Dowel bar 32mm dia @ 1000 mm c/c (transverse direction) in two rows
has to be provided 400 mm into raft and 600 mm below ground (1000 mm
length).
Existing abutment wall will be chipped vertically or stepped so that
extended wall can be properly bounded. After concreting gap has to be
grouted with cement mortar 1:3.
RCC Bed block has to be anchored with PCC Abutment/Pier
Extension.with 8mm dia rods at regular interval (say at 500mm c/c in two
rows)
Top level of wall to be checked for revised thickness of slab.
Chamber of 2% has to be provided on top of slab.
Existing slab has to be broken for 300 mm width and distributor
reinforcement of both slabs should be overlapped with anchor bend and
then continually concreted.
Tar paper bearing and asphaltic plug expansion joint has to be provided.
75 mm thick wearing coat (cc) will be provided over both existing slab and
extension with nominal reinforcement of 8mm dia at 150mmcc at bottom.
Reinforcement for top slab has to be as per standard MORTH drawing for
6.4m effective spam .Slab thickness shall be 500mm.