PHILIP

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 3

SUBJECT: BILL OF MATERIALS

PROJECT TITLE: 1-STOREY RESIDENTIAL BLDG.


LOCATION: P-1, BRGY. OBRERO, BUTUAN CITY
OWNER: MR. & MRS. DOMINADOR ROMO

WORK DESCRIPTION QUANTITY UNIT UNIT COST AMOUNT


I. CONCRETE WORKS
A. FOOTING CLASS A
CEMENT 32 BAGS ₱ 260.00 ₱ 8,320.00
SAND 1.8 CU.M ₱ 1,035.00 ₱ 1,863.00
GRAVEL 3.5 CU.M ₱ 1,010.00 ₱ 3,535.00
B. COLUMN CLASS A
CEMENT 19 BAGS ₱ 260.00 ₱ 4,940.00
SAND 1.1 CU.M ₱ 1,035.00 ₱ 1,138.50
GRAVEL 2.1 CU.M ₱ 1,010.00 ₱ 2,121.00
C. BEAM CLASS A
CEMENT 9 BAGS ₱ 260.00 ₱ 2,340.00
SAND 0.5 CU.M ₱ 1,035.00 ₱ 517.50
GRAVEL 1 CU.M ₱ 1,010.00 ₱ 1,010.00
D. CONCRETE SLAB CLASS C
CEMENT 35 BAGS ₱ 260.00 ₱ 9,100.00
SAND 2.9 CU.M ₱ 1,035.00 ₱ 3,001.50
GRAVEL 5.8 CU.M ₱ 1,010.00 ₱ 5,858.00
E. WALL FOOTING CLASS A
CEMENT 37 BAGS ₱ 260.00 ₱ 9,620.00
SAND 2.1 CU.M ₱ 1,035.00 ₱ 2,173.50
GRAVEL 4.1 CU.M ₱ 1,010.00 ₱ 4,141.00
II. MASONRY WORKS
A. CONCRETE HOLLOW BLOCKS 10x20x40
1640 PCS. ₱ 10.00 ₱ 16,400.00
B. MORTAR CLASS C
CEMENT 69 BAGS ₱ 260.00 ₱ 17,940.00
SAND 5.8 CU.M ₱ 1,035.00 ₱ 6,003.00
C. PLASTER CLASS C
CEMENT 38 BAGS ₱ 260.00 ₱ 9,880.00
SAND 4.2 CU.M ₱ 1,035.00 ₱ 4,347.00
III. FORMWORKS & SCAFFOLDING
A. FORMS COLUMN
2''x2''x8' COCO LUMBER 90 PCS. ₱ 70.00 ₱ 6,300.00
1/4''x4'x8' PLYWOOD 8 SHEETS ₱ 420.00 ₱ 3,360.00
B. BEAMS
2''x2''x8' COCO LUMBER 95 PCS. ₱ 70.00 ₱ 6,650.00
1/4''x4'x8' PLYWOOD 9 SHEETS ₱ 420.00 ₱ 3,780.00
IV. STEEL/ROOFING WORKS
A. FOOTING REINFORCEMENT
12MM DIA. X 6M STEEL BAR 19 PCS. ₱ 223.00 ₱ 4,237.00
#16 G.I WIRES 2.2 KG ₱ 65.00 ₱ 143.00
B. COLUMN REINFORCEMENT
a. STEEL REIN. VERTICAL BARS
16MM DIA. X 6M STEEL BAR 32 PCS. ₱ 394.00 ₱ 12,608.00
b. LATERAL TIES
10MM DIA. X 6M STEEL BAR 40 PCS. ₱ 156.00 ₱ 6,240.00
#16 G.I WIRES 8 KG ₱ 65.00 ₱ 520.00
C. BEAM REINFORCEMENT
a. STEEL REIN. VERTICAL BARS
12MM DIA. X 6M STEEL BAR 24 PCS. ₱ 223.00 ₱ 5,352.00
b. STIRRUP
10MM DIA. X 6M STEEL BAR 16 PCS. ₱ 156.00 ₱ 2,496.00
#16 G.I WIRES 2.9 KG ₱ 65.00 ₱ 188.50
D. CHB REINFORCEMENT
a. STEEL REIN. VERTICAL BARS
8MM DIA. X 6M STEEL BAR 65 PCS. ₱ 44.00 ₱ 2,860.00
b. STEEL REIN. HORIZONTAL BARS
10MM DIA. X 6M STEEL BAR 38 PCS. ₱ 156.00 ₱ 5,928.00
#16 G.I WIRES 6.2 KG ₱ 65.00 ₱ 403.00
E. SLAB REINFORCEMENT
10MM DIA. X 6M STEEL BAR 125 PCS. ₱ 156.00 ₱ 19,500.00
#16 G.I WIRES 10 KG ₱ 65.00 ₱ 650.00
F. ROOFING
a. FULL TRUSS
2"x4" LUMBER 6 ₱ 140.00 ₱ 840.00
2"x6" LUMBER 8 PCS. ₱ 200.00 ₱ 1,600.00
b. PURLINS
2"X2" WOODEN PURLINS 52 PCS. ₱ 85.00 ₱ 4,420.00
c. G.I ROOFING SHEET 96 SQ.M. ₱ 475.00 ₱ 45,600.00

TOTAL MATERIAL COST ₱ 247,924.50


LABOR COST 30% ₱ 74,377.35
GRAND TOTAL ₱ 322,301.85

Prepared by:

SOROÑO, ARNIEL M.
PETALLO, JAMES PHILIP M.
LOGATIMAN, EARL JOHN O.
CREDO, WILLINGTON D.
MARASIGAN, JOTHELLO P.

You might also like