Design and Construction of Warehouse in Mutare - Specifications
Design and Construction of Warehouse in Mutare - Specifications
Design and Construction of Warehouse in Mutare - Specifications
1. Earthworks 37
3. Warehouse Floor 37
3.1 Floor Hardness & Concrete Sealers 37
3.2 Floor Joints 38
3.3 Floor Strength 38
3.4 Floor Flatness 38
3.5 Damp Proofing 38
3.6 Ant Poisoning & Termite Proofing 38
4. Warehouse Structure 38
4.1 Internal Columns 38
5. Air Conditioning 39
5.1 General Air-Conditioning Specifications 39
6. Walk in Coldroom 39
6.1 General Design Requirements 39
6.2 Refridgeration Requirements 39
6.3 Electrical 39
6.4 Controls 40
7. Warehouse Height 40
8. Roof Structure 40
9. Roof Sheeting 40
12. Brickwork 42
15. Balustrades 42
16. Protection 43
16.1 Bollards 43
16.2 Building Column Protectiion 43
20 Offices 49
20.1 Reception Area 49
20.2 General Office Area Detail 49
20.3 Boardrooms 50
20.4 Air Conditioning 50
20.5 External Office Façade 51
20.6 Internal Divisions 51
20.7 Floor Finishes 51
20.8 Wall Finish 51
20.9 Ceilings 52
20.10 Doors and Ironmongery 52
20.11 Doorframes 52
20.12 Shop Fittings 53
20.13 Aluminium & Glazing 53
20.14 Plumbing 53
21 Testing 55
22 Consultants Design 55
23 Exclusions 56
2
1. EARTHWORKS
Demolitions – Tenderers are to visit the site and familiarise themselves with the existing
structures that needs to be demolished along with site conditions to clear and grub the site.
Building platform to be compacted to clients Engineers approval.
Compaction tests will be taken by a soils laboratory and properly recorded.
General founding to be in natural ground and/or compacted fill and to the tender specification
and satisfaction and client representatives satisfaction.
Platform earthworks for the future extension is to be completed.
On completion of the works the site will be cleared of all rubble.
Layer works designs are clearly shown on drawings but to be confirmed by clients Civil Engineer.
All concreting work is to be carried out in accordance with the design of a competent Structural Engineer
with placing of reinforcement in accordance with details supplied. Strengths of concrete are specified
for the various applications and all work is to be carried out under the supervision of the clients
appointed Engineer. Surface beds are to be cast in panels or to have expansion/shrinkage saw cuts.
When premises are located on suspended slabs, then the use of post tensioned floors is not permitted.
All concreting work shall be carried out in accordance with the relevant Codes of Practice for the
particular type of work.
3 WAREHOUSE FLOOR
As a generalisation, the warehouse floor thickness should be designed to accommodate for pallet and
racking loads over a 25-year design life.
Joints should include construction joints; saw cut (contraction) joints and expansion joints to
accommodate the various requirements that arise during the construction as well as the long
term serviceability of the floor.
Joints shall be properly treated and filled with a suitable joint filling compound, capable of
carrying the traffic of lift trucks with polyurethane wheels.
The floor must be power floated and a specialist floor hardener must be applied to provide a
dust free surface for increased durability. The floor surface hardener/sealer is to prevent
discolouration of the floor from the spillage of petrochemical products.
‘Allowable values of the properties of flatness for free movement areas’ Concrete Society
Technical Report № 34 fourth edition.
All floors and walls are to be damp proofed and as required for good building practice in the
particular local area.
Place surface bed directly in damp proof heavy duty polythene sheeting over compacted sub
grade laterite fill.
To be allowed for.
4 WAREHOUSE STRUCTURE
An optimal structural grid will be determined in conjunction with the structural and logistics
engineers in order to optimise the benefits a cost effective yet functional warehouse layout.
Where required in open storage areas, internal columns should be painted 2m high (chevron
style black and yellow) to improve their visibility to truck and forklift operations. Protective
barriers need to be placed around columns to protect the structure from damage incurred by
impact. Columns requiring protection will be specified by client and the appointed industrial
consultants.
5 AIR CONDITIONING
4
5.1 General Air-Conditioning Specifications
6 WALK IN COLDROOM
Strip Curtains: To be installed at all external doors – clear type, industrial Grade
6.3 Electrical
Main power supply to coldroom panel must be a dedicated supply from the generator
panel.
Complete air conditioned warehouse power supply to be supplied with an isolator rated
according to tenderers Electrical Engineers specification.
5
Individual compressor unit’s circuit to be supplied with individual circuit breakers
according to specification.
Compressor to be fitted with an overload of correct value to indicate compressor trip.
Compressor trip indicator light to be installed in same position as the Carel controller.
Power for the coldroom lights to be supplied form warehouse light circuit.
Compressor unit must supply power to its own controlling Carel controller.
6.4 Controls
Compressor unit must be controlled with a Carel controller model IRDRC (din mounted
and contacts can be changed to normally open/closed to allow one to configure your own
alarm system inputs/outputs).
Controller to be mounted in control room (position to be specified by NatPharm).
Controller to be mounted in a suitable DIN rail enclosure.
7. WAREHOUSE HEIGHT
An optimal height has been selected to suit warehouse operations based on the storage of optimum
modules of pallets.
It is recommended that a global maximum working height be used allowing forklift reach limitation,
eliminating facility/forklift damage.
8. ROOF STRUCTURE
As a generalisation, it is envisaged that the warehouse structure will consist of hot rolled structural
steel rafters or trusses depending on the final design optimisation. The design should minimize the
presence of dust collection surfaces. The roof should be designed for self-weight, maintenance loads
with insulation, lighting and the installation of solar panels by the client that requires a design weight of
20kg/m2.
All structural steelwork will be designed in accordance with local and international standards.
9. ROOF SHEETING
The warehouse needs to be a thoroughly weather-tight facility. The design must ensure that extreme
weather is taken into account; details of sheeting, flashing, counter flashing etc., need to be clearly
defined during the construction phase of the project. The profiled steel sheeting needs to be suitably
thick and purlins at close enough centres to support construction personnel and maintenance
personnel without damage to the sheeting. Roof slopes need to be selected to suit the selected roof
sheeting water carrying capacity. Roof sheets are to be in single lengths. A 10 Year back-to-back
materials and workmanship guarantee is to be provided.
All cavities etc., which might induce the nesting of birds or ingress of vermin must be closed. Anti-
bird perch material should be fixed to all exposed trusses.
The roof system to consist of GRS Zip Tek 440 patented roofing solution, which should be erected by
a GRS approved installed. The system consists of 0.58mm Chromadek, colour Fish Eagle White
profiled sheeting, all installed with concealed fixing brackets, complete with all flashings and fixtures.
6
All roof sheeting to be coated with Radiant Barrier Paint as described below.
Radiant Barrier Paint to be applied as per the specifications below:
Minimum required Functional, Performance and Technical specifications for each item:
1
2 Item 1: Radiant Barrier Paint
3 Non-toxic: Free from harmful chemicals such as Alkyl phenol ethoxylates (APEO), heavy metals and
with low Volatile Organic Compound (VOC)
Fire resistant
Water resistant
4 Coverage for optimal Radiant Barrier result: Approximately 2-3 m2 per litre per coat (Maximum 2
coats) applied by roller.
Material to be painted: Adequate for metal, timber and masonry surfaces.
Outside conditions: Adequate for outdoor surfaces of structures situated in tropical regions.
Maintenance: Able to withstand washing with soapy water
Colour: White*
5 Drying time (touch dry): at 25 C dry conditions: Less than 3 hours
6 Application Methods: By brush, roller, spray
7 Storage temperature: Able to maintain its properties when stored up to 30 Co
8 Shelf life: Minimum 2 years
9 Compliance with International standards and or certifications. Please state which here and provide
copies as annexes.
10 Warranty: at least 8 years performance warranty.
11 Minimum stock available during the duration of contract: sufficient paint to meet the needs of an
average warehouse of 4,000 m2.
12 Maximum delivery time to FCA point: 2 Weeks
The tenderer is to make provision for all necessary thermal insulation to roofs and in accordance with
the attached bill of quantities. All insulation materials to be fire rated.
12. BRICKWORK
No load-bearing brickwork is permitted within the premises without the written consent of NatPharm.
Where consent for load-bearing brickwork is given the tenderer is to provide a sign clearly indicating the
location and extent of load-bearing brickwork.
Mortars and design mixes for mortars are to be in accordance with the relevant Codes of Practice and
shall be approved by the supervising Consultant.
Internal and external walls in the warehouse to be smooth plastered and painted with a high quality
washable paint.
Generally, the external envelope is to consist of concrete masonry to a typical height as per the
drawings and be suitably braced and stiffened
Vertical cladding should be I.B.R. sheeting to same material specification as the roof sheeting fixed
vertically to steel girt rails with all trims, sills and closure pieces.
a) Type: Sectional up and over roller shutter door with viewing panel
b) Size: 3000mm Wide x 4500mm High - 2-off
15. BALUSTRADES
Balustrades to office staircase will be stainless steel balustrades. Profiles and size limitations to
meet minimum BS or SABS specifications.
All external staircases and ramps to receive wecro-lock, ball and stanchion type balustrades.
Profiles and size limitations to meet minimum BS of SABS specifications.
8
Ramps to receive standard armco barriers.
16. PROTECTION
16.1 Bollards
All doors and access ways are to be protected with steel bollards standing 1000 mm above
ground. For additional strength, outside bollards are to be sunk into the ground and keyed into
position.
It should be noted that the specification shall be in accordance with Local and International Standards
as noted within the local by laws pertaining to Electrical Installations of premises.
An allowance should be made for the main incoming telecommunication provider’s provisions.
Local council shall confirm that the site shall have telephone infrastructure provisions available
to the site, within the project duration.
Mains Power: -
A sub-station to be provided for the provision of a suitable power to the site. The sub-station
to be located no more than 100m from the warehouse infrastructure.
Client requires a main consumption KWH/KVA meter positioned with ease of reading for the
checking of the supply authority metering values.
The installation of a transformer shall be protected by a Circuit Breaker having the following
protection: -
Earth fault.
Over Load.
Bucholz protection.
Over temperature protection.
Normal and clean electrical supply earthing certificates are to be issued for both of these, the
appropriate cable will be specified by the electrical engineers. (Computer earth to link to
Telecommunication Provider earth)
The main distribution board shall be installed within the general warehouse area to suit the
areas of largest electrical consumption to be determined by the tenderers electrical engineer
and the logistics consultant. It is of paramount importance that the board be rated and certified
to the correct fault level as required by the transformer power supply.
9
The construction of all distribution boards is to be of sound structure, with the following: -
Hinged Panels.
Metal square key catches.
Engraved Labels
Legend cards to be fitted onto panels /doors as required.
All feeds over 200 amps to be coppered.
No welding cables to be used under any conditions.
No reverse circuit breaker feed will be accepted.
The main distribution board is to have a KWH meter or similar to confirm
configuration, this is the same as noted above as the check meter.
a) Normal – Orange
b) Emergency – Red
c) UPS- Blue.
A standby generator is included in the bill of quantities and the tenderer to allow for the
following: -
It should be noted that besides lighting, the standby plant will feed the office and the battery
bay.
Main Feeders: -
It should be noted that besides the standard power provisions to the warehouse and offices
the following would be required to be allowed for as the base submission: -
Ventilation/Cooling – Warehouse Main Plant
Battery Bay Distribution Board and Reticulation
Other power requirements are to be provided for inclusive of the distribution boards and the
associated requirements.
10
Note: Lighting and the general installation to this area to be vapour proof unless rationalized
alternatively.
All units to be of type welding plug, male and female components to be provided.
Power for air conditioning and ventilation system is to be provided for as per the nominated
air-conditioning contractor.
Lighting: -
General: -
Table 1
The light fittings are to be so positioned that they provide for the racking and bulk storage area
layout, ensuring that the light level design is consistent within the racking area and the open
storage area.
External lighting will be individually powered solar lights 40W with 6m poles which will provide
lighting to the compound and exterior fence. Lighting to be inclusive of all solar requirements
and individual foundations. The positions of the solar lighting poles are shown on drawing
number CHO-2-001 Site Plan.
Emergency/escape lighting system shall conform to the requirements of the Local Authority’s
Fire Officer.
Emergency lighting shall be provided as a minimum to each external exit door, each internal
emergency exit door, changes in direction or level along emergency access routes and as
11
appropriate to open plan and other areas.
Gate house: -
Lighting as required.
Power, 1 Off Normal SSO and 1 Off Telephone outlet on power skirting at 1200 affl.
Special Notes: -
No surface wiring will be allowed, all wiring to be either cast in, in ceiling voids or in
galvanized conduit. All distribution boards are to be manufactured by an approved
manufacturer; client must approve size of the distribution boards, general arrangement
drawings prior to manufacture. (All boards should be fault level cascaded)
All plant rooms and areas must be provided with small power and lighting as per the industry
norm should it not be detailed specifically above.
Lighting is to be provided under any loading canopy as indicated on the clients drawings.
Lighting circuits are to be provided for the coldroom lighting, lighting to these areas by others.
As a generalization it is anticipated that hose reels and portable fire extinguishers will be required as a
norm. External hydrants would also be a requirement. An 800mm border should be left as fire access
around the internal perimeter of the warehouse.
It is envisaged that hand held fire extinguishers will be required within the warehouse. The
size, type and final locations should be determined based on the appropriate fire code and
internal warehouse layout. (Halon extinguishers are not to be used.)
Fire Extinguisher Cabinet (FE-1): Steel unit constructed with rolled edges for semi-recessed
installation. Steel tub shall have inside dimensions of 267mm wide x 601mm high x 152mm
deep with welded joints grind smooth.
Use rated tub construction where applicable
Trim type: Radiused
Door: Solid door with break glass insert and key lock.
Acceptable Product: J.L. Industries: Ambassador Model 1015B20
Fire Extinguisher Bracket (FE-2): Wall mounted bracket sized for each extinguisher.
Manufacturer’s standard bracket with strap to secure fire extinguisher.
Provide bracket at each mechanical and electrical room
Acceptable product: J.L. Industries: Model MB846, for ABC Dry Chemical
Fire Extinguishers: Provide hand held fire extinguishers as per approved fire plan/design.
12
18.3 Fire Water Supply and Pressure
Appropriate tanks, pumps and standby pumps for the total fire system (hydrants and fire hose
reels) must be installed with pump house and all peripherals.
A conventional fire alarm system needs to be provided with a central control panel. The
position of the panel needs to be discussed further; a good position would be close to the
main entrance. The system should allow for smoke detectors or beams mounted at high level
within the warehouse (to be installed by another party). A detection grid should be provided for
in the office area, which has a high fire risk. Small bells should be placed in the office
environment to maintain maximum noise levels to acceptable levels. Flashing xenon beacons
should be provided in areas with high ambient noise levels.
Break glass units should be provided on the final escape doors from the office. Wiring should
be in red flexible fire resistant cable, which should be installed on cable trays within trunking.
18.5 General
An emergency assembly area needs to be allocated and demarcated with signage. It must be
away from product and buildings.
The Guardhouse is to be designed to house 2 security guards who perform search and
access control functions.
The Guardhouse design is to suit general aesthetic of the office building with adequate visibility
to monitor all movements at the entrance.
19.2 Guardhouse
A guardhouse constructed from 150mm block work with plaster and paint finish on internal and
external walling over a 450mm concrete foundations strip, 150mm thick solid block wall
foundation, 75mm thick reinforced slab complete with mild steel door and aluminium window
frames with glazed sliding window and solid timber door leafs, roofed with white IBR Chromadek
roof sheeting on steel frames including 4mm Alucusion insulation, electrical fittings and plumbing
fittings as shown on Architects & Engineers drawings. All to comply with the Standard
Specification for Materials and Workmanship for Building Works for the Government of
Zimbabwe.
Electrical room constructed from 150mm block work with plaster and paint finish on external
walling over a 450mm concrete foundation strip, 150mm thick solid block wall foundation, 75mm
13
thick reinforced slab.
The Electrical Room and Battery Charging Stores, all as required by the Electricity Department,
the Electrical Consultant and the Telephone Authorities are to be provided by the Professional
Team in accordance with the relevant Supply Authority's requirements. Everything necessary to
conform with the proper Codes of Practice in this regard is to be provided.
A Low flash warehouse needs to be specified in accordance with the provisions of the OSH
act the local authority and local fire department regulations. (Quantification To be provided
during detailed design.)
Pending a detailed logistics report, the Professional Team should assume the need of new
paved roads serving the medical storage hub facility.
This allowance will need to include feeder roads from municipal roads, loading and unloading
areas & truck turning areas and staging area. Roads and hard standings will generally consist
of 80mm thick interlock paving blocks. Pavement thickness should be selected to suit
anticipated axle loads and design life (25 years*) as well as subsoil conditions. The paving
blocks and sub-base is to be properly engineered and designed.
Paving must be designed to take cognisance of all vehicle turning movements and incorporate
flexibility with respect to vehicle sizes, etc.
Road markings and safety signage should be provided for. Side walks should be landscaped.
Road positioning should be inline with the relevant legislation regarding distances from
building, rail lines and site boundaries.
19.6.1 Construction
The construction of the Parking Areas shall be carried out in accordance with the
design specification.
The drawings are to show all parking areas and driveways, properly demarcated,
and showing kerbs, drive-ins, parking bays and general circulation. Minimum size of
internal parking bays to be 2,5 x 5m. Minimum width of internal roadways to be 6
500 and main roadways to be 9 000.
All road markings, traffic signs, pole signs, speed hump etc., shall be provided
including inter alia, the following: -
a) Disabled parking bays for persons with wheel chairs must be provided per the
requirements of the local authority.
d) Landscaping and planting including automatic sprinklers, plus areas within the
Site with suitable trees, shrubs, ground cover, lawn, etc.,
g) 6 No. cantilevered shade ports are required per site (to be determined in
detailed design phase)
Clearvu Fence will be installed on the gateways as per the logistics study recommendation.
Gates should consist of sliding steelwork gates, suitably painted. – Height: 2.1m. Provision is
to be made for automation and access control.
Closed circuit TV needs to be considered as an option. The feasibility of installing cable ducts
and draw chambers within the medical storage hub site for future installation of CCTV in
operational sensitive areas needs to be evaluated. Suitable sleeves and conduits are to be
provided and chased into brickwork.
Provide for the marking of pedestrian areas and “zebra crossings” etc. (To be provided during
detailed design.)
All personnel access should be controlled using turnstiles (dual turnstiles at the gate,
warehouse entrance as well as office area entrance. Only one access control point into the
warehouse and office is required, however consideration needs to be taken of any emergency
exit requirements
Access into the various areas will be controlled as per authorisation level of the individual
affected. Furthermore, all turnstile access points need to incorporate a manual, lockable,
pedestrian gate for access by disabled personnel and for managing exceptional situations.
The installation of an internal warehouse alarm system should be considered only once the
internal equipping design has been finalised. The alarm installation will be under direct advice
from Protection services upon the completion of the warehouse design.
Access control technology will be based on a access card throughout the warehouse.
Security access
Warehouse staff
Office staff
Visitors
20. OFFICES
It is envisaged that a set of main offices will be provided with a mezzanine above the despatch area
(to facilitate prompt communication and effective ground level management).
15
The layout has been designed by a competent person
Potable water will be required for drinking and tea / coffee making in the kitchen as well as
hot water for washing purposes and boiling purposes.
Power points at a rate of 1No. x 15A plug point per 15m2 of office area.
Lighting in the dispatch offices and toilets area should be via 400 LUX fluorescent lights
either recessed or surface mounted to suit ceiling type.
Lighting to the offices to be 500 Lux of fluorescent recessed ceiling mounted light fittings
within lay-in ceilings and recessed down lighters to flush plastered areas.
Containment for provision of telecomm cabling (both telephone and data network) shall be
made in the dispatch offices by means of skirting trunking or similar arrangement – 3
Compartment power skirting to all external walls of offices is required.
It is envisaged that the offices will be protected by hand held fire extinguishers and hose
reels. The size, type and location of these appliances will be determined based on fire
regulations.
It is envisaged that a despatch office, receiving office, mangers office and warehouse staff
green area is provided within the new warehouse facility will be in the form of self
contained units within the actual storage space within close proximity of the despatch
area. (To be supplied during detailed design)
20.3 Boardrooms
The facility should provide fresh air at a rate of 8l/s per person* into these spaces to achieve
comfortable conditions. The fresh air should be connected via individual space terminal air
conditioning units, thus providing necessary pre-conditioning to the incoming air. Exhaust will
be by natural ex-filtration into the warehouse space or via forced exhaust to toilet
accommodation if as anticipated, it is adjacent to the office spaces. Make-up air should be
provided by the office air conditioning system via transfer where available.
It is envisaged that offices will either be in the form of split-packaged units, possibly multi-
splits with suitable room side units in the office spaces and the condensing units at a suitable
external position. Each unit should then be sized to cater for internal and external loads of the
space served with allowance to treat incoming fresh air. The climate specifications within the
dispatch offices are 23oC ± 2 oC*. Alternatively, an open plan office structure would require the
same specifications.
Ducting system to open plan office area to be considered. Correct BTU to be specified for
each area volume.
380 Volt 3 phase 4 wire electrical supply to the switchboard on each of the air conditioning
units.
Water supply adjacent to the air conditioning units.
16
Permanent drain points adjacent to each air conditioning unit.
Provision for framed openings through the building fabric to accommodate the air
conditioning equipment.
Provision of concrete bases for the equipment.
The toilet accommodation should be provided with a forced exhaust system to insure a
minimum of 10 air changes per hour*, and to comply with the National Building Regulations.
Blockwork plastered and painted with a suitable finish to be maintenance free for the first 5
years and features to create a pleasing architectural aesthetic.
Offices to be generally open plan with a number of cellular offices subdivided with drywall
partitioning with aluminium skirtings both sides. Partitioning to meeting rooms and
boardrooms to be suitably sound proofed. An allowance of 10m per 100m2 of office area
should be provided and office doors at a rate of 1 door per 10m of partitioning.
Walls around tea kitchens, computer rooms, ablutions, stair wells, document storage, etc., to
be of brickwork.
Floor tiles laid on concrete floor to ablutions, tea kitchens, canteens, receptions and main
stair
All office floor areas to receive tiles
Plaster:
o One coat plaster – Portland cement plaster built-up to total thickness of 15mm
with a fine-sand, wood float-texture over concrete masonry units. Plaster mix
materials, and accessories shall be according to Standard Specifications for
Materials of the Republic of Zimbabwe, Interim Metric Edition (All exposed
blockwork to be plastered).
Exterior Painting:
o To the extent practicable, materials with an exterior exposure will be pre-
finished by the manufacture.
o Paint System Dulux or Plascon: Semi-gloss, finish for hollow metal service
doors and frames. Colour as selected by the Project Manager from the
manufacturers full range of available colour.
o Paint System Dulux or Plascon: High-performance, opaque urethane finish for
structural steel with exterior exposure.
Materials Mix:
o Cement:
Portland cement
Aggregate: Well grade natural sand, clean, sharp and suitable of
plastering.
Water: potable and free of substances that could damage plaster, lath
of accessories.
Interior Painting:
o Painting System for CMU walls and partitions:
Paint System Dulux or Plascon: Semi-gloss, 100 percent acrylic-resin
latex finish.
Base 1 coat block filler applied to achieve a smooth surface
17
Primer 1 coat concrete primer
Finish 2 coats, minimum, PPG, 6-50 Series, Speed hide Interior Latex
Enamel finish
Ablutions and toilets – 2.1m high with eggshell enamel paint finish above
Tea kitchens and restrooms – 600mm High tiled splash back behind fitting/sink units
All internal window sills to be tiled
20.9 Ceilings
Suspended vinyl clad ceiling panels size 1200 x 600 to offices and circulation areas
Flush plastered ceilings in reception areas and boardroom
Recessed shadow line cornices throughout
20.11 Doorframes
18
Steel/Aluminium Doorframes – furnish in configuration for single doors with or without
transom panels or sidelights as schedules.
o Steel doorframes:
Unitary frames: One-piece with casing faces welded and ground
smooth. Stops shall have hairline-tight butt joints.
Fully welded frames: one-piece with casing faces, rebates and stops
welded from behind and ground smooth.
Fabrication:
Base metal: Cold-rolled, steel sheet, 16-gauge, minimum.
Sizes: As schedule by manufacturer with AAAMSA compliance.
Finish: Prime painted for scheduled paint finish.
Locations: Use unitary frames throughout the work unless fully
welded frames are expressly indicated.
Use fully welded frames.
o Aluminium doorframes:
Doorframes to be compatible to partition system specified.
Toilets: -
Granite vanity tops with under slung basins to office toilets
Tea Kitchen: -
Formica counter tops with stainless steel drop-in sink and with cupboard and drawer units
below and wall hung units to the full extent of the wall space
Windows are to be epoxy powder coated aluminium framed with clear/frosted glass to NBR
requirements and sealed with suitable sealant. Window sills externally are to be fibre cement
sills, painted with a roadmaking/or similar paint finish.
Main entrance door to be double leaf epoxy powder coated aluminium framed with safety
glazing and suitable handles, door closers and electronic door lock.
Aluminium windows:
AAAMSA Architectural Grade Standards.
Clear glass as per safety standards.
Openable: Single hung
Fixed pane
Exposed Aluminium Finish Architectural Class 1 clear anodized finish (minimum thickness
18 microns).
Concealed Metals:
o Aluminium: chemically treated with alodine process.
o Steel ASTM A123, G90, hot dip galvanised or AAASMA equivalent.
Mirror glass:
(GL-91): ASTM C1036, Type I, Class 1 Quality q2, 17mm thick glass mirror or SABS
equivalent with polished bevelled edges, furnish with brushed stainless steel mirror clips
with concealed fasteners (above all wash hand basins).
Size of mirrors: 900mm H x 600mm W
20.14 Plumbing
19
Leadership in Effective Energy Design (LEED) principles
Relevant Local Regulations
Plumbing Fixtures
o All plumbing fixtures would be of standard quality with features of:
Durability
Water saving in line with LEED, for instance, water closet with 6 litres to 6.5
litres flush cisterns, aerators for minimal usage of water on taps, press
demand taps, electronically operated taps, electronic flushing urinals,
emergency shower and wash hand basin outside the battery changing
room.
Hot Water
o Under counter 10 litre geysers to be installed in kitchens and office bathrooms
20
The number, size and type of sinks, basins and other sanitary fittings are all to be in accordance
with the requirements of the Local Health and Licensing Authorities.
Hot and cold water is to be supplied to all wash hand basins and sinks and suitably sized
geysers positioned locally to avoid long pipe lengths.
21. TESTING
Preconstruction Testing: Submit certified copies of test reports. If testing is more than 6-months
old submit certification that products delivered will be identical in performance to tested products:
o Mortar Tests: Test mortars for conformance to BS requirements for the indicated mortar
types.
o Concrete Masonry Units: Test each type of concrete masonry unit indicated, for strength,
absorption and moisture content using ASTM C140
o Windows:
For structural performance use ASTM E 330 or AAAMSA equivalent.
For water resistance test use ASTM E 31 or AAAMSA equivalent.
For air infiltration testing use ASTM E 29 or AAAMSA equivalent.
For condensation resistance factor use AAMA 1503.1 or AAAMSA equivalent.
21
Disciplines to be included:
Civil Engineer
Structural Engineer
Electrical Engineer
23. EXCLUSIONS
Although specifically excluded from the above Project Specification, some of the following items could
be undertaken as extensions to the construction contract once the necessary information becomes
available, these items eventually attended to by Professional Team at the Lessee’s request, these
shall be at an extra cost to be agreed upon. Notwithstanding this, all necessary builder’s work
pertaining to this specialist work is to be carried by the contractor’s Professional team.
22