Earthworks
Earthworks
Earthworks
EARTHWORK
Excavation, hauling, and placing of soil, rock,
gravel or other material found below the surface of
the earth
EARTHWORK
1. Measurement of earth materials in the field
• Conversion
• 1 yard = 0.9144 m
• 1 yard = 3 ft
Swell and Shrinkage
• BANK MEASURE – volume of earth in its natural
state
( NaturalState) ( LooseState)
S%
( NaturalState)
Swell and Shrinkage
SHRINKAGE
• change in volume from its natural state to its
compacted state
• expressed as percent of natural volume
( NaturalState) (CompactedState)
S%
( NaturalState)
Example:
• Natural State: 1 m3
• Loose State: 1.2 m3
• Compacted State: 0.85 m3
• Using the equations of Swell and Shrinkage:
Swell:
S% = (1 – 1.2)*100/1 = 20%
Shrinkage:
S% = (1 - 0.85)*100/1 = 15%
RELATIONSHIP of SHRINKAGE
FACTOR (SF) and SHRINKAGE (S%)
NaturalState
SF
CompactedState
NaturalState SF * (CompactedState)
( NaturalState) (CompactedState)
S%
( NaturalState)
SF 1
S%
SF
RELATIONSHIP of SHRINKAGE
FACTOR (SF) and SHRINKAGE (S%)
( SF * S %) SF 1
SF ( S % 1) 1
1
SF
( S % 1)
1
SF
1 S%
Classification of materials
• COMMON EXCAVATION/ROCK EXCAVATION –
refers to soil; excavated material
• COMMON BORROW
• soil found outside the roadway and brought in
to the roadway.
• FILL
• excavation which is placed in embankment, or is
to be placed in embankment
Payment for earthwork
Payment is normally either for cut and not for fill
or for fill and not for cut. To pay for both would be
paying for the same earth twice.
𝑨𝟏 + 𝑨𝟐
𝑽𝒆 = (𝑳)
𝟐
A2
A1
L
VOLUME DETERMINATION
Prismoidal Formula
𝑳
𝑽𝒑 = (𝑨𝟏 + 𝟒𝑨𝒎 + 𝑨𝟐 )
𝟔
A2
Am
𝑳
𝑽𝒄𝒑 = (𝑪𝟏 − 𝑪𝟐 )(𝑫𝟏 − 𝑫𝟐 )
𝟏𝟐
D1 D2 C1, C2 – center heights
D1, D2 – center widths
C1 C2
𝑽𝒑 = 𝑽𝒆 − 𝑽𝒄𝒑
A1 A2
VOLUME DETERMINATION
Borrow Pit Method
𝑨
𝑽𝒃 = 𝒉𝟏 + 𝟐 𝒉𝟐 + 𝟑 𝒉𝟑 + 𝟒 𝒉𝟒
𝟒
Where:
h1 = elevation pf point adjacent to 1 square
h2 = elevation pf point adjacent to 2 square
h3 = elevation pf point adjacent to 3 square
h4 = elevation pf point adjacent to 4 square
VOLUME DETERMINATION
Borrow Pit Method
Problem 1
End Areas by Simple Figures. Compute the end
areas of the following cross section notes:
Note:
Slope (horizontal : vertical)
Problem 1
Problem 1
𝐿 1.5
= → 𝐿 = 4.5 𝑚, 𝑋𝐿 = 9 𝑚
3 1
𝑅 1.5
= → 𝑅 = 9 𝑚, 𝑋𝑅 = 13.5 𝑚
6 1
Problem 1
Atotal = A1 + A2 + A3 + A4
Atotal = 0.5(4.5)(3) + 0.5(5)(4.5+4.5) + 0.5(5)(4.5+9) + (0.5)(4.5)(6)
Atotal = 76.5 m2
Problem 1
𝐿 1.5
= → 𝐿 = 5.25 𝑚, 𝑋𝐿 = 9.75 𝑚
3.5 1
𝑅 1.5
= → 𝑅 = 10.5 𝑚, 𝑋𝑅 = 15 𝑚
7 1
Problem 1
Atotal = A1 + A2 + A3 + A4 + A5 + A6
Atotal = 0.5(3)(5.25) + 0.5(3)(4.5) + 0.5(5)(4.5) + (0.5)(5)(4.5) +
0.5(7.5)(4.5) + 0.5(7.5)(10.5)
Atotal = 93.375 m2
Problem 1
𝐿 1
= → 𝐿 = 1.8 𝑚, 𝑋𝐿 = 6.3 𝑚
1.8 1
𝑅 1.5
= → 𝑅 = 3 𝑚, 𝑋𝑅 = 7.5 𝑚
2 1
Problem 1
1 1
𝐷𝑜𝑢𝑏𝑙𝑒 𝐴𝑟𝑒𝑎𝑠 = −156 = −𝟕𝟖 𝒎𝟐
2 2
(double check answer using simple figures)
Note:
Negative net area – Fill
Positive net area – Cut
Problem 3
Volume Determination. Given the following cross
section notes:
Problem 3
Width of the road = 12 m
side slope is 2.5:1
A1 = 150.25 m2
Problem 3
A2 = 259.375 m2
Problem 3
a) Compute the volume between the two stations
using the end area method.
𝐴1 + 𝐴2 150.25 + 259.375
𝑉𝑒 = 𝐿 = 20
2 2
𝑽𝒆 = 𝟒𝟎𝟗𝟔. 𝟐𝟓 𝒎𝟑
Problem 3
b) Compute the volume between the two stations
using the prismoidal formula.
Am = 201.375 m2
Problem 3
b) Compute the volume between the two stations
using the prismoidal formula.
𝐿
𝑉𝑝 = 𝐴1 + 4𝐴𝑚 + 𝐴2
6
20
𝑉𝑝 = 150.25 + 4(201.375) + 259.375
6
𝑽𝒑 = 𝟒𝟎𝟓𝟎. 𝟒𝟏𝟔𝟕 𝒎𝟑
Problem 3
• For 3 level sections, we can check using
prismoidal correction.
𝐿
𝑉𝑐𝑝 = 𝐶1 − 𝐶2 𝐷1 − 𝐷2
12
20
𝑉𝑐𝑝 = 5 − 7 44.5 − 58.25 = 45.8333 𝑚3
12
𝑉𝑝 = 𝑉𝑒 − 𝑉𝑐𝑝 = 𝟒𝟎𝟓𝟎. 𝟒𝟏𝟔𝟕 𝒎𝟑
Problem 4
Unit Area or Borrow Pit Method. A 90 m x 90 m
square lot is divided into square sections, and the
elevations at every corner were recorded. If the
ground is to be leveled at an elevation of 10 m,
solve the volume of excavation.
ℎ3 = 𝟎
Unit area = 30 m x 30 m
30 × 30
𝑉𝑏 = 18.6 + 2 41.2 + 4 17.2
4
𝑉𝑏 = 𝟑𝟖𝟏𝟐𝟒 𝒎𝟑
MASS DIAGRAM
Determining:
• economic handling of material
• Quantities of overhaul
• Location of balance points
1. LINEAR DISTANCE
• linear distance of hauling earth measured along the
centerline
𝐶𝐵 ∗ 20
𝐿𝐸𝐻 = + 𝐹𝐻𝐷
𝐶𝑂𝐻
Where:
CB – unit cost of borrow
COH – unit cost of overhaul
Properties of Mass
Diagram
Grade points on the profile correspond to maximum
and minimum points of the mass diagram.
Ascending lines denote cut or excavation and
descending lines denotes fill or embankment.
The difference in length between any two vertical
ordinates of the diagram is the volume between
stations at which the ordinates were erected.
Between any two points where the curve is
intersected by a horizontal line, excavation equals
embankment.
The area cut off by any horizontal line and the curve
is the measure of the haul between the two points
where the line cuts the diagram.
In the mass diagram, a loop that forms a peak
indicates haul forward and a loop that form a sag
indicates haul backward.
Problem 6
The cross-sectional area of STA 1+260 is 40
m2 in cut and at STA 1+860 is 60 m2 in fill.
The free haul distance is 100 m and the cost
of borrow is PhP 30/m3 while that of cost of
excavation is PhP 20/m3. The cost of haul is
PhP 2/meter-station. The balancing point is
at STA 1+560. Assume the ground surface
to be sloping downward uniformly up to STA
1+560 and then with steeper slope to STA
1+860. Determine the following:
Problem 6
Stationing of the limit of free haul
Stationing of the limit of economic haul
Overhaul volume
Length of overhaul
Cost of overhaul
Cost of waste
Cost of borrow
Problem 6
a) Stationing of the limit of free haul
By ratio and proportion:
a 40 40x
= → a=
x 300 300
b 60 100 − x
= →b=
100 − x 300 5
For free haul distance:
𝐯𝐨𝐥𝐮𝐦𝐞 𝐨𝐟 𝐜𝐮𝐭 = 𝐯𝐨𝐥𝐮𝐦𝐞 𝐨𝐟 𝐟𝐢𝐥𝐥
1 1
x a = 100 − x b
2 2
1 40x 1 100 − x
x = 100 − x
2 300 2 5
𝐱 = 𝟓𝟓. 𝟎𝟓 𝐦
𝟏𝟎𝟎 − 𝐱 = 𝟒𝟒. 𝟗𝟓 𝐦
𝐚 = 𝟕. 𝟑𝟒 𝐦𝟐
𝐛 = 𝟖. 𝟗𝟗 𝐦𝟐
Cb
LEH = × 20 + FHD
Ch
Php 30/m3 20m
= 3
× + 100
Php 2/m sta sta
𝐋𝐄𝐇 = 𝟒𝟎𝟎𝐦
By ratio and proportion:
c 400 40e
= →c=
e 300 300
d 60 300 − e
= →d=
300 − e 300 5
For limit of economic haul distance:
𝐯𝐨𝐥𝐮𝐦𝐞 𝐨𝐟 𝐜𝐮𝐭 = 𝐯𝐨𝐥𝐮𝐦𝐞 𝐨𝐟 𝐟𝐢𝐥𝐥
1 1
e 2a + c = 300 − e 2b + d
2 2
1 40e 1 300 − e
e 2 7.34 + = 300 − e 2 8.99 +
2 300 2 5
𝐞 = 𝟏𝟔𝟓. 𝟏𝟓 𝐦
𝟑𝟎𝟎 − 𝐞 = 𝟏𝟑𝟒. 𝟖𝟓 𝐦
𝐜 = 𝟐𝟐. 𝟎𝟐 𝐦𝟐
𝐝 = 𝟐𝟔. 𝟗𝟕 𝐦𝟐
1
VOH = Vcut + Vfill = 3030.628125 m3
2
Theoretically, Vcut = Vfill so just take the average.
d) Length of overhaul
𝐿𝑂𝐻 = 𝐷 − 𝐹𝐻𝐷 = 𝑥𝐿 + 𝑥𝑅
d) Length of overhaul
1 1 1 2
c + 2a e xL = a e e + c e e
2 2 2 3
𝐱𝐋 = 𝟗𝟗. 𝟎𝟗 𝐦
d) Length of overhaul
1 1 1 2
d + 2b 300 − e xR = b 300 − e [300 − e] + d 300 − e [300 − e]
2 2 2 3
𝐱 𝐑 = 𝟖𝟎. 𝟗𝟏 𝐦
LOH = xL + xR = 𝟏𝟖𝟎 𝐦
e) Total cost of haul
1
TChaul = VOH × cost of haul × × length of overhaul
length per station
Php 2 1 sta
TChaul = 3030.62815 m3 × 3 × × 180 m = Php 54 551.31
m − sta 20 m
Note:
1 STA = 20 m for Metric units
1 STA = 100 ft for English units
f) Total cost of waste
STA 1+339.8 - STA+260 = 79.8 m
Volume (m3)
STA
Cut Fill
10+000 +200
10+040 +100
10+080 +150
10+120 +140
10+160 +110
10+200 +190
10+240 +50
10+280 -40
10+320 -120
10+360 -90
10+400 -80
10+440 -200
10+480 -220
10+520 -110
10+560 -320
10+600 -280
Problem 7
FHD = 50 m
LEH = 400 m
Mass ordinate of initial limit of FHD = +910 m3
Mass ordinate of initial limit of LEH = +350 m3