Saep 342
Saep 342
Saep 342
1 Scope............................................................. 2
2 Definitions....................................................... 2
3 Applicable Documents.................................... 3
4 General Information........................................ 3
5 Proponent Responsibility................................ 3
6 Engineering Services Responsibility.............. 4
7 Design Agency Responsibility........................ 4
8 Construction Agency Responsibility............... 5
1 Scope
This procedure defines a process to quickly identify, obtain and distribute usable CADD
files of engineering drawings required to repair/rebuild Saudi Aramco facilities in
emergency situations upon proponent request. In doing so, it identifies the
responsibilities and actions of various agencies involved.
1.2 Responsibilities and actions for the quick identification and delivery of Saudi
Aramco Engineering Drawings in an emergency situation.
2 Definitions
Integrated Plant - IPlant: is the sole corporate Saudi Aramco Engineering drawing,
Tags and Data Management system that contains all approved and certified engineering
data that are collected from the inception of the company. It is an automated system
designed for administration and control of Saudi Aramco engineering drawings, Tags and
data in a centralized library. This allows the users to query, view, print, retrieve and
submit engineering and vendor drawings in addition of allowing them to retrieve new
engineering drawing numbers, tag numbers, create new sheet numbers and to perform job
tracking/creation functions. Refer to IPlant Users Guide for operational details.
Page 2 of 5
Document Responsibility: Engineering Data and Drawing Systems Standards Committee SAEP-342
Issued Date: 1 June 2014
Next Planned Update: 1 June 2019 Engineering Drawings Emergency Delivery Plan
3 Applicable Document
4 General Information
4.2 The technical contents of the engineering drawings are the responsibility of the
Proponent.
4.3 All action and responsibility items included in this Plan are to be handled on top
priority basis and in the fastest manner under the direction of Chief Engineer.
4.4 EK&RD will provide electronic files of drawings on CDs that are
comprehensible by the proponents.
4.5 All Saudi Aramco IPlant users including EK&RD shall assist the proponent if
required in printing drawings from electronic files.
4.6 The contact persons identified in paragraphs 5.1, 6.1, 7.1, and 8.1 must work
together to maximize efficiency of this procedure while meeting requirements of
Saudi Aramco drawing security.
5 Proponent Responsibility
5.1 Manager (or his delegate) will assign contact person(s) to interface with
EK&RD Coordinator (or his delegate) to support day to day activity during the
emergency period.
5.2 It is the responsibility of Department Manager’s (or his delegate) to make sure
that all the updated AS-BUILT drawings shall be archived in the Corporate
Drawing Management System (IPlant) for his organization.
5.3 It is the responsibility of Department Manager’s (or his delegate) to make sure
that no other archival system shall be used for maintaining or revising AS-BUILT
Page 3 of 5
Document Responsibility: Engineering Data and Drawing Systems Standards Committee SAEP-342
Issued Date: 1 June 2014
Next Planned Update: 1 June 2019 Engineering Drawings Emergency Delivery Plan
5.5 Request EK&RD to deliver engineering drawings that are related to the affected
plant(s).
5.6 Request EK&RD to provide Query View and Print (QVP) access of drawings to
design or operations personnel that are involved in the rebuild of the facility.
5.7 Identify and deliver drawings for on-going projects that are not in IPlant to
EK&RD. Proponent to identify specific drawing numbers, rev. etc. of 'on-going
project drawings not in IPlant and supply CADD files to EK&RD, or identify
PMT responsible for these drawings.
5.8 Request FPD “Facilities Planning Department” and PMT “Project Management
Team” to identify any upcoming projects close to the emergency area that may
affect the rebuild of the affected plants. Supply any drawings available.
6.1 EK&RD Coordinator (or his delegate) shall assign contact person(s) to support
day to day activity during the emergency period.
6.3 Copy CADD electronic files of the latest revisions that are available in the
IPlant.
6.4 Provide the electronic files of drawings to the proponent or designated design
office.
6.6 Process on-line drawings QVP access requests to design or operations personnel
requested by proponent that are involved in the rebuild of the affected plant.
Page 4 of 5
Document Responsibility: Engineering Data and Drawing Systems Standards Committee SAEP-342
Issued Date: 1 June 2014
Next Planned Update: 1 June 2019 Engineering Drawings Emergency Delivery Plan
7.1 Design Manager of Design Services (or his delegate) shall assign contact
person(s) to communicate with EK&RD and the Proponent.
7.2 Search at the site and in the proponent libraries for any additional information
related to engineering drawings. Contact equipment vendors if necessary.
Coordinate searches with Proponent.
8.1 PMT Department Manager of Project Management (or his delegate) shall assign
contact person(s) to communicate with EK&RD, Design Agency and the
proponent.
Revision Summary
28 May 2014 Revised the Next Planned Update, reaffirmed the content of the document, and reissued as
major revision.
Page 5 of 5