Awarded Hydropower 2017-12-31
Awarded Hydropower 2017-12-31
Awarded Hydropower 2017-12-31
POTENTIAL INSTALLED
CITY /
ISLAND / GRID REGION PROVINCE PROJECT NAME COMPANY NAME STATUS OF COMPLIANCE CAPACITY CAPACITY
MUNICIPALITY
(MW) (MW)
1. Compliant with the Work Program. Compliant with the schedule of the Work
Program.
600MW San Roque 2. Compliant with the Posting of Performance Bond. Posted 3rd year
Upper East Pump performance bond.
Strategic Power
Storage 3. Compliant with Reportorial Obligation. Recently submitted progress report. 600.00
Development Corp.
Hydroelectric 4. Compliant with the RESHERR. Submitted quarterly statistical accident/illness
Power Project report and has an accredited Safety Officer.
5. Non-compliant with the Submission of Abandonment and Termination Plan. No
submission of Abandonment and Termination Plan.
1. Non-compliant with the Work Program. Lacking supporting documents for its
DOC.
2. Non-compliant with the Posting of Performance Bond. Failed to post 2nd year
3MW Abdao 2 perfomance bond.
AV Garcia Power Systems
Hydroelectric 3. Non-compliant with Reportorial Obligation. No submission of progress report. 3.00
Corp.
Power Project 4. Non-compliant with the RESHERR. No submission of quarterly statistical report,
and annual safety and health program. No accredited Safety Officer.
5. Non-compliant with the Submission of Abandonment and Termination Plan. No
submission of Abandonment and Termination Plan.
1. Non-compliant with the Work Program. •No DED and permits from DENR, NCIP
and NWRB
1.2MW Ampassit
Kadipo Bauko Hydro Power 2. Non-compliant with the Posting of Performance Bond. •No PB posted
Mt. Province Bauko Hydroelectric 1.20
Corp. 3. Non-compliant with Reportorial Obligation. •No submitted report
Power Project
4. Non-compliant with the RESHERR. •No Accredited Safety Officer
5. Non-compliant with the Submission of Abandonment and Termination Plan.
1. Non-compliant with the Work Program. •No DED and permits from DENR, NCIP
and NWRB
1.8MW Enodey 1A
Kadipo Bauko Hydro Power 2. Non-compliant with the Posting of Performance Bond. •No PB posted
Hydroelectric 1.80
Corp. 3. Non-compliant with Reportorial Obligation. •No submitted report
Power Project
4. Non-compliant with the RESHERR. •No Accredited Safety Officer
5. Non-compliant with the Submission of Abandonment and Termination Plan.
AWARDED HYDROELECTRIC POWER PROJECTS as of December 31, 2017
POTENTIAL INSTALLED
CITY /
ISLAND / GRID REGION PROVINCE PROJECT NAME COMPANY NAME STATUS OF COMPLIANCE CAPACITY CAPACITY
MUNICIPALITY
(MW) (MW)
1. Non-compliant with the Work Program. NCIP and NWRB permits not yet
secured
2.1MW Upper 2. Compliant with the Posting of Performance Bond. •Posted PB for the 2nd yr
Kadipo Bauko Hydro Power
Chico Hydroelectric (May 2016 - 2017) 2.10
Corp.
Power Project 3. Compliant with Reportorial Obligation. •Submitted progress report
4. Non-compliant with the RESHERR. •No Accredited Safety Officer
5. Non-compliant with the Submission of Abandonment and Termination Plan.
1. Non-compliant with the Work Program. NCIP and NWRB permits not yet
secured
3.4MW Lower 2. Compliant with the Posting of Performance Bond. •Posted PB for the 2nd yr
Kadipo Bauko Hydro Power
Luzon CAR Mt. Province Bauko Chico Hydroelectric (May 2016 - 2017) 3.40
Corp.
Power Project 3. Compliant with Reportorial Obligation. •Submitted progress report
4. Non-compliant with the RESHERR. •No Accredited Safety Officer
5. Non-compliant with the Submission of Abandonment and Termination Plan.
1. Non-compliant with the Work Plan. Delayed implementation of the Work Plan.
2. Non-compliant with the Posting of Performance Bond. Failed to post 2nd year
performance bond.
1.5MW Tubao 3. Non-compliant with Reportorial Obligation. No recent submission of progress
Tubao Mini Hydro-Electric
Tubao Hydroelectric report. 1.50
Corporation
Power Project 4. Non-compliant with the RESHERR. No submission of quarterly statistical report,
and annual safety and health program. No accredited Safety Officer.
5. Non-compliant with the Submission of Abandonment and Termination Plan. No
submission of Abandonment and Termination Plan.
1. Compliant with the Work Program. Completed Feasibility Study and with proof
of communication with other agencies.
2. Non-compliant with the Posting of Performance Bond. Failed to post 2nd year
2.2MW Coto 3 performance bond.
Masinloc Hydroelectric AT Dinum Company 3. Compliant with Reportorial Obligation. Recently submitted progress report. 2.20
Power Project 4. Non-compliant with the RESHERR. No submission of quarterly statistical report,
and annual safety and health program. No accredited Safety Officer.
5. Non-compliant with the Submission of Abandonment and Termination Plan. No
submission of Abandonment and Termination Plan.
1. Compliant with the Work Program. On-going permitting with proof of initial
coordination with other agencies.
2. Compliant with the Posting of Performance Bond. Posted 2nd year
performance bond.
0.6MW Barit 2
3. Non-compliant with Reportorial Obligation. No recent submission of progress
Hydroelectric People's Energy Services Inc. 0.60
report.
Power Project
4. Non-compliant with the RESHERR. No submission of quarterly statistical report,
and annual safety and health program. No accredited Safety Officer.
5. Non-compliant with the Submission of Abandonment and Termination Plan. No
submission of Abandonment and Termination Plan.
AWARDED HYDROELECTRIC POWER PROJECTS as of December 31, 2017
POTENTIAL INSTALLED
CITY /
ISLAND / GRID REGION PROVINCE PROJECT NAME COMPANY NAME STATUS OF COMPLIANCE CAPACITY CAPACITY
MUNICIPALITY
(MW) (MW)
1. Compliant with the Work Plan.
1.8MW Barit 1 2. N/A with the Posting of Performance Bond.
Luzon V Camarines Sur Buhi Hydroelectric People's Energy Services Inc. 3. Non-compliant with Reportorial Obligation. 1.80
Power Plant 4. Non-compliant with the RESHERR.
5. N/A with the Submission of Abandonment and Termination Plan.
1. N/A with the Work Plan.
1.5MW Rangas 2. Non-compliant with the Posting of Performance Bond.
Clean and Green Energy
Goa & Tigaon Hydroelectric 3. Compliant with Reportorial Obligation. 1.50
Solutions, Inc.
Power Project 4. Compliant with the RESHERR.
5. Non-compliant with the Submission of Abandonment and Termination Plan.
1. Non-compliant with the Work Plan. Delayed implementation of the Work Plan.
2. Non-compliant with the Posting of Performance Bond. Failed to post 2nd year
Performance Bond.
4MW Lower
3. Non-compliant with Reportorial Obligation. No submission of quarterly
Negros Himogaan
Visayas VI Sagay City LGU of Sagay accomplishment report. 4.00
Occidental Hydroelectric
4. Non-compliant with the RESHERR. No submission of quarterly statistical report,
Power Project
and annual safety and health program. No accredited Safety Officer.
5. Non-compliant with the Submission of Abandonment and Termination Plan. No
submission of Abandonment and Termination Plan.
1. Non-compliant with the Work Program. •No DED and permits from LGU, NCIP
and NWRB
1MW Saaz 2. Non-compliant with the Posting of Performance Bond. •No PB posted for the
Meadowland Developers,
Zamboanga City Hydroelectric 2nd yr of pre-development stage (January 2015 - 2016) 1.00
Inc.
Power Project 3. Non-compliant with Reportorial Obligation. •No submitted report
4. Non-compliant with the RESHERR. •No Accredited Safety Officer
5. Non-compliant with the Submission of Abandonment and Termination Plan.
1. Non-compliant with the Work Program. •No DED and permits from NWRB,
DENR, NCIP, NGCP and LGU of CDO
2.5MW Umalag 2
Meadowland Developers, 2. Non-compliant with the Posting of Performance Bond.
Mindanao X Bukidnon Libona Hydroelectric 2.50
Inc. 3. Compliant with Reportorial Obligation.
Power Project
4. Non-compliant with the RESHERR. •No Accredited Safety Officer
5. Non-compliant with the Submission of Abandonment and Termination Plan.
•No PB posted for the 2nd yr of development stage (June 2016 - 2017)
3.29MW Silo-o
•No PB posted for the 1st yr of development stage (June 2015 - 2016)
Malitbog Hydroelectric Philnewriver Power Corp. 3.29
3. Compliant with Reportorial Obligation. •Submitted report dated 20 December
Power Project
2017
4. Compliant with the RESHERR. •Safety Officer - Dominador M. Lanozo - permit
valid until March 31, 2018 - Malitbog, Silo-o, Mangima, Mati 2-3 & Kabulnan 2
HPPs
•Proponent to appoint separate Safety Officer for each HPP
5. Non-compliant with the Submission of Abandonment and Termination Plan.
AWARDED HYDROELECTRIC POWER PROJECTS as of December 31, 2017
POTENTIAL INSTALLED
CITY /
ISLAND / GRID REGION PROVINCE PROJECT NAME COMPANY NAME STATUS OF COMPLIANCE CAPACITY CAPACITY
MUNICIPALITY
(MW) (MW)
1. Compliant with the Work Program. has submitted FS/ Topograhpic study/
hydro study and proof of communication with Municipal of bukidnon and
Performance Bond for 2nd year
12MW Talakag 3
Markham Resources 2. Compliant with the Posting of Performance Bond. submitted the PB for the 2nd
Talakag Hydroelectric 12.00
Corporation year
Power Project
3. Compliant with Reportorial Obligation.
4. Non-compliant with the RESHERR.
5. Non-compliant with the Submission of Abandonment and Termination Plan.
1. Non-compliant with the Work Program. •No DED and permits from NWRB,
DENR, NCIP, NGCP and LGU of CDO
1.8MW Umalag 1
Misamis Cagayan de Oro Meadowland Developers, 2. Non-compliant with the Posting of Performance Bond.
Hydroelectric 1.80
Occidental City Inc. 3. Compliant with Reportorial Obligation.
Power Project
4. Non-compliant with the RESHERR. •No Accredited Safety Officer
5. Non-compliant with the Submission of Abandonment and Termination Plan.
1. Compliant with the Work Program. Submitted proof of coordination with other
government agencies and DED.
2. Non-compliant with the Posting of Performance Bond. Failed to post 2nd year
2MW Osmeña perfomance bond.
Davao Governor LGS Renewable Energies
Mindanao XI Hydroelectric 3. Non-compliant with Reportorial Obligation. No submission of progress report. 2.00
Oriental Generoso Corporation
Power Project 4. Non-compliant with the RESHERR. No submission of quarterly statistical report,
and annual safety and health program. No accredited Safety Officer.
5. Non-compliant with the Submission of Abandonment and Termination Plan. No
submission of Abandonment and Termination Plan.