PRINCE2 2017 Project Brief
PRINCE2 2017 Project Brief
PRINCE2 2017 Project Brief
Project brief
Providing a full and firm foundation for the initiation of the project.
Contents
1. Project definition ........................................... Error! Bookmark not defined.
2. Outline business case ....................................... Error! Bookmark not defined.
3. Project product description ............................... Error! Bookmark not defined.
4. Project approach ............................................ Error! Bookmark not defined.
5. Project management team structure .................... Error! Bookmark not defined.
6. Role descriptions ............................................ Error! Bookmark not defined.
7. References ................................................... Error! Bookmark not defined.
Guidance on how to complete ..................................................................... 4
Copyright © AXELOS Limited 2016. AXELOS® and PRINCE2® are registered trade marks of AXELOS Limited.
Used under permission and in accordance with the Terms and Conditions of Sale. All rights reserved.
1 Project definition
4 Project approach
Copyright © AXELOS Limited 2016. AXELOS® and PRINCE2® are registered trade marks of AXELOS Limited.
Used under permission and in accordance with the Terms and Conditions of Sale. All rights reserved.
6 Role descriptions
7 References
Copyright © AXELOS Limited 2016. AXELOS® and PRINCE2® are registered trade marks of AXELOS Limited.
Used under permission and in accordance with the Terms and Conditions of Sale. All rights reserved.
Guidance on how to complete
(Note: following completion of the Project brief the pages beyond this point can be deleted)
PURPOSE
A project brief is used to provide a full and firm foundation for the initiation of the project and is
created in the starting up a project process.
In the initiating a project process, the contents of the project brief are extended and refined in the
PID, after which the project brief is no longer maintained.
COMPOSITION
A project brief includes the following:
Project definition Explains what the project needs to achieve. It should include:
● background
● project objectives (covering time, cost, quality, scope, benefits and risk performance)
● desired outcomes
● project scope and exclusions
● constraints and assumptions
● project tolerances
● the user(s) and any other known interested parties
● interfaces
Outline business case (see section A.2) Reasons why the project is needed and the business
option selected. This will later be developed into a detailed business case during the initiating a
project process
Project product description (see section A.21) Includes the customer’s quality expectations,
user acceptance criteria, and operations and maintenance acceptance criteria
Project approach Defines the choice of solution that will be used within the project to deliver
the business option selected from the business case. This will take into consideration the
operational environment into which the solution must fit and any tailoring requirements (if
known)
Project management team structure A chart showing who will be involved with the project
Role descriptions These describe the roles of those in the project management team and any
other key resources identified at this time
References These include references to any associated documents or products.
Copyright © AXELOS Limited 2016. AXELOS® and PRINCE2® are registered trade marks of AXELOS Limited.
Used under permission and in accordance with the Terms and Conditions of Sale. All rights reserved.
DERIVATION
A project brief is derived from the following:
QUALITY CRITERIA
The following quality criteria apply to a project brief:
It is brief because its purpose at this point is to provide a firm basis on which to initiate a
project. It will later be refined and expanded as part of the PID.
It accurately reflects the project mandate and the requirements of the business and the users.
The project approach considers a range of solutions, such as: bespoke or off-the-shelf;
contracted-out or developed in-house; or designed from scratch or modified from an existing
product.
The project approach selected maximizes the chance of achieving overall success for the
project.
The project objectives and project approaches are consistent with the organization’s social
responsibility directive.
The project objectives are specific, measurable, achievable, relevant and time-bound (SMART).
Copyright © AXELOS Limited 2016. AXELOS® and PRINCE2® are registered trade marks of AXELOS Limited.
Used under permission and in accordance with the Terms and Conditions of Sale. All rights reserved.