Arup Method Statement PDF
Arup Method Statement PDF
Arup Method Statement PDF
Filename
Description
Signature
Filename
Description
Signature
Contents
Page
1 Introduction 1
1.1 Background 1
1.2 Scope 1
1.3 Objective of this document 1
1.4 Proposed development 2
1.5 Document Status 2
2 Existing conditions 3
2.1 General 3
2.2 Site description 3
2.3 Site history summary 4
2.4 Geology and hydrogeology 5
2.5 Ground conditions 6
2.6 Existing remediation systems 8
2.7 Existing utilities 9
2.8 Unexploded ordnance 9
3 Development proposals 11
3.1 General 11
3.2 Earthworks 12
3.3 Remediation and earthworks philosophy 12
3.4 EMS procedures 13
4 Environmental monitoring 17
4.1 Construction monitoring 17
4.2 Groundwater monitoring 17
Figures
Appendices
Appendix A
Landscape Masterplan
Appendix B
Scheme Design Information
Appendix C
Historical Remediation Information
Appendix D
Environmental Risk Assessment
Appendix E
Location of Long Term Groundwater Monitoring Wells
1 Introduction
1.1 Background
All construction work that is undertaken by developers on Greenwich Peninsula
under the planning permission granted by the London Borough of Greenwich
(LBG) to Meridian Delta Limited (MDL), the Homes and Communities Agency
(HCA) formerly the Urban Regeneration Agency (as English Partnerships)), AEG
Dome Arena Limited, and Quintain Estates & Development plc, and which
disturbs the ground, is required to follow the Environmental Method Statement
(EMS) procedures. The EMS for all of the land was prepared by Atkins and was
submitted to the LBG to discharge Outline Planning Condition 97 on December
14, 2004 (OPP reference 02/2903/O) and resubmitted in November 2008. LBG
confirmed acceptance of the EMS, and discharge of Condition 97, by their letter
dated 23 February 2005. The EMS forms part of the Integrated Management
System (IMS) for the re-development of Greenwich Peninsula, as required by
clause 41 of the Section 106 Agreement.
The EMS has been revised a number of times and the latest approved version is
document reference AC1787/D2/6325Rev 5, dated February 2011) 1.
1.2 Scope
This Works Method Statement (Planning) (WMS(P)) has been prepared by Ove
Arup & Partners Limited (Arup) on behalf of MDL (the Applicant) in support of
the hybrid planning application to Greenwich Council which comprises detailed
planning permission for the infrastructure and public realm works surrounding
Plots N0601, N0608 and N0506 including revised vehicle access routes to Plot
N0301 (AEG Hotel) and the O2 Arena (Dome). This area is collectively referred
to as the Peninsula Quays Zone A infrastructure.
The hybrid planning application also includes an outline planning application for
Plot N0506. Since the N0506 element of the planning application does not fall
under the existing outline planning permission, a WMS(P) for N0506 is not
required. However, assuming permission is granted and a condition to comply
with the EMS is imposed (as is expected), a WMS(P) for the plot will be
completed for the detailed application. Therefore, this document only presents the
WMS(P) for the Peninsula Quays (PQ) Zone A infrastructure area. A plan
showing the red line boundary of the site is presented in Figure 1.
This document has been prepared to discharge Conditions 88 (Remediation
Strategy) and 97 (Environmental Method Statement) of the detailed planning
permission of the hybrid planning submission.
1
Atkins. Greenwich Peninsula Environmental Method Statement. Volume 1 and 2. Revision 5.
Document Reference AC1787/D2/6325. February 2011.
application for the PQ Zone A site. The objective of this WMS(P) under the EMS
system is as follows:
To outline the existing ground conditions and any previously installed
remediation systems.
To outline the development proposals, design philosophy and mitigation
measures.
To present an environmental risk assessment.
To identify potential environmental issues that may arise as a direct result of
the proposed development.
To discuss the requirements for operational and long term monitoring.
2 Existing conditions
2.1 General
The general geological and hydrogeological conditions across the HCA-owned
land, and the history of remediation undertaken at the site, is outlined in Part A of
Volume 2 of the EMS.
To supplement pre-existing information, detailed desk studies have been
undertaken for the Peninsula Quays site and various phases of ground
investigation have been undertaken across the different areas of the site.
The desk studies and previous site investigations are included in the following
reports:
Arup. Works Method Statement (Planning). Peninsula Quays Access Land –
Phase 1b, Phase 2 and Phase 3 Sitewide Highway Works. Issue 1 Agreed,
April 2008.
Arup. Works Method Statement (Planning) – Meridian Gardens Central
Infrastructure Works. Issue 5 Agreed. July 2007.
RPS. Meridian Gardens North, Greenwich Peninsula Infrastructure &
Regrading Factual Geo-Environmental Site Investigation Report. August
2006.
RPS. Meridian Gardens North Greenwich Peninsula West, London.
Environmental Desk Study. November 2006.
Outline descriptions of the present ground conditions and of the exisiting
remediation systems across parts of PQ Zone A are provided below.
The history of the land associated with the Millennium Exhibition Site (HCA
Land) is summarised below
This area of land was occupied by one of the largest gasworks in Europe from
the early 1900s up until the 1970s. The gasworks complex had a range of
associated industries, including a large tar works, a chemical works for the
manufacture of sulphuric acid and ammonium sulphate fertiliser, and a power
station. The generation of coal gas and associated by-products were
undertaken on the site for nearly 80 years.
The HCA land within and adjacent to the PQ Zone A included tar acid plants,
a naphthalene plant, a naphthalene house and workshops and stores. Notably,
a a area containing numerous tar tanks and a large tar wall was located
approximately 100m north of the northern boundary of PQ Zone A. Details
on the historical gasworks infrastructure in this area is presented in Appendix
C.
Following the industrial use of the site, the Millennium Exhibition land was
subject to two phases of remediation. These stages were:
Notes:
Based on a summary of the stratigraphy for Peninsula Quays presented in previous WMS(P)2
repots.
Stockpiles of site won materials are also present across the surface on Peninsula Quays. These
are not included in the elevation or thickness details of the Made Ground.
Made Ground will also include various concrete obstructions that have been identified on
Peninsula Quays.
2
Arup. Greenwich Peninsula Re-Development. Works Method Statement (Planning) - Peninsula
Quays (formerly Meridian Gardens) Infrastructure Works. Issue 5 Agreed 22/11/07.
Statutory Remediation
The statutory remediation works were designed to remove the major source areas
of contamination. This was largely achieved by excavation and disposal of
heavily contaminated soils off-site to landfill. However it also included in-situ
remediation of benzene contamination by dual-phase groundwater and soil vapour
extraction and the very deep excavation of a large diameter bomb-damaged tar
well in two areas at the northern end of the peninsula (to the north of PQ Zone A).
The extent of the statutory remediation dig area at the northern end of the
peninsula is illustrated on Figure 3 of this report. Further information on the
statutory remediation is presented in Appendix C. There is the potential for
residual contamination to be present at the edge or below the former remediation
dig at the northern end of the Hotel Approach Road.
Development Remediation
Following English Partnership’s purchase of land on the northern and eastern side
of Greenwich Peninsula from British Gas in 1997, it was necessary to supplement
elements of the statutory remediation scheme in order to prepare the land for the
Millennium Exhibition, and some areas for their long term use.
The development remediation (and site enabling) works were completed under a
number of contracts and in summary comprised the following:
Demolition of buildings and removal of foundations and slabs to a depth of
1m below the 1998 initial and final re-graded ground levels, across the whole
area.
Re-grading of the site, including scarifying the near-surface layer to remove
obstructions, and excavation and removal (disposal off-site) of contaminated
ground from localised hotspots encountered during the enabling earthworks.
Construction, across the whole site, of a clean surface capping layer to prevent
direct contact with potentially contaminated ground, and upward migration of
potential contaminants from the underlying ground to the surface. A brightly
coloured, permeable plastic ‘marker sheet’ was placed at the base of this layer
to delineate the boundary of the clean layer and the underlying (potentially
locally contaminated) ground. The nature of the clean capping layer was
different depending on the use of the area for the Millennium Exhibition
(public hard landscaping, soft landscaped areas, car and coach parking).
The capping system in roadways comprised a marker layer placed on the
existing ground, overlain with 450 mm depth of clean hardcore. Road build-up
is on top of this typically 200 mm thick of clean backfill or cement bound
material overlaid by ‘Fibredeck’. Note that cement/lime stabilisation of soft
alluvium was used to improve the geotechnical properties below car parks and
some roadways.
The Dome area capping system consists of a marker layer placed on the
existing ground, overlain with 450 mm depth of clean hardcore a fabric
separator, 1mm LDPE gas membrane, sand blinding layer and concrete slab.
Provision of service corridors of clean soil for site wide services (electricity,
water, gas, telecommunications), underlain and surrounded by a clay liner.
Installation of foul and surface water drainage with measures to prevent
migration of contaminants and cross-contamination of clean and untreated
ground.
The schematic details of the development remediation are presented below and
discussed in Volume 1 of the EMS.
Plan of high risk areas (shaded in red) as presented in the BAE Systems Report (2006).
3 Development proposals
3.1 General
The scope of the public realm and infrastructure development in PQ Zone A has
been outlined in Section 1.4. The landscape masterplan is presented Appendix A
and plans of the infrastructure development are presented in Appendix B.
In summary the proposed development works along each of the corridors is as
follows.
Table 3. Summary of the PQ Zone A public realm development works.
Meridian Gardens The majority of this area will be public realm with a hard landscaped
cyclepath and footpath located adjacent to the river wall on the western
site boundary. Intimate garden spaces are included in the western side of
Plot N0601, which will include soft landscaping, an informal adventure
play area for toddlers and planting of cherry trees. An ornamental maze
will also be includes in the soft landscaping works. A marketing suite
building may be constructed on the southern end of the Meridian
Gardens area which could be used as a cafe in future, following
completion of the development.
The infrastructure services in this area includes surface water drainage,
an attenuation tank, outfalls to the River Thames and service corridors
for low voltage electricity cables, potable water pipes and telecoms
ducts.
Ice House Way This is a mixed vehicle and pedestrian route with limited car parking
spaces. The route will be lined with trees, placed within tree pits. The
infrastructure will include surface and foul water drainage and services
corridors for water, telecoms, gas, electricity and combined heat and
power.
Delta Strand Delta Strand, between N0601 and N0608 will be constructed over the
joint basement between the two plots. This route will be considered
under a separate application and therefore is not considered in this
report..
Draw Dock Road This is a mixed vehicle and pedestrian route, linking with the Draw
Dock slipway to the west. The infrastructure services will include
surface water drainage and services corridors for water, telecoms and
electricity supply.
Tunnel Avenue This area will be modified from its current highway use to include a
mixed vehicle and pedestrian route with some landscaping features
(trees within pits and some ground cover planting). The tree planting
will include cherry trees and external gym equipment and a rock
climbing/traversing wall is proposed for the northern end of the route.
Hotel Approach Road This area will principally comprise vehicle access routes to the Hotel
and AEG Service and the AEG service areas. The routes will be tree lined and a
Access Road pedestrian footpath will be present along the top of the retaining wall
which will be constructed as part of the development. In addition, minor
alterations to the roundabout at the northern end of Millennium Way and
the public realm to the north of the bus turning area will be required.
Service corridors and surface water drainage will be included in the
infrastructure below the vehicle access roads
3.2 Earthworks
Cross sections through the site are presented in Appendix B. These show the
current ground level and the proposed formation levels within the public realm
corridors.
Earthworks fill will be required across the majority of Meriden Gardens and Ice
House Way to raise ground levels. Ground levels will be raised by approximately
1.0 to 1.5m adjacent to the river wall using the existing stockpiled soils presently
situated on the Peninsula Quays site. The proposed ground levels will slope down
to the east, with an area of cut required towards the eastern end of Ice House Way.
The maximum cut required is approximately 1.5m.
Along the proposed Hotel Approach Road and AEG Service Access Road, the
proposed levels will generally require an earthworks cut of approximately 0.2 to
0.5m. However, a large fill area has been identified midway along the Hotel
Approach Road, where the route crosses the current corner between Tunnel
Avenue and Draw Dock Road.
Deeper earthworks excavations will be required for the installation of the service
corridors, surface and foul sewer and for landscaping, such as tree pits. Scheme
design depths of the infrastructure elements are presented in Appendix B.
Materials used in the earthworks re-profiling of the site will be sourced from both
existing site soils (arising from site re-grading and excavation for services and
foundations) and from imported select materials for particular purposes. All site-
derived and imported earthworks materials will be required to meet the particular
physical and chemical specification for their purpose.
A site specific risk assessment approach has been used to establish chemical
acceptance criteria to categorise site-won material into Suitable and Unsuitable
Materials in the Arup Remediation Strategy Framework report3. These criteria
will be described and presented in the WMS (Design).
The chemical criteria are not intended for application in ‘non-standard’ land-uses
such as gardens with fruit or vegetable cultivation, schools, playing fields, large
areas of public open space (such as parkland) or commercial land-uses which are
designed for children, such as crèche, playground or leisure facilities. Further
work may be required to assess the appropriate criteria to be used for non-
standard end uses, such as the gardens, trees or informal play areas within
Meridian Gardens or Tunnel Avenue. The details of any additional assessment
will be presented in the WMS(D).
3
Arup. Greenwich Peninsula Remediation Strategy Framework Report. AEC-SITEWIDE-REP01
Issue 1 dated 05/12/07
nature and degree of contamination, and the form of construction and end use in
the localised area in question. Any hotspot areas will be identified in the
WMS(D).
It is not considered necessary to install a plastic marker sheet beneath an
engineered capping layer in the land associated with the Western Development
area. This is consistent with the principles of the Remediation Strategy
Framework. However, an upper capping layer will be placed and a marker sheet
may be installed in any localised areas where significantly contaminated ground
will remain beneath the capping layer
Across the former Millennium Exhibition site (HCA land), the remediation
strategy in infrastructure areas (i.e. non building plots) will include:
A marker sheet installed beneath an engineered capping layer.
The provision of a capping layer consisting of either Landscape Material or
Upper Capping Material, above General Fill Material as defined in the
Remediation Strategy Framework Report.
The perforated ‘marker sheet’, separating the upper capping material from
underlying potentially contaminated ground will be maintained across the
whole site and will extend across the top of backfill to new foul and surface
water sewers.
A 200mm capillary break layer above the ‘marker sheet’ in soft landscape
areas only sufficient to prevent the capillary rise of moisture through the
Landscape Material above.
Underground services will be laid in clean service corridors with, where
necessary, a liner to restrict cross-contamination by the surrounding ground.
Measures to control potential lateral migration of contaminated perched
groundwater installed within backfill to drainage trenches, and elsewhere,
where this is necessary.
Rainfall infiltration into the ground (which could cause the build up of
contaminated perched water) will be minimised by the provision of hard
landscaping with piped surface water drainage, and soft landscaping under-
drainage.
3.4.1 General
The philosophy of the development works will include the remedial requirement
of the EMS so that in carrying the development works the necessary remediation
requirements will be included to prevent, minimise, remedy or mitigate the effects
of any harm to the Environment as a result of any pre-development site conditions
or off-site migration.
Remedial requirements will be incorporated into the detailed design of the
earthworks to ensure that the development does not pose additional risks to future
site users and the environment, in accordance with the EMS Codes of Practice
(EMS-COP), and confirms to the principles of the site wide Remediation Strategy
Framework.
The relevant EMS procedures which are relevant to the works described in this
WMS(P) are presented below.
EMS-EMP-01 Works Method Statement: the contractor will be required to
prepare and submit a Works Method Statement Construction for the works in
accordance with the EMS procedure.
EMS-EMP-02 Permit to Dig: the contractor will be required to prepare and
submit the relevant application for the Permit to Dig for any works which may
penetrate the ground and/or disturb the existing ground conditions in
accordance with the EMS procedure.
EMS-EMP-03 Competent Authority Interface: the contractor will be required
to give reasonable notice of works being undertaken on site and shall allow
access to the site for routine visits by the Authority to observe progress in
accordance with Condition 97 and specifically to observe remediation works
and measures in order to ultimately agree a validation report in accordance
with the EMS procedure.
EMS –EMP-04 Audit of Site Works: the contractor will be required to allow
the EMS Consultant access to the site for the purposes of conducting site
audits in accordance with the EMS procedure.
EMS-EMP-05 Validation of remediation works; the contractor will be
required to collect relevant information as required for the preparation of
validation reports for submission in accordance with the EMS procedure.
EMS-EMP-06 As Built Records: the contractor will be required to provide as-
built drawings of all construction works which impact, or may impact on the
environment, such as monitoring wells and decommissioning, all services and
service corridors and other items including, but not limited to, those listed in
the procedure
EMS-EMP-07 Developer Environmental Monitoring: the Competent
Authority’s requirements for environmental monitoring will be confirmed in
accordance with the EMS procedure.
EMS-ADD-01 Electronic Transfer of Geo-environmental Data; the contractor
will be required to submit all ongoing environmental monitoring data, site
investigation and remediation data to the EMS Consultant in AGS 3 format
and with the accompanying metadata in accordance with the EMS procedure
4 Environmental monitoring
4.1 Construction monitoring
Monitoring of dust, effluent discharge arising from dewatering operations, ground
gases in confined spaces, and testing of spoil leaving the site for disposal will be
undertaken during the construction works. Details of specific proposals will be
included in the Design and Construction WMSs as required by EMS-EMP-07
Developer Environmental Monitoring