Method Statement For Compaction and Backfilling
Method Statement For Compaction and Backfilling
Method Statement For Compaction and Backfilling
Backfilling
Contents
1 Method Statement for Compaction and Backfilling
o 1.1 SCOPE:
o 1.2 GENERAL:
o 1.3 DUTIES AND RESPONSIBILITIES:
1.3.2 QA/QC :
1.3.3 Civil Supervisor:
1.3.4 Foreman:
1.3.5 Safety Manager/Supervisor:
o 1.4 TOOLS AND EQUIPMENTS:
o 1.5 WORK PROCEDURE:
1.5.1 Survey:
1.5.2 Excavation Operation:
1.5.3 Start the excavation carefully:
o 1.6 BACKFILL AND COMPACTION:
o 1.7 INSPECTION:
o 1.8 SAFETY PLAN:
SCOPE:
This procedure is issued to describe the work processes involved in construction
of the excavation of concrete structure foundations, and other facilities for
TOTAL LOBP finish product Warehouse Shimanzi, Mombasa. The latest revision
of the PROJECT specifications shall be used as references and is part of this
Method Statement in the execution of work.
Method statement for excavation and backfilling,
GENERAL:
An open cut type of excavation shall be applied with safe side slopes.
Shoring and bracing system shall be used whenever required to protect
adjacent structure if any, in an excavation site or when the excavation
side slope is steeper than those mention below.
Suitable and appropriate excavator and compacting equipment shall be
used to carry out the works.
Safe angle and clearance of excavation:
The entire excavation slope shall be as per project specification of
excavation specification. Angle =45° is applied to major soil strata
found in the Plant site. Clearance of 1.0 meter from excavation top
edge to barricade shall always be kept.
Excavated soil material will be removed immediately from the work site
and equipment shall be kept away from the excavation top edge.
All access walkways, Ramps, Stair & Bridges shall be equipped with
guard rails. All Walkway crossings shall be equipped with tightly
secured uniformly sized planking. There shall always be a safe access
way for entry and exit. For excavations that are long, there shall be an
access way as per requirements.
QA/QC Manager:
The QA/QC Manager shall be responsible for the necessary inspections and tests
to be carried out for all the activities involved in the excavation, such as
excavation bottom compaction test and as per the Inspection Test Plan (ITP).
The Civil Supervisor shall be directly involved in the planning and execution of
the activities involved in the excavation. He shall be responsible for the
preparation of excavation plan, Safety Action Plan and job safe analysis (JSA).
Safe work plan application for work permits is required prior to commence of
any excavation. Supervisor to develop a JSA on a weekly basis and update is
necessary when conditions change.
Foreman:
Safety Manager or Supervisor shall review prior to the start of the work Safe
Work Plan and work permit is required, prior to submittal to the SD that must
be implemented and observed during the excavation works.
WORK PROCEDURE:
Survey:
Excavation Operation:
INSPECTION:
Inspection shall be based on approved ITP, QC Plan and Project Specifications
listed in under Technical Specification or as stated on the latest IFC drawing.
SAFETY PLAN:
Safety of men and materials is a high priority. All safety measures will be
observed during the entire works. Brief account of the safety strategy is given
under:
All the activities will be envisaged a week in advance and job safety
requirements will be worked out by analyzing the likely hazards and
resorting to preventive.
Proper house keeping at the end of the day is a part of the mandatory
tasks assigned to workers to avoid accidents due to littered tools and
materials.
Flagmen will be engaged to control the movement of trailers, cranes,
pumps and other mobile equipments.
Weekly tool box talk will be conducted and brief safety measures
required for the ensuing days will be discussed.
First aid facility will be available entire the period in the work site.