census data). In absolute terms, 2.47
Cr (50.1%) of the total population is male and 2.46 Cr (49.9%) female. The districts of
Visakhapatnam, East Godavari, West Godavari and Guntur, have registered a progressive
sex ratio moving from less than 1000 category to more than 1000 from 2001 to 2011. The
SCs and STs have registered a sex ratio of 1007 and 1009 respectively. However, despite
the overall improvement in sex ratio, there was a troubling decline in child sex ratio from
964 in 2001 to 944 in 2011 (census data).
Literacy Rate in the state has increased and was 67.35% as per the 2011 population census
as against 62.07% in the 2001 census; however this is still lower than India’s overall literacy
rate, which was 72.98% in 2011. The literacy rate is much higher for urban areas (79.2%)
than rural areas (62.4%). Also, while male literacy is 74.8%, female literacy is only 59.96%.
Among the districts West Godavari has the highest literacy (74.63% in 2011), while
Vizianagaram has the lowest (58.89% in 2011).
District-wise Demographic Data
According to the Socio Economic and Caste Census 2011, there are 13 districts in the State
of Andhra Pradesh, 670 tehsils, 14,514 gram panchayats/police stations. The total number
of villages in Andhra Pradesh are 17,521 and additionally there are 94 towns. The number
of rural households is 93.44 lakh (76.15%) and urban households is 29.26 lakh (23.85%). The
district with the highest density of population is Krishna district (518), while Kadapa district
has the lowest density (118). District wise demographic data is provided below:
District Area Population Male Female Sex Literacy Density /
(Sq. Km.) Population Population Ratio (%) Sq. Km.
Srikakulam 5,837 27,03,114 13,41,738 13,61,376 1015 61.74 463
East Godavari 10,807 51,54,296 25,69,688 25,84,608 1006 70.99 477
Guntur 11,391 48,87,813 24,40,521 24,47,292 1003 67.4 429
Krishna 8,727 45,17,398 22,67,375 22,50,023 992 73.74 518
Visakhapatnam 11,161 42,90,589 21,38,910 21,51,679 1006 66.91 384
Chittoor 15,152 41,74,064 20,90,204 20,83,860 997 71.53 275
Anantapur 19,130 40,81,148 20,64,495 20,16,653 977 63.57 213
Kurnool 17,658 40,53,463 20,39,227 20,14,236 988 59.97 230
West Godavari 7,742 39,36,966 19,64,918 19,72,048 1004 74.63 509
Nellore 13,076 29,63,557 14,92,974 14,70,583 985 68.9 227
YSR (Kadapa) 15,359 28,82,469 14,51,777 14,30,692 985 67.3 188
Prakasam 17,626 33,97,448 17,14,764 16,82,684 981 63.08 193
Vizianagram 6,539 2,344,474 1,161,477 1,182,997 1019 58.89 359
Data taken from Census 2011
Economic Profile
Andhra Pradesh’s Gross State Domestic Product (GSDP) at constant (2011-12) Prices grew
by 10.99% from INR 4,44,752 Cr in 2014-15 to INR 4,93,641 Cr in 2015-16; this was higher
Page 41
than India’s overall GDP growth which was 7.6% over the same time period. In terms of
sectoral contribution to the economy, the services sector contributed the most to overall
Gross Value Added (GVA) in 2015-16 (47%) followed by agriculture (29%) and industry
(24%). The services sector in fact has been the major driver of economic growth in the State
and continued to be so in 2015-16, registering a growth rate of 11.39% over the previous
year. Real estate and trade, hotels and restaurants were the major contributors to the
service sector growth. The industry sector saw the second fastest growth, growing by
11.13% over the previous year led by growth in manufacturing and construction.
While the agriculture and allied activities sector did not grow by double digits, it still grew
by an impressive 8.4% over the previous year. The main crops in the state are Rice, Maize
and Pulses. The area under food grains in Andhra Pradesh grew by 4.21% to 41.30 lakh
hectares in 2015-16 from 39.63 lakh hectares in 2014-15. The total production of food grains
however decreased by 14.4% in 2015-16 to 137.56 lakh tonnes from 160.03 lakh tonnes in
2014-15. This decline was due to unfavourable seasonal conditions in some parts of the
State. This resulted in a negative growth in agriculture sub-sector of the agriculture and
allied sector. The overall positive growth was instead fuelled by the livestock, fisheries and
horticulture sub-sectors.
Under the livestock sub-sector, increase in the production of Milk, Meat & Egg resulted in
posting an encouraging growth rate of 11.2%; while the increase in the production of
Marine fish and brackish water prawns helped to register a significant growth rate of 32.8%
in Fishing Sector. Horticulture too grew impressively by 9.96% and contributed 5.6% to the
overall GSDP of Andhra Pradesh. There is 14.74 lakh hectares area under Horticulture in
Andhra Pradesh with production of 188.22 lakhs MTs.
The per capita income (at current prices) of Andhra Pradesh also rose by 12.38% in this
time period from INR 95,689 in 2014-15 to INR 1,07,532 in 2015-16. However, as per the
National Sample Survey Office (NSSO) of 68th Round (2011-12) the unemployment rate for
Andhra Pradesh State for Rural and Urban sectors stood at 12% and 43% respectively.
While the rural unemployment rate is lower than the corresponding figure for India (which
is 17%), the urban unemployment is significantly higher than the national average which
was 34%.
Page 42
4. Environment Profile of State
Overview
General
Geographical area of Andhra Pradesh is 1,62,440.1 km2 which is 5.13% of the landmass of
the country. The state is one of the six states/ union territories of India adjoining the Bay of
Bengal with a coastline of 974 km and continental shelf area of 33,227 sq. km. The average
width of the productive continental shelf area is 32 km with rich pelagic and demersal
fisheries. The continental shelf area narrows from north to south.
Page 43
Drainage
Andhra Pradesh is popularly referred to as a “River State”. Nearly 75% of the State territory
is covered by the basins of three major rivers - Godavari, Krishna and Pennar and their
tributaries. In addition, there are 17 other rivers like Sarada, Nagavali, Musi and other
streams. The Godavari with its 1,464 km length, of which about 772 km lies within the State,
is the longest and the broadest river in South India. Godavari, Krishna and Pennar are the
3 principal rivers of the State which drain into the Bay of Bengal. Godavari with its
tributaries Pranahita, Manjeera, Maneru, Indravati, Kinnerasani, Pamuleru and Sileru,
drains through the northern parts of the State. The River Krishna with its tributaries
Tungabhadra, Vedhavati, Hundri, Musi, Paleru and Munneru flows through the central
parts of the State. The River Pennar, the third biggest river, with its tributaries Chitravati,
Papaghni, Cheyyeru and Pincha drains through Rayalaseema region and Nellore district.
Geology and Mineral Resources
Andhra Pradesh is well known globally for variety of rocks & minerals and called as 'Ratna
Garbha', a state endowed with variety of minerals. Many of the ancient travellers and
historians have mentioned the ancient mining of Gold, diamond, base metals, precious
stones etc. The tertiary and quaternary formations with different litho units / rocks contain
host of industrial, non-industrial, metallic minerals. The geological formations of the
project districts are: (1) The unclassified Archaean crystalline rocks are mainly granite but
in the Eastern Ghats they comprise of granulite suites (khondalites and kodurites); (2) The
Middle– Upper Proterozoic the Cuddapahs and its equivalents; (3) The Mesozoic coal
bearing Gondwana strata; (4) Eocene lava flows (the Deccan traps); and (5) The semi-
consolidated or unconsolidated tertiary and recent rocks.
The state of Andhra Pradesh is rich in minerals such as limestone (34%), coal (10%),
mica(86%), Dolomites (11%), bauxite (40%), barytes (96%), clays (30%), heavy mineral
Page 44
beach sand (40%), manganese (10%), feldspar (11%), quartz, silica sand soapstone (16%),
gold, diamonds (16%), uranium, oil and natural gas, iron ore, semi-precious stones, granite
(40%), slates, limestone slabs, marbles, dimensional and building stones (40%).
The State is first in Barytes, Limestone and Beach sand heavy Mineral deposits in the
country.
The State is well known for Gold, Diamond, Precious and Semi-precious stones
occurrences over vast areas.
There are huge deposits of Bauxite in East Godavari and Visakhapatnam districts.
Krishna-Godavari on shore and off shore basin contain huge reserves of oil and
natural gas.
The State also contains huge uranium deposits in Kadapa and Nalgonda districts.
Andhra Pradesh is only State in the entire Southern India which contains large
deposits of Coal.
The State also has number of scattered low grade iron ore deposits in Prakasam,
Krishna, Khammam, Karimnagar, Kurnool and Kadapa districts.
The State is well known for exclusive granite varieties viz., Chimakurthy Black Galaxy
Granite, Srikakulam Blue, Khammam and Warangal Black granite Karimnagar Tan
Brown etc.
Climate
The State experiences tropical climate with slight variations depending on the elevation
and maritime influence which varies according to the three regions. Rainfall is received
from both the South-West and North-East monsoons, predominantly the former, but
precipitation varies across the State. The climate of Andhra Pradesh is generally hot and
humid. The summer season in this state generally extends from March to June. During
these months the moisture level is quite high. The coastal areas have higher temperatures
than the other parts of the state. In summer, the temperature generally ranges between
20 °C and 40 °C.
The summer is followed by the monsoon season, which starts during July and continues
till September. This is the season for heavy tropical rains in Andhra Pradesh. The major
role in determining the climate of the state is played by South-West Monsoons. About one
third of the total rainfall in Andhra Pradesh is brought by the North-East Monsoons around
the month of October in the state. The winters in Andhra Pradesh are pleasant. This is the
time when the state attracts most of its tourists. October to February are the winter months
in Andhra Pradesh. Since the state has quite a long coastline the winters are comparatively
mild. The range of winter temperatures is generally from 13°C to 30°C.
Page 45
Forest Resources of the State
Table: District wise Forest cover (in Square Km) for the State of Andhra Pradesh.
(Source: AP Forest Department)
District Geographic Very Mode. Open Total % of Change Scrub
Area Dense Dense Forest G.A.
Forest Forest
Anantapur 19,130 0 73 353 426 2.23 -2 956
Chittoor 15,151 7 929 1,463 2,399 15.83 -3 1,566
East-Godawari(T) 10,807 72 2,519 970 3,561 32.95 -1 168
Guntur 11,391 0 219 644 863 7.58 -1 392
Cuddapah 15,359 9 1,898 1,502 3,409 22.2 -1 1,304
Krishna 8,727 0 83 230 313 3.59 0 2.14
Kurnool 17,658 59 1,331 741 2,131 12.07 -7 403
Nellore 13,076 5 261 671 937 7.17 -3 680
Prakasam 17,626 172 1,342 1,590 3,104 17.61 13 859
Srikakulam(T) 5,837 0 108 508 616 10.55 0 471
Vizainagaram(T) 6,539 0 145 604 749 11.45 0 352
Vishakapatnam(T) 11,161 0 2,054 1,391 3,445 30.87 0 1,071
West Godawari (T) 7,742 12 621 276 909 11.74 -1 28
Total 1,60,204 336 11,583 10,943 22,862 14.271 -6 8,252
Page 46
Figure: Vegetation map cover for the state of Andhra Pradesh. The figure identifies
seven different categories indicated in the map in various colour patterns viz., very
dense forest; moderately dense forest; open forest; scrub; non-forested area; water
bodies and mangroves.
Page 47
Protected Areas
Page 48
Table: List of Wildlife Sanctuaries and Zoological Parks in the State of Andhra Pradesh
Sri Penusila Nellore District It covers an area of 1030.85 km2 is managed by the
Narasimha Wildlife Andhra Pradesh Forest Department
Sanctuary
Pulicat Lake Bird Nellore District It is a 481 km2 Protected area in Nellore District of
Sanctuary Andhra Pradesh state. Pulicat Lake is the second
largest brackish-water ecosystem in India
managed by the Andhra Pradesh Forest
Department and Tamil Nadu Forest Department.
108 km2 of this sanctuary is national park area.
Page 49
Historical and Cultural Sites
Page 50
5. Approach and Methodology
The methodology to design the Environment and Social Management Framework is
provided below:
Identify Training
Scoping and
Requirement Cost Estimation
Establish Baseline
Legal and
Draft GAP, RPF and Consultation and
Institutional
TPPF Disclosure
Framework
Define area of
Monitoring Plan
influence of the
project
1) Scoping and establishing baseline: Detailed project specific activities planned by each
utility for project implementation were identified and listed. This information was primarily
collected from initial discussions with the identified project implementation team and from
secondary data sources such as detailed project reports for each site, site survey and
assessment sheets, identified investment planning and related project schedule plans
provided by the utilities. At this stage, a generic socio-economic and environmental
baseline was also established. The parameters for the social baseline were:
Demography [age, ethnicity, gender, economic status, level of education, income
level and employment]
Land use
Access to basic infrastructure
Household asset/infrastructure
Page 51
Surface water
Waste
Noise
Traffic and transport
Visual impact
2) Understand the laws and policies applicable to Environment and Social Assessments:
India has a wide range of policies and regulations that are applicable to environmental and
social issues. A desk review of applicable national and state level laws and regulations was
undertaken to understand the applicability of these laws to the proposed projects.
Additionally, the relevant guidelines by the state power utilities, for planning, construction
and operations of the sub-stations and the transmission and distribution lines and the
World Bank Safeguard Policies and the World Bank Environmental and Social Framework
were also reviewed.
3) Define area of influence for each investment: The area of influence for each of the
investment was identified.
4) Identify potential risks/impacts and develop mitigation plan for the construction phase
and operations phase of the project: The socio-economic and environmental assessments
were undertaken to identify the potential social and environmental impacts and define the
mitigation plan. The proposed projects are likely to create impact on the environment in
two distinct phases -during the construction phase, which may be regarded as temporary
or short term; and during the operation phase that may be long-term effects.
5) Define the grievance redressal mechanism: The grievance redressal mechanism was
described to provide channels to address any adverse impact not pre-empted by the ESMF
and highlighted by the public.
6) Define monitoring plan and institutional arrangements for risk mitigation and grievance
redressal: The monitoring plan was defined to ensure that risk mitigation measures defined
in the previous step are implemented effectively.
7) Define GAP, RPF and TPPF: Gender Action Plan (GAP) was defined to ensure the gender
specific needs (for both men and women) are considered while assessing and managing
the impacts of the proposed investments.
The Resettlement Policy Framework (RPF): An RPF was designed to provide guidelines for
resettlement and rehabilitation in cases where the land for projects is acquired from the
community and may involve displacement of the population. The aim is to ensure that
impacts due to displacement and relocation are effectively managed, proper compensation
Page 52
is provided to the dislocated population and the livelihood of the displaced population is
restored.
Tribal Peoples Planning Framework (TPPF) was defined for the areas which may have some
concentration of tribal population, to ensure proper management of any potential adverse
impacts on the tribal population.
8) Training and Capacity Building: Training needs for the staff of implementing agencies were
identified to ensure that the screening form is completed correctly, monitoring of the
environment and social assessments is undertaken properly and the mitigation methods
are implemented and monitored appropriately.
9) Cost Estimates: The costs incurred to implement the various requirements of the ESMF
were budgeted. The broad cost estimates were provided for capacity building, training and
implementation of the ESMF and mitigation measures.
10) Consultation and Disclosure: The affected communities and stakeholders will be consulted
on the draft of the ESMF. It will ensure that sufficient time is provided to the stakeholder
groups to participate in the consultations. Once the guidelines for environment and social
management are finalized, the guidelines will be disclosed to the public.
Page 53
6. Stakeholder Analysis
The purpose of stakeholder analysis is to identify the stakeholder groups which can affect
or are directly/indirectly affected by the project activities. The analysis further maps the
relationship between the stakeholder groups, defines their roles, responsibilities and
interest in the project; and highlights the key expectations / concerns these stakeholders
have with respect to the planned investments. The key stakeholder groups include:
Government and regulatory agencies at national and state level which define the legal
and regulatory framework within which the project will operate.
Multilateral agencies such as the World Bank and Asian Development Bank that fund
power projects.
Power sector utilities in Andhra Pradesh which are implementing the project.
Different government departments at state and district level whose permission and
support is required to undertake various project activities like cutting trees and digging
roads to lay the overhead and underground lines respectively, securing land for
construction of substations and transmission and distribution towers, distributing
compensation for RoW and damage to trees and crops.
Panchayats and municipal corporations at the village/city level whose permission and
support is required to undertake various activities. The panchayats and municipal
corporations also provide a platform for the people to raise their grievances.
Public and Private sector companies like BSNL and Reliance who have their own
underground cabling network
Non-government organisations (NGOs), community based organisations (CBOs) like
resident welfare associations and informal groups like women’s group, farmer’s group
which provide platform to raise the concerns of the community and vulnerable groups
like women, SC and ST. This stakeholder group also act as channel to undertake public
consultations on the project design, planning and implementation and provides a
platform for grievance redressal.
Commercial and residential complexes, and communities which are the end-
beneficiaries of the project and are also receptors of various intended and unintended
externalities of the project like noise and water pollution, damage of crop/trees etc.
Vulnerable groups like women, SCs and STs
Page 54
Stakeholder Role/Responsibility/interest Expectations / Issues / Concerns
National Level
Ministry of Power The Ministry is primarily responsible for Proposed projects support the
(MoP) development of electrical energy in MoP aim to ensure 24x7 power
India. MoP lays down the legal and supply in the country
regulatory framework for the electrical Andhra Pradesh is one the first
energy sector. 3 states where 24x7 power for
Note: Electricity is a concurrent subject. all (PFA) project is being rolled
out. The learnings and best
practices from implementation
in Andhra Pradesh will guide
the roll out of 24x7 PFA in
other states.
Multilateral Agencies like the World Bank, ADB and Social impacts on vulnerable
Agencies GIZ fund power projects in the State. In groups including indigenous
addition they provide technical advisory people are avoided,
services to the projects and prescribe minimised, or mitigated
environment and social safeguard Environmental impacts are
policies. minimal
Projects are cleared and
completed on time
Ministry of Tribal The Ministry is the nodal agency for Protection of rights of tribal /
Affairs overall policy, planning and indigenous persons
coordination of the programmes for Access to reliable electricity for
development of Scheduled Tribes (ST). tribals
The ministry notifies the tribal areas
and also enacts laws like Forest Rights
Act 2006 to protect the rights of the ST.
National Highway NHAI was constituted by an act of Road surface is not damaged
Authority of India Parliament and is responsible for due to construction work
(NHAI) development, maintenance and Compensation for repairing
management of National Highways road surface when
entrusted to it. It provides permission to underground cabling crosses
dig highway or construct along the highways
highways (within the margin as Minimal disruption of traffic
approved during highway design). movement
Ministry of Railway The ministry is responsible for Transmission towers / lines are
development, maintenance and at least 8 km distance from the
management of the country’s rail railway signal lines to prevent
network. It provides permission to dig disruption in signalling
(for UG cabling) or construct (for Minimal disruption of rail
substations and overhead cabling) on services
Page 55
Stakeholder Role/Responsibility/interest Expectations / Issues / Concerns
or along the railway property including Compensation for loss of
rail tracks and stations. income due to stoppage of rail
services
State Level
Andhra Pradesh APERC was constituted under the A.P. The distribution utilities
Electricity Electricity Reform Act, 1998 and is provide services (supply of
Regulatory primarily tasked to improve the electricity, fulfilling of demand,
Commission functionality of the power sector in the tariff, accident compensation
(APERC) state. The commission formulates and etc.) at least at the minimum
enact regulations on important aspects applicable standard of
of electric supply to consumers. The performance
commission also issues licenses to the The utilities complete project
Transmission Corporation of Andhra activities within the timelines
Pradesh Limited (APTRANSCO), and consented tariffs.
distribution companies and rural
electric cooperatives in the state
APTRANSCO APTRANSCO is responsible for power Ensuring 24x7 power supply in
transmission from power plants and the State & minimization of
power grids to distribution companies. transmission losses
Ensuring requisite clearances /
permissions are obtained and
projects are completed on
time
APSPDCL, APSPDCL and APEPDCL are the One of the key performance
APEPDCL distribution companies responsible for indicators for SPDCL and
distributing power to end-consumers EPDCL this year is reduction of
like households, industry and AT&C losses to single digit
agricultural farms from the current 14%. Planned
activities like HVDS under the
proposed projects will help in
reducing AT&C losses.
Andhra Pradesh APFD is one of the nodal departments Ensuring the protection of
Forest Department dealing with forest conservation and forest land and wildlife
(APFD) environmental management of the habitats
State. Their permission is required for Where it is not possible to
any construction or cutting of trees in avoid forest land, ensuring
the forest area. that:
− Compensation is received
as per relevant National or
State law. In Andhra
Pradesh 2 times the land
Page 56
Stakeholder Role/Responsibility/interest Expectations / Issues / Concerns
used for a project has to
be given to the forest
department
− The towers / lines do not
harm wildlife. If required,
utilities are asked to fence
off towers / substations
Department of Department of Revenue manages Ensuring that the land
Revenue functions related to the matters of requested for transmission /
Government land, excise, commercial distribution projects is for
tax, land and property registrations, public purpose
surveys and settlements, endowments Ensuring that there is no
and so on. The department will help in dispute over ownership of
securing land for projects and will also land allotted for projects
help in deciding the compensations for Setting compensation as per
land and RoW where applicable. relevant National/State laws
Ensuring that allotted land is
used for stated purposes
Andhra Pradesh APLMA was constituted by Government Government land allotted for
Land Management of Andhra Pradesh through a transmission / distribution
Authority (APLMA) Government Order (G.O. Ms. No. 571 projects has received an NOC
dated 14 September 2012) issued by the from the Urban Local Body or
Revenue Department. The role of the Urban Development Authority
APLMA is to manage allotment of or Directorate of Town and
Government lands for public purposes. Country Planning
Only that extent of land is
allotted for the project that is
stipulated by the C.E.A for
power projects
Environmentally sensitive and
fragile lands are not allotted
Allotted Government land is
utilized for stated purposes
and prime land is put to the
optimum use. For this land
may be re-allotted if needed
Department of Department of Agriculture is Compensation for crop
Agriculture, responsible for State policies and damage is paid as per the
Government of programmes aimed at achieving relevant National or State law
Andhra Pradesh agricultural growth. The department
helps in deciding crop compensation in
case project activities result in any crop
damage.
Page 57
Stakeholder Role/Responsibility/interest Expectations / Issues / Concerns
Department of Department of Horticulture is Compensation for tree damage
Horticulture responsible for state policies and is paid as per relevant law
programmes aimed at achieving
horticulture growth. Permission is
required from the department to
cut/prune any Tree.
Water Resources The department caters to the irrigation Ensuring that irrigation canals
Department needs of the state. The permission from / tanks / water bodies are not
(Department of the department is required in case the damaged, polluted, or in any
Irrigation) project activities can potentially way affected by the
damage or obstruct any water way. construction of towers or
substations
The water ways are not
blocked
Andhra Pradesh The authority was established by Act Sufficient and reliable
Capital Region No. 11 of 2014 in Andhra Pradesh. The electricity supply in the new
Development authority has been established for the capital
Authority purpose of planning, coordination,
execution, supervision, financing,
funding and for promoting and securing
the planned development of the Capital
Region Development Area, undertaking
the construction of the new capital for
the state of Andhra Pradesh and for
managing and supervising urban
services in the new capital area.
Roads and The Roads & Buildings department is Minimum damage to the roads
Buildings responsible for the construction and and highways during the
Department maintenance of the State Principal Road construction of substations,
Network including National highways erection of towers and laying
(on behalf of Govt. of India), State of cables.
Highways and Major District Roads and Utilities pay appropriate
assigned buildings of various compensation for any
Departments under the control of State unavoidable damage.
Government. It provides permission to
dig highways/roads or construct along
the highways/roads (within the margin
as approved during highway design).
Power & Central standing committee for Proposed projects do not
Telecommunication coordination of Power and cause any induction / noise /
Coordination Telecommunication system. The disruption in existing
Committee (PTCC) committee was formed by Government communication and signal
of India in the year 1949. The role of the networks of
Page 58
Stakeholder Role/Responsibility/interest Expectations / Issues / Concerns
committee is to deal with route telecommunication
approval for all new power lines. The companies, defence and
clearance of this committee is required railways
before energization of new power lines That utilities have considered
of 11kV and above, which is given after worst fault conditions in the
clearances from Railway/Telecom proposed route and included
having lines in the area. appropriate mitigation
measures in their plan
Implementation Level (District / City / Village)
District Collector / The district officials of the revenue Effective utilization of land –
District Magistrate department help in securing land for minimum land required
District projects and in deciding the should be used and minimum
administration – compensations for land and RoW where number of people should be
District Collectors applicable. They also support regular affected
/District Magistrate / co-ordination / consultation between
tahsildars at block implementation agency and projected
level affected persons for early resolution of
grievances & conflict management.
Regional and local Undertake activities like Securing land and negotiating
office of construction, operations and Right of Way
APTRANSCO maintenance of substations, towers Ensuring transmission lines do
and lines not pass through forest areas
Undertake pre-construction as receiving clearances take
activities like site selection and over a year
route alignment Ensuring timely completion of
projects by contractors
Local offices Undertake activities like Ensuring reduction in AT&C
APSPDCL / construction, operations and losses as per targets set by
APEPDCL maintenance of substations, poles the Corporate Office
and lines Increase in accidents due to
Undertake pre-construction shift to High Voltage
activities like site selection and Distribution System
route alignment Handling objections from shop
First level to receive grievances owners when distribution
from end-consumers transformers are placed in
front of their shops
Handling objections from
house owners if distribution
lines are close to their
property
Ensuring timely completion of
projects by contractors
Page 59
Stakeholder Role/Responsibility/interest Expectations / Issues / Concerns
Contractors and Responsible for constructing Timely payment of fees
suppliers substations, towers and lines in line Required approvals clearances
with contract signed with utilities and from different departments are
supplying various equipment and other in place
material required for construction and Right of Way has been secured
maintenance Land for substations has been
secured
There are no disturbances
from communities during
construction
Panchayats / Gram These are the local governance bodies Reliable electricity supply to
Sabha at village level. Their permission is village
required to undertake any activity in the Appropriate permissions /
village including securing land. They clearances have been taken
also provide a channel to the project Land owners have been
affected persons to raise their consulted & appropriate
grievances. compensation paid
Police Department The police department is responsible Contractors / utilities have
for maintaining law and order in their requisite approvals /
jurisdiction. Police supports the project permissions / clearances for
activities by regulating the traffic flow the proposed work
(especially in congested areas) during Prior notification is given
the construction and maintenance before work where road traffic
phases. will be disrupted so that
arrangements can be made
There are no protests /
disputes related to land where
the work is being undertaken
Municipal These are the local governance bodies Utility has required
Corporations/Urban at city/town level. Their permission is permissions / clearances for
Development required to undertake any activity in the use of land
Authorities village including securing land. They
also provide a channel to the project
affected persons to raise their
grievances.
NGO’s and citizen’s They provide a platform to raise Rights of vulnerable groups
collectives like concerns of the community and are protected and they can
RWAs vulnerable groups like women, SC and participate in the benefits from
ST. This stakeholder group also act as the project
channel to undertake public Environmental impacts of
consultations on the project design, projects are taken into
planning and implementation and consideration
Page 60
Stakeholder Role/Responsibility/interest Expectations / Issues / Concerns
provides a platform for grievance Grievances of affected people
redressal. are heard and appropriately
handled by the utilities
Informal groups Local community leaders, elders, The people are informed in
community groups, women groups advance about any proposed
provide platform to inform the general project
public about the project activities, Environmental and social
undertake public consultations and impacts of projects are taken
grievance redressal. into consideration
Grievances of affected people
are heard and appropriately
handled by the utilities
Commercial and Commercial and Residential Access to 24x7 power supply
Residential complexes/societies are end- at sufficient voltage levels
complexes/societies beneficiaries of the project and are also Project does not cause
receptors of various intended and disruptions to business and
unintended externalities of the project block access to commercial /
like noise and water pollution, damage residential properties
of crop/trees etc. Minimization of disturbances
during construction including
noise and air pollution as well
as access to roads, movement
of traffic etc.
Communities and Communities and families are the end- Access to 24x7 power supply
families beneficiaries of the project and are also at sufficient voltage levels
receptors of various intended and Minimization of losses / theft
unintended externalities of the project Minimization of disturbances
like noise and water pollution, damage during construction including
of crop/trees etc. noise and air pollution as well
as access to roads, movement
of traffic etc.
Vulnerable groups: The adverse effects of the project Access to reliable 24x7 power
Minorities / activities, if any, are more pronounced supply
Scheduled Castes on the vulnerable groups in the society. Ensuring adequate
Therefore, it is essential to understand compensation is paid in case
how the project activities specifically their land is used for
impact these groups. construction of towers /
substation
The forums for public
consultations and grievance
redressal should ensure that
vulnerable groups are heard
Page 61
Stakeholder Role/Responsibility/interest Expectations / Issues / Concerns
and their views/problems are
adequately addressed.
Page 62
S.No Enforcement Agencies Overview
3 Andhra Pradesh APPCB is a statutory authority constituted in the year 1976 and
Pollution Control Board entrusted to control pollution from any activities in the state as
(APPCB) well as to implement environmental laws and rules within the
jurisdiction of the state of Andhra Pradesh. APPCB also
provides advisory support to the department of environment
in the states on environmental policy matters. It implements
and enforces the policies of the department of environment in
addition to those formulated by the Ministry of Environment
and Forests (MoEF). The project activities will be monitored by
APPCB with respect to any environmental
emissions/discharges.
Page 63
S.No Enforcement Agencies Overview
4 Andhra Pradesh Forest APFD is one of the nodal departments dealing with forest
Department (APFD) conservation and environmental management of the State level
and is headed by the Principal Chief Conservator of Forests
(PCCF). The PCCF is supported by divisional forest offices for all
matters related to diversion of forest land and management of
forest in the divisions within the state.
The next section maps the positive and negative social impacts of the proposed projects
on the stakeholder groups identified above.
Page 64
7. Social Impact & Mitigation Methods
7.1 Social Impacts
This section identifies the potential intended and unintended impacts of the proposed
projects on the communities around the project sites. The section further disaggregates the
impacts on vulnerable population including farmers, women, Scheduled Castes (SC),
Scheduled Tribes (ST) and minorities. The impact can result from activities throughout the
project life-cycle from project design, construction, operations and maintenance to
decommissioning stages. The major social impacts of the project are identified below.
Positive impacts
Improved and reliable power supply: Andhra Pradesh is one of the few states in India to
provide 100% rural electrification4. However, about 18.4%5 of rural households do not
have electricity connections in Andhra Pradesh. The proposed project aims to ensure
24x7 power for all. Furthermore, the focus of the activities planned under the project is
also to provide power at consistent voltage (at least 220V for household consumption),
thereby reducing dependence on other sources of energy.
Replacing LVDS systems by HVDS, as planned under the proposed projects, will ensure
that even the last farmer/power pump connected on the power line receives reliable
voltage.
Increased social inclusion: As per the rural electrification plan of the state of Andhra
Pradesh dated July 2011, there are about 11 lakh rural households without an electricity
connection in the State of which BPL households constitute 46%6. The proposed projects
will support the GoAP’s effort to reach these un-electrified rural households and bridge
urban-rural divide in access to electricity. As per Piyush Goyal, Union Minister of Power,
“Electricity consumption is one of the most important indices that decide the
development level of a nation. The per capita consumption of electricity in FY 2012-13
was 917 units, which is around 20% of that in China or 5% of the level in USA. The
Government of India is committed to improving the quality of life of its citizens through
higher electricity consumption. This joint initiative of Government of India and
Government of Andhra Pradesh aims to enhance the satisfaction levels of the consumers
4
http://www.cea.nic.in/reports/monthly/dpd_div_rep/village_electrification.pdf
5
www.ap.gov.in/wp-content/uploads/2016/01/12-AP-Households.pdf
6
Rural Electrification Plan of the State of Andhra Pradesh (2011). Energy Department, Gazette Notification
Page 65
and improve the quality of life of people through 24x7 power supply. This would lead to
rapid economic development of the state in primary, secondary & tertiary sectors
resulting in inclusive development of the State”7.
Improved quality of life: One of the planned activities is to install mobile controlled
switch on/Switch off mechanism on irrigation pump sets. Currently, the rural feeders
receive electricity for around 7 hours every night. Using mobile phones to remotely
switching-on/off the pump sets will ensure that farmers do not have to travel to their
farms during the night to irrigate the fields, thereby improving their quality of life.
Additionally, access to electricity would reduce the time spent by women on household
activities which will entail availability of more time for other activities including caring
for their own health.
Positive impact for women and girls: As per the working paper on Energy, Gender and
Development of the World Bank 2011, the literature on gender and energy suggests that
providing electricity to communities and homes and motive power for tasks considered
women’s work can promote gender equality, women’s empowerment, and women’s and
girls’ access to education, health care, and employment. Most gender benefits of
providing electricity and motive power occur because women tend to spend more time
at home, are responsible for household chores that can be carried out more productively
with electricity, and because certain tasks that are culturally defined as women’s work
can benefit from motive power.8
Increased economic activity: As per Mr. Chandrababu Naidu, Chief Minister of Andhra
Pradesh, “power sector is a critical infrastructure element required for the smooth
functioning of the economy. An efficient, resilient and financially healthy power sector
is essential for growth and poverty reduction. The availability of reliable, quality and
affordable power helps in the rapid agricultural, industrial and overall economic
development of the state”9.
The energy deficit in Andhra Pradesh was 17.6% during 2012-13 as against the all India
average of 8.7%10. To meet the deficit, the power transmission and distribution networks
7
Power for All, A joint initiative of Government of India and Government of Andhra Pradesh. Available at:
http://powermin.nic.in/upload/pdf/joint_initiative_of_govt_of_india_and_andhrapradesh.pdf
8
Kohlin, G., Pattanayak, S., Sills, E., Wilfong, C. (2011), Energy, Gender and Development: What are the linkages?
Where is the Evidence?, Social Development Papers, A background paper for the World Development Report 2012
on Gender Equality and Development, Paper no. 125.
9
Power for All, A joint initiative of Government of India and Government of Andhra Pradesh. Available at:
http://powermin.nic.in/upload/pdf/joint_initiative_of_govt_of_india_and_andhrapradesh.pdf
10
White paper on power sector in Andhra Pradesh. Available at:
http://ap.meeseva.gov.in/DeptPortal/Download-
lat/White%20Paper%20on%20AP%20Power%20Sector_V10.pdf
Page 66
need to be strengthened, in addition to increased generation capacity. The proposed
projects aim to strengthen the power system and augment its capacity to meet the future
requirement of electricity by the domestic users, commercial and industrial users and
for irrigation purposes.
Employment creation: Due to the power deficit, industries in Andhra Pradesh have
suffered load shedding of up to 40% of their demand (3 days a week power holiday) in
recent years11. Due to this, some of the existing industries have shifted their operations
from the state12 resulting in loss of employment. Reliable supply of electricity will attract
industry and create industrial jobs.
Additionally, as per, rural electrification plan of the state of Andhra Pradesh dated July
2011, one acre of assured irrigation results in 100 man-days of potential employment13.
The proposed HVDS work will ensure reliable electricity supply for agricultural purposes,
thereby ensuring assured irrigation and creating employment.
Negative impacts
Securing land: Land is required to undertake various project activities like construction of
sub-stations, erection of transmission towers and laying of underground and overhead
transmission and distribution lines. Land for the project can be secured in four different
ways:
(i) Transfer of Government land to utility
(ii) Voluntary donation from private individuals
(iii) Purchase of land on willing buyer and willing seller basis at a negotiated price;
and
(iv) Involuntary acquisition of land
In all the four cases, there might be changes in the land use pattern in case the site identified
for the project is currently being used for some other purposes. Specific examples of impact
include:
- Loss of land: There is loss of land during setting up substations. The land requirement for
setting-up substation:
Voltage Land required for Sub-station14
11
Power for All, A joint initiative of Government of India and Government of Andhra Pradesh. Available at:
http://powermin.nic.in/upload/pdf/joint_initiative_of_govt_of_india_and_andhrapradesh.pdf
12
White paper on power sector in Andhra Pradesh. Available at:
http://ap.meeseva.gov.in/DeptPortal/Download-
lat/White%20Paper%20on%20AP%20Power%20Sector_V10.pdf
13
Rural Electrification Plan of the State of Andhra Pradesh (2011). Energy Department, Gazette Notification
14
Reference manuals on construction and operational practices of EHV substations & lines and commercial
and load dispatch operations. Available at: http://www.aptransco.gov.in/transco/images/APTRANSCO-
Technical-reference-book-2011-vol-ii.pdf
Page 67
132/33 kV and 220/33 kV 5 acres
33/11kV 0.5 acres
*As per information received from Utilities
Note: The land for the proposed investments in APTRANSCO has been secured either from
the discoms where they have provided extra land available in their existing substations to
APTRANSCO or government land has been identified. The status of sites for the proposed
12 substations as on 5th May 2016 is provided below:
Method of securing land No. of substations
- It should be noted that as stated earlier, for the proposed transmission and distribution
projects no involuntary acquisition is required for securing land and the projects will not
result in any physical or economic displacement of people.
- Restricted use of land and RoW: The MoEF guidelines mandate utilities to maintain right of
way corridors:
Voltage Width of RoW* (in meters)
220 kV 35
132 kV 27
33 kV 15
11 kV 7
*Width of Right of Way is as per MoEF guidelines dated May 2014
In the width of the RoW, some restrictions are imposed and trees are cut or pruned to the
extent required for preventing electrical hazards by maintaining the following:
Voltage Minimum clearance between conductor and
trees (in meters)
220 kV 4.6
132 kV 4.0
33 kV 2.8
11 kV 2.6
Change in land use: Sometimes government land is also leased out for some other activity.
That land has to be reclaimed for construction of sub-stations and towers. In cases where
private land is secured, the land will no longer be available for activities like agriculture
Page 68
and horticulture. Additionally, in some instances land may be in-use for housing, schools
and hospitals. Reduction in value of farm land: There is a decrease in value of land around
the substations. As an instance, the value of land around the substation in Nellore
decreased from INR 10-12 lakhs per acre to INR 4-5 lakhs per acre.
Impact on community health and safety: The communities close to transmission and
distribution lines face health and safety concerns. The safety concerns for Electric Power
Transmission and Distribution are highlighted below:
-
Exposure to electric and magnetic fields (EMF): Electric and magnetic fields are produced
by voltage and current respectively. Although there is public and scientific concern over
the potential health effects associated with EMF, there is no empirical data demonstrating
adverse health effects from exposure to typical EMF levels from power transmission lines
and equipment.15
- Noise: Transformers and high voltage power lines create buzzing or humming sound,
which can be a nuisance. However, the noise produced by power lines or transformers do
not cause any known health risk.16
- Electric shocks and electrocution: The electric voltage higher than 11kV pose serious threat
of electrocution to humans, transmission lines carry very high voltages to the tune of 220kV
(and 132kV) and can be fatal. Furthermore, electric charge can travel through induction and
hence poses threat to high rise structures, even when they are not in direct contact with
live wire.
- Electromagnetic Interference: The overhead transmission and distribution lines might
create interference with radio and cell phone signals through mutual induction.
Impact on Workers / employees health and safety: The workers and employees face health
and safety concerns as highlighted below:
- Live power lines: Field staff such as linemen are exposed to the threat of electric shock and
electrocution from contact with live wires during the construction, operation and
maintenance activities.
- Working at height: Workers and field staff are at risk of falling from heights while working
at elevation during the construction, operation and maintenance activities.
- Electric and magnetic fields: Electric utility workers typically have a higher exposure to EMF
than the general public due to working in proximity to electric power lines.17 Some studies
15
IFC’s Environmental, Health, and Safety Guidelines for Electric Power Transmission and Distribution.
Available at: http://www.ifc.org/wps/wcm/connect/554e8d80488658e4b76af76a6515bb18/Final+-
+General+EHS+Guidelines.pdf?MOD=AJPERES
16
IFC’s Environmental, Health, and Safety Guidelines for Electric Power Transmission and Distribution.
Available at: http://www.ifc.org/wps/wcm/connect/554e8d80488658e4b76af76a6515bb18/Final+-
+General+EHS+Guidelines.pdf?MOD=AJPERES
17
IFC’s Environmental, Health, and Safety Guidelines for Electric Power Transmission and Distribution.
Available at: http://www.ifc.org/wps/wcm/connect/554e8d80488658e4b76af76a6515bb18/Final+-
+General+EHS+Guidelines.pdf?MOD=AJPERES
Page 69
have suggested a possible association between occupational exposure to EMF and cancer
indicating there is evidence to warrant limited concern
- Exposure to chemicals: Workers are at risk of exposure to chemicals during handling of
pesticides used for right-of-way maintenance and polychlorinated biphenyls (PCB) in
transformer oil and other electrical components.
Impact on vulnerable populations
- Women: The proposed investments could increase the security risk for women specifically
during the construction phase when there will be an increased movement of strangers in
the area and also due to the blockage of access roads. The Gender Action Plan annexed
with this document provides a detailed mapping of potential positive and negative impacts
on women and girls.
- Tribal population: The impacts of the proposed investments on tribal population are of a
similar nature to those identified for the rest of population in this document. However the
extent of the impacts may vary owing to the socio-economic position of tribal persons in
villages. The tribal population living in protected and reserved forest areas is at a
heightened risk because of dependence of their livelihoods on forest resources like trees,
which may be cut or pruned to undertake project activities.
- Scheduled Castes and Minorities: The impacts of the proposed investments on minorities
and SCs are of a similar nature to those identified for the rest of population in this
document. However, the extent of the impacts may vary owing to the vulnerable socio-
economic position of these communities.
- Farmers: Crops and trees are may be damaged during the construction phase and also for
the maintenance of the RoW. Also, the value of agricultural land may decrease if it is in the
immediate proximity of sub-stations or has transmission towers on it. This poses a serious
economic cost and livelihood loss for small and marginal farmers (land holding less than
5 acres).
Cultural Heritage: One of the activities in the proposed investments is to convert overhead
lines to under-ground lines near sites of cultural, heritage and religious importance.
Damage could potentially be caused to the sites during the construction, operations and
maintenance phases while digging up for laying and maintaining underground cables.
Interference with communication channels: The electrical interference with railway, defence
and telecommunication lines and signals due to mutual induction poses the risk of
disruption to noise-free communication for these critical establishments.
Page 70
provisions that are potentially applicable to this project. Based on this framework, the
impact management and mitigation framework has been developed in the subsequent
section.
Act / Rules / Policies Applicability
Page 71
Act / Rules / Policies Applicability
(vi) The damage (if any) boa fide resulting from diminution of the
profits of the land between the time of notification and the time
of possession
(vii) Any other ground that may be in the interest of equity, justice
and beneficial to the affected families
Page 72
Act / Rules / Policies Applicability
3 The Electricity Act, According to Section 14 of the Electricity Act, licenses can be awarded
2003 (With by the ‘Appropriate Commission’ to any person for transmission of
Amendments in 2003 electricity, distribution of electricity or trading of electricity. These
& 2007) persons will be known as licensees
Under Section 67 (1) of the Act, a licensee has the power “to open
and break up the soil and pavement of any street, railway or tramway;
to open and break up any sewer, drain or tunnel in or under any street,
railway or tramway; to alter the position of any line or works or pipes,
other than a main sewer pipe; to lay down and place electric lines,
electrical plant and other works; to repair, alter or remove the same;
and to do all other acts necessary for the transmission or supply of
electricity
Section 68 (1) of the Act, provides for the installation and maintenance
of overhead lines subject to the provisions in Section 68 (2-4).
Page 73
Act / Rules / Policies Applicability
4 The Indian Telegraph Under Section 164 of the Electricity Act, 2003, for the placing of
Act, 1885 electric lines or electrical plant for the transmission of electricity, the
‘Appropriate Government can confer upon a licensee any of the
powers which the telegraph authority possesses under the Indian
Telegraph Act, 1885 with respect to the placing of telegraph lines and
posts for the purposes of a telegraph established or maintained, by
the Government or to be so established or maintained.
Therefore, Part III - Section 10-19 of the Indian Telegraph Act, 1885 is
applicable as well.
Under Section 10, The telegraph authority may, from time to time,
place and maintain a telegraph line under, over, along, or across, and
posts in or upon any immovable property. This implies, that a licensee
as mentioned in Section 164 of the Electricity Act, 2003, has the
authority to place and maintain transmission lines under over along
or across and posts in or upon, any immoveable property.
Under Section 11, a licensee may, at any time, for the purpose of
examining, repairing, altering or removing any telegraph line or post,
enter on the property under, over, along, across, in or upon which the
line or post / tower has been placed.
Page 74
Act / Rules / Policies Applicability
compensation to all persons interested for any damage sustained by
them by reason of the exercise of those powers. According to
Sections 16 (3) and (4) any disputes regarding compensation are to be
decided by the District Judge whose decision in the matter will be final
as per Section 16 (5)
5 Ministry of Power, These guidelines have been formulated for “determining the
Guidelines for compensation towards “damages” as stipulated in Section 67 and 68
Payment of of the Electricity Act, 2003 read with Section 10 and 16 of the Indian
Compensation Telegraph Act, 1885 which will be in addition to the compensation
Towards Damages in towards normal crop and tree damages”
Regard to Right of
Way for Transmission According to Section 2 of the Guidelines, compensation will be
Lines, 2015 payable only for transmission lines supported by a tower base of 66
kV and above, and not for sub-transmission and distribution lines
below 66 kV.
Page 75
Act / Rules / Policies Applicability
2. Over and above the normal crop and tree damage, the land owner
is compensated for the land taken up by the tower base. The value of
compensation is determined by the District Collector and is set on the
basis of voltage. The compensation is determined separately for each
zone.
− In the Kadapa Zone (comprising of Ananthapur, Kadapa,
Kurnool, Chittoor) compensation for 132 kV towers is INR
55,000 per tower and for 220 kV towers compensation is INR
99,500 per tower.
− In the Vishakhapatnam Zone:
o Vizanagaram, Visakhapatnam- compensation for 132
kV towers is INR 55,000 and for 220 kV towers
compensation is INR 99,500 per tower
o Sirakulam, East Godavari, West Godavari-
compensation for 132 kV towers is INR 43,900 and for
220 kV compensation is INR 79,600 per tower
− In the Vijayawada Zone (comprising of Krishna, Guntur,
Prakasham, Nellore) compensation for 132 kV towers is INR
55,000 and for 220 kV towers compensation is INR 99,500 per
tower
Page 76
Act / Rules / Policies Applicability
For fixing cost of land, provisions of BSO-24 shall apply to all the
land allotments along with the conditions stipulated by the
alienating agencies/departments
The allotment / alienation shall be on market value as
recommended by the Collector and the A.P.L.M.A.
Government lands may be given free of cost to State Government
Departments for welfare and development purposes
A.P. Land Management Authority (APLMA) to be constituted for
processing and recommending land allotment, with the task of
monitoring the utilization of land for the intended purpose and
resumption of land in case of violation of conditions
NOC from Urban Local Body (ULB) or Urban Development
Authority (UDA) (in case of areas falling outside Urban Local Body
limits) and Directorate of Town and Country Planning (DT&CP) for
the areas falling outside ULBs and UDA areas may be insisted
before taking a decision on the allotment of land by APLMA.
The administrative department and the APLMA shall therefore
invariably ensure that the statutory environmental and zonal
regulations are strictly complied with in this regard
Government lands owned by various departments and which are
not being utilized to the full extent by the respective departments
shall be proposed for allotment for public purpose
All the Departments should prepare comprehensive plans for
Rehabilitation and Resettlement (R&R) where displacement of
people is involved
Wherever applicable, the allottee shall also provide green buffer
along the nalas, tanks and water bodies, as specified in the
building rules
7 The Scheduled Tribes The Act recognises and vests the forest rights and occupation in forest
and Other Traditional land in forest dwelling Scheduled Tribes and other traditional forest
Forest Dwellers dwellers who have been residing in such forests for generations but
(Recognition of Forest whose rights could not be recorded. The Act provides a framework for
Rights) Act, 2006 recording forest rights so vested and the nature of evidence required
for such recognition and vesting in respect of forest land.
During laying of transmission / distribution lines or erecting towers,
all possible efforts should be made to avoid forest areas. In case,
passing through forest areas is unavoidable, prior permission of the
forest department should be sought.
8 The Andhra Pradesh The Act consolidates and amends the laws relating to protection and
Forest Act, 1967 and management of forests in the state of Andhra Pradesh. It lays down
Rules (thereunder) guidelines to constitute any land as reserved forest and protected
Page 77
Act / Rules / Policies Applicability
forest, and guidelines for preservation of private forests. The act also
provides rules for:
a) Timber and other forest produce in transit or possession
b) Possession of Sandalwood
c) Collection of drift and stranded timber
Page 78
Act / Rules / Policies Applicability
Page 79
Act / Rules / Policies Applicability
Page 80
Act / Rules / Policies Applicability
Page 81
Act / Rules / Policies Applicability
21 Employees P. F. and The Act for monthly contributions by the employer plus workers
Miscellaneous @10% or 8.33%. the benefits payable under the Act are:
Provision Act 1952 Pension or family pension on retirement or death, as the case may
be
Deposit linked insurance on the death in harness of the worker.
Payment of P. F. accumulation on retirement /death etc.
22 Maternity Benefits Act The Act provides for leave and some other benefits to women
1951 employees in case of confinement or miscarriage etc.
23 Contract labour The Act provides for certain welfare measures to be provided by the
(Regulation & contractor to contract labour and in case the Contractor fails to
Abolition) Act 1970 provide, the same are required to be provided, by the principal
Employer by Law. The Principal Employer is required to take
Certificate of Registration and the Contractor is required to take license
from the designated officer. The Act is applicable to the
establishments or Contractor of Principal Employer if they employ 20
or more contract labour.
24 Minimum Wages Act The Employer is supposed to pay not less than the Minimum Wages
1948 fixed by appropriate Government as per provision of the Act if the
employment is a scheduled employment. Construction of Buildings,
Roads, Runways are scheduled employment’s
25 Payment of Wages It lays down as to by what date the wages are to be paid, when it will
Act 1936 be paid and what deductions can be made from the wages of the
workers.
26 Equal Remuneration The Act provides for payment of equal wages for work of equal nature
Act 1979 to Male and Female workers and for not making discrimination against
Female employees in the matters of transfers, training and
promotions etc.
27 Payment of Bonus Act The Act is applicable to all establishments employing 20 or more
1965 employees. The Act provides for payments of annual bonus subject to
a minimum of 8.33% of wages and maximum of 20% of wages to
employees drawing Rs.3500/- per month or less. The bonus to be paid
to employees getting Rs.2500/- per month or above up to Rs.3500/- per
month shall be worked out by taking wages as Rs.2500/- per month
only. The Act does not apply to certain establishments. The newly
set-up establishments are exempted for five years in certain
circumstances. Some of the State Governments have reduced the
employment size from 20 to 10 for the purpose of applicability of this
Act.
28 Industrial Disputes The Act lays down the machinery and procedure for resolution of
Act 1947 Industrial disputes, in what situations or lock-out becomes illegal and
what are the requirements of laying off or retrenching the employees
or closing down the establishments.
Page 82
Act / Rules / Policies Applicability
29 Industrial It is applicable to all establishments employing 100 or more workmen
Employment (employment size reduced by some of the States and Central
(Standing Orders) Act government to 50). The Act provides for laying down rules governing
1946 the conditions of employment by the Employment on matters
provided in the Act and get the same certified by the designated
Authority.
30 Trade Union Act 1926 The Act lays down the procedure for registration of trade unions of
workmen and employers. The Trade Unions registered under the Act
have been given certain immunities from civil and criminal liabilities
31 Child Labour The Act prohibits employment of children below 14 years of age in
(prohibition & certain occupations and process and provides for regulation of
Regulation) Act 1986 employment of children in all other occupations and processes.
Employment of Child Labour is prohibited in Building and
Construction Industry.
32 Inter-State Migrant The Act is applicable to an establishment which employ 5 or more
Workmen’s inter-state migrant workmen through an intermediary (who has
(Regulation of recruited workmen in one state for employment in the establishment
Employment & situated in another state). The Inter State migrant workmen, in an
Conditions of Service) establishment to which this Act becomes applicable, are required to
Act 1979 be provided certain facilities such as housing, medical aid, traveling
expenses from home up to the establishment and back, etc.
33 The Building and All the establishments who carry on any building or other construction
Other Construction work and employs 10 or more workers are covered under this Act. All
Workers (Regulation such establishments are required to pay cess at the rate not exceeding
of Employment and 2% of the cost of construction as may be modified by the Government.
Conditions of Service) The Employer of the establishment is required to provide safety
Act 1996 and the Cess measures at the building or construction work and other welfare
Act of 1996 measures, such as Canteens, First- Aid facilities, Ambulance, Housing
accommodations for workers near the work place etc. The Employer
to whom the Act applies has to obtain a registration certificate from
the Registering Officer appointed by the Government.
34 Factories Act 1948 The Act lays down the procedure for approval at plans before setting
up a factory, health and safety provisions, welfare provisions, working
hours, annual earned leave and rendering information regarding
accidents or dangerous occurrences to designated authorities. It is
applicable to premises employing 10 persons or more with aid of
power or 20 or more persons without the aid of power engaged in
manufacturing process.
World Bank Operational Policies
35 Involuntary This policy covers direct economic and social impacts that both result
Resettlement (OP from Bank-assisted investment projects, and are caused by the
4.12) involuntary taking of land. To avoid or minimize involuntary
Page 83
Act / Rules / Policies Applicability
Page 84
Act / Rules / Policies Applicability
38 World Bank Policy on The source book provides guidelines for ROW for transmission lines.
RoW for transmission It states that depending on technical specifications, transmission lines
lines require a corridor of impact 12–25 meters wide, or even more in the
Source: World Bank case of high-voltage electric lines (500 kilovolts or more). Although the
Source Book on impact of a tower is likely to be slight, especially in rural areas,
Involuntary transmission lines extending hundreds of kilometres may produce a
Resettlement significant aggregate displacement, especially if the lines cannot
avoid more heavily populated areas.
However, transmission lines themselves do not require land
acquisition, except for the towers. Instead, an ROW is established,
imposing restrictions on land use. Local laws and regulations
determine these constraints; for example, height restrictions might be
imposed on crops grown under transmission lines.
Synergies between World Bank Policy on Land Acquisition and National Policies / Laws
Page 85
Chapter II Section 4 (1) of the RFCTLARRA,
2013 also requires that a Social Impact
Assessment Study (SIA) be conducted in
consultation with the concerned Panchayat,
Municipality or Municipal Corporation. The
SIA shall also include reports of public
hearings conducted in the affected area.
Page 86
implementation, whichever is livelihoods are primarily dependent on lands
higher being acquired
Page 87
Assistance (such as moving This is provided for in the Second Schedule
allowances) during relocation; to the RFCTLARRA 2013
residential housing or housing
sites as required and other
advantages equivalent to the
advantages of the old site; and
support after displacement for a
transition period
Eligibility of benefits is to: All three are covered in the Definitions
a) those who have formal legal (Section 3) of the RFCTLARRA 2013
right to the land including
customary and traditional rights
b) those who do not have formal
rights at the time of census but
have claim to such land or assets
that are recognized by the laws of
the country
c) those who have no recognizable
rights
Resettlement planning Chapter II Section 16 (1) of the RFCTLARRA
implementation and monitoring 2013 requires that a Resettlement Schedule
be prepared; while Chapter V provides
details of the Resettlement Award while
Chapter VI provides the procedure for the
Award; Chapter VII provides for the
monitoring of the Resettlement Scheme; and
Chapter VIII calls for establishment of a Land
Acquisition, Resettlement and Rehabilitation
Authority
The policy, legal and administrative acts, laws, regulations and guidelines provide a
framework for managing the impacts identified in the previous section. The next section
describes the applicability of the policy, legal and administrative framework to manage the
negative impacts of the proposed projects. The next section also identifies the
arrangements within the utilities and amongst other institutions and stakeholder groups
like panchayats, forest department, revenue department etc. to manage the impacts.
Page 88
clearly specifies which type of project (transmission and / or distribution) the specified
management / mitigation methods apply to.
The following framework has been designed in accordance with applicable National and
State laws as well as with international standards for social impact management. The
framework is built on the principle of avoidance, minimization and mitigation wherein
preference is given to avoiding negative social impacts wherever possible. If it is not
possible to avoid negative impacts, utilities will strive to minimize these impacts and take
appropriate mitigation measures. The impact areas covered in the section include: loss of
land; change in, or restrictions on, land use; negative health and safety outcomes for both
employees and the broader community; potential gender differentiated impacts; negative
outcomes for tribal / indigenous peoples; and loss of / damage to cultural heritage.
Land is required for construction of transmission and distribution substations and erecting
transmission towers and distribution poles. Land secured for construction of substations is
a permanent loss of land owner and hence in such cases ownership is transferred from the
existing owner to the respective utility. However, land used for erecting towers and poles
continues to be available for usage and hence it remains with the existing land owner and
the utility only receives rights to use the land. Therefore when we talk of loss of land, it
refers to land secured for substation construction. As mentioned earlier in the document,
there are four ways in which land can be secured; these are:
In order to avoid the loss of private / community lands or agriculture and forest lands, the
transmission and distribution utilities will endeavour, wherever possible, to secure
Government land for their projects and avoid private or community lands, even if this
requires realignment of the proposed route. Only in rare cases when Government land is
not available, other methods of securing land will be pursued. In any case, minimal amount
of land required for substations (the land required for a 132kV / 33kV substation is approx.
5 acres18). The following steps are to be followed depending on the method of land
acquisition:
18
Reference manuals on construction and operational practices of EHV substations & lines and commercial
and load dispatch operations. Available at: http://www.aptransco.gov.in/transco/images/APTRANSCO-
Technical-reference-book-2011-vol-ii.pdf
Page 89
(i) Transfer of Government land: The Andhra Pradesh Land Allotment Policy (G.O. Ms. No.
571 issued 14.09.2012) prescribes that only waste lands will be allotted and
environmentally sensitive / fragile areas such as tank beds, river, beds, hillocks with
afforestation shall not be allotted. Similarly, lands assigned to poor people for agriculture
purpose should not be resumed for other purposes, and if it is unavoidable then the
assignees should be provided with alternate land in addition to rehabilitation. In all cases,
a NOC from the Urban Local Body, Urban Development Authority, or Department for
Town and Country Planning (DT&CP) is required before any allotment is made. The
allotted land may be given free of cost or on payment basis. When land is allotted on
payment basis, the cost of the land will be determined as per market value recommended
by the Collector and the A.P. Land Management Authority (APLMA). APLMA will also
ensure that only the minimum amount of land needed is allotted and the allotted land is
used only for the stated purpose.
(ii) Voluntary donation: In the case of voluntary donation of land, there should not be any
undue pressure on the land owner / user(s) to transfer ownership of their land. Apart from
this following shall also be ensured:
a. The donation will not cause significant impacts on the livelihood of the donor.
b. The donor fully understands the value of their donated land.
c. The donation will not cause any economical or physical displacement of the current
land users.
d. The land donations does not come from coercion or asymmetrical power relation
between the land owner and the government.
e. The land in question must be free of squatters, encroachers, or other claims or
encumbrances.
f. Verification of the voluntary nature of land donations must be obtained from each
of the persons donating land.
g. In case of any loss of income or physical displacement is envisaged, verification of
voluntary acceptance of mitigation measures must be obtained from those expected
to be adversely affected.
h. Subsequently title of land shall be transferred in the name of the utility.
(iii) Purchase of land on willing buyer and willing seller basis on negotiated price: When
land is purchased from a willing seller, the utility shall ensure:
a. Consultation with the affected person has to be carried out and documented.
b. All negotiations have to be carried out in a transparent manner.
c. That land owners are aware of the basis on which compensation is calculated.
d. The land in question must be free of squatters, encroachers, or other claims or
encumbrances.
e. Subsequently title of land shall be transferred in the name of the utility.
Page 90
(iv) Involuntary acquisition of land: Involuntary acquisition of land will be the last resort
and be undertaken when other methods are not feasible. In the case of involuntary
acquisition, the provisions of RFCTLARRA, 2013 and the A.P. RFCTLARRR, 2014 shall be
applicable.
As per RFCTLARRA, 2013 the Appropriate Government shall ensure that a Social Impact
Assessment study is carried out in consultation with the concerned Panchayat,
Municipality or Municipal Corporation in the affected area and also hold public hearings
in the process. Further, the Appropriate Government will ensure minimum
displacement of people, minimum disturbance to the infrastructure, ecology and
minimum adverse impact on the individuals affected. For this, the Appropriate
Government shall ensure:
There is a legitimate and bona fide public purpose which necessitates the
acquisition.
The potential benefits and the public purpose shall outweigh the social costs and
adverse social impact as determined by the SIA.
Only the minimum area of land required for projects is to be acquired.
There is no unutilized land which has been previously acquired in the area.
Any land acquired earlier and remaining unutilized is used for the purpose.
Also, as far as possible no acquisition of land shall be made in Scheduled Areas. Where
this is done, it shall be only as a demonstrable last resort and with the prior consent of
the concerned Gram Sabha or the Panchayats.
The A.P. RFCTLARRR, 2014 further details the process to be followed for land
acquisition as follows:
a. Request for Land: Any requiring body, or its representative duly authorized by it,
for whom land is to be acquired shall file the Requisition to the concerned District
Collector and to the Commissioner, Rehabilitation & Resettlement in the formats
prescribed in the annexures of the RFCTLARRA Act. In case of acquisition for
Government, the requisition shall be filed by concerned Secretary of the
Department or a person authorized by him.
The District Collector upon receiving requisition shall constitute a team of revenue
and agriculture officers to make field visit along with the representative of the
requiring body to make a preliminary enquiry about the correctness of the
particulars furnished in the requisition including the enquiry whether the
requisition is consistent with the provisions of the Act, and submit a report to the
District Collector
If the District Collector, based on the report of the team, other information available
with him and instructions issued by the State Government in this regard, is
satisfied that the requisition is consistent with the provisions of the RFCTLARRA;
he shall make a preliminary estimate of the cost of the acquisition as defined under
Page 91
Section 3 (i) of the Act. The administrative cost under item (A) of Section 3 (i) (vi)
of the Act, shall be at the rate of 10% of the cost of compensation as provided in
item (i) of Section 3 (i) of the Act. The District Collector will inform the Requiring
Body to deposit the estimated cost of acquisition in his office within a period as
may be specified by him and the Requiring Body
b. Social Impact Assessment: A Social Impact Assessment (SIA) will be carried out
for all land acquisition proposals except for when land is proposed to be acquired
invoking urgency provisions under section 40 of RFCTLARRA. In such cases, the
District Collector, where he is not the Appropriate Government, shall submit a
report to the State Government to issue appropriate directions. In other cases, the
District Collector shall take the decision
The District Collector shall, within a period of fifteen days from the date of deposit
of the processing fee for carrying the SIA study by the Requiring Body, issue a
notification for carrying out SIA in the format prescribed in RFCTLARRA. The
notification shall be made available in Telugu language to the Gram Panchayat,
Mandal Parishad, Municipality or Municipal Corporation, as the case may be, and
in the offices of the District Collector, the Sub-Divisional Magistrate and the
Tahsildar at Mandal level.
The notification shall be published in the form of posters and pamphlets circulated
in the affected area and by affixing the posters at some conspicuous places in the
affected areas and shall be uploaded on the website of the State Government and
the revenue district concerned. Provided that such notification shall be issued
within thirty days after the deposit of the processing fee for carrying Social Impact
Assessment by the Requiring Body.
The Commissioner, Rehabilitation & Resettlement shall be the state Social Impact
Assessment Unit to arrange to carry out Social Impact Assessment Study (SIA).
The Commissioner, Rehabilitation & Resettlement shall select the SIA team for
each project from the individuals and institutions registered or empanelled in the
State Database of Qualified SIA Resource Partners and Practitioners. The size and
selection criteria for the SIA team shall be as per the project-specific ToR developed
by the State SIA Unit. The SIA team may be constituted by appointing individuals
or an organization with experience in conducting SIAs or related field-based
assessments and the team may include-
A combination of independent practitioners, qualified social activists,
academics, technical experts, who are not directly connected with the
requiring body; and
At least one woman member
The Requiring Body shall not be involved in any way in the appointment of the SIA
team and while selecting the team it shall be ensured that there is no conflict of
Page 92
interest involving the team members appointed to assess the concerned project. If
any team member is found to have a conflict of interest, the said member shall be
disqualified.
The SIA shall be conducted in consultation with concerned Gram Panchayat,
Mandal Parishad, Municipality or Municipal Corporation, as the case may be, at
village level or ward level in the affected areas. This will be followed by a public
hearing at the affected areas to ascertain the views of the affected families; these
views shall be recorded in writing. Adequate publicity about the date and time and
venue for the public hearing shall be given.
The SIA report shall be submitted in the prescribed format to the Commissioner,
Rehabilitation & Resettlement within a period of Six months from the date of
commencement and shall include the views of the affected families recorded in
writing. The SIA Report including summaries shall be prepared and divided into
three parts;
The Project Feasibility Report
The Project Impact Report
The Social Impact Management Plan
Details of how the SIA is to be carried out are given in Annexure 2.
A Social Impact Management Plan listing the ameliorative measures required to
be undertaken for addressing the impact of the project shall be submitted in
prescribed format along with the SIA report to the Commissioner, Rehabilitation &
Resettlement.
The SIA team must provide a conclusive assessment of the balance and
distribution of the adverse social impacts, social costs, benefits of the proposed
project and land acquisition, including the mitigation measures, and provide an
assessment as to whether the benefits from the proposed project exceed the social
costs and adverse social impacts that are likely to be experienced by the affected
families or even after the proposed mitigation measures, the affected families
remained at risk of being economically or socially worse, as a result of the said
land acquisition and resettlement.
The SIA Report and the Social Impact Management Plan shall be made available
in the Telugu language to the concerned Gram Panchayat, Mandal Parishad,
Municipality or Municipal Corporation, at village level or ward level in the affected
areas and in the Offices of the District Collector, the Sub-Divisional Officer and
Tahsildar. It shall also be published by way of a public notice by affixing at some
conspicuous places in the affected areas and shall be uploaded on the website of
the State Government and the revenue district concerned.
Page 93
c. Validation of SIA by Expert Group: The Appropriate Government shall ensure that
the SIA report is validated by an independent multi-disciplinary Expert Group, as
may be constituted by it. The Expert Group shall have:
Two non-official social scientists
Two representatives of Panchayat, Gram Sabha, Municipality or Municipal
Corporation
Two experts on rehabilitation, and a technical expert in the subject relating
to the project
If the Expert Group determines that the project does not serve any public purpose,
or the social costs and adverse social impacts of the project outweigh the potential
benefits, it shall make a recommendation within two months from the date of its
constitution and the project shall be abandoned forthwith and no further steps to
acquire land will be initiated in respect of the same.
If the Expert Group believes that there is a public purpose and that the benefits
outweigh social costs, it shall make recommendations within two months of its
constitution as to whether the extent of land proposed to be acquired is the
absolute bare-minimum extent needed for the project and whether there are no
other less displacing options available.
All recommendations of the Expert Group shall be recorded in writing along with
details and reasons for their decisions. The recommendations shall be made
available in the Telugu language to the Panchayat, Municipality, or Municipal
Corporation; and the offices of the District Collector, the Sub-Divisional Magistrate
and the Tehsil; and shall be published in the affected areas and also uploaded on
the website of the Appropriate Government.
d. Decision by Appropriate Government: The Appropriate Government shall examine
the Social Impact Assessment report, the recommendations of the Expert Group,
if any, and decide such area for acquisition which would ensure minimum
displacement of people, minimum disturbance to the infrastructure, ecology and
minimum adverse impact on the individuals affected. Before taking a decision the
appropriate Government shall ensure that consent is obtained the cases where
such consent is required.
The decision of the Appropriate Government shall be made available in the local
language to the Panchayat, Municipality, or Municipal Corporation; and the offices
of the District Collector, the Sub-Divisional Magistrate and the Tehsil; and shall be
published in the affected areas and also uploaded on the website of the
Appropriate Government.
Each acquisition case will be uploaded, on a public website that is to be created by
The Commissioner, Rehabilitation & Resettlement shall. All details regarding the
Page 94
case beginning with the notification of the SIA and tracking each step of decision
making, implementation and audit will be made available on the website.
e. Publication of Preliminary Notification: After conclusion of the SIA and consent of
the affected persons or Gram Sabha, as the case may be, when it appears to the
appropriate Government that land is required or likely to be required in any area
for any public purpose, a preliminary notification shall be issued in in the
prescribed format.
The notification shall be published in the following manner:
In the Andhra Pradesh Gazette;
In two daily newspapers circulating in the locality of such area of which one
shall be in the Telugu language;
In the Telugu language in the Panchayat, Municipality or Municipal
Corporation, as the case may be and in the offices of the District Collector,
the Sub-divisional Magistrate and the Tehsil;
Uploaded on the website of the Appropriate Government;
In conspicuous places in the affected areas and shall also be informed to the
public by beat of Tom-tom.
After issuing the preliminary notification, the Collector shall update land records
within a period of two months.
f. Preliminary survey of land proposed for acquisition: The officer authorized by the
District Collector to conduct preliminary survey shall have all the powers as
provided under section 12 of the RFCTLARRA 2013.
g. Disposal of objections: Any person interested in any land which has been notified
as being required or likely to be required for a public purpose, may within sixty
days from the date of the publication of the preliminary notification object to:
The area and suitability of land proposed to be acquired
Justification offered for public purpose
The findings of the SIA report
Every objection shall be made to the Collector in writing and the Collector shall
give the objector an opportunity of being heard in person or by any person
authorized by him in this behalf or by an Advocate and shall, after hearing all such
objections and making such further inquiry, if any, as he thinks necessary, shall
submit a report along with his recommendations on the objections to the District
Collector for decision. The decision of the District Collector shall be final.
h. Preparation of Rehabilitation and Resettlement Scheme and Public Hearing: On
publication of the preliminary notification by the Appropriate Government, the
Administrator for Rehabilitation and Resettlement shall conduct a survey and
Page 95
undertake a census of the affected families within a period of two months from the
date of publication of such preliminary notification.
For the survey and the census of the affected families the Administrator shall
collect data based on the SIA report as well as data from secondary sources such
as Panchayat and Government records and verify that data by door visit of the
affected families and by site visits in case of infrastructure in the affected area.
The draft Rehabilitation and Resettlement Scheme prepared by the Administrator
shall include particulars of the rehabilitation and resettlement entitlements of each
land owner and landless whose livelihoods are primarily dependent on the lands
being acquired. While resettling affected families is involved the scheme shall
contain the following:
List of Government buildings to be provided in Resettlement Area
Details of public amenities and infrastructural facilities which are to be
provided in Resettlement Area
List of likely to be displaced families
List of infrastructure in the affected area
List of land holdings in the affected area
List of trades/business in the affected area
List of landless people in the affected area
List of persons belonging to disadvantageous groups like persons belonging
to Scheduled Castes or Scheduled Tribes, handicapped persons in the
affected area
List of landless agricultural labourers in the affected area
List of unemployed youth in the affected area
Page 96
before issue of a notification. This prior consent shall be taken in all cases, even in
the case of urgency.
In cases of a project involving land acquisition on behalf of a requiring body which
involves involuntary displacement of the Scheduled Castes or Scheduled Tribes
families, a Development Plan shall be prepared in the prescribed format. The
Development Plan shall lay down the details of the procedure for settling land
rights due, but not settled and restoring titles of the Scheduled Tribes as well as he
Scheduled Castes on the alienated land by undertaking a special drive together
with land acquisition.
The Development Plan shall also contain a programme for development of
alternate fuel, fodder and non-timber forest produce resources on non-forest lands
within a period of five years, sufficient to meet the requirements of tribal
communities as well as the Scheduled Castes.
The affected families of the Scheduled Tribes shall be resettled preferably in the
same Scheduled Area in a compact block so that they can retain their ethnic,
linguistic and cultural identity. Further, the resettlement areas predominantly
inhabited by the Scheduled Castes and the Scheduled Tribes shall get land, to such
extent as may be prescribed by the Appropriate Government free of cost for
community and social gatherings.
The affected Scheduled Tribes, other traditional forest dwellers and the Scheduled
Castes having fishing rights in a river or pond or dam in the affected area shall be
given fishing rights in the reservoir area of the irrigation or hydel projects.
All the benefits, including the reservation benefits available to the Scheduled
Tribes and Scheduled Castes in the affected areas shall continue in the
resettlement area.
Any alienation of tribal lands or lands belonging to members of the Scheduled
Castes in disregard to the laws and regulations for the time being in force shall be
treated as null and void.
j. Publication of declaration for acquisition: A declaration for acquisition of the land
along with the summary of the Rehabilitation and Resettlement Scheme shall be
made by the appropriate government in the prescribed format. However, no such
declaration shall be made unless the requiring body has deposited an amount in
full towards the cost of acquisition of the land. Every declaration shall be published
in the same manner as described above in the case of the preliminary notification.
k. Land acquisition award: The Collector shall make an award within a period of
twelve months from the date of publication of the declaration for acquisition. If no
award is made within this period, the entire proceedings for the acquisition of the
land shall lapse.
Page 97
l. Compensation for land acquisition: The compensation shall be calculated by the
Collector on the basis of the provisions laid down under section 26 to section 30
and \ the First Schedule of the RFCTLARRA 2013. The compensation shall be paid
to all parties whose land or other immovable property or assets attached to the
land or building have been acquired. As per the Act, land owners are defined as
any person:
Whose name is recorded as the owner of the land or building or part thereof,
in the records of the authority concerned; or
Who is granted forest rights under the Scheduled Tribes and Other
Traditional Forest Dwellers (Recognition of Forest Rights) Act, 2006 or under
any other law for the time being in force; or
Who is entitled to be granted Patta rights on the land under any law of the
State including assigned lands; or
Who has been declared as such by an order of the court or Authority
The Collector shall determine the market value of the land to be acquired on the
basis of whichever of the following is higher:
Market value, if any, specified in the Indian Stamp Act, 1889 for the
registration of sale deeds or agreements to sell in the area where the land is
situated; or
The average sale price for similar type of land situated in the nearest village
or nearest vicinity area; or
Consented amount of compensation as agreed in case of acquisition of lands
for private companies or for public private partnership project
The Collector having determined the market value of the land to be acquired shall
calculate the total amount of compensation to be paid to the land owner by
including all assets attached to the land. This will be done as follows:
Component of Compensation Manner of Determination of Value
1. Market value of land Whichever of the following is higher:
Market value, if any, specified in the Indian
Stamp Act, 1889 for the registration of sale deeds
or agreements to sell in the area where the land
is situated; or
The average sale price for similar type of land
situated in the nearest village or nearest vicinity
area; or
Consented amount of compensation as agreed in
case of acquisition of lands for private companies
or for public private partnership project
Page 98
2. Factor by which the market In case of rural areas (other than Scheduled
value is to be multiplied Areas) a multiplication factor of 1.25 will be
applied
In case of Scheduled (Tribal) Areas, a
multiplication factor of 1.50 will be applied
In case of urban areas, a multiplication factor of
1.00 will be applied
3. Value of assets attached to
land or building
a. Market value of the The Collector shall use the services of a
building and other competent engineer, or any other specialist in
immovable property or the relevant field, as may be considered
assets attached to the land necessary
or building that is to be
acquired
b. Damage sustained to For fruit bearing trees, the value of
standing trees and plats compensation per tree will be determined from
time to time by the Horticulture Department
based on the species of tree
For non-fruit bearing trees, the value of
compensation will be determined by the Forest
Department
c. Damage sustained to For standing crops, the compensation will be
standing crops determined by the Agricultural Officer on a case
by case basis
4. Solatium The solatium shall be equivalent to one hundred
percent of the market value of the land
mentioned against serial number 1 multiplied by
the relevant factor mentioned against serial
number 2 plus the value of assets attached to
land or building mentioned against serial
number 4a, 4b and 4c.
5. Total Compensation The total compensation = Market value of land
mentioned against serial number 1 X relevant
factor mentioned against serial number 2 + Value
of assets as mentioned against serial number 3 +
Soaltium mentioned against serial number 4
In addition to the market value of the land provided, the Collector shall, in every
case, award an amount calculated at the rate of twelve per cent per annum on the
market value for the period commencing on and from the date of the publication
of the notification of the SIA till the date of the award of the Collector or the date
of taking possession of the land, whichever is earlier.
Page 99
m. Compensation for Rehabilitation and Resettlement: In addition to the
compensation detailed above, the Collector shall pass Rehabilitation and
Resettlement Awards for each affected family. According to the RFCTLARRA 2013,
affected family is defined as:
A family whose land or other immovable property has been acquired;
A family which does not own any land but a member or members of such
family may be agricultural labourers, tenants including any form of tenancy
or holding of usufruct right, share-croppers or artisans or who may be
working in the affected area for three years prior to the acquisition of the land,
whose primary source of livelihood stand affected by the acquisition of land;
The Scheduled Tribes and other traditional forest dwellers who have lost any
of their forest rights recognized under the Scheduled Tribes and Other
Traditional Forest Dwellers (Recognition of Forest Rights) Act, 2006 due to
acquisition of land
Family whose primary source of livelihood for three years prior to the
acquisition of the land is dependent on forests or water bodies and includes
gatherers of forest produce, hunters, fisher folk and boatmen and such
livelihood is affected due to acquisition of land;
A member of the family who has been assigned land by the State
Government or the Central Government under any of its schemes and such
land is under acquisition;
A family residing on any land in urban areas for preceding three years or
more prior to the acquisition of the land or whose primary source of
livelihood for three years prior to the acquisition of the land is affected by the
acquisition of such land
Page 100
three years preceding the date of notification of the
affected area
No family shall be given more than one house
Page 101
7. Onetime resettlement Each affected family shall be give a onetime Resettlement
allowance Allowance of INR 50,000 /-
8. Stamp duty and registration The stamp duty and any other fees payable for registration
fee of the land or house allotted to the affected families shall
be borne by the requiring body
The land for house allotted to the affected family shall be
free from all encumbrances
The land or house allotted may be in the joint names of
wife and husband of the affected family
9. Special provisions for Scheduled Castes and Scheduled Tribes displaced from
Scheduled Castes and Scheduled Areas shall receive an amount equivalent to
Scheduled Tribes INR 50,000 /- per family
Families settled outside the district shall be entitled to an
additional 25% R&R benefits;
Payment of one third of the compensation amount at very
outset;
Free land for community and social gatherings;
However, the Act allows the utilities to from time to time, place and maintain transmission
/ distribution lines under, over, along, or across, and towers / poles in or upon any
immovable property. Further, the utility may at any time for the purpose of examining,
repairing, altering or removing any transmission / distribution line or tower, enter on the
property under, over, along, across, in or upon which the line or tower / pole has been
placed.
In addition, the MoEF provides guidelines for maintaining a Right of Way (RoW) corridor
which shall be kept clear of any obstruction. The width of the RoW corridor depends on the
voltage of the lines as depicted in the table below:
Page 102
220 kV 35
132 kV 27
33 kV 15
11 kV 7
*Width of Right of Way is as per MoEF guidelines dated May 2014
In the width of the RoW trees are cut or pruned to the extent required for preventing
electrical hazards by maintaining the following:
Therefore, while the ownership of land used for towers and lines remains with the existing
owners, the construction of towers and laying of lines could lead to damage of crops or
trees on the land. Further, the construction of the tower may restrict the use of land under
the tower footing. Similarly, use of the land in the RoW corridor may also be restricted.
Keeping this in mind, the concerned utility shall endeavour to cause as little damage,
detriment and inconvenience as possible. Further, the utility shall make full compensation
for any damage, detriment or inconvenience caused. In addition to the compensation for
damage, the utility shall also pay compensation for restriction of land use due to
construction of towers. The compensation for damage is calculated as follows:
Page 103
Elements of Compensation Entitlement / Provision
1. Temporary damage to crops Full compensation shall be paid for the damage to crops and
and trees during construction trees as well as structures in the corridor.
of towers and laying of lines The compensation for crops will be determined by the
Agriculture officer on a case to case basis
The compensation for fruit trees will be determined by the
horticulture department from time to time
In the case of non-fruit trees the compensation shall be
determined by the forest department. However, the utility
shall endeavor to avoid forest land wherever possible
2. Restriction of use of land The land owner is given a onetime compensation for the
area below the tower footing area under the tower footing at a rate determined by the
District Collector. The rate is depended on voltage. At
present the following guidelines are in place:
In the Kadapa Zone compensation for 132 kV towers is INR
55,000 per tower and for 220 kV towers compensation is
INR 99,500 per tower.
In the Vishakhapatnam Zone
- Vizanagaram, Visakhapatnam- compensation for
132 kV towers is INR 55,000 and for 220 kV towers
compensation is INR 99,500 per tower
- Sirakulam, East Godavari, West Godavari-
compensation for 132 kV towers is INR 43,900 and
for 220 kV compensation is INR 79,600 per tower
In the Vijayawada Zone compensation for 132 kV towers is
INR 55,000 and for 220 kV towers compensation is INR
99,500 per tower.
As discussed in the section policy, legal and administrative framework, the guidelines for
ensuring community health and safety are provided by CEA regulations 2010 and CEA
regulations 2011.The methods to avoid, limit and mitigate the impacts on community
health and safety are provided below:
As per CEA guidelines, each utility has appointed a Safety Officer to ensure
community health and safety
Regular maintenance of the equipment at consumer premises as mandated in CEA
Regulation 2010
Exposure to electric and magnetic fields: Although there is public and scientific
concern over the potential health effects associated with EMF, there is no empirical
Page 104
data demonstrating adverse health effects from exposure to typical EMF levels
from power transmission lines and equipment.19
Exposure to hazardous material: SF6 is used as a gas insulator for electrical
switching equipment, transformers and cables. Ensure that the equipment with
low leakage rate is used.
Noise: The noise produced by power lines or transformers do not cause any known
health risk
Electric Shocks and electrocution: Electric shocks and electrocution present a major
threat. The methods employed to avoid and mitigate the threat are provided below:
- Display danger signs at appropriate locations
- Display boards with precautions to be adopted by consumers, owners,
occupiers, electrical contractors, electric workmen and suppliers
- Display of instructions for resuscitation of persons suffering from electric
shock
- The compensation is paid to non-departmental persons in the case of fatal
accidents due to electrocution. The ex-gratia amount payable in case of fatal
accidents recommended by APERC is as follows:
S.No. Fatal Accident Ex-gratia amount payable (for each case)
1. Non Departmental Person
a. Adult INR 2,00,000
b. Child INR 2,00,000
2. Animal
a. Cattle INR 20,000
b. Other animal (goat & sheep) INR 4,000
The compensation is sanctioned by Chief Engineer/In-charge of zones.
19
IFC’s Environmental, Health, and Safety Guidelines for Electric Power Transmission and Distribution.
Available at: http://www.ifc.org/wps/wcm/connect/554e8d80488658e4b76af76a6515bb18/Final+-
+General+EHS+Guidelines.pdf?MOD=AJPERES
Page 105
For management of debris disposal, necessary measures must be integrated in the
construction contract.
The health and safety policy of and conditions of contract, the contractor shall be
responsible for (i) establishing construction camps with adequate sanitation
facilities; (ii) periodic health check-up for its employees and (iii) maintaining strict
safety guidelines with a provision of penalty for offences.
Further the safety policy ensures safety awareness among the workers organized
on daily basis by the safety personnel of the contractor. The safety policy also
frames out some specific safety requirements of workers pertaining to: (i) welding,
cutting and stone breaking (ii) hoisting of equipments; (iii) electrical works; (iv)
working at heights (v) erection of structural steels etc. Additionally the general
safety guidelines include: (i) restricting vehicle speed plying with the construction
site area (ii) wearing of safety helmets as per color coding (iii) following various
codes like HSE codes/provisions as per factories acts/Environmental Protection Act
etc.
The workers are provided with Safety shoes, helmets, reflectors, earplugs and
double lanyard safety belts (being worn by the gang workers working at heights)
as personnel protective equipments.
The mitigation methods to manage the impact on women and tribal population are
provided in Gender Action Plan and Tribal Peoples Policy framework annexed with this
document.
Page 106
The measures to manage the impact of loss of land and RoW are provided under point 1.
Loss of land, resettlement and Rehabilitation, and point 2. Change in Land Use or
Restrictions to Land use. Specific provisions for vulnerable population include:
Page 107
- All the benefits, including the reservation benefits available to the Scheduled
Tribes and Scheduled Castes in the affected areas shall continue in the
resettlement area.
- Any alienation of tribal lands or lands belonging to members of the Scheduled
Castes in disregards of the laws and regulations for the time being in force
shall be treated as null and void.
F. Cultural Heritage
Applicability: Transmission & Distribution Projects where line work is in vicinity of
historically or culturally important sites
Avoid routing the lines through any of the identified archeologically, historically or
culturally important sites. If any cultural property is found during construction, the work
will be stopped immediately and contractor will intimate utilities about availability of
cultural property. Utilities will intimate to Department of Archaeology & Museums, Andhra
Pradesh and approval will be taken to erect the tower for transmission line.
The proposed projects require approval from Power & Telecommunication Coordination
Committee (PTCC) before commission. The committee considers the worst fault conditions
(measure of interference) and coordinates with the relevant telecommunication, railway
and defence authorities before providing approval for the project. The process to receive
PTCC approval is provided below:
During the project design phase, EE (Electrical engineer) prepares a topography
map which identifies the railway, defence and telecommunication
infrastructure/crossings on the route of transmission lines.
Page 108
The head quarter calculates the fault levels, if any, for 132 kV lines. Fault levels
for 220 kV line are calculated at PTCC and submits the same for approval by PTCC
PTCC coordinates with designated authorities in BSNL, private operators like
Reliance, Railways and Defence establishments to understand their concerns
Each department adds their lines on the topographic map and provides approval
Page 109
8. Enviornmental Impacts & Mitigation Methods
8.1 Environmental Screening and Analysis of Alternatives
The following general procedure shall apply for all the projects and sub-projects proposed
by APTRANSCO and the Distribution Companies. The details of this procedure may vary
depending on the specific nature of the proposed project activity.
For every project activity the respective project implementation team of the Utility will
undertake an initial environmental screening. At the screening stage one of the key factors
to be evaluated is the possible infringement of the project activities with any
environmentally sensitive areas such as protected ecosystems, wildlife sanctuaries,
national parks, reserved forest area, protected monuments etc., for which whether any
World Bank safeguard polic(y)ies is/are triggered. The project implementation team will
study each activity in detail for potential impacts to identify the triggered safeguard
policies. Also, wherever such infringements are substantial, different alternative
locations/alignment options need to be considered. The project implementation team shall
prepare a short screening report based on the above.
During the selection of alignment for the transmission lines and identifying the site for sub-
stations, preliminary site selection survey needs to be carried out for avoiding the
environmentally and socially sensitive areas to the extent possible. The alignment of the
proposed new transmission and sub-transmission lines needs to be finalised after
conducting desktop as well as physical survey of the land though which the lines passes.
For selecting the optimum route, the following points may be considered for both the
transmission and distribution line projects:
Page 110
8. Reasons for selection of final
route:
The potential environmental issues associated with transmission and distribution (T&D)
projects are manageable since (a) They are mostly localised to Right of Way (ROW); (b) the
‘footprint’ associated with towers is small and (c) there is flexibility in siting facilities within
relatively large host area. The transmission line project may have some adverse effects on
natural resources. However, they can be minimized by careful route selection and siting of
substations.
Page 111
The environmental issues as associated with two main activities viz., (a) Transmission and
distribution lines and (b) Construction of sub-stations are discussed as below:
Pre-Construction
Page 112
on forest electrocutions and assistance towards
land sometime impact on compensatory afforestation to
livelihood. restore the forest land
wherever applicable).
Construction phase
Page 113
quality as a result of
compaction and
excavation. Removal
of vegetation and
trees during
construction of
foundation will make
soil vulnerable to
erosion. Movement
of workers during the
construction phase
may also damage the
vegetation or crops if
passing thorough
cultivable area.
Page 114
negligible impacts done only with prior approval
from the traffic. of the forest department.
Ambient Air Construction activities Not withstanding the potential for Contractor
Quality will involve excavation atmospheric emissions from (monitored by
for erection of tower construction and related activities APTRANSCO)
and movement of is low, the follwong mitigation
vehicles carrying the measures will further reduce the
construction material, impact of emissions leading to
etc. This will result in insignificant impacts;
limited fugitive
o Sprinkling of water on dust
emission at site.
generating areas
As the construction o Restricting the speed limit of
activity will involve vehicles during movement
limited ground work,
on unpaved roads and;
the potential for dust
o Covering of vehicles
generation is low and
carrying loose soil and
shortlived. The increse
constriction materials.
in traffic during the
construction of the
transmission line is
expected to be
occasional and
negligible. Hence, it is
considered that the
contributions to the
pollutant
concentrations arising
from the construction
activities and traffic is
small and insufficient
to cause any increase
in the stipulated air
standards or existing
concentrations.
Page 115
pumping excess water) be done manually instead of
and compressors etc. cranes and other heavy
There is a potential for equipment, which will reduce
disturbance to potential for noise impacts.
habitations, schools,
Construction activity will be
temples in proximity to
undertaken during the daytime.
the towers due to
Some noise generation is
construction related
anticipated from movement of
activities . During
machinery and other
erction of towers there
eqipments like tractors and
can be disturbance
trailers transporting the
frpm noise of workers.
materials and the equipments
Also during stringing
but the traffic volumes are
there is a potential for
expected to be occasional and
disturbance from
insignificant.
continous operation of
equipments like The process of stringing of cable
tractors. will only produce human voices,
which might be audible to the
residents in very close proximity
of the operations. However,
these impacts are expected to be
localized and short-lived.
Water The project area will Optimal use of water will be Contractor
Quality not be criss-crossed planned and followed at the (monitored by
by any stream or river construction site. In case any APTRANSCO)
however in some construction activity is in
areas the presence of proximity to any water body
some small surface prevention of any runoff to the
water body is same must be ensured.
anticipated. The use of
ground water is also
not anticipated for the
project activities.
Soil The excavation work The excavation work involved Contractor
involved in the project in the project is limited to (monitored by
is limited to construction of tower APTRANSCO)
construction of tower foundation. The loss of top
foundation. The loss soil as envisaged during such
of top soil as construction activities can
envisaged during largely be reduced by storing
such construction the top soil and spreading it
activities can largely back for filling up the
be reduced by storing excavated area of the tower
the top soil and foundation.
Page 116
spreading it back for
filling up the
excavated area of the
tower foundation.
Flora and For setting up of the Care must be taken to avoid Contractor
Fauna/ power transmission thick vegetation; towers to be (monitored by
line, there will be located where vegetation is APTRANSCO)
requirement of thin. This will greatly minimize
localised clearence of tree loss and compensation to
vegetation, which may be paid to tree owners.
affect flora and fauna Clearance for trees to be cut
within the corridor. will be taken from concerned
The land requirement authorities and if required
for substations varies compensatory afforestation
from 0.3 acres to 10 (CA) has to be done in
acres depending upon association with the
voltage level and no. of concerned authorities.
bays. Trimming of trees should be
done in consultation with the
The potenial impacts concerned authorities.
that are likely from the
construction of The existing land use for the
transmission line are transmission line is rarely
disturbance or used for grazing by domestic
damage to any flora or animals like cow, buffalo,
fauna species in the goats etc.; hence minimal
impact area due to disturbance to local animals is
movement of vehicles, anticipated during
dust, noise etc. and construction. The forest types
due to clearence of in the mentioned sections are
trees for lying of the mostly governed by Open
transmission line. Forests and Non-forest types
thereby minimizing presence
of rare and endangered
species.
Aesthetics The visual amenity will The route is to be planned to Contractor
and Visual be disturbed mainly avoid any dense habitation (monitored by
Impact during casting of or forested area. The clearing APTRANSCO)
foundation and leaving of trees must be kept to
the site with stubs of minimum and clearing of
tower. The erction of trees must be kept to
towers and conductors minimum and whereever
across the terrain will possible, trimming of trees
be an extrinsic element must be adopted vis-à-vis
to th existing felling of trees.
Page 117
ambience. The visual
impact and change of
landscape will be for a
short period however,
the route of the towers
and transmission line
is expected to cross
other transmission line
or roads which may
lead to change of
landscape character
due to introduction of
manmade character.
Health and There is a possibility The developer need to have a Contractor
Safety of an increased risk defined safety management (monitored by
due to exposure to protocol. Site safety manager APTRANSCO)
electromagnetic must be deployed for
radiations from enforcement of safety measures
overhead transmission during construction. In respect of
lines. Further, management of debris disposal,
construction workers necessary measures must be
might get injured or integrated in the construction
meet accidents during contract. The health and safety
construction activities. policy of and conditions of
Injuries, bruises etc. contract, the contractor shall be
might occur in case of responsible for (i) establishing
inadequate protective construction camps with
measures and lack of adequate sanitation facilities; (ii)
awareness. periodic health check-up for its
employees and (iii) maintaining
strict safety guidelines with a
provision of penalty for offences.
Page 118
Additionally the general safety
guidelines include: (i) restricting
vehicle speed plying with the
construction site area; (ii) wearing
of safety helmets as per color
coding;(iii) following various
codes like HSE codes/provisions
as per factories
acts/Environmental Protection Act
etc.
The workers are provided with
Safety shoes, helmets, reflectors,
earplugs and double lanyard
safety belts (being worn by the
gang workers working at heights)
as personnel protective
equipments.
Cultural SitesNo archaeological, Avoid routing the lines through Contractor
historical or culturally any of the identified (monitored by
important sites are archeologically, historically or APTRANSCO)
anticipated near the culturally important sites. If any
proposed cultural property is found during
transmission line construction, the work will be
corridors. If any stopped immediately and
cultural property is contractor will intimate utilities
found during about availability of cultural
construction, the work property. Utilities will intimate to
will be stopped Department of Archeology &
immediately and Museums, Andhrapradesh and
contractor will approval will be taken to erect the
intimate utilities about tower for transmission line.
availability of cultural
property. Utilities will
intimate to
Department of
Archeology &
Museums,
Andhrapradesh and
approval will be taken
to erect the tower for
transmission line.
Operation phase
Page 119
Waste The main type of waste Hazardous waste will be Contractor
Disposal likely to be generated managed as per the (monitored by
will be used transformer provisions under the APTRANSCO)
oil which is a category of hazardous waste
hazardous waste management rules. The
egenrated at the site. hazardous waste will only
be sent to authorised
vendor for disposal.
Soil The project document Moreover, project line Contractor
ensures designing of section must not block (monitored by
different types of the drainage within the APTRANSCO)
foundations according to alignment and also
the soil types within the should not increase the
project alignments. The run-off in the local
engineering design must catchmen area.
be made considering the
soil quality and erosion
potential of the region.
Flora and Trees near transmission Since avian fauna might Contractor
Fauna lines may increase the be at small risks by hitting (monitored by
chances of fire hazards the transmission lines, APTRANSCO)
due to electric sparks hence a minor impact is
requiring trimming of predicted during the
trees to minimize the risk operational phases.
of accidents and proper Addition of deflectors is
maintenance. As part of proposed to minimize the
maintaining the ROW risk.
such trimming of trees
may need to be
undertaken which may
require approval from
Forest Department. The
ROW maintenance team
of utilities shall coordinate
with the forest department
in order to obtain
necessary NOC for tree
cutting.
Land Use Minor changes in land No mitigation measures Contractor
use pattern is required at this stage. (monitored by
envisaged during the APTRANSCO)
operation phase. The
land use for the project
is primarily non-
Page 120
agrivultural land. This
land will be aquired
and developed in the
construction phase
itself.
Page 121
ladders/monkey ladders (as
per IS: 3696), fall arrestor etc.
There have been some
concerns about the possibility
of an increased risk from
exposure to electromagnetic
radiations from overhead
transmission lines. However
the exposure limit shall be
kept at minimum level and
regular medical checkup of
the employees shall be
conducted to minimize such
impacts.
- Careful design
- Safety awareness
- Emergency planning
- Sanitation and medical
facilities
Pre-Construction
Page 122
places of historical or
cultural importance.
Construction phase
Page 123
movement of cultivable and non-
construction material cultivable land.
and manpower through
cultivated areas. As per the consultations
with the utilities, most of
The most significant
the land used for the
potential impact
project purpose is
anticipated for the soil
estimated to be
will be change in soil
government land however,
structure and soil quality for the cultivable land due
as a result of compaction to the tower construction
and excavation. Removal activity, crop production in
of vegetation and trees the area occupied by the
during construction of tower will be stopped for
foundation will make soil short run and after the
vulnerable to erosion. erection of towers the crop
Movement of workers production work can start
during the construction again.
Page 124
movement during Any increase in traffic
construction phase is during the construction
expected to be phase will be shortlived
occasional and very low and will return to normal
resulting in negligible once construction
impacts from the traffic. activity is complete.
Ambient Air Construction activities Not withstanding the Contractor
Quality will involve excavation for potential for atmospheric (monitored by
erection of tower and emissions from DISCOMS)
movement of vehicles construction and related
carrying the construction activities is low, the
material, etc. This will follwong mitigation
result in limited fugitive measures will further
emission at site. reduce the impact of
emissions leading to
As the construction
insignificant impacts:
activity will involve
limited ground work, the o Sprinkling of water on
potential for dust dust generating areas
generation is low and o Restricting the speed
shortlived. The increse in limit of vehicles
traffic during the
during movement on
construction of the
unpaved roads and;
transmission line is
o Covering of vehicles
expected to be occasional
carrying loose soil
and negligible. Hence, it
is considered that the and constriction
contributions to the materials.
pollutant concentrations
arising from the
construction activities and
traffic is small and
insufficient to cause any
increase in the stipulated
air standards or existing
concentrations.
Page 125
of pumps (for pumping between laying of
excess water) and foundations and
compressors etc. There is erection of towers. Most
a potential for disturbance of the work will be done
to habitations, schools, manually instead of
temples in proximity to cranes and other heavy
the towers due to equipment, which will
construction related reduce potential for
activities . During erction noise impacts.
of towers there can be
The process of stringing
disturbance frpm noise of
of cable will only produce
workers. Also during
human voices, which
stringing there is a
might be audible to the
potential for disturbance
residents in very close
from continous operation
proximity of the
of equipments like
operations. However,
tractors.
these impacts are
expected to be localized
and short-lived.
Water Quality The project area will not Optimal use of water will Contractor
be criss-crossed by any be planned and followed (monitored by
stream or river however at the construction site. In DISCOMS)
in some areas the case any construction
presence of some small activity is in proximity to
surface water body is any water body
anticipated. The use of prevention of any runoff
ground water is also not to the same must be
anticipated for the project ensured.
activities.
Soil The excavation work The excavation work Contractor
involved in the project is involved in the project is (monitored by
limited to construction of limited to construction DISCOMS)
tower foundation. The of tower foundation.
loss of top soil as The loss of top soil as
envisaged during such envisaged during such
construction activities construction activities
can largely be reduced can largely be reduced
by storing the top soil by storing the top soil
and spreading it back for and spreading it back
filling up the excavated for filling up the
area of the tower excavated area of the
foundation. tower foundation.
Page 126
Aesthetics and The visual amenity will be The route is to be Contractor
Visual Impact disturbed mainly during planned to avoid any (monitored by
casting of foundation and dense habitation or DISCOMS)
leaving the site with stubs forested area. The
of tower. The erction of clearing of trees must
towers and conductors be kept to minimum
across the terrain will be and clearing of trees
an extrinsic element to th must be kept to
existing ambience. The minimum and
visual impact and change whereever possible,
of landscape will be for a trimming of trees must
short period however, the be adopted vis-à-vis
route of the towers and felling of trees.
transmission line is
expected to cross other
transmission line or roads
which may lead to change
of landscape character
due to introduction of
manmade character.
Health and There is a possibility of an The developer need to have Contractor
Safety increased risk due to a defined safety (monitored by
exposure to management protocol. Site DISCOMS)
electromagnetic safety manager must be
radiations from overhead deployed for enforcement
transmission lines. of safety measures during
Further, construction construction. In respect of
workers might get injured management of debris
or meet accidents during disposal, necessary
construction activities. measures must be
Injuries, bruises etc. integrated in the
might occur in case of construction contract. The
inadequate protective health and safety policy of
measures and lack of and conditions of contract,
awareness. the contractor shall be
responsible for (i)
establishing construction
camps with adequate
sanitation facilities; (ii)
periodic health check-up for
its employees and (iii)
maintaining strict safety
guidelines with a provision
of penalty for offences.
Page 127
Further the safety policy
ensures safety awareness
among the workers
organized on daily basis by
the safety personnel of the
contractor. The safety
policy also frames out
some specific safety
requirement of workers
pertaining to: (i) Welding,
cutting and stone breaking;
(ii) hoisting of equipments;
(iii) Electrical works; (iv)
working at heights; (v)
erection of structural steels
etc. Additionally the
general safety guidelines
include: (i) restricting
vehicle speed plying with
the construction site area;
(ii) wearing of safety
helmets as per color
coding;(iii) following
various codes like HSE
codes/provisions as per
factories
acts/Environmental
Protection Act etc.
The workers are provided
with Safety shoes, helmets,
reflectors, earplugs and
double lanyard safety belts
(being worn by the gang
workers working at heights)
as personnel protective
equipments.
Cultural Sites No archaeological, Avoid routing the lines Contractor
historical or culturally through any of the (monitored by
important sites are identified archeologically, DISCOMS)
anticipated near the historically or culturally
proposed transmission important sites. If any
line corridors. If any cultural property is found
cultural property is found during construction, the
during construction, the work will be stopped
work will be stopped immediately and contractor
Page 128
immediately and will intimate utilities about
contractor will intimate availability of cultural
utilities about availability property. Utilities will
of cultural property. intimate to Department of
Utilities will intimate to Archeology & Museums,
Department of Andhrapradesh and
Archeology & Museums, approval will be taken to
Andhrapradesh and erect the tower for
approval will be taken to transmission line.
erect the tower for
transmission line.
Operation phase
Page 129
Flora and Trees near transmission Since avian fauna Contractor
Fauna lines may increase the might be at small risks (monitored by
chances of fire hazards by hitting the DISCOMS)
due to electric sparks transmission lines,
requiring trimming of hence a minor impact
trees to minimize the risk is predicted during the
of accidents and proper operational phases.
maintenance. As part of Addition of deflectors
maintaining the ROW is proposed to
such trimming of trees minimize the risk.
may need to be
undertaken which may
require approval from
Forest Department. The
ROW maintenance team
of utilities shall
coordinate with the forest
department in order to
obtain necessary NOC for
tree cutting.
Land Use Minor changes in land No mitigation measures Contractor
use pattern is required at this stage. (monitored by
envisaged during the DISCOMS)
operation phase. The
land use for the project
is primarily non-
agrivultural land. This
land will be aquired
and developed in the
construction phase
itself.
Air and Noise The operation of Impacts are expected to Contractor
Quality transmission line does be minimal at operation (monitored by
not involve any stage. No specific DISCOMS)
emission of gases and mitigation measures will
generation of dust be required.
particles and hence the
impact on ambient air
quality is anticipated to
be very less during
erection of
transmission lines.
Similarly impact on
noise quality is
Page 130
envisaged to be very
low.
Water Quality The operation of Impacts are expected to Contractor
transmission line do be minimal at operation (monitored by
not involve generation stage. No specific DISCOMS)
of any effluent and mitigation measures will
discarding of any be required.
hazardous chemical
which could have
chances of impact on
nearby water bodies.
Thus no impacts on
ground water or
surface water quality
are anticipated during
the operational stage.
Workers Injury and sickness/health As part of the health and Contractor
health and hazards safety policy, utilities will (monitored by
Safety ensures that the workers DISCOMS)
involved working in heights
are provided with
necessary personal
protective equipments like
safety shoes tested for
11/33kV, Handgloves tested
for 11/33kV (IS 4770), safety
belts, ladders/monkey
ladders (as per IS: 3696),
fall arrestor etc. There have
been some concerns about
the possibility of an
increased risk from
exposure to
electromagnetic radiations
from overhead
transmission lines.
However the exposure limit
shall be kept at minimum
level and regular medical
checkup of the employees
shall be conducted to
minimize such impacts.
Page 131
- Careful design
- Safety awareness
- Emergency
planning
- Sanitation and
medical facilities
Potential environmental impacts specific to project activities undertaken by APTRANSCO and DISCOMS (viz., APSPDCL and
APEPDCL)
Page 132
carried out manually and therefore trimming/pruning of tree branches
are only required instead of cutting of trees in large numbers.
Page 133
8.3 Policy and Legal Framework
Policy and Legal Framework applicable to the project activities
Constitutional Provisions
A The State shall endeavour to protect and improve the environment and
Article 48 A
to safeguard the forests and wildlife of the country.
It shall be the duty of every citizen of India to protect and improve the
B Article 51 A (g) natural environment including forests, lakes, rivers and wildlife and to
have compassion for living creatures.
The policy seeks to stimulate partnerships of different stakeholders, i.e.
public agencies, local communities, academic and scientific
institutions, the investment community, and international
development partners, in harnessing their respective resources and
C Environmental strengths for environmental management. The dominant theme of this
Policy, 2006 policy is that while conservation of environmental resources is
necessary to secure livelihoods and well-being of all, the most secure
basis for conservation is to ensure that people dependent on particular
resources obtain better livelihoods from the fact of conservation, than
from degradation of the resource."
Provisions/Law
Applicability
of Land/Rules
Electricity Act, 2003 Transmission line projects are constructed under the ambit of Electricity
(EA, 2003) Act, 2003 following the provisions of Section 67 & 68 of Act.
The Electricity Act under Section 164 has a provision to grant licensee the
power of Telegraph Authority as provided in the Indian Telegraph Act, 1885
GoAP on request of utilities may by order in writing/through notification
authorize them for using powers of telegraph authority after fulfilling the
requirement as laid down in the rules thereof.
Forest (Conservation) This Act provides for the conservation of forests and regulates the
Act, 1980 diversion of forest land to non-forestry purpose. When any
transmission/distribution line traverses forest land, prior clearance is
mandatorily required from Ministry of Environment and Forests (MoEF),
GoI under the Forest (Conservation) Act, 1980.
Page 134
Provisions/Law
Applicability
of Land/Rules
Environment It is an umbrella Act for the protection and improvement of environment.
(Protection) Act, 1986 This Act as such is not applicable to transmission/ distribution projects of
utilities. Project categories are specified under the schedule of the EIA
notification. EPA is an umbrella Act under which several pollution
prevention and control Acts and Rules such as Water (Prevention and
Control of Water Pollution) Act, 1974 (as amended in 1988); The Air
(Prevention and Control of Pollution) Act, 1981, amended in 1987; The
Noise Pollution (Regulation & Control) Rules, 2000 (as amended in 2002);
Hazardous Wastes (Management, Handling and Transboundary
Movement) Rules, 2008; Coastal Regulation Zone (CRZ) Notification, 2011
(as amended) are prescribed under the Act. At all stages of the project, the
compliance against the applicable conditions of these key Acts and Rules
must be adhered to by the utilities.
The Water The purpose of this Act is to provide for the prevention and control of water
(Prevention and pollution and maintaining or restoring of wholesomeness of water. The Act
Control of Water asked for establishment of pollution control boards at central and state
Pollution) Act, 1974 level and assigned functions and powers to these boards for the prevention
(as amended in and control of water pollution and for matters connected therewith.
1988)
For the current project, labour will mainly be resorted from the local
sources and no significant of camp site is envisaged hence, no significant
sewage generation is anticipated.
The Air (Prevention The Air (Prevention and Control of Pollution) Act, 1981 an Act of the
and Control of Parliament of India to control and prevent air pollution. It was amended in
Pollution) Act, 1981, 1987. The project implementing utility will need to ensure that any
amended in 1987 construction contractor setting up a labour camp takes consent to
establish/NOC prior to its set-up in case an air pollution source above
certain rated capacity is proposed to be installed at the camp site.
For the current project, labour will mainly be resorted from the local
sources and no significant of camp site is envisaged. Some of the activities
of the project that will generate fugitive emissions like dust will include
movement of vehicles, excavation of pits for tower erection, operation of
diesel generator sets at campsites or other construction activities among
others. Appropriate measure must be taken to contain these emissions.
The Noise Pollution Noise Control Rules, 2000 (as amended) were notified to prescribe the
(Regulation & ambient noise quality standards are have to be complied with in different
Control) Rules, 2000 areas/zones viz., residential, commercial etc. These rules also restrict the
(as amended in use of loud speakers and public addressal systems within certain time
2002) period. State Pollution Control Boards (SPCB) are provided with
responsibility to monitor the implementation of the Rules.
Page 135
Provisions/Law
Applicability
of Land/Rules
There will be generation of noise during the erection of transmission line
during the construction activities during the project phases. Based on the
land use classification, areas where the project phase is being executed
may be falling under various categories such as Residential, Commercial
etc. The day and night time noise limits as per the prescribed standards
must be complied with by the executing agencies. Noise pollution
generated from the project activities must stay within the prescribed limits
(viz., standards specified by CPCB for different categories). Andhra Pradesh
Pollution Control Board (APPPCB) and district administration will
enforcement agency for the current project location.
The Motor Vehicles The Motor Vehicles Act (MVA), 1988 regulates all aspects of road transport
Act, 1988 (as vehicles. The Act provides in detail the legislative provisions regarding
amended) and licensing of drivers/conductors, registration of motor vehicles, control of
Central Motor motor vehicles through permits, special provisions relating to state
Vehicle Rules, 1989 transport undertakings, traffic regulation, insurance, liability, offences and
(as amended) penalties, etc. For exercising the legislative provisions of the Act, the
Government of India made the Central Motor Vehicles Rules (CMVR), 1989.
Ministry of Road Transport and Highways /State Transport is the nodal
authority for the implementation and monitoring the provisions of the Act
and the Rules.
Ozone Depleting As per the notification, certain control and regulation has been imposed on
Substances manufacturing, import, export, and use of these compounds. SF6 is used
(Regulation and as an alternative to any ODS substance for providing insulation in
Control) Rules, 2000 transformers.
Page 136
Provisions/Law
Applicability
of Land/Rules
Hazardous Wastes As per notification, used oil is categorized as hazardous waste and require
(Management, proper handling, storage and disposed only to authorize disposal facility
Handling and (registered recyclers/ re-processors) Being a bulk user, utilities shall
Transboundary comply with provision of said rules and obtain authorization for disposing
Movement) Rules, off their used transformer oil to authorised recycler.
2008
As a bulk user of transformer oil which is categorized as Hazardous Waste,
utilities shall comply with the provisions of the said rules if the practice of
storing of used oil is maintained. In case it is decided to outsource the
process of recycle of used oil to registered recycler as per the provisions of
notification then utilities (APTRANSCO / APSPDCL / APEPDCL) shall submit
the desired return in prescribed form to APPCB at the time of disposal of
used oil.
Biological Diversity This Act is not directly applicable to transmission projects because it deals
Act, 2002 with the conservation of biological diversity, sustainable use of its
components and fair and equitable sharing of the benefits arising out of
the use of biological resources, knowledge and for matters connected
therewith. Utilities (APTRANSCO/DISCOMS) must abide by the provision
of the Act in case any component of transmission line passes through any
of these wildlife protected area (national park/sanctuary), all necessary
precautions will be required for sheltering scheduled wildlife under the Act.
Page 137
Provisions/Law
Applicability
of Land/Rules
Wildlife Protection The Act inter-alia deals with prohibition of hunting of wild animals except
Act, 1972 in certain cases; protection of specified plants; declaration and protection
of sanctuaries; restrictions on entry in sanctuary; prohibition on destruction
in sanctuary except under a permit; declaration of national parks; power of
central government to declare as sanctuaries. The state of Andhra Pradesh
has several protected areas including 13 wildlife sanctuaries, 3 national
parks and one tiger reserve including Nagarjuna Sagar–Srisailam Tiger
Reserve (NSTR) which is the biggest tiger reserve of India.
Rights of Way In case of agricultural or private land the provisions of Section- 67 and or
(RoW) and Section-68 (5 & 6) of the Electricity Act, 2003 and Section-10 of the Indian
Compensation Telegraph Act, 1885 are followed for assessment and payment of
compensation towards such damages.
The Electricity Act, These Rules specify general safety requirements for construction,
2003 and Indian installation, protection, operation and maintenance of electricity supply
Electricity Rules, lines and apparatus.
1956 and 2005
International Conventions
Ramsar India has ratified Ramsar Convention, 1971 for protection of wetlands.
Convention, 1971 Kolleru Lake in Andhra Pradesh is identified Ramsar wetland and is added
to the list of protected wetlands in the year 2002. As understood during the
discussions with utilities, the proposed transmission and distribution
corridor is not expected to pass through the protected area and hence the
adverse impacts are not anticipated.
Basel Convention Basel Convention was signed by India in March 1990 and ratified in June
on the Control of 1992. The import and export norms of the hazardous waste have been
Trans-boundary provided in conformance with Basel Convention.
Movements of
No Trans-boundary movement of hazardous waste is proposed during any
Hazardous Wastes
stage of the project hence, it is not applicable.
and their Disposal
Page 138
World Bank Safeguard policies triggered and explanation
Environmental Yes The project will invest substantially in grid roll-out through
Assessment: the purchase of equipment including for MV-substations
(expansion of existing substations and new), MV/LV
OP/BP 4.01 transformers, MV and LV lines, household connections,
meters, and off-grid systems.
Page 139
Safeguard Policy Triggered
Explanation
Triggered (Y/N)
Natural Habitats Yes Significant impacts on natural habitats are not expected
OP/BP 4.04 since it is a linear project and also the footprint is limited
to small area only. However as specific subprojects and
their locations are yet to be determined further
information may be needed during implementation to
ascertain specific impacts. This ESMF provides specific
screening provisions to determine if natural habitats are
an issue, and what environmental instrument is needed if
the level of significance of the impacts is unknown. If the
impacts were to be considered significant, the Project will
not finance the particular subproject.
Forests OP/BP 4.36 Yes This policy is triggered as the Project is expected to pass
through some of the forest areas and have some impacts
on the health and quality of forests, or affect the rights
and welfare of people and their level of dependence
upon or interaction with forests, nor aims to bring about
changes in the management, protection or utilization of
natural forests or plantations. This ESMF provides for
screening investments to avoid impacting the health and
quality of forests.
Physical Cultural Yes Since specific project investments are not known, it is not
Resources possible to rule out the presence of physical cultural
OP/BP 4.11 resources. However, based on the initial discussions with
the utilities, the project is expected to pass through some
tourist and places of religious importance so the policy
will be triggered.
Safety of Dams No The project interventions are not expected to require the
OP/BP 4.37 construction of dams or impoundment structures, nor is
it expected that they could cause impacts to existing
structures as governed by this policy.
Page 140
9. Institutional Arrangements
The power sector in Andhra Pradesh comprises four key state owned enterprises to focus
on the core operation power generation – Andhra Pradesh Power Generation Corporation
Ltd. (APGENCO), power transmission, The Transmission Corporation of Andhra Pradesh
(APTRANSCO) and distribution (Southern Power Distribution Company of Andhra Pradesh
Ltd. (APSPDCL) and Eastern Power Distribution Company of Andhra Pradesh Ltd.
(APEPDCL). These are corporatized entities with their own boards. The state also has New
and Renewable Energy Development Corporation of Andhra Pradesh Ltd. (NREDCAP) to
promote renewable energy deployment in the state. Lastly, Andhra Pradesh Electricity
Regulatory Commission (APERC) provides the regulatory overview to the sector.
Generation Distribution
Regulation Transmission
(APGENCO) (APSPDCL &
(APERC) (APTRANSCO)
(NREDCAP) APEPDCL)
Additionally, the utilities coordinate with other administrative institutions, private players
and civil society organisations to manage the impacts. These institutional arrangements
for each utility are also provided below. These arrangements has been documented based
on consultations with the respective utilities:
9.1 APTRANSCO
A typical transmission project is commissioned after a Long Term Systems Study identifies
the need and a Feasibility Report is prepared by the Chief Engineer (CE) power systems.
Subsequently, a Field Feasibility report is prepared by the field staff (Executive Engineer
(EE), Assistant Divisional Engineer (ADE) and Divisional Engineer (DE)) which identifies the
load demand in their area of operation and a resource plan is prepared, which lists the
resources required to undertake the project. Based on these reports, the CE construction
prepares a scheme (project). The scheme is submitted for administration approval to a full
board (all directors and chairman). Once the scheme is approved, other relevant internal
approvals - the approval on BEE line, location for the substations, raw material required
etc. from CE (Civil), CE (Construction), CE (Telecom) and financial approval from Finance
Advisor & Chief Controller of accounts (FACCA) - are taken, following which tender is
Page 141
released for hiring a contractor to undertake the work. The EE oversees the work of the
contractor.
Once the contractor is selected and a purchase order is released, the approvals and
coordination is required with other external stakeholders like revenue department and
PTCC. The institutional arrangement to take these approvals is provided below:
After the purchase order is issued, the contractor conducts a check survey of every point.
The Revenue Officer is informed by the EE and Superintendent Engineer (SE) regarding
the land requirements and the route is published in the gazette, an English daily and a
Telugu daily. The public can raise grievances at this point.
Right of Way (RoW): The contractor and the AE approach the farmers and negotiate the
RoW. Currently, the RoW compensation is provided for base of the tower and not for the
corridor.
- In the Kadapa Zone (comprising of Ananthapur, Kadapa, Kurnool, Chittoor)
compensation for 132 kV towers is INR 55,000 per tower and for 220 kV towers
compensation is INR 99,500 per tower.
- In the Vishakhapatnam Zone:
o Vizanagaram, Visakhapatnam- compensation for 132 kV towers is INR 55,000
and for 220 kV towers compensation is INR 99,500 per tower
o Sirakulam, East Godavari, West Godavari- compensation for 132 kV towers is
INR 43,900 and for 220 kV compensation is INR 79,600 per tower
- In the Vijayawada Zone (comprising of Krishna, Guntur, Prakasham, Nellore)
compensation for 132 kV towers is INR 55,000 and for 220 kV towers compensation
is INR 99,500 per tower
Page 142
- Compensation for damage to crops is decided by the Agriculture Officer under the
Revenue Department
- The compensations are paid through the Revenue Department
Public consultations are undertaken in case of resistance from the community regarding
securing of land or the amount of compensation offered. The panchayats and local public
leaders may help in convincing the land owners.
In case of grievances, the affected people can raise their concerns through the Consumer
Grievance Redressal Forum (CGRF). If people are still not convinced by the solution
provided throught the CGRF, they can approach the courts for a judicial settlement.
During construction, police help is sought in case of any anticipated disruption to work
from the community.
Page 143
In cases the scheme is along or near any water channel like river, canal etc., approval from
Irrigation Department is required to certify the proposed scheme does not obstruct any
water ways.
APTRANSCO has established a corporate cell to implement the Environment and Social
Management Plans (ESMPs). The Environment and Social Management System (ESMS)
cell has following members:
1. SE/PM/400 kV/ APTRASNCO/VS/Hyderabad
2. SE/PM/Construction/APTRANSCO/VS/Hyderabad
3. EE/Civil/APTRANSCO/VS/Hyderabad
4. Concerned EE/Civil in field (covering the jurisdiction of the Transmission Project)
5. Concerned DE/Construction in Vidyutsoudha looking after the Transmission Project
The cell will also deal with redressal of grievances and requests for public information. The
implementation arrangements are summarised in the table below:
Page 144
Milestone Process Responsibility
Preparation Approval
Pre-Construction Phase
Formulation of Scheme Feasibility Report prepared in line with State CE Power Systems Technical Committee of
Level Long Term Systems Study APTRANSCO
Field Feasibility Report prepared to identify Field Staff (EE, AE, ADE) CE Power Systems
load demand in their area of operation
Resource plan prepared by Field Staff listing Field Staff (EE, AE, ADE) CE Construction
the resources required to undertake the
project
Preparation of Scheme including details of CE Construction Full Board – All Directors
land and other resources required and Chairman
Identify Sites for Detailed Survey carried out to determine route Field Staff (EE, AE, ADE) Environment and Social
Substations and line Route of the transmission line. As part of the survey Management Cell
social and environment assessment
undertaken to determine whether there are CE/Zone and SE OMC
any residential areas, schools / hospitals,
historical sites, scheduled areas, forest areas,
water bodies railway crossings, identification
of vulnerable population including SCs, STs,
marginal farmers and women
Three alternatives are determined and the
least problematic line is chosen
Securing Sites for the Approach the Revenue Department for Land CE, SE and DE Revenue Department
Project for substations
Identify Private Land in case Thasildar certifies CE, SE and DE Full Board of
no government land is available APTRANSCO
In case of involuntary acquisition of private Refer to Annexure 8 for details
land is unavoidable, the provisions of the
RFCTLARRA, 2013 will be triggered:
Identify Sites for Detailed Survey carried out to determine route Field Staff (EE, AE, ADE) Environment and Social
Substations and line Route of the transmission line. As part of the survey Management Cell
social and environment assessment
undertaken to determine whether there are CE/Zone and SE OMC
any residential areas, schools / hospitals,
Page 145
historical sites, scheduled areas, forest areas,
water bodies railway crossinggs etc.
Three alternatives are determined and the
least problematic line is chosen
Contracting Prepare cost estimates for the Schemes EE APTRANSCP HQ
- CE Civil for civil
works
- CE Telecom for
telecommunication
- ESMS cell (for
environment and
social safeguards)
Consolidate estimates CE Construction Finance Advisor and
Chief Controller (FACCA)
Prepare tender documents with the technical EE CE Construction
and financial specifications
Construction Phase
Transfer of Land Contractor conducts a check survey to finalize Contractor EE
the sites
Revenue officer informed about land EE SE
requirements
Route details are disclosed through EE SE
publication in the AP Gazette, an English Daily
and a Telugu Daily
The public can raise grievances in case of AE / ADE DE
issues with land securing ESMS Cell
Securing RoW Approach farmers for RoW AE & Contractor SE OMC and EE
Construction
Give RoW compensation for tower footing as Revenue Department
per District Collector’s directions
Compensation for Land Compensation for government land is MRO District Collector
determined
Compensation for private land is determined Negotiating Committee CE Construction
(Govt. Representative,
State Board Officer,
Page 146
Local DE, Evaluator from
Private Party)
Compensation for crop damage determined Agriculture Officer under
Revenue Department
Grievance Redressal Public consultations are undertaken in case of AE & Contractor SE OMC and EE
resistance Construction
Negotiations regarding compensation AE & Contractor SE OMC and EE
Construction
In case affected persons have grievances even CGRF CMD
after the public consultations, they can raise ESMS Cell
their concerns through CGRF
Approvals from other Help from police department is sought in case AE/ADE SE OMC and EE
Departments of anticipated disruptions to traffic Construction
Topographical map of the project area is EE SE OMC and EE
prepared. The map also identifies the railway, Construction
telecom and defence crossings.
Determine the fault levels for 132 kV APTRANSCO Head PTCC
Quarter
Determine fault levels for 220kV lines PTCC PTCC
Approvals from appropriate departments PTCC Appropriate Department
(BSNL, Railway and Defence) (BSNL, Railway and
Defence)
Chief conservator of forest is informed if any CE Construction Principal Chief
forest area is required Conservator of Forest
Secure 2 times the forest land as a District Collector Full board of
compensation APTRANSCO
Page 147
The process to implement the ESMF is provided below:
Project Identification
Project Approvals
Project Implementation
Page 148
9.2 APSPDCL/APEPDCL
The impacts of a distribution project are similar in nature to those of transmission projects.
However, as transmission substations and towers require more area then distribution
substations and poles; and as transmission lines carry very high voltage, the impacts
created by transmission projects are more critical than those created by the distribution
projects. The institutional arrangements to manage the impacts created by distribution
projects are as follows:
Securing Land:
- In urban areas, the land is provided by Municipal Corporation
- The land allotted should not change the land use pattern in the city. For instance,
courts do not allow land allotted for parks to be used for setting-up substations.
- The District Collector can permit construction anywhere other than on forest land
and reserved areas
- Community consultations are undertaken in case transformers and lines are
situated close to houses / shops.
- Residential complexes usually have space for transformer installation in their floor
plan
- For setting-up transformers in commercial area, alternative sites are identified in
consultation with the people
- A negotiating committee consisting of a Govt. Representative, State Board Officer,
Local DE and a valuator from a private party is constituted to negotiate price for
securing private property
Transformers are fenced or insulated to prevent the accidents. Caution boards are put
up at appropriate location to avoid accidents
The ADE Construction and the DE construction coordinate with the municipal
corporation while digging for under-ground cabling to ensure that underground
drainage systems are not damaged
The ADE Construction and the DE construction coordinate with the police department to
regulate traffic during construction
The Superintending Engineer/Operations submits the design to the local railway
authority for approval in case Railway crossings are in or around the route of the
distribution line
Filed Staff (AE/ADE) negotiate for RoW and clearance between conductor and trees
Handling sick transformers:
− AE/Operations and ADE/operations identify and inspect the sick unit on field and
prepare a preliminary report.
− The sick unit along with the preliminary report is sent to the Special Maintenance
Unit, where the transformer is further inspected to determine the cause of the fault
Page 149
− In case, the unit cannot be repaired an estimate is prepared and sent to corporate
office of DISCOMS, where a committee of 5 to 6 officers is formed to supervise the
scraping of the transformer including removal of waste oil, scrapping of aluminum
and copper coil and scrapping of iron in the body of the transformer
− The oil is stored in sealed drums and all scrap, including oil, is devoluted to
DISCOMS stores, where the scraps are stored until auction to registered recyclers.
SPDCL and EPDCL have identified an Environment and Social Management member to
manage the potential social and environmental impacts from the proposed projects.
SPDCL: SE/Civil
EPDCL: EE/Civil
Page 150
10. Grievance Redressal Mechanism
Grievance Redressal Mechanism
The grievance redressal mechanism (GRM) provides the procedure to address/resolve the
concerns and grievances of people affected by the projects. All the three utilities have three
systematic and robust mechanism for addressing the grievances. The formal arrangements
existing for DISCOMS is quite exhaustive as the framework rests on consultative
mechanisms involving officials as well non-official representation:
APSPDCL/APEPDCL
Informal mechanisms to resolve grievances are described below:
Any person with grievance can visit the local office of the utility for redressal. The DE is
the main officer to handle any complaints.
Awareness camps are held in villages to inform about the new initiatives of the utilities
like the proposed project to replace existing irrigation pump sets with the energy-
efficient pump sets. People can raise their complaints during these camps.
SPDCL and EPDCL also have a formal framework in place to address the grievances. The
key mechanisms available are described below:
Substation Advisory Committee
District Electrical Coordination Committee
Meet the CMD
Online registration of complaints
Registering complaints at a Toll-Free number
Grievance Redressal in Scheduled Areas
Grievance Redressal Forum
Judicial intervention
Page 151
Meet the CMD - Spandana
Consumer meetings are held at the corporate office of SPDCL (in Tirupati) and EPDCL (in
Vishakhapatnam) every Monday from 9:30 AM onwards. Consumers/public with
grievances can personally meet the CMD and other senior officials of SPDCL and EPDCL.
Apart from consumers, contractors can also participate in ‘Spandana’
Page 152
If any issues are identified by the consumer, s/he can register a complaint with call
center of the utility or on the website.
The complaint must be mentioned in detail on a white paper along with the
following:--Contact details of the complainant (viz., address, cell phone details) and
Registration of support documents
Complaint
Acknowledgement receipt is issued for every complaint registered.
In case consumer receives inadequate/no response for the complaint filed, s/he can
approach the Consumer Grievance Redressal Forum (CGRF) referring to the
acknowledgement receipt number.
CGRF provides a complaint copy to the utility for comments within five days.
Grievance Redressal Utility has to provide comments on the CGRF intimation within ten days.
Forum If case of no reply from utility, the forum proceeds on the basis of the material
available on record.
CGRF intimates hearing date to all parties in writing.
CGRF members record and document their opinion as evidence at forum office.
Consumer may represent the case through an advocate or qualified person of his/her
choice duly at the hearing (after authorizing him/her).
Decision of the Forum Decision of CGRF is recorded in writing and communicated to the complainant and
the utility for compliance within 45 days from the date of receipt of complaint.
Judicial Intervention
In case the grievances are not resolved at the utility level. The people can approach the
judicial authority and file a court case against the utilities.
APTRANSCO
APTRANSCO’s ROG mechanisms are bit different as they have very little to interact with
the consumers directly. Their interface is chiefly with the people on whose lands towers/
corridors are laid, contractors, labourers, and other departments and utilities. Currently, the
arrangements are as follows:
People with grievances can approach local Divisional Engineer (DE). He is the main
officer to handle any complaints at the local offices.
Page 153
At the corporate office, ED Planning and HRD is the nodal officer for Grievance Redressal
in APTRANSCO. He is supported by Additional Secretary, APTRANSCO. In case any
grievance is not satisfactorily handled at the DE level, it gets escalated to the corporate
office. For the World Bank Projects, the ESMS cell will support the DE in resolving any
project related grievances before escalation to ED Planning and HRD. Towards enabling
this support, the following supplementary measures are planned: (i) online registration
of complaints; (ii) registration of complaints on toll free numbers; (iii) receipt of
grievances through sub-station advisory as well as district electrical coordination
committees; (iv) receipt of grievances through ITDAs in schedule areas; and (v)
Spandana viz., regional meetings with the CMD.
Judicial Intervention
In case the grievances are not resolved at the utility level. The people can approach the
judicial authority and file a court case against the utilities.
Immediate Action
Complainant Local Divisional Engineer
Not addressed
Court of Law
Page 154
APTRANSCO
The mechanism for grievance redressal is provided below:
People with grievances can approach local Divisional Engineer (DE). He is the main
officer to handle any complaints at the local offices.
At the corporate office, ED Planning and HRD is the nodal officer for Grievance Redressal
in APTRANSCO. He is supported by Additional Secretary, APTRANSCO. In case any
grievance is not satisfactorily handled at the DE level, it gets escalated to the corporate
office.
For the World Bank Projects, the ESMS cell will support the DE in resolving any project
related grievances before escalation to ED Planning and HRD.
Judicial Intervention
In case the grievances are not resolved at the utility level. The people can approach the
judicial authority and file a court case against the utilities.
Immediate Action
Complainant Local Divisional Engineer
Not addressed
Court of Law
Page 155
11. Monitoring Plan
This section details out the plan to monitor the implementation of social impact
management and mitigation measures and grievance redressal mechanism.
The ESMS cell of the APTRASNCO and the environment and social member of the project
team for Discoms has overall responsibility for achieving the environmental and social
performance. They will be responsible for monitoring the ESMF, including monitoring the
implementation of the ESMF and subsequent preparation, implementation and monitoring
of environmental and social safeguards for the sub-projects.
The environmental and social monitoring plan for each project will be integrated with
construction, operation and maintenance and shall be monitored by the ESMS
cell/designated environment and social member on a monthly basis.
The Environment and Social Member (Discoms) and the field staff (Concerned EE/Civil in
field - covering the jurisdiction of the Transmission Project, Concerned DE/Construction in
Vidyut Soudha, looking after the Transmission Project) of ESMS cell (APTRANSCO) will
also perform supervision site visits during the construction and operations phases of the
sub-projects to confirm that environmental and social safeguards are being effectively
implemented, and status of the same will be reported periodically in the site visit reports.
Participation of PAPs in the monitoring will also be ensured through regular consultation
and their active participation. Major monitoring indicator identified for regular monitoring
of activities will be carried out by different department at field and will be reviewed by the
designated officer (ESMS cell or designated environment and social member) on monthly
basis.
The quarterly and annual reports on the key steps, outputs and results of the environmental
and social management actions taken to support the implementation of the ESMF and the
sub-projects will be prepared. The Environment and Social Member (corporate members
of ESMS cell (SE / PM / 400 kV / APTRASNCO / VS / Hyderabad, SE / PM / Construction /
APTRANSCO / VS / Hyderabad, EE / Civil / APTRANSCO /VS / Hyderabad) will track the
overall status and any shortcomings in the implementation of the ESMF and of any
circumstances or occurrences that could adversely impact the environmental and social
performance of the project beyond the already anticipated impacts.
Page 156
Monitoring plan for a subproject
The primary objective of monitoring is to verify the absence of or record environmental
and social impacts resulting from the subproject activities and to ensure compliance with
the "mitigation measures" identified earlier under the ESIA/ESMP/RAP/TPPF/GAP in order
to prevent or reduce adverse impacts and enhance positive impacts from project activities.
Page 157
& alignment and
design
Consultation Once CE Zone or SE √ √
with local OMC
authorities/ (APTRANSCO)
autonomous DE Construction
councils and (Discoms)
land owners on
location of
overhead line
towers/poles/
laying of
underground
distribution line
& alignment and
design
Payment of Quarterly till Concerned EE √
damages / process is Civil in the field
compensation completed (covering
jurisdiction of
APTRANSCO
project) (also a
member of
ESMS cell)
DE Construction
(Discoms)
Following table provides the general environmental parameters to be monitored during the
construction phase of the sub-projects.
Page 158
Guidelines for social monitoring during construction phase
Activity / Issues Parameter to be Measurement & Monitoring Applicability
monitored frequency Responsibility T* D*
Laying of Discovery of Quarterly Concerned EE √ √
underground cultural property Civil in the field
cables or lines Approval from (covering
near heritage / Department of jurisdiction of
tourist sites Archaeology APTRANSCO
and Museums, project) (also a
Andhra Pradesh member of
ESMS cell)
DE Construction
(Discoms) under
supervision of
Environment
and Social
member
Construction of Presence of Daily for safety Concerned EE √ √
substation and documented equipment Civil in the field
laying of lines health & safety Weekly for other (covering
protocols measures jurisdiction of
Safety manger APTRANSCO
present at site project) (also a
during member of
construction ESMS cell)
Use of safety Construction
equipment by contractor & DE
workers Construction
Presence of (Discoms)
signboards at
appropriate
locations
Adequate
sanitation /
safety standards
at camps
Signboards / Weekly for Concerned EE √ √
instructions are signboards Civil in the field
displayed at Monthly for (covering
appropriate compensation jurisdiction of
places APTRANSCO
Use of insulated project) (also a
wires in member of
congested areas ESMS cell)
Compensation is Construction
paid contractor & DE
Page 159
Construction
(Discoms)
Page 160
Guidelines for environmental monitoring during construction phase
Parameter Frequency Responsibility
Storage and disposal of used Provision of a covered shed with Construction contractor
oil impervious floor for storage of waste under the guidance of
oil containers respective Social and
Monitoring once a week during the Environment Member
construction period, as and when
needed
Visual monitoring of drainage Weekly Construction contractor
congestion within around Monthly under the guidance of
subproject location respective Social and
Environment Member
Visual monitoring of traffic Daily basis as and when needed Construction contractor
within around sub project under the guidance of
location respective Social and
Environment Member
Monitoring and surveillance Once a week Construction contractor
for prevention of fire hazard under the guidance of
respective Social and
Environment Member
Page 161
on the type of subproject, the anticipated impacts and the field situation, and will
have to be determined during preparation of the ESMP.
Page 162
Water Pollution Once in 6 months, Testing equipment, Results to be reported
and as directed by the Monitoring team to Utility
Field Engineer
Soil / water During routine Visual inspection Results to be reported
contamination due to maintenance to Utility
spillage / leakage of
hazardous chemicals
and oil
Page 163
12. Training and Capacity Building
Training and development of employees is an integral part for implementation of ESMF
and ESMP. Training needs identification has been carried out at corporate and field level,
based on which focused training modules are suggested for:
Strengthening in-house corporate level capacity and the capacities of the field
offices to implement the provision of ESMP.
Creating Awareness, providing the tools for implementation of Environmental and
Social Policy, and accompanying set of management procedure
ESMS cell (for APTRANSCO), environment and social member (for EPDCL and SPDCL)
and Field office are key stakeholders identified for implementation of ESMPs. The training
programs, identified in the table below, are to be conducted with the help of local or
national training institutions and experts in various aspects of environmental and social
management.
Page 164
13. Cost and Budget
The costs incurred to implement the various requirements of the ESMF are budgeted and
adequate financial provisions are required to meet the management measures to be
undertaken to mitigate the impacts as underlined in this ESMF document. The tentative
cost estimates for environmental and social management are provided below:
Construction phase
*Note: Our conservative estimate will be max 10 samples per scheme i.e a longitudinal
Transmission line laying project including receiving station.
Page 165
Trainings will be held at
offices of respective
utility so no venue cost
Assuming INR 60,000
for logistics including
travel and food for
participants
Assuming INR 24000 for
travel cost for resource
person
Total: 24,01,16,000
Page 166
Assuming INR 24000
for travel cost for
resource person
Total: 10,76,000
Page 167
14. Consultations and Disclousre
Consultations
The draft ESMF that was created through these consultations was then shared with the
World Bank whose inputs further strengthened the framework. Details of consultations are
provided below:
Page 168
7 4th Aug* East Godavari Tribals 10
*Planned
Broadly the following points emerged from the consultations:
Page 169
Women land right owners confirmed that the
amount of compensation was transferred to their
bank account.
Respondents are not aware of the GRM
mechanism. They usually approach the lineman in
case of any problem.
Disclosure
The final draft of the ESMF, RPF, TPPF and GAP were disclosed on the websites of the three
utilities, i.e. APTRANSCO, APEPDCL and APSPDCL for the information of the general
public. Following the online publication of the documents, each utility held a public
disclosure workshop to solicit the feedback / comments / recommendations of key
stakeholders including: other government departments, academic institutes, NGOs and
community based organisations, media, and members of the general public.
During these workshops, the utilities informed the participants of the different components
of the World Bank supported schemes, the potential social and environmental impact that
these schemes may have, and the proposed management and mitigation measures that
will be put in place. This was followed by a detailed presentation on the ESMF, RPF, TPPF
and GAP documents. The floor was then thrown open for the participants to ask questions
and provide their feedback on the documents. This feedback was documented and the
relevant comments / suggestions have been incorporated into this ESMF document. The
subsequent tables provide information regarding the workshops held, the main points
raised and the response / action taken to address these points; the complete minutes of all
three disclosure workshops can be found in Annexure 11.
Details of Disclosure Workshops Held
S.No. Utility Location Date No. of Participants
1. APEPDCL Eluru 19.08.2016 --
2. APSPDCL Tirupati 29.08.2016 81
3. APTRANSCO Vijayawada 03.09.2016 67
Page 170
Summary of Key Discussion Points from Disclosure Workshops
S.No. Query / Comment / Feedback Response / Action Taken
Discussions regarding Distribution Projects
The utilities said that this option will be
Under the HVDS works, if proposed
examined. Further the ESMF recommends
lines are to pass through tree
1. avoiding such plantations where possible
plantations such as oil palm fields
and that utilities are to minimize damage /
should be shifted to adjacent roads
inconvenience caused by the proposed works
Under the HVDS works, where it is not
The utilities said that this option of covered
possible to avoid tree plantations,
conductors will be examined and that that
2. insulated conductors may be used to
old conductors will be replaced wherever
avoid accidents. Also old conductors
necessary
should be replaced to avoid accidents
Existing single phase 15 KVA
transformers for agricultural services The utilities responded that single phase
3.
should be converted to HVDS in order to transformers will also be converted to HVDS
limit power supply to 7 hours
Under the HVDS works, AB switches are
The utilities confirmed that under the World
required so that line faults can be
4. Bank supported works AB switches have
rectified during the 7 hours when three
been proposed
phase power is available
The utilities stated that the required
Under the smart meter scheme, care precautions would be taken and that e-waste
should be taken of the e-waste will be disposed through MSTC by e-auction.
5.
generated in the process of replacing The ESMF has been updated to include
electronic meter with smart meters management of e-waste in the environmental
impacts and mitigation measures chapter.
The utilities responded that in the majority of
the cases government lands are being
Where new substations are being
selected for substations. In the unlikely
constructed, if land is procured from
chance that private land is procured, the rate
6. private parties rate should be paid at
will be determined as per government policy
market rate as the government rate is
and employment on contract basis will be
very low
provided to any one of the family members
of land owners.
Discussions regarding Transmission Projects
Compensation for diminution of land
7.
value should be paid for RoW corridor
APTRANSCO clarified that the compensation
100% of land value should be
8. rates are determined by the Revenue
compensated for tower footing
Department as per prevailing government
Higher compensation should be paid for
rules and policies and that the utility has no
crop damage. This should be calculated
9. role to play in calculating the compensation.
based on the per square yard market
value of the crop rather than the current
Page 171
S.No. Query / Comment / Feedback Response / Action Taken
practice of considering market value per
acre of crop
Compensation should be based on the
location of the project area; higher
10. compensation should be paid for
locations closer to urban centers relative
to those in rural areas
The ESMF already recommends careful route
While designing the route plan,
alignment to avoid settlements wherever
APTRANSCO should consider the
possible. APTRANSCO coordinates with a
11. layouts approved by the Revenue
number of other governmebt departments
Department so as to avoid any areas
including the Revenue Department while
with any planned construction
selecting the most appropriate route
The final ESMF, RPF, TPPF and GAP will be disclosed to the general public as well. The
following mechanisms are suggested for disclosure:
Page 172
Annexure 1 – Definitions
The definitions provided below are as per Chapter 1 Section 3 of the Right to Fair
Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act,
2013 (RFCTLARRA 2013).
An officer appointed for the purpose of rehabilitation and resettlement of
Administrator
affected families under sub-section 1 of section 43 of the RFCTLARRA 2013
Such area as may be notified by the Appropriate Government for the purposes
Affected Area
of land acquisition
Includes:
(i) A family whose land or other immovable property has been acquired;
(ii) A family which does not own any land but a member or members of
such family may be agricultural labourers, tenants including any form of
tenancy or holding of usufruct right, share-croppers or artisans who
may be working in the affected area for three years prior to the
acquisition of the land, whose primary source of livelihood stand
affected by the acquisition of land’
(iii) The Scheduled Tribes and other traditional forest dwellers who have
lost any of their forest rights recognized under the Scheduled Tribes
and Other Traditional Forest Dwellers (Recognition of Forest Rights) Act,
Affected
2006 due to acquisition of land;
Family
(iv) Family whose primary source of livelihood for three years prior to the
acquisition of the land is dependent on forests or water bodies and
includes gatherers of forest produce, hunters, fisher folk and boatmen
and such livelihood is affected due to acquisition of land;
(v) A member of the family who has been assigned land by the State
Government or the Central Government under any of its schemes and
such land is under acquisition;
(vi) A family residing on any land in the urban areas for preceding three
years or more prior to the acquisition of the land or whose primary
source of livelihood for three years prior to the acquisition of the land is
affected by the acquisition of such land
Means:
(i) In relation to acquisition of land situated within the territory of a State,
the State Government;
(ii) In relation to acquisition of land for public purpose in more than one
Appropriate
State, the Central Government, in consultation with the concerned State
Government
Governments or Union territories;
Provided that in respect of a public purpose in a District for an area not
exceeding such as may be notified by the Appropriate Government, the
Collector of such District shall be deemed to be the Appropriate Government
Means the Collector of a revenue district, and includes District Commissioner
Collector and any officer specially designated by the Appropriate Government to
perform the function of a Collector under the RFCTLARRA 2013
Page 173
Means the Commissioner for Rehabilitation and Resettlement appointed under
Commissioner
sub-section (1) of section 44 of the RFCTLARRA 2013
Includes:
(i) Amount of compensation which includes solatium, any enhanced
compensation ordered by the Land Acquisition and Rehabilitation and
Resettlement Authority or the Court and interest payable thereon and
any other amount determined as payable to the affected families by
such Authority or Court;
(ii) Demurrage to be paid for damages caused to the land and standing
corps in the process of acquisition
(iii) Cost of acquisition of land and building for settlement of displaced or
adversely affected families;
Cost of (iv) Cost of development of infrastructure and amenities at the resettlement
Acquisition areas;
(v) Cost of rehabilitation and resettlement as determined in accordance
with the provisions of the RFCTLARRA 2013
(vi) Administrative cost for (a) acquisition of land, including both in the
project site and out of the project area lands, not exceeding such
percentage of the cost of compensation as may be specified by the
Appropriate Government; and (b) rehabilitation and resettlement of
owners of the land and other affected families whose land has been
acquired or proposed to be acquired or other families affected by such
acquisition;
(vii) Cost of undertaking Social Impact Assessment Study
Displaced Means any family, who on account of acquisition of land has to be relocated
Family and resettled form an affected area to the resettlement area
Includes a person, his or her spouse, minor children, minor brothers and
Family minor sisters depended on him: provided that widows, divorces and women
deserted by families shall be considered separate families
Holding of Means the total land held by a person as an owner, occupant or tenant or
Land otherwise
Includes benefits to arise out of land, and things attached to the ear or
Land
permanently fastened to anything attached to the earth
Means such persons or class of persons who may be:
(i) Considered or specified as such under any State law for the time being
Landless in force; or
(ii) In a case of landless not being specified as above, as may be specified
by the Appropriate Government
Page 174
Includes any person:
(i) Whose name is recorded as the owner of the land or building or part
thereof, in the records of the authority concerned; or
(ii) Any person who is granted forest rights under the Scheduled Tribes and
Other Traditional Forest Dwellers (Recognition of Forest Rights) Act,
Land Owner
2006 or under any other aw for the time being in force; or
(iii) Who is entitled to be granted Patta rights on the land under any law of
the State including assigned lands; or
(iv) Any person who has been declared as such by an order of the court or
Authority
Includes a town planning authority (by whatever name called) set up under
Local
any law for the time being in force, a Panchayat as defined in article 243 and a
Authority
Municipality as defined in article 243P of the Constitution
Means the value of land determined in accordance with section 26 of the
Market Value
RFCTLARRA 2013
Means:
(i) All persons claiming an interest in compensation to be made on
account of the acquisition of land under the RFCTLARRA 2013
(ii) The Scheduled Tribe and other traditional forest dwellers, who have lost
any forest rights recognized under the Scheduled Tribes and Other
Person
Traditional Forest Dwellers (Recognition of Forest Rights) Act, 2006;
Interested
(iii) A person interested in an easement affecting the land;
(iv) Persons having tenancy rights under the relevant State laws including
share-croppers by whatever name they may be called; and
(v) Any person whose primary source of livelihood is likely to be adversely
affected;
Means a company, a body corporate, an institution, or any other organisation
or person form whom land is to be acquired by the Appropriate Government,
and includes the Appropriate Government, if the acquisition of land is for such
Requiring
Government either for its own use or for subsequent transfer of such land is
Body
for public purpose to a company, body corporate, an institution, or any other
organisation, as the case may be, under lease, licence or through any other
mode of transfer of land
Resettlement Means an area where the affected families who have been displaced as a
Area result of land acquisition are resettled by the Appropriate Government
Scheduled Means the Scheduled Areas as defined in section 2 of the Provision of the
Areas Panchayats (Extension to the Scheduled Areas) Act, 1996.
Page 175
Annexure 2 – SIA Process
The process of carrying out the SIA is provided for in Section 10 of the A.P. RFCTLARRR
2014. The process is as follows:
(1) The SIA team shall collect and analyse a range of quantitative and qualitative data,
undertake detailed site visits, use participatory methods such as focused group
discussions, participatory rural appraisal techniques and informant interviews in preparing
the Social Impact Assessment report.
(2) All relevant project reports and feasibility studies shall be made available to the SIA
team throughout the SIA process, as required. Any request for information from SIA team
shall be met at the earliest but not exceeding seven days. The District Collector shall be
responsible for providing the information requisitioned by the SIA team.
(3) A detailed assessment based on a thorough analysis of all relevant land records and
data, field verification, review and comparison with similar projects shall be conducted by
the SIA team. The assessment shall determine the following, namely:-
(a) Area of impact under the proposed project, including both land to be acquired and
areas that will be affected by environmental, social or other impacts of the project;
(b) Area and location of land proposed to be acquired for the project;
(c) The land proposed for acquisition is the bare minimum required;
(d) Possible alternative sites for the project and their feasibility;
(e) Whether the land proposed for acquisition is irrigated multi-cropped land and if so,
whether the acquisition is a demonstrable last resort;
(f) Land, if any, already purchased, alienated, leased or acquired, and the intended use
for each plot of land required for the project;
(g) The possibility of use of any public, unutilised land for the project and whether any
of such land is under occupation;
(h) Nature of the land, present use and classification of land and if it is an agricultural
land, the irrigation coverage for the said land and the cropping pattern;
(i) The special provisions with respect to food security have been adhered to in the
proposed land acquisition;
(j) Size of holdings, ownership patterns, land distribution, number of residential
houses, and public and private infrastructure and assets; and
(k) Land prices and recent changes in ownership, transfer and use of lands over the last
three years.
(4) Based on the land assessment, land records and field verification, the SIA team shall
provide an accurate estimate of the number of affected families and the number of
displaced families among them and ensure that, as far as possible, all affected families are
enumerated:
Provided that where enumeration is not possible, a representative sample shall be done.
Page 176
(5) A socio-economic and cultural profile of the affected area must be prepared, based on
available data and statistics, field visits and consultations as per FORM-III:
Provided that in projects where resettlement is required, the identified resettlement sites
shall be visited and a brief socio-economic profile of the land and its current resident
population shall be indicated.
(6) Based on the data collected in processes listed above and in consultation with the
affected communities and key stakeholders, the SIA team shall identify and assess the
nature, extent and intensity of the positive and negative social impacts associated with the
proposed project and land acquisition as per FORM-III.
(7) The SIA process includes the preparation of a Social Impact Management Plan (SIMP),
which will present the ameliorative measures to be undertaken to address the social
impacts identified in the course of the assessment. The SIA team must assess the viability
of impact mitigation and management strategies with clear indication of costs, timelines
and capacities. The Social Impact Management Plan(SIMP) shall include the following
measures-
(a) That have been specified in the terms of Rehabilitation and Resettlement and
compensation for all the categories of affected families as outlined in the Act;
(b) That the Requiring Body has stated that it will undertake in the project proposal and
other relevant project documents; and
(c) That additional measures being undertaken by the Requiring Body, which have been
undertaken by it in response to the findings of the SIA process and public hearings.
(8) The SIA team must provide a conclusive assessment of the balance and distribution of
the adverse social impacts and social costs and benefits of the proposed project and land
acquisition, including the mitigation measures, and provide an assessment as to whether
the benefits from the proposed project exceed the social costs and adverse social impacts
that are likely to be experienced by the affected families or even after the proposed
mitigation measures, the affected families remained at risk of being economically or
socially worse, as a result of the said land acquisition and resettlement.
Page 177
Annexure 3 – Structure of SIA
The structure provided below is as per Form III in the Annexure to the Andhra Pradesh Right
to Fair Compensation and Transparency in Land Acquisition, Rehabilitation & Resettlement Rules 2014.
2. Poverty levels
Vulnerable groups - Women, children, the elderly, women-headed households,
the differently abled
Kinship patterns and women's role in the family
Social and cultural organisation
Administrative organisation
Political organisation
Civil society organisations and social movements
Page 178
Co-operatives and other livelihood-related associations
II. Part-B: Key impact areas Impacts on land, livelihoods and income
− Level and type of employment Intra-household employment patterns Income
levels
− Food security
− Standard of living
− Access and control over productive resources
− Economic dependency or vulnerability
− Disruption of local economy
− Impoverishment risks
− Women's access to livelihood alternatives
3. Health impacts
Health impacts due to in-migration
Health impacts due to project activities with a special emphasis on
Impact on women's health
Impact on the elderly
Page 179
Impacts on the norms, beliefs, values and cultural life
Crime and illicit activities
Stress of dislocation
Impact of separation of family cohesion
Violence against women
Construction phase
Displacement and relocation
Influx of migrant construction workforce
Health impacts on those who continue to live close to the construction site
6. Operation phase
Reduction in employment opportunities compared to the construction phase
Economic benefits of the project
Benefits on new infrastructure
New patterns of social organisation
7. De-commissioning phase
Loss of economic opportunities
Environmental degradation and its impact on livelihoods
9. Differential impacts
Impact on women, children, the elderly and the different abled
Impacts identified through tools such as Gender Impact Assessment
Checklists, and Vulnerability and Resilience Mapping
Page 180
10. Cumulative impacts
Measureable and potential impacts of other projects in the area along with the
identified impacts for the project in question.
Impact on those not directly in the project area but based locally or even
regionally.
III. PART-C. Table of Contents for SIA Report and Social Impact Management Plan
Chapter Contents
1. Executive Summary - Project and public purpose Location
- Size and attributes of land acquisition
- Alternatives considered
- Social Impacts
- Mitigation measures
- Assessment of social costs and benefits
2. Detailed Project - Background of the project, including developers
Description background and governance/ management structure,
- Rationale for project including how the project fits the
public purpose criteria listed in the Act
- Examination of alternatives
- Phases of project construction
- Core design features and size and type of facilities
- Need for ancillary infrastructural facilities
- Work force requirements (temporary and permanent)
- Details of SIA/EIA if already conducted and any technical
feasibility reports
- Applicable legislations and policies
3. Team Composition, - List of all team members with qualifications. Gender experts
Approach, Methodology to be included in team
and Schedule of SIA - Description and rationale for the methodology and tools
used to collect information for the SIA
- Sampling methodology used
- Overview of information/data sources used. Detailed
reference must be included separately in the forms
- Schedule of consultations with key stakeholders and brief
description of public hearings conducted. Details of the
public hearings and the specific feedback incorporated into
the Report must be included in the forms
4. Land Assessment - Describe with the help of the maps, information from land
inventories and primary sources
- Entire area of impact under the influence of the project (not
limited to land area for acquisition)
- Total land requirement for the project
- Present use of any public, unutilised land in the vicinity of
the project area
- Land (if any) already purchased, alienated, leased or
acquired, and the intended use for each plot of land
required for the project
- Quantity and location of land proposed to be acquired for
the project
Page 181
Chapter Contents
- Nature, present use and classification of land and if
agricultural rand, irrigation coverage and cropping patterns
- Size of holdings, ownership patterns, land distribution, and
number of residential houses
- Land prices and recent changes in ownership, transfer and
use of lands over the last 3 years
5. Estimation and - Estimation of the following types of families that are (where
Enumeration required) of affected (a) Directly affected (own land that is
proposed to be Families and assets acquired):
- Are tenants/occupy the land proposed to be acquired
- The Scheduled Tribes and other traditional forest dwellers
who have lost any of their forest rights
- Depend on common property resources which will be
affected due to acquisition of land for their livelihood
- Have been assigned land by the State Government or the
Central Government under any of its schemes and such
land is under acquisition;
- Have been residing on any land in the urban areas for
preceding three years or more prior to the acquisition of the
land
- Have depended on the land being acquired as a primary
source of livelihood for three years prior to the acquisition
(b) Indirectly impacted by the project (not affected directly
by the acquisition of own lands) (c) Inventory of productive
assets and significant lands
6. Socio-economic and Profile - Demographic details of the population in the project area
(affected area and - Income and poverty levels
resettlement area) - Vulnerable groups
- Land use and livelihood
- Local economic activities
- Factors that contribute to local livelihoods
- Kinship patterns and social and cultural organisation
- Administrative organization
- Political organisation
- Community-based and civil society-organisations
- Regional dynamics and historical change processes
- Quality of the living environment
7. Social Impacts - Framework and approach to identifying impacts
- Description of impacts at various stages of the project cycle
such as impacts on health and livelihoods and culture. For
each type of impact, separate indication of whether it is a
direct / indirect impact, differential impacts on different
categories of affected families and where applicable
cumulative impacts
- Indicative list of impacts areas include: impacts on land,
livelihoods and income, physical resources, private assets,
public services and utilities, health, culture and social
cohesion and gender based impacts
Page 182
Chapter Contents
8. Analysis of Costs and - Final conclusions on: assessment of public benefits
Recommendation on purpose, less-displacing alternatives minimum on
Acquisition requirements of land, the nature and intensity of social
impacts, the viability of the mitigation measures and the
extent to which mitigation measures described in the SIMP
will address the full range of social impacts and adverse
social costs.
- The above analysis will use the equity principle as a criteria
of analysis for presenting a final recommendation on
whether the acquisition should go through or not
9. References and Forms - For reference and further information
The structure provided below is as per Form IV in the Annexure to the Andhra Pradesh Right
to Fair Compensation and Transparency in Land Acquisition, Rehabilitation & Resettlement Rules 2014.
a) Approach to mitigation
b) Measures to avoid, mitigate and compensate impact
c) Measures that are included in the terms of R&R and compensation as outlined in the
Act
d) Measures that the Requiring Body has stated it will introduce in the Project Proposal
e) Additional measures that the Requiring Body has stated it will undertake in response
to the findings of the SIA process and public hearings
f) The SIMP must include a description of institutional structures and key person
responsible for each mitigation measure and timelines and costs for each activity
Page 183
Annexure 4 – EIA Process
Power transmission and distribution projects do not require an EIA/ Environmental
Clearance as per the EIA notification, 2009 by Ministry of Environment and Forests (MoEF),
Govt. of India (GoI). However, these sub-projects requires Environmental Assessment as
per World Bank’s OP 4.01: Environment Assessment. The consolidated Environmental
Impact Assessment Report is prepared with a basic objective to collate and analyze the
addressal of environmental impacts and environmental management measures. The report
also covers the project compliance with environmental regulations of Government of India
(GoI) and the environmental safeguards requirements of the World Bank.
The EIA team reviews the available documents and assesses the compliance of the
subproject with the respect (i) regulatory clearances (like environmental clearance, forest
clearance, CRZ clearance etc.); (ii) applicable operational policies of WB (iii) analysis of
alternatives; (iv) identifying environmental impacts and integration of environmental
management measures; (v) public consultations and information disclosure etc. The EIA
process involves a number of steps, which are listed below;
Page 184
to contaminants/pollutants and the impact on rare and endangered species,
endemic species, and migratory path/route of animals are to be assessed.
c) The prediction of impacts: This step aims to identify the likely magnitude of the
change (i.e., impact) in the environment when the project is implemented in
comparison with the situation when the project is not carried out.
d) Mitigation: This involves the introduction of measures to avoid, reduce, remedy or
compensate for any significant adverse impacts.
e) A mitigation plan supplemented with an environmental management plan (EMP)
shall be drawn up for the selected option to guide the proponent towards
environmental improvements.
Page 185
Annexure 5 – Sample SMP
An illustrative Social Management Plan is presented below:
Typical “general impacts” during “pre-construction phase” and corresponding mitigation measures for transmission and distribution
projects.
Activity / Potential Applicability Proposed Mitigation and Parameter to be Measurement Monitoring Implementation
Issues Impacts T* D* Enhancement Measures monitored & Responsibility Schedule
frequency
Securing Loss of √ In case of land acquisition: SIA process Monthly ESMS Cell On filing of land
land for land, assets − The land should be carried out until requisition by
substation and obtained as per the completed utility
s income; provisions of the
Change in RFCTLARRA, 2013 and
social the APRFCTLARRR, 2014. Distribution Monthly ESMS Cell Prior to start of
status − An SIA should be of until substation
Social conducted and an Expert compensatio completed construction
Inequities Group established to n /
evaluate the same. entitlements
−A Rehabilitation & for land
Resettlement Scheme has Implementat Quarterly State Prior to start of
to be drafted in ion of R&R until Monitoring substation
accordance with the Scheme completed Committee construction
Resettlement Policy
Framework.
− Compensation and Consultation Once ESMS Cell Prior to start of
entitlements should be with local substation
paid as per the provisions authorities/ construction
of the RFCTLARRA, 2013 autonomous
− Careful route selection to councils and
avoid existing land owners
settlements and sensitive
locations
Page 186
Careful selection of site to
avoid existing settlements
and sensitive locations
Careful selection of site to
avoid encroachment of
socially, culturally and
archaeological sensitive
areas (e.g. sacred groves,
graveyards, religious
worship place, monuments
etc.)
Ensure women receive
compensation for land in
cases where land rights are
with women
Location Social √ √ Careful route selection to Consultation Once CE Zone or At time of
of inequities avoid existing settlements with local SE OMC detailed survey
overhead and sensitive locations authorities/ (APTRANS for route
line Ensure women receive autonomous CO) alignment
towers/pol compensation for RoW, councils and DE
es/ and damage to crops, trees land owners Constructio
etc. in cases where land on location n
laying of
rights are with women of overhead (Discoms)
undergrou
line
nd
towers/poles
distributio
/ laying of
n line & undergroun
alignment d
and distribution
design line &
alignment
and design
Damage to √ √ Careful selection of site Consultation Once CE Zone or At time of
socially / and route alignment to with local SE OMC detailed survey
Page 187
culturally avoid encroachment of authorities/ (APTRANS for route
sensitive socially, culturally and autonomous CO) alignment
and archaeological sensitive councils and DE
historical areas (e.g. sacred groves, land owners Constructio
sites graveyards, religious on location n
worship place, monuments of overhead (Discoms)
etc.) line
towers/poles
/ laying of
undergroun
d
distribution
line &
alignment
and design
Loss of √ Use existing tower or Payment of Quarterly Concerned Prior to the start
agricultural footings wherever damages / till process EE Civil in of construction
production/ possible. compensatio is the field
change in Avoid sitting new towers n completed (covering
cropping on farmland wherever jurisdiction
pattern possible of
Payment for damages APTRANSC
during construction and O project)
compensation for tower (also a
footing member of
ESMS cell)
Interferenc √ Proposed projects which PTCC Once PTCC At time of
e with involve lines over 132kV to Approval detailed survey
communica get approval from Power & for route
tion Telecommunication alignment
channel Coordination Committee
(PTCC) before commission
Page 188
Typical “general impacts” during “construction phase” and corresponding mitigation measures for transmission and distribution projects.
Page 189
exposure to Construction camps should Use of safety member of
magnetic have adequate sanitation / equipment ESMS cell)
fields safety facilities by workers Constructio
Safety equipment should Presence of n
be provided to workers signboards contractor
Signboarding of hazardous at & DE
areas / materials should be appropriate Constructio
done locations n
Adequate (Discoms)
sanitation /
safety
standards at
camps
Impact on √ √ Display danger signs at Signboards / Weekly for Concerned During
community appropriate locations instructions signboards EE Civil in Construction
health and Display boards with are Monthly the field
safety due precautions to be adopted displayed at for (covering
to exposure by consumers, owners, appropriate compensat jurisdiction
to electric occupiers, electrical places ion of
currents, contractors, electric Use of APTRANSC
hazardous workmen and suppliers insulated O project)
materials, Display of instructions for wires in (also a
electromag resuscitation of persons congested member of
netic fields suffering from electric areas ESMS cell)
etc. shock. Compensati Constructio
Use of insulated wires in on is paid n
highly congested contractor
residential areas & DE
Compensation is paid to Constructio
non-departmental persons n
in the case of fatal (Discoms)
accidents due to
electrocution.
Page 190
Safety and √ √ Construction sites are Site is Weekly Concerned During
security properly lit adequately EE Civil in construction
concerns of Minimize blockage of lit at night the field
women and access roads Access (covering
other roads are jurisdiction
population usable of
around the APTRANSC
constructio O project)
n site (also a
member of
ESMS cell)
Constructio
n
contractor
& DE
Constructio
n
(Discoms)
Violation of √ √ Contractor should follow Labour laws Monthly Concerned During
labour labour standards as per are being EE Civil in Construction
standards applicable laws such as followed the field
minimum wages, equal Welfare (covering
pay for equal work, no child facilities are jurisdiction
labour etc. available of
Provision of welfare APTRANSC
measures such as O project)
canteens, first aid facilities, (also a
housing accommodation member of
for workers near the work ESMS cell)
place etc. DE
Constructio
n
(Discoms)
Page 191
Typical “general impacts” during “operation and maintenance phase” and corresponding mitigation measures for transmission and
distribution projects.
Operation Impact on √ √ Safety equipment should Use of safety Weekly Concerned During running
and worker be provided to workers equipment EE Civil in of the substation
maintenan health and Sign boarding of by workers the field
ce of safety – hazardous areas / materials Presence of (covering
substation possibility should be done signboards jurisdiction
s and of Careful design at of
electrocutio Safety awareness appropriate APTRANSC
maintenan
n, falling Emergency planning locations O project)
ce of lines
from Sanitation and medical Adequate (also a
height, and facilities sanitation / member of
exposure to safety ESMS cell)
magnetic standards DE
fields Operations
(Discoms)
Impact on √ √ Display danger signs at Signboards / Weekly for Concerned During running
community appropriate locations instructions signboards EE Civil in of the substation
health and Display boards with are Monthly the field
safety due precautions to be adopted displayed at for (covering
to exposure by consumers, owners, appropriate compensat jurisdiction
to electric occupiers, electrical places ion of
current contractors, electric Compensati APTRANSC
workmen and suppliers on is paid O project)
Display of instructions for (also a
resuscitation of persons member of
suffering from electric ESMS cell)
shock. DE
Compensation is paid to Operations
non-departmental persons (Discoms)
in the case of fatal
accidents due to
electrocution.
Page 192
Annexure 6 – Compensation plan for Temporary
Damages
Unlike in case of substations, for the construction of transmission towers / distribution
poles and the transmission / distributions lines, ownership of the land remains with the
existing owner and is not transferred to the requesting body. The Electricity Act 2003,
provides utilities with powers under the Telegraph Act 1885 which in turn states that land
for the lines and poles (towers) will not be acquired. The utility will have the right of user
only in the property under, over, along, across in or upon which the lines and poles / towers
are placed.
Further affected families will receive compensation for temporary damage as well as for
the land under the tower footing. Thus the compensations are made for following:
Land under the tower footing
Damage to trees
Damage to crops
Damage to constructed structure
Pre-Construction Phase
Identify Sites Detailed Survey carried out Field Staff (EE, AE, Environment and
for to determine route of the ADE) Social Management
Substations transmission line. As part of Cell
and line Route the survey social and
environment assessment CE/Zone and SE OMC
undertaken to determine
whether there are any
residential areas, schools /
hospitals, historical sites,
scheduled areas, forest
areas, water bodies railway
crossings, identification of
vulnerable population
including SCs, STs,
marginal farmers and
women, extent of
temporary damage to
crops, trees, structures etc.
Three alternatives are
determined and the least
problematic line is chosen
Contracting Prepare cost estimates for EE APTRANSCP HQ
the Schemes - CE Civil for civil
works
Page 193
- CE Telecom for
telecommunication
- ESMS cell (for
environment and
social safeguards)
Consolidate estimates CE Construction Finance Advisor and
Chief Controller
(FACCA)
Prepare tender documents EE CE Construction
with the technical and
financial specifications
Construction Phase
Securing RoW Approach farmers for RoW AE & Contractor SE OMC and EE
Construction
Give RoW compensation for Revenue Department
tower footing as per District
Collector’s directions
RoW compensation for Revenue Department
damage to constructed
Structure
Grievance Public consultations are AE & Contractor SE OMC and EE
Redressal undertaken in case of Construction
resistance
Negotiations regarding AE & Contractor SE OMC and EE
compensation Construction
In case affected persons CGRF CMD
have grievances even after ESMS Cell
the public consultations,
they can raise their
concerns through CGRF
Page 194
o Vizanagaram, Visakhapatnam- compensation for 132 kV towers is INR
55,000 and for 220 kV towers compensation is INR 99,500 per tower
o Sirakulam, East Godavari, West Godavari- compensation for 132 kV towers is
INR 43,900 and for 220 kV compensation is INR 79,600 per tower
− In the Vijayawada Zone (comprising of Krishna, Guntur, Prakasham, Nellore)
compensation for 132 kV towers is INR 55,000 and for 220 kV towers compensation
is INR 99,500 per tower
As of now, RoW compensation is not paid for corridor. Govt. of AP and APTRANSCO
are yet to decide on payment of RoW compensation for corridor.
APEPDCL/APSPDCL
The assessment of temporary damages are undertaken during pre-construction stage when
probable location of poles and route of the distribution line are being decided. As the
location of poles is flexible, efforts are made to avoid the damages to public and private
property. In cases, where damages are unavoidable following mechanism is used:
- Community consultations are undertaken in case transformers and lines are situated
close to houses / shops to assess the damages. The consultations are undertaken by
ADE Construction and the DE construction
- The ADE Construction and the DE construction coordinate with respective authority
– Municipal Corporation or revenue department for calculating compensation and
payment of damages.
- The assessment of damage and calculation and payment of compensation is
supervised by the environment and social member of the project implementation
unit.
Preparation of CPTD
The outline of CPTD is provided below:
Project Description: Description of project context and background, benefits of the
project and objective of compensation plan
Project Impacts: Highlight the anticipates positive and negative impacts of the project
including the expected temporary damages due to the project activities
Compensation Framework: Description of compensation plan and procedure for
tree/crop compensation
Stakeholder Participation and Consulations: Public consulations undertaken during
preconstruction activities and details of planned consultations during construction
phase
Institutional Arrangements for Implementation and Monitoring: Describe the
implemenation schedule, monitoring mechanism, grievance redressal mechanism and
budgetary allocations.
Page 195
Annexure 7 – Tribal People Planning Framework
As a part of the project preparation a number of analytical studies on environment and
social aspects are conducted, including with a focus on any potential impacts on the tribal
population as has also been detailed out in OP 4.10, of the World Bank. These studies
include (some of them are on-going):
a screening survey to identify whether tribal people are present in or have collective
attachment to the tentative list of sub-project areas already identified
an environment and social impact assessment for a sub-set of schemes identified and
resultant Environment and Social Management Plans
Preparation of Environment and Social Management Framework
Preparation of a Tribal Peoples Planning Framework
During the course of social screening and social assessment, if any tribal people are
identified, the impacts (both positive and negative) of the subproject component on the
affected communities/groups will be addressed as per this framework. This framework sets
out:
The types of programs and subprojects likely to be proposed for financing under the
project
A plan for carrying out the screening and social assessment for such projects
Page 196
Socio-economic profile and baseline
The potential positive and adverse effects of such programs or subprojects on tribal
people
A framework for ensuring free, prior, and informed consultation with the affected tribal
communities at each stage of project preparation and implementation
Institutional arrangements (including capacity building where necessary) for screening
project supported activities, evaluating their effects on tribals, preparing Tribal People
Plan (TPP), and addressing any grievances.
Monitoring and reporting arrangements, including mechanisms and benchmarks
appropriate to the project
Disclosure arrangements for TPPs to be prepared under the TPPF
The term ‘Scheduled Tribe’ is defined in Article 366 (25) of Indian constitution as, “such
tribes or tribal communities or parts of or groups within such tribes or tribal communities
as are deemed under Article 342 to be Scheduled Tribes for the purposes of this
Constitution".
Article 342 prescribes the procedure to be followed in the matter of specification of
Scheduled Tribes. The criterion followed for specification of a community as a Scheduled
Tribe, as per Ministry of Tribal Affairs, Government of India, are:
Indications of primitive traits
Distinctive Culture
Geographical isolation
Shyness of contact with the community at large, and
Backwardness
Scheduled Areas
The Scheduled Areas are established in the country under the Article 244 and 5th Schedule
of the Indian Constitution. Certain special provisions for the administration of these areas
have been provided with the key objective to provide protection to the tribals living in the
Scheduled Areas from alienation of their lands and natural resources to non-tribals.
Page 197
Need for TPPF
Initial screening has indicated that some of the sub-project will be undertaken in districts
in Andhra Pradesh that have scheduled tribes. However, the exact sub-projects, their exact
location and hence, the exact nature of impacts thereof, is yet to be determined. Thus, at
this stage of project preparation, a Tribal People Planning Framework (TPPF) is being
prepared which shall form the basis of preparation of Tribal People Plan (TPP), once the
sub-projects are identified and if the presence of tribal people impacted by the project is
ascertained in the sub-project areas. The content sheet for TPP is provided below:
Socio-Economic Profile
Andhra Pradesh (AP) is the 10th largest state in India with a population of 4.94 Cr (4.08% of
India’s population) and a population density of 304 persons per Sq. Km. There are 126.65
lakh households in the State and the average size of the household is 3.95. AP is largely
rural with 70.42% of the population living in rural areas and 29.58% living in urban areas.
Of the total population Scheduled Cates (SC) constitute 17.10% and Scheduled Tribes (ST)
5.33%. Prakasam is the district with the highest SC population (7.88 lakh) while
Vizianagaram has the lowest (2.47 lakh). Visakhapatnam is the district with the largest
concentration of STs with 14.42% of the total ST population, while Kurnool with 2.04% has
the lowest concentration.
20
Land holding among scheduled tribes is very less compared to other caste and ethnic groups. Scheduled
tribes use public land and forest land. Therefore, details on the land tenure and usage pattern has to be
collected in order to measure the dependency of Scheduled Tribes on the land.
Page 198
The growth rate of population has slowed from 11.89% in 2001 to 9.21% in 2011 while the
sex ratio rose from 983 in 2001 to 997 in 2011 (as per census data). In absolute terms, 2.47
Cr (50.1%) of the total population is male and 2.46 Cr (49.9%) female. The districts of
Visakhapatnam, East Godavari, West Godavari and Guntur, have registered a progressive
sex ratio moving from less than 1000 category to more than 1000 from 2001 to 2011. The
SCs and STs have registered a sex ratio of 1007 and 1009 respectively. However, despite
the overall improvement in sex ratio, there was a troubling decline in child sex ratio from
964 in 2001 to 944 in 2011 (census data).
Literacy Rate in the state has increased and was 67.35% as per the 2011 population census
as against 62.07% in the 2001 census; however this is still lower than India’s overall literacy
rate, which was 72.98% in 2011. The literacy rate is much higher for urban areas (79.2%)
than rural areas (62.4%). Also, while male literacy is 74.8%, female literacy is only 59.96%.
Among the districts West Godavari has the highest literacy (74.63% in 2011), while
Vizianagaram has the lowest (58.89% in 2011).
District-wise Demographic Data
According to the Socio Economic and Caste Census 2011, there are 13 districts in the State of
Andhra Pradesh, 670 tehsils, 14,514 gram panchayats/police stations. The total number of villages
in Andhra Pradesh are 17,521 and additionally there are 94 towns. The number of rural households
is 93.44 lakh (76.15%) and urban households is 29.26 lakh (23.85%). The district with the highest
density of population is Krishna district (518), while Kadapa district has the lowest density (118).
District wise demographic data is provided below:
District wise Demographic Data
Page 199
Scheduled tribes form 5.53 % (Census 2011) of Andhra Pradesh’s total population. Out of
the total scheduled tribes in Andhra Pradesh, approximately 50% reside in four districts
Vishakhapatnam (23%), East Godavari (11%), Nellore (10%) and Vizianagaram (9%). The
district-wise distribution of scheduled tribes is provided below:
Scheduled Tribe Population in Andhra Pradesh per district
The list of notified Scheduled Tribes in Andhra Pradesh under the Scheduled Castes and
Scheduled Tribes Orders (Amendment) Act are provided below:
Scheduled Tribes of Andhra Pradesh
Page 200
6 Gond, Naikpod, Rajgond, Koitur 23 Nayaks
7 Goudu 24 Pardhan
8 Hill Reddis 25 Proja, Parangiperja
9 Jatapus 26 Reddidora
10 Kammara 27 Rona, Rena
11 Kattunayakan 28 Savaras, Kapu Savaras, Maliya Savaras,
Khutto Savaras
12 Kolam 29 Sugalis. Lambadis, Banjara
13 Konda Dhoras, Kubi 30 Valmiki
14 Konda Kapus 31 Yenadis, Chella Yenadi, Kappala
Yenadi, Manchi Yenadi, Reddi Yenadi
15 Kondareddis 32 Yerukulas, Koracha, Dabba Yeukula,
Kunchapuri Yeukula, Uppu Yeukula
16 Kondhs, Kodi, Kodhu, Desaya Kondhs, 33 Nakkala, Kurvukaran
Dongria Kondhs, Kuttiya Kondhs, Tikiria
Kondhs, Yenity Kondhs, Kuvinga
17 Kotia, Bentho Oriya, Bartika, Dulia, 34 Dhulia
Holva, Sanrona, Sidhopaiko
Source: Census 2011
Further, tribal dominated areas in Andhra Pradesh have been declared as “Scheduled
Areas” as specified by the fifth schedule of the constitution. The list of Scheduled Areas in
Andhra Pradesh is provided below21:
Visakhapatnam Agency area (excluding the areas comprised in the villages of Agency
Lakshmipuram, Chidikada, Konkasingi, Kumarapuram, Krishnadevipeta,
Pichigantikothagudem, Golugondapeta, Gunupudi, Gummudukonda,
Sarabhupalapatnam, Vadurupalli, Pedajaggampeta)
Sarabhupathi Agraharam, Ramachandrarajupeta Agraharam, and Kondavatipudi
Agraharam in Visakhapatnam district.
East Godwari Agency area (excluding the area comprised in the village of
Ramachandrapuram including its hamlet Purushothapatnam in the East Godavari
district)
West Godawari Agency area in West Godavari district.
Data includes the Submergence of Sch. Villages of 7 mandals from Khamman district
to AP State (as per Reorganization Act, 2014):
Nellipapaka, Kunavaram, Chintoor and V.R.Puram in East Godavari district and
Burgampad, Kukunoor and Valaipadu in West Godavari district.
Scheduled Tribes are amongst the most marginalized and vulnerable segments of the
society. Literacy rate among the males and females among Scheduled Tribes at the state
level is respectively 47.66% and 26.11%. The aggregate percentage of literacy rate for
schedule tribes is around 37% which is significantly lower than literacy rate of 67.35% at
the state level. The STs have registered a sex ratio of 1009 which is higher than the state
21
http://aptribes.gov.in/pdfs/table9.pdf
Page 201
average (997). Therefore, this document has been developed to manage and mitigate the
possible project impacts to the Scheduled Tribes. The next section provides the objectives
of this document.
As discussed earlier, this TPPF would be applicable only for the project interventions that
may be undertaken in the scheduled areas and may impact the tribal populations.
Objectives of TPPF
The objectives of the TPPF are to ensure that if indigenous peoples22 (referred to as tribal
in India) are affected by a project/scheme, they:
i. are adequately and fully consulted;
ii. receive benefits and compensation equal to that of the mainstream population:
iii. are provided with special assistance as per laws and policies because of their
vulnerabilities vis-à-vis the mainstream population; and
iv. receive adequate protection against project adverse impacts on their culture
identities.
There are several policies which provide a legal framework for ensuring dedicate attention
to the tribals. The relevant policies are provided in the section below.
5th Schedule of Provides for the administration and control For sub-projects
Constitution of Scheduled Areas and Scheduled Tribes. (transmission lines and
(Article 244) towers) passing through
Article 244(1) and Article 244 (2) of the
Scheduled Areas
constitution of India enables the
government to enact separate laws for
governance and administration of the tribal
areas. In pursuance of these articles,
President of India had asked each of the
state to identify tribal dominated areas.
Areas thus identified by the states were
declared as Fifth schedule areas
22
Indigenous People (IP) referred as tribal in India are the distinct groups identified based on their social, cultural,
economic, and political traditions and institutions, which are distinct from the mainstream or dominant society and
culture. Tribal with similar cultural characteristics are known as ‘Adivasi’ in Hindi and are recognized as Schedule
Tribes (STs) as per the Indian Constitution.
As per OP-4.10 definition these are Members of a distinct indigenous cultural group, Collective attachment to
geographically distinct habitats or ancestral territories in the project area and to the natural resources in these
habitats and territories, Customary cultural, economic, social, or political institutions that are separate from those
of the dominant society or culture, An indigenous language, often different from the official language of the
country or region
Page 202
73rd Amendment of Enables participation of Panchayat level For any sub-project located
Constitution, 1992 institutions in decision-making and in panchayat area
supporting preparation and implementation
of development schemes.
Panchayats The provisions of PESA Act extends the For approval of any sub-
(Extension to provisions of Part IX of constitution relating project located in
Scheduled Areas) to Panchayats to the Scheduled Areas. As Scheduled Areas
Act, 1996 per the provisions, every village in Schedule
V areas will have Gram Sabha which would
approve of the plans, programmes and
projects for social and economic
development before such plans,
programmes and projects are taken up for
implementation at village level.
The Scheduled The act recognizes and vests the forest For sub-projects
Tribes and Other rights and occupation in forest land in forest (transmission lines and
Traditional Forest dwelling Scheduled Tribes and other towers) passing through
Dwellers traditional forest dwellers who has been forest land
(Recognition of residing in such forests for generations but
Forest Rights) Act, whose rights could not be recorded. The act
2006 provides a framework for recording forest
rights so vested and the nature of evidence
required for such recognition and vesting in
respect of forest land.
Andhra Pradesh These rules have been notified by the In cases of involuntary
Right to Fair Government of Andhra Pradesh in exercise acquisition of land
Compensation and of the powers conferred by Section 109 of
Transparency in the RFCTLARRA, 2013.
Land Acquisition,
As per Chapter V Sections 25, 26 and 27 of
Rehabilitation and
the Andhra Pradesh Rules, awards and
Resettlement
compensations are in line with the
Rules, 2014
provisions of the RFCTLARRA, 2013. Section
28, further specifies the following that were
to be notified by the State Government:
Page 203
areas other than scheduled areas and
1.50 for scheduled (tribal) areas
The one-time grant to artisan, small
traders and certain others is set at INR
25,000
The payment of compensation shall be
made expeditiously through account
payee cheques / electronic mail transfer
In addition, to the National and state laws, bank financed projects should also comply with
World Bank Operational Policies. The World Bank Policy on indigenous people (IP) is
provided below:
Applicable World Bank Operational Policies
OP 4.10: The policy aims to protect the dignity, right and cultural uniqueness of
Indigenous indigenous people, to ensure that they do not suffer due to development and
People that they receive social and economic benefits.
Applicability The policy is triggered if there are indigenous /tribal people in the project area,
potential adverse impacts on indigenous people are anticipated and if
indigenous people are among the intended beneficiaries.
OP 4.12: This policy covers direct economic and social impacts that both result from
Involuntary Bank-assisted investment projects, and are caused by the involuntary taking of
Resettlement land. To avoid or minimize involuntary resettlement and, where this is not
feasible, assist displaced persons in improving or at least restoring their
livelihoods and standards of living in real terms relative to pre-displacement
levels or to levels prevailing prior to the beginning of project implementation,
whichever is higher.
Applicability The policy is triggered if there is involuntary acquisition of land for project
activities
Thus adequate provisions exists in the country to address the issues related to tribals.
Potential Impacts
The most important component of the TPPF is to lay down a mechanism to assess the type
and magnitude of impacts, both positive and negative on the tribal communities. The
assessment of impacts on tribal population in the projects shall focus on the probable
Page 204
consequences of the project according to specific criteria / indicators. The indicators are
provided below:
Changes in access to natural resources (such as forest, grazing land, weekly markets,
etc.)
Loss of land due to project activities
Increase or decrease in the number of job opportunities through wage labour within or
outside agriculture
Change in employment and income generating opportunities in agriculture, trades,
services and business
Threat to tribal community rights, institutions, values and way of life
Increased or decreased access to social infrastructure and public services such as
sources of water, health facilities, schools, etc.
Reduction in political power and increased marginalization
Change in farming methods, cropping pattern, crop yield, income, expenditure pattern,
etc.
Negative Impacts:
Loss of land: There is loss of land during setting up substations. The land requirement
for setting-up substation:
Voltage Land required Sub-station25
Note: The land for the proposed investments in APTRANSCO (132/33 kV and 220/33 kV
substations) has been secured either from the Discoms where they have provided extra land
available in their existing substations to APTRANSCO or government land has been identified. The
status of sites for the proposed 12 substations as on 5th May 2016 is provided below:
Method of securing land No. of substations
23
http://www.cea.nic.in/reports/monthly/dpd_div_rep/village_electrification.pdf
24
www.ap.gov.in/wp-content/uploads/2016/01/12-AP-Households.pdf
25
Reference manuals on construction and operational practices of EHV substations & lines and commercial
and load dispatch operations. Available at: http://www.aptransco.gov.in/transco/images/APTRANSCO-
Technical-reference-book-2011-vol-ii.pdf
Page 205
Extra land available in existing substations 4
No involuntary acquisition is expected for securing land and the projects are not expected to result
in any physical or economic displacement of people.
The land required for distribution substation is comparatively small and will be secured either
through transfer of government land or purchase of land on willing-buyer willing-seller basis
Restricted use of land and RoW: The ownership of land is not transferred to the utilities
for construction of transmission towers / distribution poles and laying of power lines.
The utility will have the right of user only in the property under, over, along, across in
or upon which the lines and poles / towers are placed. Further, the construction of the
tower may restrict the use of land under the tower footing for transmission towers. For
distribution projects a pole is erected and there is no restriction on land use.
In addition, the MoEF provides guidelines for maintaining a Right of Way (RoW) corridor
which shall be kept clear of any obstruction. The width of the RoW corridor depends on
the voltage of the lines as depicted in the table below:
However, the impact on environment is minimal as trees are cut or pruned to the extent
required for preventing electrical hazards by maintaining the following limited
clearances:
Voltage Minimum clearance between
conductor and trees (in meters)
132 kV 4.0
33 kV 2.8
11 kV 2.6
Note: RoW requirements are very low for 33 kV and 11 kV lines. Generally, there is no need to cut
trees for electrical clearances. Furthermore, in urban areas, the lines will be laid along the roads or
the streets to minimize RoW issues.
Page 206
Change in land use: The land use pattern will change due to project activities, for
instance, the proposed site for the substation or tower footing might be used for farming
or might have trees.
Impact Mitigation
Securing land
Land is required for construction of transmission and distribution substations and erecting
transmission towers and distribution poles. Land secured for construction of substations is
no longer accessible to the existing owner and hence in such cases ownership is transferred
from the existing owner to the respective utility. There are four ways in which land can be
secured; these are:
(vi) Transfer of Government land to utility
(vii) Voluntary donation
(viii) Purchase of land on willing buyer and willing seller basis on negotiated price
(ix) Involuntary acquisition of land
In order to avoid the loss of private / community lands or agriculture and forest lands, the
transmission and distribution utilities will endeavor, wherever possible, to secure
Government land for their projects and avoid private or community lands, even if this
requires realignment of the proposed route. Only in rare cases that Government land is not
available will other methods of securing land be pursued. Further, only the minimal amount
of land required for substations will be allotted. The following steps are to be followed
depending on the method of securing land:
(v) Transfer of Government land: The Andhra Pradesh Land Allotment Policy (G.O. Ms.
No. 571 issued 14.09.2012) prescribes that only waste lands will be allotted and
environmentally sensitive / fragile areas such as tank beds, river, beds, hillocks with
afforestation shall not be allotted. Similarly, lands assigned to poor people for
agriculture purpose should not be resumed for other purposes, and if it is
unavoidable then the assignees should be provided with alternate land in addition to
rehabilitation. In all cases, a NOC from the Urban Local Body, Urban Development
Authority, or Department for Town and Country Planning (DT&CP) is required before
any allotment is made. The allotted land may be given free of cost or on payment
basis. When land is allotted on payment basis, the cost of the land will be determined
as per market value recommended by the Collector and the A.P. Land Management
Authority (APLMA). APLMA will also ensure that only the minimum amount of land
needed is allotted and the allotted land is used only for the stated purpose.
(vi) Voluntary donation: In the case of voluntary donation of land, there should not be
any undue pressure on the land owner / user(s) to transfer ownership of their land.
Apart from this following shall also be ensured:
a. The donation will not cause significant impacts on the livelihood of the donor
b. The donor fully understands the value of their donated land
Page 207
c. The donation will not cause any economical or physical displacement of the
current land users
d. The land donations does not come from coercion or asymmetrical power
relation between the land owner and the government
e. The land in question must be free of squatters, encroachers, or other claims or
encumbrances.
f. Verification of the voluntary nature of land donations must be obtained from
each of the persons donating land.
g. In case of any loss of income or physical displacement is envisaged, verification
of voluntary acceptance of mitigation measures must be obtained from those
expected to be adversely affected.
h. Subsequently title of land shall be transferred in the name of the utility.
(vii) Purchase of land on willing buyer and willing seller basis on negotiated price:
When land is purchased from a willing seller, the utility shall ensure:
a. Consultation with the affected person has to be carried out and documented.
b. All negotiations have to be carried out in a transparent manner
c. That land owners are aware of the basis on which compensation is calculated
d. The land in question must be free of squatters, encroachers, or other claims or
encumbrances.
e. Subsequently title of land shall be transferred in the name of the utility.
(viii) Involuntary acquisition of land: Involuntary acquisition of land will be the last
resort and be undertaken only in the case of non-availability of Government lands
in the area. In the case of involuntary acquisition, the provisions of RFCTLARRA,
2013 and the A.P. RFCTLARRR, 2014 shall be applicable. The land acquisition and
resettlement policy is provided in the section below.
Page 208
supply and health care facilities. The SIA agency shall also prepare a Social Impact
Management Plan (SIMP) listing ameliorative measures required for addressing the likely
impact vis-à-vis intended benefit of the project. The SIA report and SIMP shall be subject
to public hearing in the affected area after giving adequate publicity for the venue, time etc
to ascertain the views of affected families/communities which shall be included in the SIA.
The final SIA report shall be published including its translation in local language and shall
also be made available to Panchyats, District/Village Councils & Deputy Collector/District
Magistrate office for wider circulation. Detailing of the same is provided below:
i. the prior consent of the concerned Gram Sabha or the Panchayats at the appropriate
level in Scheduled Areas under the Fifth Schedule to the Constitution, shall be
obtained in all cases of land acquisition in such areas, before issue of a notification
under this Act, or any other Central Act or a State Act for the time being in force.
ii. Provided that the consent of the Panchayats shall be obtained in cases where the
Gram Sabha does not exist or has not been constituted.
iii. In the case of a project involving land acquisition on behalf of a Requiring Body
which involves involuntary displacement of the Scheduled Tribes, a Tribal People
Development Plan (TPDP) shall be prepared in such a form as may be prescribed.
Laying down the details of procedure for settling land rights due, but not settled and
restoring titles of the Scheduled Tribes on the alienated land by undertaking a
special drive together with land acquisition.
iv. TPDP also contain a program for development of alternate fuel, fodder and non-
timber forest produce resources on non-forest lands within a period of five years
sufficient to meet the requirements of tribal communities.
v. In the case of land being acquired from the members of the Scheduled Tribes, at
least one-third of the compensation amount due shall be paid to the affected families
initially as first instalment and the rest shall be paid after taking over of the
possession of the land.
vi. The affected families of' the Scheduled Tribes shall be resettled preferably in the
same Scheduled Area in a compact block so that they can retain their ethnic,
linguistic and cultural identity.
vii. The resettlement areas predominantly inhabited by the Scheduled Tribes shall get
land, to such extent as may be decided by the appropriate Government free of cost
for community and social gatherings.
viii. Any alienation of tribal lands or lands belonging to members of the Scheduled
Tribes in disregard of the laws and regulations for the time being in force shall be
treated as Null and void. In the case of acquisition of such lands, the rehabilitation
and resettlement benefits shall be made available to the original tribal land owners
ix. The affected Scheduled Tribes having fishing rights in a river or pond or dam in the
affected area shall be given fishing rights in the reservoir area of the irrigation or
hydel projects.
Page 209
x. Where the affected families belonging to the Scheduled Tribes are relocated outside
of the district, then they shall be paid an additional 25% rehabilitation and
resettlement benefits to which they are entitled in monetary terms along with a
onetime entitlement of Rs. 50,000/-.
xi. All benefits, including the reservation benefits available to the Scheduled Tribes in
the affected areas shall continue in the resettlement area.
xii. Whenever the affected families belonging to the Scheduled Tribes who are residing
in the Scheduled Areas referred to in the Fifth Schedule to the Constitution are
relocated outside those areas, than, all the statutory safeguards. entitlements and
benefits being enjoyed by them under this Act shall be extended to the area to which
they are resettled regardless of whether the resettlement area is a scheduled Area
referred to in the said Fifth Schedule or not.
xiii. Where the community rights have been settled under the provisions of the
Scheduled 'tribes and Other Traditional Forest Dwellers (Recognition of Forest
Rights) Act, 2006. The same shall be quantified in monetary amount and be paid to
the individual conceded who has been displaced.
Page 210
Families, a Development Plan
shall be prepared laying down
the details of procedure for
settling land rights due but not
settled and restoring titles of
the scheduled Tribes as well as
the Scheduled Castes on the
alienated land by undertaking a
special drive together with land
acquisition
b) The Development Plan shall
also contain a programme for
development of alternate fuel,
fodder and non-timber forest
produce resources on non-
forest lands within a period of
five years sufficient to meet
the requirements of tribal
communities as well as the
Scheduled Castes.
Public hearing for Social Impact
Assessment (when prepared
under section-4 of the act)
2 Appraisal of SIA SIA report is evaluated by an
by expert group independent multi-disciplinary
Expert Group, as may be
constituted by appropriate
Govt.
Recommendations of the
expert group made available to
the local bodies and in the
affected areas in local language
The appropriate govt. would
recommend the such area for
acquisition after examining the
expert group report (and report
from the collector if any)
3 Publication of Notification (hereinafter ln case of acquisition or
preliminary referred to as preliminary alienation of any land in the
notification notification) to that effect along Scheduled Areas, the prior
with details of the land to be consent of the concerned Gram
acquired in rural and urban Sabha or the Panchayats or the
areas shall be published ITDA, at the appropriate level in
(Notification to be issued within Scheduled Areas under the
12 months from DoA of SIA) Fifth Schedule to the
Constitution, as the case may
be, shall be obtained. In all
cases of land acquisition in
such areas, including
acquisition in case of urgency,
before issue of a notification
under this Act, or any other
Page 211
Central Act or a State Act for
the time being in force.
Immediately after issuance of
the notification, the concerned
Gram Sabhas at the village
level, municipalities in case of
municipal areas and the ITDA
in case of the areas referred to
in the Fifth Schedule to the
Constitution, shall be informed
of the contents of the
notification issued under the
said sub-section in all cases of
land acquisition at a meeting
called especially for this
purpose.
After issuance of notice, the
Collector shall, before the issue
of a declaration under section
19, undertake and complete the
exercise of updating of land
records as prescribed within a
period of two months.
Preliminary survey of land
Payment for damage (if any)
during survey
4. Preparation of Upon the publication of the
Rehabilitation preliminary notification by the
And Resettlement Collector, the Administrator for
Scheme by the Rehabilitation and
Administrator Resettlement shall conduct a
survey and undertake a census
of the affected families
The Administrator shall, based The affected families of the
on the survey and census Scheduled Tribes shall be
prepare a draft Rehabilitation resettled preferably in the same
and Resettlement Scheme Scheduled Area in a compact
(including time limit) block so that they can retain
their ethnic, linguistic and
cultural identity.
Page 212
The affected Scheduled Tribes,
other traditional forest dwellers
and the Scheduled Castes
having fishing rights in a river
or pond or dam in the affected
area shall be given fishing
rights in the reservoir area of
the irrigation or hydel projects.
The draft Rehabilitation and
Resettlement scheme referred
to in sub-section (2) shall be
made known locally by wide
publicity in the affected area
and discussed in the concerned
Gram Sabhas or Municipalities
A public hearing shall be Provided further that the
conducted in such manner as consultation with the Gram
may be prescribed, after giving Sabha in Scheduled Areas shall
adequate publicity about the be in accordance with the
date, time and venue for the provisions of the Provisions of
public hearing at the affected the Panchayats (Extension to
area: the Scheduled Areas) Act, 1996.
The Administrator shall, on
completion of public hearing
submit the draft Scheme for
Rehabilitation and
Resettlement along with a
specific report on the claims
and objections raised in the
public hearing to the Collector.
The Collector shall review the
draft Scheme submitted by the
Administrator with the
Rehabilitation and
Resettlement
Committee at the Rehabilitation
project level constituted under
section 45.
The Collector shall submit the
draft Rehabilitation and
Resettlement Scheme with his
suggestions to the
Commissioner Rehabilitation
and Resettlement for approval
of the Scheme.
Approved Rehabilitation and
Resettlement Scheme to be
made public
Publication of declaration and
summary of Rehabilitation and
Resettlement.
Page 213
5 Land to be marked The Collector shall thereupon
out, measured and cause the land to be marked
Planned including out and measured, and a plan
marking of specific to be made of the same.
areas
6 Notice to persons The Collector to publish the
interested and public notice on his website
making of and cause public notice to be
statements given at convenient places, to
stating that the Government
intends to take possession of
the land, and that claims to
compensations and
rehabilitation and resettlement
for all interests in such land
may be made to him
The collector may require a
statement containing the name
of every person possessing any
interest in the land and nature
of interest for three years
preceding the date of statement
7. Enquiry and The Collector shall proceed to
land acquisition enquire into the objections (if
award by any) which any person
Collector interested has stated
The Collector shall make an
award within a period of twelve
months from the date of
publication of the declaration
under section 19
8. Determination of Determination of market value In case of land being
amount of of the land by the collector acquired from members of
compensation the Scheduled Castes or the
Scheduled Tribes, at least
one-third of the compensation
amount due shall be paid to the
affected families initially as first
instalment and the rest shall be
paid after taking over of the
possession of the land.
The market value is multiplied
by a factor as described in the
first schedule of the Act
Determination of value of
things attached to land or
building
Determination of value of
things attached to land or
building
9. Rehabilitation The Collector shall pass Where the affected families
Page 214
and Resettlement Rehabilitation and belonging to the Scheduled
Award for Resettlement Awards for each Castes and the Scheduled
affected families affected family in terms of the Tribes are relocated outside of
entitlements provided the district, then, they shall be
in the Second Schedule paid an additional twenty-five
per cent R&R benefits to which
they are entitled in monetary
terms along with a one-time
entitlement of fifty thousand
rupees.
Page 215
Following entitlement matrix shall be the basis for providing compensation and compatible
R&R measures for tribal peoples:
Page 216
schemes and such land is under
acquisition; or
A family residing on any land in
urban areas for preceding three
years or more prior to the
acquisition of the land or whose
primary source of livelihood for
three years prior to the acquisition
of the land is affected by the
acquisition of such land
b. R&R Package
S.No Elements of R&R Provisons
Entitlements
1. Provision of housing units in If a house is lost in rural areas, a constructed house
case of displacement shall be provided as per Indira Awas Yojana
specifications; or if the family opts not to take the
house, the equivalent cost of the house may be
offered instead
If a house is lost in urban areas, a constructed house
shall be provided, which will be no less than 50 sq mts
in plinth area; or if the family opts not to take the
house offered, it shall get a one-time financial
assistance for house construction which shall not be
less than INR 1,50,000 / -
These benefits shall also be extended to any affected
family which is without homestead land and which
has been residing in the area continuously for not less
than three years preceding the date of notification of
the affected area
No family shall be given more than one house
2. Choice of Annuity or The Appropriate Government shall provide the following
Employment options:
Where jobs are created through the project, after
providing suitable training and skill development, the
Appropriate Government shall make provision for
employment to at least one member per affected
family in the project or arrange a job in such other
project as maybe required. The wages for the job
shall not be less than the minimum wages provided
for in any law for the time being in force
Or
Onetime payment of INR 5,00,000 / - per affected
family
Page 217
Or
Annuity policies that shall pay not less than INR 2,000
per month per family for twenty years, with
appropriate indexation to the Consumer Price Index
for Agricultural Labourers
3. Subsistence grant for Each affected family which is displaced form the land
displaced families for a acquired shall be given a monthly subsistence allowance
period of one year equivalent to INR 3,000 per month for a period of year
from the date of award
4. Transportation cost for Each affected family which is displaced shall get a
displaced families onetime financial assistance of INR 50,000 /- as
transportation cost for shifting of the family, building
materials, belongings and cattle
5. Cattle shed / petty shops Each affected family having cattle or having a petty shop
cost shall get onetime financial assistance of such amount as
the Appropriate Government may specify subject to a
minimum of INR 25,000 /- for the construction of cattle
shed or petty shop
6. Onetime grant to artisan, Each affected family of an artisan, small trader or self-
small traders and certain employed person or an affected family which owned
others non-agricultural land or commercial, industrial or
institutional structure in the affected area, shall get a one-
time financial assistance of INR 25,000 /-
7. Onetime resettlement Each affected family shall be give a onetime
allowance Resettlement Allowance of INR 50,000 /-
8. Stamp duty and registration The stamp duty and any other fees payable for
fee registration of the land or house allotted to the affected
families shall be borne by the requiring body
The land for house allotted to the affected family shall
be free from all encumbrances
The land or house allotted may be in the joint names
of wife and husband of the affected family
Special provisions for Scheduled Castes and Scheduled Tribes
In addition to the R&R package, SC/ST families will be entitled to the following additional benefits:
One time financial assistance of INR 50,000 /- per family
Families settled outside the district shall be entitled to an additional 25% R&R benefits
Payment of one third of the compensation amount at very outset
Preference in relocation and resettlement in area in same compact block
Free land for community and social gatherings
In case of displacement, a Development Plan is to be prepared
Continuation of reservation and other Schedule V area benefits from displaced area to
resettlement area
Page 218
Right of Way
Right of Way (ROW) does require lands for two purposes: (i) one, for tower footing; and (ii)
the other, transmission/ distribution lines (corridor). Unlike in case of substations, for the
construction of transmission towers / distribution poles and the transmission / distributions
lines, there is no permanent loss of lands. Lands under the tower and/ corridor can continue
to be used. So, ownership of the land remains with the existing owner and is not transferred
to the requesting body. The utility will have the right of user only in the property under,
over, along, across in or upon which the lines and poles / towers are placed.
Further affected families will receive compensation for temporary damage as well as for
the land under the tower footing. Thus the compensations are made for following:
Land under the tower footing
Damage to trees
Damage to crops
Damage to constructed structure
Page 219
Consultation and Participation
In line with the World Bank operation policy on Indigenous People (OP 4.10), the affected
Scheduled Tribes will be consulted in preparation of the tribal people plan (TPP).
Consultations will be undertaken to ensure that needs, priorities and preferences of
Scheduled Tribes are adequately reflected and considered in the TPP. The implementation
agency should ensure that free, prior and informed consultations are undertaken with the
affected Scheduled Tribes at each stage of the project. The key points to remember while
undertaking consultations are:
Scheduled Tribes should be informed about the potential impact and proposed
mitigation methods and their views will be taken into account in finalizing the plan.
Sufficient time should be provided to the stakeholder groups to participate in the
consultations.
The consultation should be undertaken in a manner accessible to project affected
people where there are differing levels of literacy skills.
The consultations will be undertaken by field staff of the utility with support from
external experts/NGOs if required.
In this project, however, the process will go beyond consultations, as it is mandatory for
the project to seek consent for all plans from the Gram Sabhas.
Disclosure
The final TPPF and TPP should be disclosed to the general public. The plan will be
translated in local language and made available to the project affected people before
implementation.
Following mechanisms are suggested for disclosure:
Upload the final TPP and periodic monitoring reports on the website of each utility
A copy of the documents will be made available at panchayat and municipal
corporation office
A copy of the documents will be made available at the local offices of the utilities
A copy of the documents will be made available at the offices of any NGO and
informal group working in the project area
Page 220
Implementation and Institutional Arrangements
The implementing agencies (utilities) will have overall cooridination, implementation and
financing responsibilities. The implementing agencies will formulate, implement and
monitor the TPP through the environment and social systems (ESMS) cell within the project
implementation unit. Since the tribal issues are sensitive, the ESMS cell will ensure that a
social specialist or consultant or designated official responsible for TPP has knowledge and
experience of working among the tribal groups.
C. Preparation of TPP
ESMS cell to arrange for
ESMS cell field staff to ESMS cell corporate team to
disclosure meetings to finalize
prepare TPP monitor preparation activities
TPP at community level
D. Implementation of TPP
Local NGO will Officer in ESMS cell with
ESMS cell field staff to
implement TPP experience in handling tribal
supervise implementation
activities affairs to monitor implementation
Page 221
Monitoring and Grievance Redressal Mechanism
The budgetary implications and monitoring mechanism for activities identified in TPP are
provided below:
Each Tribal Development Plan (TPP) will have its own budget. The implementing
agencies (power utilities in this case) will provide sufficient resources to formulate TPP
for each sub-project which impacts Scheduled Tribes. A detailed budget will be
prepared by the social and environment cell within the project implementation unit,
after taking into account all activities associated with formulation and implementation
of TPP.
The ESMS cell will be responsible to implement and monitor all the activities specified
in this document with support from the field staff of the utilities (AE and ADE).
For projects with significant adverse impacts26 on Scheduled Tribes, participatory
monitoring mechanism will be established involving the staff of project implementation
unit, people from social and environment cell within implementation unit,
representatives of affected Scheduled tribes and local community.
The implementation of TPP will be monitored regularly and periodic monitoring reports
will be submitted to World Bank. The monitoring reports will be prepared by social and
environment cell.
The implementing agency can hire an external expert agency/individual or an NGO to
formulate and implement TPP and/or to monitor the implementation of TPP.
The costs of monitoring requirement will be reflected in project budgets.
26
Involves displacement of Tribal people, affects their association to land or threatens their cultural identity
27
Integrated Tribal Development Projects (ITDP) were conceived during fifth five year plan in India (and have
continued ever since) to delineate projects for welfare of tribal population. Andhra Pradesh has opted for
“Agency” model under the Registration of Societies Act and the ITDP are called Integrated Tribal Development
Agencies (ITDA) in the state.
Page 222
In case the grievances are not resolved at the utility level. The people can approach the
judicial authority and file a court case against the utilities.
Immediate Action
Complainant Local Divisional Engineer
Supported by appropriate officer
in ESMS cell
Not addressed
Court of Law
Page 223
Annexure 8 – Resettlement Policy Framework (RPF)
Land is required for construction of substations and erecting transmission and distribution
towers. Land secured for construction of substations is no longer accessible to the existing
owner and hence in such cases ownership is transferred from the existing owner to the
respective utility. However, ownership of land used for erecting towers remains with the
existing land owner and the utility only receives rights to use the land. Therefore when we
talk of loss of land, it refers to land secured for substation construction. There are four ways
in which this land can be secured; these are:
(x) Transfer of Government land to utility
(xi) Voluntary donation
(xii) Purchase of land on willing buyer and willing seller basis on negotiated price
(xiii) Involuntary acquisition of land
The RPF is applicable in instances where securing of land results in the need to rehabilitate
and resettle affected families.
The proposed project includes the establishment of new of new sub-stations, the
construction of which requires securing of land by the concerned utility. For a 132 / 33 kV
sub-station 5 acres of land is required. While the majority of the land required for sub-
station construction will be secured through transfer of Government lands, there is a
possibility that some private land may need to be acquired. However, this will be done only
as a demonstrable last resort in the case of non-availability of Government lands in the
area.
Objective of the policy framework
The objective of the RPF is to appropriately identify, address and mitigate adverse socio-
economic impacts that may occur due to the implementation of projects that involve the
securing of land and subsequent resettlement of affected families. Without proper planning
and management, resettlement may result in long-term hardship for affected people.
Hence, the RPF aims to avoid resettlement wherever possible and in cases where it is
unavoidable, the RPF requires the Appropriate Government to develop of a robust
rehabilitation and resettlement plan to effectively manage the social impacts crated by the
project. The plan would identify the full range of people affected by the project and justify
their displacement after consideration of alternatives that would avoid or minimize
displacement.
Basic Principles
The basic principles on the basis of which the RPF has been developed are:
Avoidance: wherever possible, securing of land that leads to displacement of people
should be avoided
Page 224
Least disturbance: where displacement is not avoidable, efforts will be made to
minimize displacement, damage to / loss of property, loss of livelihood and any other
negative social impact the project may have. Only the minimum amount of land
required for a project is to be secured
Public purpose: the land secured must be found to serve a legitimate and bonafide
public purpose and the social benefits should outweigh and potential social costs
Participative: the process of land securing should be done through a humane,
participative, informed and transparent process in which local self-government and
Gram Sabhas are consulted and interested parties are fully informed and have a
chance to air their grievances
Fair compensation: the affected families will receive fair compensation for any loss
of land along with a compensation award for resettlement
Maintaining the social and economic status of families: the RPF is based on the
principle that there should be minimal possible negative impacts on the livelihoods
of the affected families. Where resettlement is unavoidable, the resettlement plan
should attempt to ensure that affected families are able to maintain the same social
and economic status as they did before displacement. Affected families will be
provided appropriate compensation and where possible jobs in the project.
Resettlement Entitlement Matrix
Compensation for Land Acquisition
The compensation shall be calculated by the Collector on the basis of the provisions laid
down under section 26 to section 30 and the First Schedule of the RFCTLARRA 2013. The
compensation shall be paid to all parties whose land or other immovable property or assets
attached to the land or building have been acquired. As per the Act, land owners are defined
as any person:
Whose name is recorded as the owner of the land or building or part thereof, in the
records of the authority concerned; or
Who is granted forest rights under the Scheduled Tribes and Other Traditional Forest
Dwellers (Recognition of Forest Rights) Act, 2006 or under any other law for the time
being in force; or
Who is entitled to be granted Patta rights on the land under any law of the State
including assigned lands; or
Who has been declared as such by an order of the court or Authority
The Collector shall determine the market value of the land to be acquired on the
basis of whichever of the following is higher:
Page 225
Market value, if any, specified in the Indian Stamp Act, 1889 for the registration of
sale deeds or agreements to sell in the area where the land is situated; or
The average sale price for similar type of land situated in the nearest village or
nearest vicinity area; or
Consented amount of compensation as agreed in case of acquisition of lands for
private companies or for public private partnership project
The Collector having determined the market value of the land to be acquired shall calculate
the total amount of compensation to be paid to the land owner by including all assets
attached to the land. This will be done as follows:
Component of Compensation Manner of Determination of Value
1. Market value of land Whichever of the following is higher:
Market value, if any, specified in the Indian Stamp Act,
1889 for the registration of sale deeds or agreements to
sell in the area where the land is situated; or
The average sale price for similar type of land situated
in the nearest village or nearest vicinity area; or
Consented amount of compensation as agreed in case
of acquisition of lands for private companies or for
public private partnership project
2. Factor by which the market value In case of rural areas (other than Scheduled Areas) a
is to be multiplied multiplication factor of 1.25 will be applied
In case of Scheduled (Tribal) Areas, a multiplication
factor of 1.50 will be applied
In case of urban areas, a multiplication factor of 1.00
will be applied
3. Value of assets attached to land
or building
a. Market value of the building The Collector shall use the services of a competent
and other immovable property engineer, or any other specialist in the relevant field,
or assets attached to the land as may be considered necessary
or building that is to be
acquired
b. Damage sustained to standing For fruit bearing trees, the value of compensation per
trees and plats tree will be determined from time to time by the
Horticulture Department based on the species of tree
For non-fruit bearing trees, the value of compensation
will be determined by the Forest Department
c. Damage sustained to standing For standing crops, the compensation will be
crops determined by the Agricultural Officer on a case by
case basis
Page 226
4. Solatium The solatium shall be equivalent to one hundred
percent of the market value of the land mentioned
against serial number 1 multiplied by the relevant
factor mentioned against serial number 2 plus the
value of assets attached to land or building mentioned
against serial number 4a, 4b and 4c.
5. Total Compensation The total compensation = Market value of land
mentioned against serial number 1 X relevant factor
mentioned against serial number 2 + Value of assets as
mentioned against serial number 3 + Soaltium
mentioned against serial number 4
In addition to the market value of the land provided, the Collector shall, in every case, award
an amount calculated at the rate of twelve per cent per annum on the market value for the
period commencing on and from the date of the publication of the notification of the SIA
till the date of the award of the Collector or the date of taking possession of the land,
whichever is earlier.
Compensation for Rehabilitation and Resettlement
In addition to the compensation detailed above, the Collector shall pass Rehabilitation and
Resettlement Awards for each affected family. According to the RFCTLARRA 2013, affected
family is defined as:
A family whose land or other immovable property has been acquired;
A family which does not own any land but a member or members of such family
may be agricultural labourers, tenants including any form of tenancy or holding of
usufruct right, share-croppers or artisans or who may be working in the affected
area for three years prior to the acquisition of the land, whose primary source of
livelihood stand affected by the acquisition of land;
The Scheduled Tribes and other traditional forest dwellers who have lost any of their
forest rights recognized under the Scheduled Tribes and Other Traditional Forest
Dwellers (Recognition of Forest Rights) Act, 2006 due to acquisition of land
Family whose primary source of livelihood for three years prior to the acquisition of
the land is dependent on forests or water bodies and includes gatherers of forest
produce, hunters, fisher folk and boatmen and such livelihood is affected due to
acquisition of land;
A member of the family who has been assigned land by the State Government or
the Central Government under any of its schemes and such land is under
acquisition;
Page 227
A family residing on any land in urban areas for preceding three years or more prior
to the acquisition of the land or whose primary source of livelihood for three years
prior to the acquisition of the land is affected by the acquisition of such land
Page 228
transportation cost for shifting of the family, building
materials, belongings and cattle
5. Cattle shed / petty shops cost Each affected family having cattle or having a petty shop
shall get onetime financial assistance of such amount as
the Appropriate Government may specify subject to a
minimum of INR 25,000 /- for the construction of cattle shed
or petty shop
6. Onetime grant to artisan, Each affected family of an artisan, small trader or self-
small traders and certain employed person or an affected family which owned non-
others agricultural land or commercial, industrial or institutional
structure in the affected area, shall get a one-time financial
assistance of INR 25,000 /-
7. Onetime resettlement Each affected family shall be give a onetime Resettlement
allowance Allowance of INR 50,000 /-
8. Stamp duty and registration The stamp duty and any other fees payable for registration
fee of the land or house allotted to the affected families shall
be borne by the requiring body
The land for house allotted to the affected family shall be
free from all encumbrances
The land or house allotted may be in the joint names of
wife and husband of the affected family
9. Special provisions for Scheduled Castes and Scheduled Tribes displaced from
Scheduled Castes and Scheduled Areas shall receive an amount equivalent to
Scheduled Tribes INR 50,000 /- per family
Families settled outside the district shall be entitled to an
additional 25% R&R benefits;
Payment of one third of the compensation amount at very
outset;
Free land for community and social gatherings;
Page 229
2) Administrator for Rehabilitation and Resettlement: As per section 43(1) of the
RFCTLARRA 2013, where the Appropriate Government is satisfied that there is likely to
be involuntary displacement of persons due to acquisition of land, then the State
Government shall, by notification, appoint in respect to that project, an officer not below
the rank of Joint Collector or Additional Collector or Deputy Collector or equivalent
official of Revenue Department to be Administrator for Rehabilitation and Resettlement.
3) Powers of the Administrator for Rehabilitation and Resettlement: As per section 30 of
the A.P. RFCTLARRR 2014, the Administrator shall exercise the following powers and
have the following responsibilities:
a. To conduct a survey and undertake a census of the affected families in the
manner and within the time provided under the A.P. RFCTLARRR 2014;
b. To prepare a draft Rehabilitation and Resettlement Scheme;
c. To publish the draft scheme by the mode provided under the A.P. RFCTLARRR
2014;
d. To make the draft scheme available to the concerned persons and authorities;
e. To organize and conduct public hearings on the draft scheme;
f. To provide an opportunity to the Requiring Body to make suggestions and
comments on the draft scheme;
g. To submit the draft scheme to the Collector;
h. To publish the approved Rehabilitation and Resettlement Scheme in the affected
area;
i. To assist the Collector in preparing the Rehabilitation and Resettlement award;
j. To monitor and supervise the implementation of the Rehabilitation award;
k. To assist in post-implementation audit of Rehabilitation and Resettlement; and
l. Any other work required to be done for Rehabilitation and Resettlement
4) Project Level Rehabilitation and Resettlement Committee: As per section 45(1 & 2) of
the RFCTLARRA 2013, where land proposed to be acquired is equal to or more than one
hundred acres, the Appropriate Government shall constitute a Committee under the
chairmanship of the Collector to monitor and review the progress of implementation of
the Rehabilitation and Resettlement Scheme and to carry out post-implementation
audits in consultation with the Gram Sabha in rural areas and municipality in urban
areas. The Committee shall include the following members:
a. Officers from the Appropriate Government;
b. A representative of women residing in the affected area;
Page 230
c. A representative each of the Scheduled Castes and the Scheduled Tribes residing
in the affected area;
d. A representative of a voluntary organization working in the area;
e. A representative of a nationalized bank;
f. The Land Acquisition Officer of the project;
g. The Chairperson of the panchayats or municipalities located in the affected area
or their nominees;
h. The Chairperson of the District Planning Committee or his nominee;
i. The Member of Parliament and Member of the Legislative Assembly of the
concerned area or their nominee;
j. A representative of the Requiring Body; and
k. Administrator for Rehabilitation and Resettlement as the Member-Convenor
As per section 31(2) of the A.P. RFCTLARRR 2014, the Committee shall have its first
meeting when a draft Rehabilitation and Resettlement Scheme has been prepared by
the Administrator. The Committee shall discuss the scheme and make suggestions and
recommendations. Thereafter the Committee shall meet and review and monitor the
progress of Rehabilitation and Resettlement once in a month till the process is
completed. For the post-implementation social audits, the Committee shall meet once
in three months. In order to monitor the progress, the Committee may visit the affected
area and hold discussions with the affected families and also visit the resettlement area.
Implementation Arrangements
The RPF is follows the strategy of avoidance, minimization and mitigation. This means that
preference is given to avoiding displacement and resettlement wherever possible. If it is
not possible to avoid this, utilities will strive to minimize the extent of displacement and
take appropriate mitigation measures for all social impacts caused by such displacement.
In order to avoid the loss of land and subsequent need for resettlement, the following
safeguards are put in place:
The Appropriate Government will endeavour, wherever possible, to secure
Government land for projects even if this requires realignment of the proposed route
Only the minimal amount of land required for substations will be secured; the land
required for a 132kV / 33kV substation is approx. 5 acres.28
28
Reference manuals on construction and operational practices of EHV substations & lines and commercial
and load dispatch operations. Available at: http://www.aptransco.gov.in/transco/images/APTRANSCO-
Technical-reference-book-2011-vol-ii.pdf
Page 231
Only in rare cases that Government land is not available will other methods of
securing land be pursued (voluntary donation or willing buyer and willing seller)
with involuntary acquisition being the last resort
Even, when Government lands are used, lands assigned to poor people for
agriculture purpose will not be resumed unless unavoidable
In case of voluntary donation, no undue pressure will be put on the land owner / user
to transfer ownership of the land; and in the case of willing buyer and willing seller,
the compensation shall not be less than the rate provided for under RFCTLARRA
2013
There should be no unutilized land which has been previously acquired in the area
where land is sought for the project. Further, any land acquired earlier and remaining
unutilized is to be used for the purpose of the project before additional land is
allotted
The Appropriate Government shall ensure that a Social Impact Assessment (SIA)
study is carried out in consultation with the concerned Panchayat, Municipality or
Municipal Corporation in the affected area and also hold public hearings in the
process
An Expert Committee will be required to review the SIA and certify that the requested
land serves a legitimate public purpose; that the social benefits of the proposed
project outweigh any potential social costs; that only the minimum amount of land
required is being utilized; and that no other less displacing option was available
Where it is not possible to avoid the acquisition of land and displacement of affected
families, the provisions of RFCTLARRA, 2013 and the A.P. RFCTLARRR, 2014 shall be
applicable.
The table below provides a snapshot of the process involved in land acquisition and
determining the awards for rehabilitation and resettlement along with details who the
competent authority responsible at each step of the process. Following the table, the
implementation process is elaborated in detail.
Competent Authority Responsible at Various Stages
Milestone Process Responsibility
Involuntary Acquisition of Land – Process as per APRFCTLARRR, 2014
1. Request for Requisition for land: Requiring body files Principal Secretary
Land requisition to the concerned District Energy Department or
Collector and the Commissioner any Person authorised
Rehabilitation and Resettlement by him
Preliminary inquiry about the correctness Team of Revenue and
of particulars furnished in the requisition Agriculture Officers
Report on preliminary inquiry submitted along with
to the District Collector Representative of
Requiring Body
Page 232
Milestone Process Responsibility
Preliminary estimate of the cost: If the District Collector
District Collector is satisfied that the
requisition is consistent with the
provisions of the RFCTLARRA, 2013, he
shall make a preliminary estimate of the
cost of acquisition
The requiring body will deposit the Requiring body
estimated cost of acquisition in District
collector’s office
2. Social Impact Notification to undertake SIA District Collector
Assessment Disclosure of the notification District Collector
Select team to carryout SIA from the Commissioner,
individuals and institutions registered or Rehabilitation and
empanelled in the state database of Resettlement acting
Qualified SIA Resource Partners and as state Social Impact
Practitioners Assessment Unit
Undertake SIA in consultation with Appointed team to
concerned Gram Panchayat, Mandal conduct SIA
Parishad, Municipality or Municipal
Corporation, followed by a public hearing
to ascertain the views of the affected
families
Submit SIA report to Commissioner, Appointed team to
Rehabilitation and Resettlement within a conduct SIA
period of six months from the date of
commencement
Submit Social Impact Management Plan Appointed team to
listing the ameliorative measures conduct SIA
required to be undertaken for addressing
the impacts
Disclosure of SIA report and Social Commissioner,
Impact Management Plan Rehabilitation and
Resettlement
Validation of Constitute an expert group consisting of AP State Government
SIA by Expert two non-official social scientists, two
Group representatives of panchayats, Gram
Shabha, municipality or municipal
corporation, two experts on
rehabilitation and a technical expert in the
subject related to the project
Recommendations of the expert group, Expert Group
within two months of its constitution, on
whether the proposed project should be
implemented or not
Disclosure of recommendations of the AP State Government
expert group
3. Decision by Decide area for acquisition based on the AP State Government
appropriate Social Impact Assessment report and the
Government recommendations of the expert group
Page 233
Milestone Process Responsibility
Obtain consent from the affected people, AP State Government
where required
Disclosure of the decision AP State Government
Create public website to upload and Commissioner,
disclose each acquisition case Rehabilitation and
Resettlement
4. Publication of Preliminary notification shall be issued, AP State Government
Preliminary after conclusion of SIA and consent of the
Notification affected persons or Gram Sabha, as the
case may be, when it appears to the
Government that land is required or likely
to be required in any area for any public
purpose
Update land records within 2 months of District Collector
the notification
5. Preliminary Officer authorized by District collector to Officer authorized by
survey of land conduct preliminary survey and shall District collector
proposed for have powers as provided under the
acquisition Section 12 of the RFCTLARRA 2013
6. Disposal of Every objection shall be made to the Collector / District
objections Collector in writing and the Collector shall Collector
give the objector an opportunity of being
heard in person or by any person
authorized by him in this behalf
After hearing all such objections and
making further inquiries as he thinks
necessary, the Collector shall submit a
report along with his recommendations
on the objections to the District Collector
for decision
7. Preparation of The Administrator for Rehabilitation and Administrator for
Rehabilitation Resettlement shall conduct a survey and Rehabilitation and
and undertake a census of the affected Resettlement
Resettlement families within a period of two months Commissioner of
Scheme and from the date of publication of such Rehabilitation and
Public preliminary notification. Resettlement
Hearing: The Administrator shall prepare
comprehensive and detailed draft
Rehabilitation and Resettlement Scheme
and give publicity in the affected area
The Commissioner of Rehabilitation and
Resettlement shall publish the approved
Rehabilitation and Resettlement Scheme
in the affected area
8. Development Prior consent of the concerned Gram Concerned Utility
Plan for Sabha or the Panchayats at the
Scheduled appropriate level in the Scheduled Areas
Castes or under the Fifth Schedule to the
Scheduled Constitution shall be obtained before
Page 234
Milestone Process Responsibility
Tribes issue of a notification for acquiring land
Families: in Scheduled Areas
In case there is involuntary displacement
in Scheduled areas, a Development Plan
will be prepared by the requiring body
9. Publication of A declaration for acquisition of the land Appropriate
Declaration along with the summary of the Government
Regarding Rehabilitation and Resettlement Scheme
Acquisition of
shall be made by the appropriate
Land
Government in the prescribed format.
10. Payment of The award for land acquisition shall be Collector
Compensation made within 12 months of the public
and declaration of the acquisition
Entitlements
The compensation shall be calculated on
the basis of provisions laid down under
section 26 to section 30 and \ the First
Schedule of the RFCTLARRA 2013.
In addition to the compensation for land
acquisition, Rehabilitation and
Resettlement Awards will also be
provided to each affected family
Page 235
2) Set up Social Impact Assessment Unit: The Commissioner, Rehabilitation &
Resettlement shall be the state Social Impact Assessment Unit to arrange to carry out
Social Impact Assessment Study (SIA). The Commissioner, Rehabilitation &
Resettlement shall select the SIA team for each project from the individuals and
institutions registered or empanelled in the State Database of Qualified SIA Resource
Partners and Practitioners. The size and selection criteria for the SIA team shall be as
per the project-specific ToR developed by the State SIA Unit. The SIA team may be
constituted by appointing individuals or an organization with experience in conducting
SIAs or related field-based assessments and the team may include:
A combination of independent practitioners, qualified social activists, academics,
technical experts, who are not directly connected with the requiring body; and
At least one woman member
The Requiring Body shall not be involved in any way in the appointment of the SIA team
and while selecting the team it shall be ensured that there is no conflict of interest
involving the team members appointed to assess the concerned project. If any team
member is found to have a conflict of interest, the said member shall be disqualified.
3) Conduct Social Impact Assessment: A Social Impact Assessment (SIA) will be carried
out for all land acquisition proposals except for when land is proposed to be acquired
invoking urgency provisions under section 40 of RFCTLARRA 2013. In such cases, the
District Collector, where he is not the Appropriate Government, shall submit a report to
the State Government to issue appropriate directions. In other cases, the District
Collector shall take the decision.
The District Collector shall, within a period of fifteen days from the date of deposit of
the processing fee for carrying the SIA study by the Requiring Body, issue a notification
for carrying out SIA in as per Form II found in the annexures of the A.P. RFCTLARRR
2014. The notification shall be made available in Telugu language to the Gram
Panchayat, Mandal Parishad, Municipality or Municipal Corporation, as the case may
be, and in the offices of the District Collector, the Sub-Divisional Magistrate and the
Tahsildar at Mandal level.
The notification shall be published in the form of posters and pamphlets circulated in
the affected area and by affixing the posters at some conspicuous places in the affected
areas and shall be uploaded on the website of the State Government and the revenue
district concerned. Provided that such notification shall be issued within thirty days after
the deposit of the processing fee for carrying Social Impact Assessment by the
Requiring Body.
The SIA shall be conducted in consultation with concerned Gram Panchayat, Mandal
Parishad, Municipality or Municipal Corporation, as the case may be, at village level or
ward level in the affected areas. This will be followed by a public hearing at the affected
Page 236
areas to ascertain the views of the affected families; these views shall be recorded in
writing. Adequate publicity about the date and time and venue for the public hearing
shall be given.
The SIA report shall be submitted as per Form III found in the annexures of A.P.
RFCTLARRR 2014 to the Commissioner, Rehabilitation & Resettlement within a period
of Six months from the date of commencement and shall include the views of the
affected families recorded in writing. The SIA Report including summaries shall be
prepared and divided into three parts;
The Project Feasibility Report;
The Project Impact Report, and
The Social Impact Management Plan
4) Develop Social Impact Management Plan: A Social Impact Management Plan listing the
ameliorative measures required to be undertaken for addressing the impact of the
project shall be submitted as per Form IV found in the annexures of A.P. RFCTLARRR
2014 along with the SIA report to the Commissioner, Rehabilitation & Resettlement.
The SIA team must provide a conclusive assessment of the balance and distribution of
the adverse social impacts and social costs and benefits of the proposed project and
land acquisition, including the mitigation measures, and provide an assessment as to
whether the benefits from the proposed project exceed the social costs and adverse
social impacts that are likely to be experienced by the affected families or even after the
proposed mitigation measures, the affected families remained at risk of being
economically or socially worse, as a result of the said land acquisition and resettlement.
5) Publicizing the SIA Report and Social Impact Management Plan: The SIA Report and
the Social Impact Management Plan shall be made available in the Telugu language to
the concerned Gram Panchayat, Mandal Parishad, Municipality or Municipal
Corporation, at village level or ward level in the affected areas and in the Offices of the
District Collector, the Sub-Divisional Officer and Tahsildar. It shall also be published by
way of a public notice by affixing at some conspicuous places in the affected areas and
shall be uploaded on the website of the State Government and the revenue district
concerned.
6) Validation of SIA by Expert Group: The Appropriate Government shall ensure that the
SIA report is validated by an independent multi-disciplinary Expert Group, as may be
constituted by it. The Expert Group shall have:
Two non-official social scientists;
Two representatives of Panchayat, Gram Sabha, Municipality or Municipal
Corporation;
Page 237
Two experts on rehabilitation, and a technical expert in the subject relating to the
project
If the Expert Group determines that the project does not serve any public purpose, or
the social costs and adverse social impacts of the project outweigh the potential
benefits, it shall make a recommendation within two months from the date of its
constitution and the project shall be abandoned forthwith and no further steps to
acquire land will be initiated in respect of the same.
If the Expert Group believes that there is a public purpose and that the benefits
outweigh social costs, it shall make recommendations within two months of its
constitution as to whether the extent of land proposed to be acquired is the absolute
bare-minimum extent needed for the project and whether there are no other less
displacing options available.
All recommendations of the Expert Group shall be recorded in writing along with details
and reasons for their decisions. The recommendations shall be made available in the
Telugu language to the Panchayat, Municipality, or Municipal Corporation; and the
offices of the District Collector, the Sub-Divisional Magistrate and the Tehsil; and shall
be published in the affected areas and also uploaded on the website of the Appropriate
Government.
7) Decision by Appropriate Government: The Appropriate Government shall examine the
Social Impact Assessment report, the recommendations of the Expert Group, if any, and
decide such area for acquisition which would ensure minimum displacement of people,
minimum disturbance to the infrastructure, ecology and minimum adverse impact on
the individuals affected. Before taking a decision the appropriate Government shall
ensure that consent is obtained the cases where such consent is required.
The decision of the Appropriate Government shall be made available in the local
language to the Panchayat, Municipality, or Municipal Corporation; and the offices of
the District Collector, the Sub-Divisional Magistrate and the Tehsil; and shall be
published in the affected areas and also uploaded on the website of the Appropriate
Government.
Each acquisition case will be uploaded, on a public website that is to be created by the
Commissioner, Rehabilitation & Resettlement. All details regarding the case beginning
with the notification of the SIA and tracking each step of decision making,
implementation and audit will be made available on the website.
8) Publication of Preliminary Notification: After conclusion of the SIA and consent of the
affected persons or Gram Sabha, as the case may be, when it appears to the appropriate
Government that land is required or likely to be required in any area for any public
purpose, a preliminary notification shall be issued as per Form VI (a & b) found in the
annexures of A.P. RFCTLARRR 2014.
Page 238
The notification shall be published in the following manner:
In the Andhra Pradesh Gazette;
In two daily newspapers circulating in the locality of such area of which one shall
be in the Telugu language
In the Telugu language in the Panchayat, Municipality or Municipal Corporation,
as the case may be and in the offices of the District Collector, the Sub-divisional
Magistrate and the Tehsil;
Uploaded on the website of the Appropriate Government;
In conspicuous places in the affected areas and shall also be informed to the
public by beat of Tom-tom.
After issuing the preliminary notification, the Collector shall updated land records
within a period of two months.
9) Preliminary survey of land proposed for acquisition: The officer authorized by the
District Collector to conduct preliminary survey shall have all the powers as provided
under section 12 of the RFCTLARRA 2013.
10) Disposal of objections: Any person interested in any land which has been notified as
being required or likely to be required for a public purpose, may within sixty days from
the date of the publication of the preliminary notification object to:
The area and suitability of land proposed to be acquired;
Justification offered for public purpose;
The findings of the SIA report
Every objection shall be made to the Collector in writing and the Collector shall give the
objector an opportunity of being heard in person or by any person authorized by him
in this behalf or by an Advocate and shall, after hearing all such objections and making
such further inquiry, if any, as he thinks necessary, shall submit a report along with his
recommendations on the objections to the District Collector for decision. The decision
of the District Collector shall be final.
11) Preparation of Rehabilitation and Resettlement Scheme and Public Hearing: On
publication of the preliminary notification by the Appropriate Government, the
Administrator for Rehabilitation and Resettlement shall conduct a survey and
undertake a census of the affected families within a period of two months from the
date of publication of such preliminary notification.
For the survey and the census of the affected families the Administrator shall collect
data based on the SIA report as well as data from secondary sources such as Panchayat
and Government records and verify that data by door visit of the affected families and
by site visits in case of infrastructure in the affected area.
Page 239
The draft Rehabilitation and Resettlement Scheme prepared by the Administrator shall
include particulars of the rehabilitation and resettlement entitlements of each land
owner and landless whose livelihoods are primarily dependent on the lands being
acquired: Where resettlement of affected families is involved the scheme shall contain
the following:
List of Government buildings to be provided in Resettlement Area
Details of public amenities and infrastructural facilities which are to be provided
in Resettlement Area
List of likely to be displaced families;
List of infrastructure in the affected area;
List of land holdings in the affected area;
List of trades/business in the affected area;
List of landless people in the affected area;
List of persons belonging to disadvantageous groups like persons belonging to
Scheduled Castes or Scheduled Tribes, handicapped persons in the affected area;
List of landless agricultural labourers in the affected area;
List of unemployed youth in the affected area.
The Administrator shall prepare comprehensive and detailed draft Rehabilitation and
Resettlement Scheme, as per Form VIII found in the Annexures of the A.P. RFCTLARRR
2014, and give wide publicity in the affected area. The Administrator or an officer
authorized by him shall conduct a public hearing in the affected areas on such date,
time and venue as decided by giving advance notice of fifteen days.
The Commissioner of Rehabilitation and Resettlement shall publish the approved
Rehabilitation and Resettlement Scheme in the affected area by affixing in conspicuous
places in addition to making it public by other means as described above in the case of
the preliminary notification.
12) Development Plan for Scheduled Castes or Scheduled Tribes Families: As far as
possible, no acquisition of land shall be made in Scheduled Areas; and where this is
done, it shall be only as a demonstrable last resort. Further the prior consent of the
concerned Gram Sabha or the Panchayats at the appropriate level in the Scheduled
Areas under the Fifth Schedule to the Constitution shall be obtained before issue of a
notification. This prior consent shall be taken in all cases, even in the case of urgency.
In cases of a project involving land acquisition on behalf of a requiring body which
involves involuntary displacement of the Scheduled Castes or Scheduled Tribes
families, a Development Plan shall be prepared in the prescribed format. The
Development Plan shall lay down the details of the procedure for settling land rights
Page 240
due, but not settled and restoring titles of the Scheduled Tribes as well as he Scheduled
Castes on the alienated land by undertaking a special drive together with land
acquisition.
The Development Plan shall also contain a programme for development of alternate
fuel, fodder and non-timber forest produce resources on non-forest lands within a
period of five years, sufficient to meet the requirements of tribal communities as well
as the Scheduled Castes.
The affected families of the Scheduled Tribes shall be resettled preferably in the same
Scheduled Area in a compact block so that they can retain their ethnic, linguistic and
cultural identity. Further, the resettlement areas predominantly inhabited by the
Scheduled Castes and the Scheduled Tribes shall get land, to such extent as may be
prescribed by the Appropriate Government free of cost for community and social
gatherings.
All the benefits, including the reservation benefits available to the Scheduled Tribes and
Scheduled Castes in the affected areas shall continue in the resettlement area.
Any alienation of tribal lands or lands belonging to members of the Scheduled Castes
in disregards of the laws and regulations for the time being in force shall be treated as
null and void.
13) Publication of declaration for acquisition: A declaration for acquisition of the land along
with the summary of the Rehabilitation and Resettlement Scheme shall be made by the
appropriate Government in the prescribed format. However, no such declaration shall
be made unless the requiring body has deposited an amount in full towards the cost of
acquisition of the land. Every declaration shall be published in the same manner as
described above in the case of the preliminary notification.
14) Land acquisition award: The Collector shall make an award for land acquisition within
a period of twelve months from the date of publication of the declaration for
acquisition. If no award is made within this period, the entire proceedings for the
acquisition of the land shall lapse.
15) Mode of payment of compensation: The payment of compensation shall be made
expeditiously through account payee cheques/electronic mail transfer.
Dispute Settlement
As per section 51(1) of the RFCTLARRA 2013, the Appropriate Government shall, for the
purpose of providing speedy disposal of disputes relating to land acquisition,
compensation, rehabilitation and resettlement, establish one or more Authorities to be
known as “the Land Acquisition, Rehabilitation and Resettlement Authority”.
Section 52(1, 2 & 3) specifies that the Authority shall consist of one person only (Presiding
Officer) who will be appointed by the Appropriate Government in consultation with the
Chief Justice of a High Court in whose jurisdiction the Authority is proposed to be
Page 241
established. The Presiding Officer must be, or have been, a District Judge; or a qualified
legal practitioner who has been practicing for not less than seven years. The Presiding
Officer shall hold office for a term of three years or until the age of sixty-five, whichever is
earlier.
The Appropriate Government shall also provide the Authority with a Registrar and such
other officers and employees as it deems fit. As per section 33 of the A.P. RFCTLARRR 2014,
the salaries, allowances, and conditions of service of the Registrar and other Officers and
employees of the Authority shall be the same as applicable to the officers and employees
of similar grades working in the Judicial Department of the State Government; while the
salaries and allowances of the Presiding Officer shall be the same as that applicable to a
District Judge working in the State.
Any person interested who has not accepted the rehabilitation and resettlement award
may, by written application to the Collector, require that the matter be referred by the
Collector to the Authority for determination. The objection of the interested person may
concern:
a. Measurement of the land;
b. The amount of the compensation;
c. The person who is payable;
d. The rights of Rehabilitation and Resettlement; or
e. The appointment of the compensation among the interested persons
The application objecting to the award will be accepted if the application is made:
a. Within six weeks from the date of Collector’s award, in the case that the person
making the application was present or represented before the Collector at the
time when the award was made; or
b. In other cases, within six weeks of receipt of the notice from the Collector, or
within six months from the date of the Collector’s award, whichever period shall
expire first
However, the Collector may entertain an application within a further period of one year
after the expiry of the stipulated period if there is sufficient cause for not filing it within the
specified time period.
Once the Collector receives the application, he shall refer it to the Authority within a period
of thirty days from the date of receipt of the application. If the Collector fails to refer the
matter within the stipulated time period, the applicant may apply to the Authority,
requesting it to direct the Collector to make the reference.
While making the reference to the Authority, the Collector shall specify:
a. The situation and extent of the land, with particulars of any tress, buildings or
standing crops on it;
b. The names of the persons interested in the land;
c. The amount awarded for damages and paid or tendered, and the amount of
compensation awarded;
d. The amount paid or deposited under any other provisions of the RFCTLARRA
2013; and
Page 242
e. If the objection is to the amount of the compensation or the grounds on which
the amount of compensation was determined.
On receiving the reference, the Authority shall issue a notice specifying the day on which
the objection will be determined and direct that the applicant and all interested persons
appear on the notified date. The proceedings shall take place in public and all persons
entitled to appear in any Civil Court in the State shall be entitled to appear, plead and act
in such proceedings.
In determining whether the amount of compensation awarded for land acquisition and
rehabilitation and resettlement entitlements is appropriate, the Authority shall take into
consideration whether the Collector has followed the parameters set under section 26 to
section 30 of the RFCTLARRA 2013. If the Collector’s award is not upheld by the Authority,
the cost of the proceedings shall be paid by the Collector.
If the Authority believes that the compensation should have been in excess of that awarded
by the Collector, the Authority may direct the Collector to pay interest on such excess at
the rate of nine percent per annum from the date on which the Collector took possession
of the land to the date of payment of the excess amount. If the payment of the excess
amount is after the expiry of one year form the date the Collector took possession, the
interest rate applied will be fifteen percent per annum for the period after the expiry of one
year to the time the excess payment is made.
In such cases where the Authority awards compensation in excess of the amount awarded
by the Collector, any person interested in any other land covered by the same preliminary
notification, may submit a written application to the Collector to re-determine the amount
of compensation made to them. Such applications should be made within three months of
the Authority’s awards.
If the Requiring Body or any person aggrieved by the Authority’s award may file an appeal
to the High Court within sixty days from the date of the award. This period maybe
extended by a further sixty days if the High Court determines that the appellant was
prevented by sufficient cause from filing the appeal in the stipulated period. The high Court
will be require do dispose of any such appeal within six months from the date on which
the appeal is presented to the High Court.
Monitoring Mechanism
As per section 50(1 & 2) of the RFCTLARRA 2013, the State Government shall constitute a
State Monitoring Committee for reviewing and monitoring the implementation of
rehabilitation and resettlement schemes or plans. The Committee may, besides having
representatives of the concerned Ministries and Departments of the State Government,
associate with eminent experts from the relevant fields.
Further, as per section 32(1) of the A.P. RFCTLARRR 2014, the State Monitoring Committee
shall have its first meeting for review and monitoring the implementation of the
rehabilitation and resettlement scheme within a month of the date that the said scheme is
approved and published by the Commissioner for Rehabilitation and Resettlement.
Thereafter, the meetings of the Committee shall be held once in three months to review
and monitor the implementation of the rehabilitation and resettlement schemes.
Page 243
Section 32(2) of the A.P. RFCTLARRR 2014 prescribes that the experts associated with the
State Monitoring Committee shall be paid an amount of INR 1,000 as sitting fee and
travelling and daily allowance at the rate admissible to the Class-I rank Officers of the State
Government for journeys outside headquarters.
Page 244
Annexure 9 – Implementation Arrangements for RTFCTLARRA
Page 245
Milestone Process Responsibility
Submit Social Impact Management Plan listing the Appointed team to
ameliorative measures required to be undertaken for conduct SIA
addressing the impacts
Disclosure of SIA report and Social Impact Management Plan Commissioner,
Rehabilitation and
Resettlement
Validation of SIA by Expert Constitute an expert group consisting of two non-official social AP State Government
Group scientists, two representatives of panchayats, Gram Shabha,
municipality or municipal corporation, two experts on
rehabilitation and a technical expert in the subject related to
the project
Recommendations of the expert group, within two months of Expert Group
its constitution, on whether the proposed project should be
implemented or not
Disclosure of recommendations of the expert group AP State Government
3. Decision by appropriate Decide area for acquisition based on the Social Impact AP State Government
Government Assessment report and the recommendations of the expert
group
Obtain consent from the affected people, where required AP State Government
Disclosure of the decision AP State Government
Create public website to upload and disclose each acquisition Commissioner,
case Rehabilitation and
Resettlement
4. Publication of Preliminary Preliminary notification shall be issued, after conclusion of SIA AP State Government
Notification and consent of the affected persons or Gram Sabha, as the
case may be, when it appears to the Government that land is
required or likely to be required in any area for any public
purpose
Update land records within 2 months of the notification District Collector
5. Preliminary survey of land Officer authorized by District collector to conduct preliminary Officer authorized by
proposed for acquisition survey and shall have powers as provided under the Section District collector
12 of the RFCTLARRA 2013
6. Disposal of objections Every objection shall be made to the Collector in writing and Collector / District
the Collector shall give the objector an opportunity of being Collector
Page 246
Milestone Process Responsibility
heard in person or by any person authorized by him in this
behalf or by an Advocate
After hearing all such objections and making further inquiries
as he thinks necessary, the Collector shall submit a report
along with his recommendations on the objections to the
District Collector for decision
7. Preparation of Rehabilitation The Administrator for Rehabilitation and Resettlement shall Administrator for
and Resettlement Scheme conduct a survey and undertake a census of the affected Rehabilitation and
and Public Hearing: families within a period of two months from the date of Resettlement
publication of such preliminary notification. Commissioner of
The Administrator shall prepare comprehensive and detailed Rehabilitation and
draft Rehabilitation and Resettlement Scheme and give wide Resettlement
publicity in the affected area
The Commissioner of Rehabilitation and Resettlement shall
publish the approved Rehabilitation and Resettlement Scheme
in the affected area
8. Development Plan for Prior consent of the concerned Gram Sabha or the Panchayats Concerned Utility
Scheduled Castes or at the appropriate level in the Scheduled Areas under the Fifth
Scheduled Tribes Families: Schedule to the Constitution shall be obtained before issue of
a notification for acquiring land in Scheduled Areas
In case there is involuntary displacement in Scheduled areas, a
Development Plan will be prepared by the requiring body
9. Publication of Declaration A declaration for acquisition of the land along with the Appropriate
Regarding Acquisition of summary of the Rehabilitation and Resettlement Scheme shall Government
Land be made by the appropriate Government in the prescribed
format.
10. Payment of Compensation The award for land acquisition shall be made within 12 months Collector
and Entitlements of the public declaration of the acquisition
The compensation shall be calculated on the basis of
provisions laid down under section 26 to section 30 and \ the
First Schedule of the RFCTLARRA 2013.
In addition to the compensation for land acquisition,
Rehabilitation and Resettlement Awards will also be provided
to each affected family
Page 247
Annexure 10 – Implementation of RTI Act
The Government of India has enacted Right to Information Act 2005 to provide for setting
out the practical regime of right to information for citizens and to secure access to
information under the control of Public Authorities29 in order to promote transparency
and accountability in the working of any public authority.
The right to information includes an access to the information which is held by or under
the control of any public authority and includes the right to inspect the work, documents,
records, taking notes, extracts or certified copies of documents/ records and taking certified
samples of the materials and obtaining information which is stored in electronic form
Any citizen can request for information by making an application in writing in English /
Telugu / official language of the areas, in which the application is being made together with
the prescribed fees.
48 hours From the time of receipt of application concerning the life and
liberty of person
30 days From the date of application
29
“Public Authority” means any Authority or Body or Institution of Self- Government established or
constituted:-
a) by or under the constitution;
b) by any other law made by the Parliament;
c) by any other law made by the State Legislature;
d) by notification issued or order made by the appropriate Government, and includes any:-
i. body owned, controlled or substantially financed;
ii. non-Government organization substantially financed directly or indirectly by funds provided by
the appropriate Government;
Page 248
5 days If the information sought for by the public relates to another
Public Authority the request should be transferred to such Public
Authority not later than 5 days of receipt of such request.
40 days If the interest of a third party is involved.
Appeal Provision: Any person who, does not receive a decision within the time specified,
or is aggrieved by a decision of the Central Public Information Officer or State Public
Information Officer, as the case may be, may within thirty days from the expiry of such
period or from the receipt of such a decision prefer an appeal to such officer who is
senior in rank to the Central Public Information Officer or State Public Information Officer
as the case may be, in each public authority:
An appeal shall be disposed of within thirty days of the receipt of the appeal or within
such extended period not exceeding a total of forty five days from the date of filing
thereof, as the case may be, for reasons to be recorded in writing. The details of the
Public Information Authority and Appellate authority for each of the utility is provided
below:
APTRANSCO
Designation under RTI Act 2005 Designation of the officer
1st Appellate Authority Director(Projects)
State Public Information Officer Executive Director(General) (Corporate
Communications)
Appellate Authority, Vijayawada Chief Engineer,(FAC) of the respective zone
Visakhapatnam and Kadapa zone
Public Information Officer, Vijayawada Superintending Engineer/OMC of the
Visakhapatnam and Kadapa zone respective zone
APSPDCL/APEPDCL
Designation under RTI Act 2005 Name of the officer and designation
SPDCL EPDCL
1st Appellate Authority Director Projects Director (I/c)
Page 249
Annexure 11 – Minutes of Disclousre Workshops
Minutes of the stakeholders’ Workshop conducted with public and MPs & MLAs on
19/08/16 at Dist. Collector’s Conference Hall, Eluru, West Godavari District on the impact
on ‘Environmental And Social issues while Implementation of ‘Power for All’
Scheme(24X7) with Financial assistance from World Bank.
Members present:
1. Sri Maganti Venkateswara Rao(Babu),Member of Parliament, Eluru Parliamentary
Constituency
2. Sri Ch.Prabhakar, Whip & MLA, Denduluru Assembly Constituency
3. Sri B.Ramesh Prasad, Executive Director, World Bank Projects & QC/APEPCL
Visakhapatnam.
4. Sri K. V. Ch. Panthulu, General Manager /World Bank Projects/APEPDCL Visakhapatnam
5. Sri Ch. Satyanarayana Reddy, Superintending Engineer/Operation/APEPDCL, Eluru
6. Public, APEPDCL officials, other departmental officials, local body members, press etc.,
Introduction:
The Superintending Engineer/operation/Eluru while delivering the keynote address
explained the various components in the proposed PFA Scheme in details and how it is
being implemented with World Bank’s financial assistance in APEPDCL. Further he
explained the public that the components like HVDS, erection of new Sub-stations and
installation of smart meters etc. were envisaged to ensure reliable and quality power
supply to all domestic, commercial & Industrial consumers. As West Godavari District
consists of predominantly agricultural area, the HVDS scheme has been proposed with Rs.
130 cr. for conversion of 9884 Agricultural services. Adding small capacity distribution
transformers to the existing system would help to improve tail end voltages and reduce
distribution transformer failures. During the course of execution compensation would be
paid for the trees cut and for the crop damaged if any. Approvals would be taken from the
authorities for Railway crossings, telecommunication channels. He further informed that
the KPMG Team had organized field visits along with APEPDCL officials to explore
Environmental and social management problems. It was further informed that any
grievances raised on executing works will be addressed with the following grievances
redressal mechanisms.
Substation Advisory Committee Meeting
District Electricity committee Meeting
Spandana Program
Prajavani
Consumer Grievance Redressal Forum
Judicial Interventions
Mr. B.Ramesh Prasad, Executive Director explained the importance of ‘Power for All’
scheme with World Bank Assistance and he has introduced the KPMG team Sri P.Ramesh,
Rahul Singh, & Rama Subrahmanyam Environment Specialists to the gathering.
Mr. Ch. Prabhakara Rao, Whip & MLA / Denduluru addressed the gathering and suggested
that the mistakes cropped up while execution of HVDS works earlier should be taken care
of in this project. He expressed concern over the fire accidents occurred in fields due to
Page 250
passing of electrical lines in the oil palm gardens. He has advised the utility to shift such
lines to road side to avoid accidents to the extent possible.
Page 251
NREDCAP / Satyanarayana Murthy/Development Officer:
He has opined that HVDS system is very useful for Agl consumers. The fire accidents in
palm oil & coco plantations could be avoided if the HVDS lines are erected in road
margins. Insulated wires may to be used in maximum extent to mitigate the problem.
Reply : Will be examined
ZPTC / T.Narasapuram
He has advised to enhance the PTR Capacities in the substations
The Superintending Engineer/operation/Eluru informed that 27 PTRs were enhanced
recently from 5 to 8 MVA.
Page 252
Minutes of the stakeholders’ Workshop conducted with public representatives and MLA
on 29/08/16 at Conference Hall, Corporate Office, APSPDCL, Tirupati,Chittoor District on
the impact on ‘Environmental And Social issues while Implementation of ‘Power for All’
Scheme(24X7) with Financial assistance from World Bank.
Members present:
1. Smt Sugunamma, Member of Legislative Assembly, Tirupati
2. Smt T Vanaja,Executive Director, Projects /APSPDCL Tirupati
3. Sri D.Yesunathu, Chief General Manager/HRD/APSPDCL/Tirupati
4. Sri K Nagaraju, SE/Civil/APSPDCL Tirupati
5. Prof Sri Murali, Dept. of Civil Eng., SV University, Tirupati
6. Prof Sri Marutheeswarrao, Det. Of Electrical Eng., SV University, Tirupati 7
7. Prof Sri Damodaram,Dept. of Environmental Science, SV University,
Tirupati.
8. Sri B Narasappa, DSP,CCS, Tirupati
9. Sri V.Munichandra Reddy, ROPE ( NGO), Tirupati.
10. Sri N.M.Mohan, RIPE ( NGO), Tirupati.
11. Sri M.Narasimhulu Naidu, Farmers Association,KVBPuram
Mandal,Chittoor Dist.
12. Sri Dhananjaya Naidu, Agriculturist, Nagari.
13. SriP.N.Chandra, Member, Sri Kalahasteeswaraswamy vari Trust Board.
14. M.Shivaji, Imperial granites(P) Ltd.,Nagari
15. Sri P.Venkatramana Reddy, M/sUniversal Chemicals (
India),IDA,Gajulamandyam
16. KPMG Team Mr. Rahul Singh, Mr.Anand Kulakarni and Mr.Ramesh P
17. Public, APSPDCL officials,Farmers, , local body members, Media and other
departmental officials.
Page 253
Introduction:
The Executive Director, Projects /APSPDCL Tirupati while delivering the keynote address
explained the various works involved in the proposed PFA Scheme in detail and how it is
being implemented with World Bank’s financial assistance in APSPDCL. Further she
explained the public that the works like HVDS, erection of new Substations, UG Cabling,
Covered Conductor and R & M of Sub-Stations, etc., were envisaged to ensure reliable,
qualitative and affordable power supply to all domestic, commercial and industrial
consumers. As Ananthapur & Kurnool Districts consists of predominantly Agriculture area,
the HVDS scheme has been proposed with Rs.1082 Cr duly adding small capacity
distribution transformers to the existing system which would help to reduce distribution
transformer failures. Erection of new sub-stations & strengthening of lines will improve tail
end voltages and reduce AT & C losses. By installation of smart meters, consumer can
know their power consumption from their home. All the proposed works under World Bank
will not have any impact on the environment and social aspects and will further boost up
the financial status of the farmers. During the course of execution compensation would be
paid as per Govt. rules for the trees cut and for the crop damaged if any. Approvals would
be taken from the appropriate authorities for Railway crossings, telecommunication
channels. She further informed that the KPMG Team had organized field visits along with
APSPDCL officials to explore Environmental and social management problems. It was
further informed that any grievances raised while execution of works will be addressed
with the following grievances redressal mechanisms.
Substation Advisory Committee Meeting
District Electricity committee Meeting
Spandana Program
Consumer Grievance Redressal Forum
Page 254
Further she explained the importance of ‘Power for All’ scheme with World Bank Assistance
and she has introduced the KPMG team Sri Anand Kulakarni and Rahul Singh, Environment
Specialists to the gathering.
Very much impressed by the various measures taken by the APSPDCL in extending
uninterrupted, reliable and affordable 24X7 power supply to the consumers and
requested their co-operation in moving the project ahead. She has further informed
that the works involved have no effect on environment and social aspects.
Page 255
Public suggestions and concerns
Page 256
Reply: In the present HVDS systems AB switches have proposed old
conductor will be replaced with new conductor wherever necessary.
KPMG Team
KPMG Team explained how the survey was conducted in 8 Districts and ascertained
the inputs from the public. The team understood that HVDS project is environment
friendly and there were no social
issues reported during their visit.
Irrigation department, Forest
Department and Panchayatraj
Department also touched and
obtained feedback during survey.
KPMG Team has expressed that
this project is very Energy Efficient
and space requirement is also very
less and there are no major
problems and no involvement of
private land.
Page 257
Page 258
Page 259
Page 260
Minutes of the stakeholders’ Workshop conducted with public and NGOs on 03/09/16 at
Conference Hall APSPDCL Zonal Office, Vijayawada on environmental And social issues
and their management, while Implementation of ‘Power for All’ Scheme(24X7) with
Financial assistance from World Bank.
Introduction:
The key note address was delivered by Director Projects, APTRASNCO. He informed that
the proposed projects under the World Bank funding will be implemented in 5 districts –
Krishna, East Godavari, Prakasham, Kadapa and Nellore. He also informed the gathering
that the purpose of the proposed project is to supply quality and reliable power to domestic
and industrial consumers and to ensure 100% households have electric connection by
March 2017. He further stated that personnel from Revenue Department, Police and other
government departments are present for the consultation in addition to the members of
NGOs, farmer leaders and farmers. The list of attendees is provided as annexure to this
document.
Continuing his address, Director Projects said that KPMG has been hired by APTRASNCO
to undertake the Environment and Social Assessment of the proposed projects.
Consultations were undertaken by KPMG with various stakeholder groups including the
staff of APTRANSCO, revenue department, forest department, farmers, women groups and
tribal, to draft an Environment and Social Management Framework, the meeting today is
to get your inputs and suggestions on the Framework.
The key note address was followed by a presentation on the Environment and Social
Management Framework, after which suggestions and concerns were requested.
Public suggestions and concerns:
Mr. Gopalkrishna Rao, State Apex Committee, Water Resources Department
He stated that fair amount of compensation for tower footing and crop damages are
being paid in Andhra Pradesh for past 3 years only, before that no compensation was
paid. He recommended that compensation on land diminution value should be paid for
RoW corridor, 100% of land value should be paid as compensation for tower footing
and a higher compensation should be paid for crop damages. He suggested that for
calculating compensation for crop damage market value of per square yard of crop
should be considered instead of current practice of considering market value of per acre
of crop. He also stated that prevailing land cost is high in some districts like Krishna
(INR 50 lakh/ acre), therefore higher compensation should be paid in such districts.
Response – Compensations are decided by Revenue Department and APTRASNCO has
no role to play in calculation of compensation
Mr. Narsima Reddy, Ex-Officio Member of Institute of Engineers
He highlighted that farmers should receive fair compensation for RoW corridor and
compensation should be based on diminutive land value. He further stated that
compensation should also be based on the location of the project area, for instance,
more compensation should be paid in areas closer to urban centers relative to
compensation paid in rural areas.
Response – Compensations are paid as per existing rules and policies of Government
of Andhra Pradesh. The compensation can be revised in future, if the policies/rules are
changed or modified.
Person from public
Page 261
One of the attendees suggested that while designing the route plan, APTRANSCO
should consider the layouts approved by Revenue department so as to avoid any areas
with any planned construction.
Mr. Venugopal Rao, Prof and Head, Department of EEE, PVP Siddhartha Institute of
Technology
He recommended that communication amount of compensation should be listed and
communicated to the farmers.
Another person from Public
One of the attendees stated that compensations should be paid as per Indian Electricity
Act, 2003. He observed that even private companies are not paying compensation. He
said that as per law EIA and SIA should be conducted for project’s worth INR 100 Cr. He
further requested TRANSCO to bring transparency in compensation records
NGO Representative
NGO representative welcomed the project and appreciated that the project would
ensure uninterrupted quality power supply to all house holds
Closing Remarks:
The closing remarks were delivered by SE/OMC/Vijayawada. He said that the concerns
expressed during the workshop will be considered and appropriate measures would be
initiated.
Page 262
Page 263
Page 264
Thank you
The information contained herein is of a general nature and is not intended to address the circumstances of any particular individual or
entity. Although we endeavor to provide accurate and timely information, there can be no guarantee that such information is accurate as of
the date it is received or that it will continue to be accurate in the future. No one should act on such information without appropriate
professional advice after a thorough examination of the particular situation.
© 2016 KPMG, an Indian Registered Partnership and a member firm of the KPMG network of independent member firms affiliated with
KPMG International Cooperative (“KPMG International”), a Swiss entity. All rights reserved.
The KPMG name and logo are registered trademarks or trademarks of KPMG International.
Page 265