Bidding Docs
Bidding Docs
Bidding Docs
BIDDNG DOCUMNTS
FOR
Contract Name:
2
epartment of Public Works and Highways (DPWH)
Contract ID: 17NI0057 (Re-ad)
Contract Name: Installation of the Structured Network Cabling and Electrical Requirements
in the new DPWH Surigao del Sur 2nd DEO Building
Location of the Contract: Bislig City, Surigao del Sur
INVITATION TO BID
The Department of Public Works and Highways (DPWH), Surigao del Sur 2nd District
Engineering Office, Bislig City, through its Bids and Awards Committee (BAC), invites
contractors to submit bids for the following Contract:
The BAC is conducting the public Bidding for this contarct in accordance with republic Act No. 9184
and its implementing Rules and Regulation (IRR).
To be eligible to bid for this Contract, a contractor must meet the following major requirements:
(a) Filipino citizen or 75% Filipino-owned partnership/corporation with PCAB license for Size Range
____, (b) completion of a similar contract costing at least 50% of the ABC*, and (c) Net Financial
Contracting Capacity (NFCC) at least equal to ABC.
The DPWH will use non-discretionary “pass/fail” criteria in the eligibilit check, preliminary
examination of bids, evaluation of bids, post qualification, and award.
As stipulated in Section 8.2.4.3 of the Implementing Rules and Regulations of RA 9184, the
PhilGEPS may support the implementing of e-Bid submission processes, which includes creation of
electronic bid forms, creation of bid box, deivery of bid submissions, notification to supplier of
receipt of bids, bid receiving and electronic bid evaluation. This facility shall cover all types of
procurement for goods, infrastructure projects and consulting services
E-Bid submission shall be conducted wherein bidders shall submit their bids electronically through
the PhilGEPS. Manual submission of bids shall not be allowed. This notwithstanding, bidders who
submit e-bids shall be required to sumit hard copies of the documents submitted electronically for
purposes of validation and/or verification during the electronic opening in the event the BAC
encounters technical problems or difficulty in opening e-bids. Fr this purpose, bidders shall register
as Platinum Members in the Government-Official Merchants Registry (OMR). In addition, bidders
who have purchased the Bidding Documents for this project shall be tagged as pilot users of the
e-Bidding.
Registered e-bidding pilot user can download the original copy of the bidding documents including
the electronic bid response form, submit and modify bids online, submit queries online and monitor
the progress of bidding online.
The schedule of key procurement activities for this Contract is shown below:
3
Department of Public Works and Highways (DPWH)
Bidders shall pay the BAC a non-refundable fee of ₱ 5,000.00 for the Bidding Documents, upon
securing hard copies of the Documents. Bidders that download the Documents from the DPWH/PhilGPES
website shall pay the fee upon submission of their bids.
The Department of Public Works and Highways (DPWH), Surigao del Sur 2nd District
Engineering Office, Bislig City, reserves the right to accept or reject any bid and to annual the
bidding process any time before the Contract award, without incurring any liability to the affected
bidders, in accordance with the provisions of Section 41 of RA 9184 and its IRR.
Any request for additional information concerning this bidding shall be directed to the following:
Approved by:
*For PCAB Small A and Small B Contractors, delete (b) of this paragraph, and rename (c) as (b)
4
Section II. Instructions to Bidders
5
TABLE OF CONTENTS
A. GENERAL ................................................................................. 8
1. Scope of Bid .......................................................................................... 8
2. Source of Funds ..................................................................................... 8
3. Corrupt, Fraudulent, Collusive, and Coercive Practices .............................. 8
4. Conflict of Interest ............................................................................... 10
5. Eligible Bidders .................................................................................... 11
6. Bidder’s Responsibilities........................................................................ 13
7. Origin of GOODS and Services .............................................................. 14
8. Subcontracts........................................................................................ 14
B. CONTENTS OF BIDDING DOCUMENTS ........................................... 15
9. Pre-Bid Conference .............................................................................. 15
10. Clarification and Amendment of Bidding Documents ............................... 15
C. PREPARATION OF BIDS ............................................................. 16
11. Language of Bids ................................................................................. 16
12. Documents Comprising the Bid: Eligibility and Technical Components ..... 16
13. Documents Comprising the Bid: Financial Component ............................ 19
14. Alternative Bids .................................................................................... 19
15. Bid Prices ............................................................................................ 20
16. Bid Currencies ..................................................................................... 20
17. Bid Validity .......................................................................................... 21
18. Bid Security ......................................................................................... 21
19. Format and Signing of Bids ................................................................... 23
20. Sealing and Marking of Bids .................................................................. 24
D. SUBMISSION AND OPENING OF BIDS ........................................... 25
21. Deadline for Submission of Bids ............................................................ 25
22. Late Bids ............................................................................................. 25
23. Modification and Withdrawal of Bids ...................................................... 25
24. Opening and Preliminary Examination of Bids ........................................ 26
E. EVALUATION AND COMPARISON OF BIDS ...................................... 27
25. Process to be Confidential .................................................................... 27
26. Clarification of Bids .............................................................................. 27
6
27. Detailed Evaluation and Comparison of Bids .......................................... 27
28. Post Qualification ................................................................................. 29
29. Reservation Clause ............................................................................... 30
F. AWARD OF CONTRACT .............................................................. 31
30. Contract Award .................................................................................... 31
31. Signing of the Contract ......................................................................... 32
32. Performance Security ........................................................................... 32
33. Notice to Proceed................................................................................. 33
7
A. General
1. Scope of Bid
The Procuring Entity as defined in the BDS, invites bids for the construction of
Works, as described in Section VI. Specifications. The name and
identification number of the Contract is provided in the BDS.
The successful bidder will be expected to complete the Works by the intended
completion date specified in SCC Clause 1.16.
2. Source of Funds
The Procuring Entity has a budget or has applied for or received funds from the
Funding Source named in the BDS, and in the amount indicated in the BDS.
It intends to apply part of the funds received for the Project, as defined in the
BDS, to cover eligible payments under the Contract for the Works.
(a) defines, for purposes of this provision, the terms set forth below
as follows:
8
Procuring Entity of the benefits of free and open
competition;
(b) will reject a proposal for award if it determines that the bidder
recommended for award has engaged in corrupt or fraudulent
practices in competing for the Contract; and
Further, the Procuring Entity will seek to impose the maximum civil,
administrative, and/or criminal penalties available under the applicable
laws on individuals and organizations deemed to be involved in any of
the practices mentioned in ITB Clause 3.1(a).
9
Furthermore, the Funding Source and the Procuring Entity reserve the right to
inspect and audit records and accounts of a contractor in the bidding for
and performance of a contract themselves or through independent
auditors as reflected in the GCC Clause 34.
4. Conflict of Interest
All bidders found to have conflicting interests shall be disqualified to participate
in the procurement at hand, without prejudice to the imposition of
appropriate administrative, civil, and criminal sanctions. A Bidder may
be considered to have conflicting interests with another Bidder in any of
the events described in paragraphs (a) through (c) and a general conflict
of interest in any of the circumstances set out in paragraphs (d) through
(g) below:
(e) A Bidder submits more than one bid in this bidding process.
However, this does not limit the participation of subcontractors in
more than one bid;
10
In accordance with Section 47 of the IRR of RA 9184, all Bidding Documents
shall be accompanied by a sworn affidavit of the Bidder that it is not
related to the Head of the Procuring Entity, members of the Bids and
Awards Committee (BAC), members of the Technical Working Group
(TWG), members of the BAC Secretariat, the head of the Project
Management Office (PMO) or the end-user unit, and the project
consultants, by consanguinity or affinity up to the third civil degree. On
the part of the bidder, this Clause shall apply to the following persons:
(k) If the Bidder is a joint venture (JV), the provisions of items (a),
(b), or (c) of this Clause shall correspondingly apply to each of
the members of the said JV, as may be appropriate.
5. Eligible Bidders
Unless otherwise indicated in the BDS, the following persons shall be eligible to
participate in this Bidding:
(b) Partnerships duly organized under the laws of the Philippines and
of which at least seventy five percent (75%) of the interest
belongs to citizens of the Philippines;
11
seventy five percent (75%) may be eligible where the structures
to be built require the application of techniques and/or
technologies which are not adequately possessed by a
person/entity meeting the seventy five percent (75%) Filipino
ownership requirement: Provided, finally, that in the latter case,
Filipino ownership or interest shall not be less than twenty five
percent (25%). For this purpose Filipino ownership or interest
shall be based on the contributions of each of the members of the
joint venture as specified in their JVA.
The Procuring Entity may also invite foreign bidders when provided for under
any Treaty or International or Executive Agreement as specified in the
BDS.
(a) Unless otherwise provided in the BDS, the Bidder must have completed,
within ten (10) years from the submission of bids, a single contract that
is similar to this Project, equivalent to at least fifty percent (50%) of the
ABC adjusted to current prices using the National Statistics Office
consumer price index.
For this purpose, contracts similar to the Project shall be those described
in the BDS, and completed within the period stated in the Invitation to
Bid and ITB Clause 12(a)(iii).
12
6. Bidder’s Responsibilities
The Bidder or its duly authorized representative shall submit a sworn statement
in the form prescribed in Section IX. Bidding Forms as required in ITB
Clause 12(b)(iii).
(g) Authorizing the Head of the Procuring Entity or its duly authorized
representative/s to verify all the documents submitted;
13
The Bidder, by the act of submitting its bid, shall be deemed to have inspected
the site, determined the general characteristics of the contract works
and the conditions for this Project and examine all instructions, forms,
terms, and project requirements in the Bidding Documents.
The Procuring Entity shall not assume any responsibility regarding erroneous
interpretations or conclusions by the prospective or eligible bidder out of
the data furnished by the procuring entity.
Before submitting their bids, the Bidders are deemed to have become familiar
with all existing laws, decrees, ordinances, acts and regulations of the
Philippines which may affect the contract in any way.
The Bidder shall bear all costs associated with the preparation and submission
of his bid, and the Procuring Entity will in no case be responsible or liable
for those costs, regardless of the conduct or outcome of the bidding
process.
Bidders should note that the Procuring Entity will only accept bids only from
those that have paid the nonrefundable fee for the Bidding Documents
at the office indicated in the Invitation to Bid.
8. Subcontracts
Unless otherwise specified in the BDS, the Bidder may subcontract portions of
the Works to an extent as may be approved by the Procuring Entity and
stated in the BDS. However, subcontracting of any portion shall not
relieve the Bidder from any liability or obligation that may arise from the
contract for this Project.
14
event that any subcontractor is found by the Procuring Entity to be
ineligible, the subcontracting of such portion of the Works shall be
disallowed.
The Bidder may identify the subcontractor to whom a portion of the Works will
be subcontracted at any stage of the bidding process or during contract
implementation. If the Bidder opts to disclose the name of the
subcontractor during bid submission, the Bidder shall include the
required documents as part of the technical component of its bid.
9. Pre-Bid Conference
(a) If so specified in the BDS, a pre-bid conference shall be held at the venue
and on the date indicated therein, to clarify and address the Bidders’
questions on the technical and financial components of this Project.
(b) The pre-bid conference shall be held at least twelve (12) calendar
days before the deadline for the submission of and receipt of bids. If
the Procuring Entity determines that, by reason of the method, nature,
or complexity of the contract to be bid, or when international
participation will be more advantageous to the GOP, a longer period for
the preparation of bids is necessary, the pre-bid conference shall be
held at least thirty (30) calendar days before the deadline for the
submission and receipt of bids, as specified in the BDS.
Bidders are encouraged to attend the pre-bid conference to ensure that they
fully understand the Procuring Entity’s requirements. Non-attendance
of the Bidder will in no way prejudice its bid; however, the Bidder is
expected to know the changes and/or amendments to the Bidding
Documents as recorded in the minutes of the pre-bid conference and
the Supplemental/Bid Bulletin.
Any statement made at the pre-bid conference shall not modify the terms of
the bidding documents unless such statement is specifically identified in
writing as an amendment thereto and issued as a Supplemental/Bid
Bulletin.
15
Supplemental/Bid Bulletins may be issued upon the Procuring Entity’s initiative
for purposes of clarifying or modifying any provision of the Bidding
Documents not later than seven (7) calendar days before the deadline
for the submission and receipt of Bids. Any modification to the Bidding
Documents shall be identified as an amendment.
Any Supplemental/Bid Bulletin issued by the BAC shall also be posted on the
Philippine Government Electronic Procurement System (PhilGEPS) and
the website of the Procuring Entity concerned, if available. Unless,
otherwise provided in the BDS, it shall be the responsibility of all Bidders
who secure the Bidding Documents to inquire and secure
Supplemental/Bid Bulletins that may be issued by the BAC. However,
bidders who have submitted bids before the issuance of the
Supplemental/Bid Bulletin must be informed and allowed to modify or
withdraw their bids in accordance with ITB Clause23.
C. Preparation of Bids
16
(iii) Statement of all its ongoing and completed government
and private contracts within ten (10) years from the
submission of bids, including contracts awarded but not
yet started, if any. The statement shall include, for each
contract, the following:
17
which should not be earlier than two (2) years from the
date of bid submission;
18
13. Documents Comprising the Bid: Financial Component
Unless otherwise stated in the BDS, the financial component of the bid shall
contain the following:
(b) Any other document related to the financial component of the bid
as stated in the BDS.
(a) Unless indicated in the BDS, all Bids that exceed the ABC shall not be
accepted.
19
Bidders shall submit offers that comply with the requirements of the Bidding
Documents, including the basic technical design as indicated in the
drawings and specifications. Unless there is a value engineering clause
in the BDS, alternative bids shall not be accepted.
Each Bidder shall submit only one Bid, either individually or as a partner in a
JV. A Bidder who submits or participates in more than one bid (other
than as a subcontractor if a subcontractor is permitted to participate in
more than one bid) will cause all the proposals with the Bidder’s
participation to be disqualified. This shall be without prejudice to any
applicable criminal, civil and administrative penalties that may be
imposed upon the persons and entities concerned.
The Bidder shall fill in rates and prices for all items of the Works described in
the Bill of Quantities. Bids not addressing or providing all of the required
items in the Bidding Documents including, where applicable, bill of
quantities, shall be considered non-responsive and, thus, automatically
disqualified. In this regard, where a required item is provided, but no
price is indicated, the same shall be considered as non-responsive, but
specifying a "0" (zero) for the said item would mean that it is being
offered for free to the Government.
All duties, taxes, and other levies payable by the Contractor under the Contract,
or for any other cause, prior to the deadline for submission of bids, shall
be included in the rates, prices, and total bid price submitted by the
Bidder.
All bid prices for the given scope of work in the contract as awarded shall be
considered as fixed prices, and therefore not subject to price escalation
during contract implementation, except under extraordinary
circumstances as specified in GCC Clause 48.Price escalation may be
allowed in extraordinary circumstances as may be determined by the
National Economic and Development Authority in accordance with the
Civil Code of the Philippines, and upon the recommendation of the
Procuring Entity. Furthermore, in cases where the cost of the awarded
contract is affected by any applicable new laws, ordinances, regulations,
or other acts of the GOP, promulgated after the date of bid opening, a
contract price adjustment shall be made or appropriate relief shall be
applied on a no loss-no gain basis.
20
foreign currencies shall be converted to Philippine currency based on the
exchange rate prevailing on the day of the Bid opening.
If so allowed in accordance with ITB Clause 0, the Procuring Entity for purposes
of bid evaluation and comparing the bid prices will convert the amounts
in various currencies in which the bid price is expressed to Philippine
Pesos at the exchange rate as published in the BSP reference rate
bulletin on the day of the bid opening.
Unless otherwise specified in the BDS, payment of the contract price shall be
made in Philippine Pesos.
21
(c.) Surety bond callable upon
demand issued by a surety or Five percent (5%)
insurance company duly certified by
the Insurance Commission as
authorized to issue such security
For biddings conducted by LGUs, the procuring entity may also require
bidders to submit bid securities in the form of cashier’s/manager’s check,
bank draft/guarantee, or irrevocable letter of credit from other banks
certified by the BSP as authorized to issue such financial statement.
The bid security should be valid for the period specified in the BDS. Any bid
not accompanied by an acceptable bid security shall be rejected by the
Procuring Entity as non-responsive.
No bid securities shall be returned to bidders after the opening of bids and
before contract signing, except to those that failed or declared as post-
disqualified, upon submission of a written waiver of their right to file a
motion for reconsideration and/or protest. Without prejudice on its
forfeiture, Bid Securities shall be returned only after the bidder with the
Lowest Calculated Responsive Bid has signed the contract and furnished
the Performance Security, but in no case later than the expiration of the
Bid Security validity period indicated in ITB Clause 0.
Upon signing and execution of the contract, pursuant to ITB Clause 31, and
the posting of the performance security, pursuant to ITB Clause 32, the
successful Bidder’s Bid security will be discharged, but in no case later
than the Bid security validity period as indicated in ITB Clause 0.
(a) if a Bidder:
(i) withdraws its bid during the period of bid validity specified
in ITB Clause 17;
22
(iv) submission of eligibility requirements containing false
information or falsified documents;
(xii) all other acts that tend to defeat the purpose of the
competitive bidding, such as habitually withdrawing from
bidding, submitting late Bids or patently insufficient bid, for
at least three (3) times within a year, except for valid
reasons.
23
eligibility requirements under ITB Clause 0, and the second shall contain
the financial component of the bid.
The Bidder shall prepare an original of the first and second envelopes as
described in ITB Clauses 12 and 13.
The bid, except for unamended printed literature, shall be signed, and each
and every page thereof shall be initialed, by the duly authorized
representative/s of the Bidder.
Any interlineations, erasures, or overwriting shall be valid only if they are signed
or initialed by the duly authorized representative/s of the Bidder.
Each copy of the first and second envelopes shall be similarly sealed duly
marking the inner envelopes as “COPY NO. ___ - TECHNICAL
COMPONENT” and “COPY NO. ___ – FINANCIAL COMPONENT” and the
outer envelope as “COPY NO. ___”, respectively. These envelopes
containing the original and the copies shall then be enclosed in one
single envelope.
The original and the number of copies of the Bid as indicated in the BDS shall
be typed or written in indelible ink and shall be signed by the bidder or
its duly authorized representative/s.
(b) bear the name and address of the Bidder in capital letters;
24
(e) bear a warning “DO NOT OPEN BEFORE…” the date and time for
the opening of bids, in accordance with ITB Clause 21.
(e)(f) shall be book binded with index tab of each of the documents
required in the checklist.
If bids are not sealed and marked as required, the Procuring Entity will assume
no responsibility for the misplacement or premature opening of the bid.
A Bidder may, through a letter of withdrawal, withdraw its bid after it has been
submitted, for valid and justifiable reason; provided that the letter of
withdrawal is received by the Procuring Entity prior to the deadline
prescribed for submission and receipt of bids.
No bid may be modified after the deadline for submission of bids. No bid may
be withdrawn in the interval between the deadline for submission of bids
and the expiration of the period of bid validity specified by the Bidder on
25
the Financial Bid Form. Withdrawal of a bid during this interval shall
result in the forfeiture of the Bidder’s bid security, pursuant to ITB
Clause 0, and the imposition of administrative, civil, and criminal
sanctions as prescribed by RA 9184 and its IRR.
Letters of withdrawal shall be read out and recorded during bid opening, and
the envelope containing the corresponding withdrawn bid shall be
returned to the Bidder unopened. If the withdrawing Bidder’s
representative is in attendance, the original bid and all copies thereof
shall be returned to the representative during the bid opening. If the
representative is not in attendance, the Bid shall be returned unopened
by registered mail. The Bidder may withdraw its bid prior to the deadline
for the submission and receipt of bids, provided that the corresponding
letter of withdrawal contains a valid authorization requesting for such
withdrawal, subject to appropriate administrative sanctions.
In the case of an eligible foreign Bidder as described in ITB Clause 5, the Class
“A” Documents enumerated in ITB Clause 12(a)may be substituted with
26
the appropriate equivalent documents, if any, issued by the country of
the foreign Bidder concerned.
Each partner of a joint venture agreement shall likewise submit the documents
required in ITB Clauses 12(a)(i) and 12(a)(ii). Submission of documents
required under ITB Clauses 12(a)(iii) to 12(a)(vi)by any of the joint
venture partners constitutes compliance.
A Bidder determined as “failed” has three (3) calendar days upon written notice
or, if present at the time of bid opening, upon verbal notification within
which to file a request for reconsideration with the BAC: Provided,
however, that the request for reconsideration shall not be granted if it is
established that the finding of failure is due to the fault of the Bidder
concerned: Provided, further, that the BAC shall decide on the request
for reconsideration within seven (7) calendar days from receipt thereof.
If a failed Bidder signifies his intent to file a request for reconsideration,
the BAC shall keep the bid envelopes of the said failed Bidder unopened
and/or duly sealed until such time that the request for reconsideration
or protest has been resolved.
Any effort by a bidder to influence the Procuring Entity in the Procuring Entity’s
decision in respect of Bid evaluation, Bid comparison or contract award
will result in the rejection of the Bidder’s Bid.
27
In evaluating the Bids to get the Lowest Calculated Bid, the Procuring Entity
shall undertake the following:
(b) The ranking of the total bid prices as so calculated from the lowest
to highest. The bid with the lowest price shall be identified as the
Lowest Calculated Bid.
(c) Completeness of the bid. Unless the ITB specifically allows partial
bids, bids not addressing or providing all of the required items in
the Schedule of Requirements including, where applicable, bill of
quantities, shall be considered non-responsive and, thus,
automatically disqualified. In this regard, where a required item
is provided, but no price is indicated, the same shall be considered
as non-responsive, but specifying a "0" (zero) for the said item
would mean that it is being offered for free to the Procuring
Entity; and
Based on the detailed evaluation of bids, those that comply with the above-
mentioned requirements shall be ranked in the ascending order of their
total calculated bid prices, as evaluated and corrected for computational
errors, discounts and other modifications, to identify the Lowest
Calculated Bid. Total calculated bid prices, as evaluated and corrected
for computational errors, discounts and other modifications, which
exceed the ABC shall not be considered, unless otherwise indicated in
the BDS.
The Procuring Entity’s evaluation of bids shall only be based on the bid price
quoted in the Financial Bid Form
Bids shall be evaluated on an equal footing to ensure fair competition. For this
purpose, all bidders shall be required to include in their bids the cost of
all taxes, such as, but not limited to, value added tax (VAT), income tax,
local taxes, and other fiscal levies and duties which shall be itemized in
the bid form and reflected in the detailed estimates. Such bids, including
said taxes, shall be the basis for bid evaluation and comparison.
28
28. Post Qualification
The Procuring Entity shall determine to its satisfaction whether the Bidder that
is evaluated as having submitted the Lowest Calculated Bid (LCB)
complies with and is responsive to all the requirements and conditions
specified in ITB Clauses 5, 12, and 13.
Within a non-extendible period of three (3) calendar days from receipt by the
Bidder of the notice from the BAC that it submitted the LCB, the Bidder
shall submit the following documentary requirements:
(a) Tax clearance per Executive Order 398, Series of 2005;as finally
reviewed and approved by the BIR
(b) Latest income and business tax returns in the form specified in
the BDS;
(d) Other appropriate licenses and permits required by law and stated
in the BDS.
If the BAC determines that the Bidder with the Lowest Calculated Bid passes all
the criteria for post-qualification, it shall declare the said bid as the
Lowest Calculated Responsive Bid, and recommend to the Head of the
Procuring Entity the award of contract to the said Bidder at its submitted
price or its calculated bid price, whichever is lower, subject to ITB Clause
0.
29
Within a period not exceeding seven (7) calendar days from the date of receipt
of the recommendation of the BAC, the Head of the Procuring Entity
shall approve or disapprove the said recommendation. In the case of
government owned and government-owned and/or -controlled
corporations (GOCCs) and government financial institutions (GFIs), the
period provided herein shall be fifteen (15) calendar days.
Based on the following grounds, the Procuring Entity reserves the right to reject
any and all Bids, declare a Failure of Bidding at any time prior to the
contract award, or not to award the contract, without thereby incurring
any liability, and make no assurance that a contract shall be entered into
as a result of the bidding:
(c) for any justifiable and reasonable ground where the award of the
contract will not redound to the benefit of the Government as
follows:
30
(iii) If the source of funds for the project has been withheld or
reduced through no fault of the Procuring Entity.
In addition, the Procuring Entity may likewise declare a failure of bidding when:
(f) All bids fail to comply with all the bid requirements or fail post-
qualification; or
(g) The bidder with the Lowest Calculated Responsive Bid refuses,
without justifiable cause to accept the award of contract, and no
award is made.
F. Award of Contract
Prior to the expiration of the period of Bid validity, the Procuring Entity shall
notify the successful Bidder in writing that its Bid has been accepted,
through a Notice of Award received personally or sent by registered mail
or electronically, receipt of which must be confirmed in writing within
two (2) days by the LCRB and submitted personally or sent by registered
mail or electronically to the Procuring Entity.
(ii) Valid PCAB license and registration for the type and cost of
the contract to be bid for foreign bidders, within thirty (30)
calendar days, followed under a Treaty or International or
Executive Agreement mentioned in ITB Clause 12(a)(iv);
31
(d) Approval by higher authority, if required.
Within ten (10) calendar days from receipt of the Notice of Award, the
successful Bidder shall post the required performance security, sign and
date the contract and return it to the Procuring Entity.
The Procuring Entity shall enter into contract with the successful Bidder within
the same ten (10) calendar day period provided that all the documentary
requirements are complied with.
The procuring entity shall prescribe at least two (2) acceptable forms of
performance security taken from two (2) categories below that bidders
may opt to use, denominated in Philippine Pesos and posted in favor of
the Procuring Entity in an amount equal to the percentage of the total
contract price as stated in the BDS in accordance with the following
schedule:
32
Amount of Performance Security
Form of Performance Security (Equal to Percentage of the Total
Contract Price)
(a) Bank draft/guarantee or
irrevocable letter of credit
issued by a Universal or
Commercial Bank: Provided,
however, that it shall be Ten percent (10%)
confirmed or authenticated
by a Universal or Commercial
Bank, if issued by a foreign
bank.
(b) Surety bond callable upon
demand issued by a surety or Thirty percent (30%)
insurance company duly
certified by the Insurance
Commission as authorized to
issue such security; and/or
The contract effectively date shall be provided in the Notice to Proceed by the
Procuring Entity, which date shall not be later than seven (7) calendar
days from the issuance of the Notice to Proceed.
33
Section III. Bid Data Sheet
34
Bid Data Sheet
ITB Clause
0 The PROCURING ENTITY is Department of Public Works and Highways,
Surigao del Sur 2nd Engineering District, Bislig City, Surigao del Sur.
The name of the Contract is
Installation of the Structured Network Cabling and Electrical
Requirements in the new DPWH Surigao del Sur 2nd DEO Building
The identification number of the Contract is 17NI0057 (Re-ad).
“Not applicable”.
0 The Procuring Entity will hold a pre-bid conference for this Project on
September 12, 2017 at DPWH Surigao del Sur 2ndDistrict Engineering Office,
Bislig City, Surigao del Sur.
No further instructions.
35
0 If the Procuring Entity maintains a registry system using the PhilGEPS or its
own electronic system:
The first envelope shall contain the eligibility and technical documents stated
in the ITB Clause. However, if the Bidder maintains a current and updated
file of his Class “A” Documents with the Procuring Entity, a written letter of
intent may be submitted in lieu of the Class “A” Documents; otherwise, it
shall submit an application for eligibility and its latest Class “A” Documents
17NI0057 (Re-ad)
T E C H N I C A L
MANPOWER REQUIRED
PERSONNEL NUMBER
Foreman 1
Electrician 1
Skilled 1
Welder 1
I. Technology 2
A.C. Technician 1
Laborer 4
Note:
Also attached the following documents:
Certified Photocopy of Professional License
Certified Photocopy of Professional Tax Receipt
Certified Photocopy of Certificate of Accreditation for Materials
Engineer I.
Certified Photocopy of Certificate of Trainings for the Const.
Safety & Health Officer
36
The pledged equipment shall be listed in complete to include the
brand, engine, chassis and serial numbers, capacity, present
location and must be ready for inspection during the post
qualification stage.
Failure of the prospective bidder to state a complete technical
description of the pledged equipment and the specific location,
whether owned, leased or under purchased agreement shall result
in the bidder’s automatic post-disqualification for award of
contract and forfeiture of its bid security (D.O. 58 series of 2012).
LIST OF CONTRACTOR’S EQUIPMENT PLEDGE TO THE CONTRACT
Capacit
No. Model/ y/ Proof of
Perform Motor
of Year Plate Specific Condi Ownership/
Description ance No./
Unit( Manufa No. Location tion Lessor or
Body No.
s) ctured Vendor
Size
A. Owned
B. Leased
C. Under
Purchase
Agreement
___________________________________
_____________________
(Name/Signature of Bidder’s Representative)
Date
____________________________________
(Name of Bidder)
37
17NI0057 (Re-ad) - Installation of the Structured Network
Cabling and Electrical Requirements in the new DPWH Surigao del
Sur 2nd DEO Building
T E C H N I C A L
EQUIPMENT REQUIRED
NUMBER
DESCRIPTION
NEDDED/AVAILABLE
Welding machine 1
A. ADDITIONAL REQUIREMENTS:
13(b) The ABC is Three Million Seven Hundred Eighty Two Thousand Five
Hundred Ninety Two Pesos Only and 58/100 (PHP 3,782,592.58)
Any bid with a financial component exceeding this amount shall not be
accepted.
The bid security shall be limited to Bid Securing Declaration (BSD) or one
other form in accordance with the following amount:
1. The amount Seven Five Thousand Six Hundred Fifty One Pesos and
85/100 (Php75,651.85) if bid security is in Bank draft/guarantee or
irrevocable letter of credit issued by a Universal or Commercial Bank:
Provided, however, that it shall be confirmed or authenticated by a
Universal or Commercial Bank, if issued by a foreign bank. (2%)
0 The bid security shall be valid until Two Hundred Ten Calendar Days
(210 CD) FROM THE OPENING OF BIDS.
38
0 Each Bidder shall submit original copies of the first and second
components of its bid. It must be book bounded with index tab on
each of the documents required. The contents are all
numbered/paginated consecutively, the total number of which are
indicated in the checklist of the requirements and signed by the
duly authorized representative.
The Chairman,
Bids and Awards Committee
Department of Public Works and Highways
Surigao del Sur 2nd Engineering District
Bislig City, Surigao del Sur
The date and time of bid opening is October 25, 2017 at 10:00 A. M.
39
Requirements:
Contract ID:
Contract Name:
Location of the Contract:
I . TECHNICAL DOCUMENTS : B
4. Duly Signed List of Contractor’s Equipment Pledged to the Contract supported with Proof of Ownership.
5. Minimum Materials Testing Equipment (D.O.138 series of 2015)
SWORN STATEMENT IN ACCORDANCE WITH SECTION 25.2 (b) (IV) OF THE IRR OF R.A. 9184.
11. Sworn Statement that it complies with Section II-A-4, (Conflict of Interest)
provided in the Bidding Documents.
1 Form of Bid
2 Duly signed Bid Prices in the Bill of Quantities
3 Duly signed Detailed Estimates
4 Duly signed Cash Flow by Quarter and Payment Schedule
Initials of BAC Members if all the documents are included
40
Conflict of Interest, Section II-A-4 (PBD 3rd Ed.)
Verification of:
*Tax Clearance
*Mayor’s Permit
*Latest Income and Business Tax Returns
*Certificate of PhilGEPS Registration
*Contractor’s Registration Certificate
*Other appropriate licenses
41
Section IV. General Conditions of Contract
42
TABLE OF CONTENTS
1. DEFINITIONS .......................................................................... 46
2. INTERPRETATION .................................................................... 48
3. GOVERNING LANGUAGE AND LAW ............................................... 48
4. COMMUNICATIONS................................................................... 49
5. POSSESSION OF SITE................................................................ 49
6. THE CONTRACTOR’S OBLIGATIONS .............................................. 49
7. PERFORMANCE SECURITY .......................................................... 50
8. SUBCONTRACTING ................................................................... 51
9. LIQUIDATED DAMAGES ............................................................. 52
10. ......................................................................................... SITE INVESTIGATION
REPORTS ............................................................................... 52
11. ....................................................... THE PROCURING ENTITY, LICENSES AND
PERMITS................................................................................ 52
12. ............................................................ CONTRACTOR’S RISK AND WARRANTY
SECURITY .............................................................................. 52
13. ............................................................................................... LIABILITY OF THE
CONTRACTOR.......................................................................... 55
14. ........................................................................................ PROCURING ENTITY’S
RISK ..................................................................................... 55
15. ..........................................................................................................INSURANCE
........................................................................................... 56
16. ....................................................................... TERMINATION FOR DEFAULT OF
CONTRACTOR.......................................................................... 57
17. ................................................. TERMINATION FOR DEFAULT OF PROCURING
ENTITY .................................................................................. 58
18. ................................................................................ TERMINATION FOR OTHER
CAUSES ................................................................................. 58
19. ................................................................ PROCEDURES FOR TERMINATION OF
CONTRACTS ............................................................................ 60
20. .................................................................... FORCE MAJEURE, RELEASE FROM
PERFORMANCE ........................................................................ 63
43
21. .................................................................................................. RESOLUTION OF
DISPUTES .............................................................................. 63
22. .................................................. SUSPENSION OF LOAN, CREDIT, GRANT, OR
APPROPRIATION ..................................................................... 64
23. ..................................................... PROCURING ENTITY’S REPRESENTATIVE’S
DECISIONS............................................................................. 64
24. . APPROVAL OF DRAWINGS AND TEMPORARY WORKS BY THE PROCURING
ENTITY’S REPRESENTATIVE ........................................................ 64
25. ....... ACCELERATION AND DELAYS ORDERED BY THE PROCURING ENTITY’S
REPRESENTATIVE..................................................................... 65
26. .................................................. EXTENSION OF THE INTENDED COMPLETION
DATE .................................................................................... 65
27. ............................................................................................................. RIGHT TO
VARY .................................................................................... 65
28. .................................................................................. CONTRACTORS RIGHT TO
CLAIM ................................................................................... 66
29. .......................................................................................................... DAYWORKS
........................................................................................... 66
30. ...................................................................................................................EARLY
WARNING .............................................................................. 66
31. ....................................................................................................... PROGRAM OF
WORK ................................................................................... 67
32. ..................................................................................................... MANAGEMENT
CONFERENCES......................................................................... 67
33. ................................................................................................................ BILL OF
QUANTITIES ........................................................................... 68
34. ................................................................. INSTRUCTIONS, INSPECTIONS AND
AUDITS ................................................................................. 68
35. .......................................................................................................IDENTIFYING
DEFECTS ................................................................................ 68
36. ............................................................................................................... COST OF
REPAIRS ................................................................................ 69
37. ..................................................................................................CORRECTION OF
DEFECTS ................................................................................ 69
44
38. .................................................................................................... UNCORRECTED
DEFECTS ................................................................................ 69
39. ............................................................................................................. ADVANCE
PAYMENT ............................................................................... 69
40. ........................................................................................................... PROGRESS
PAYMENTS ............................................................................. 70
41. ............................................................................................................. PAYMENT
CERTIFICATES ......................................................................... 71
42. .......................................................................................................... RETENTION
........................................................................................... 71
43. .......................................................................................................... VARIATION
ORDERS ................................................................................ 72
44. ........................................................................................................... CONTRACT
COMPLETION .......................................................................... 74
45. .................................................................................................. SUSPENSION OF
WORK ................................................................................... 74
46. ....................................................................................................... PAYMENT ON
TERMINATION......................................................................... 75
47. ................................................................................. EXTENSION OF CONTRACT
TIME..................................................................................... 75
48. ................................................................................................................... PRICE
ADJUSTMENT .......................................................................... 77
49. ....................................................................................................... COMPLETION
........................................................................................... 77
50. ................................................................................................................ TAKING
OVER .................................................................................... 77
51. .......................................................................OPERATING AND MAINTENANCE
MANUALS .............................................................................. 77
45
1. Definitions
For purposes of this Clause, boldface type is used to identify defined terms.
1.1. The Arbiter is the person appointed jointly by the Procuring Entity and
the Contractor to resolve disputes in the first instance, as provided for
in GCC Clause 21.
1.2. Bill of Quantities refers to a list of the specific items of the Work and
their corresponding unit prices, lump sums, and/or provisional sums.
1.4. The Contract is the contract between the Procuring Entity and the
Contractor to execute, complete, and maintain the Works.
1.5. The Contract Price is the price stated in the Letter of Acceptance and
thereafter to be paid by the Procuring Entity to the Contractor for the
execution of the Works in accordance with this Contract.
1.6. Contract Time Extension is the allowable period for the Contractor to
complete the Works in addition to the original Completion Date stated in
this Contract.
1.7. The Contractor is the juridical entity whose proposal has been accepted
by the Procuring Entity and to whom the Contract to execute the Work
was awarded.
1.8. The Contractor’s Bid is the signed offer or proposal submitted by the
Contractor to the Procuring Entity in response to the Bidding Documents.
1.10. Dayworks are varied work inputs subject to payment on a time basis
for the Contractor’s employees and Equipment, in addition to payments
for associated Materials and Plant.
1.11. A Defect is any part of the Works not completed in accordance with the
Contract.
1.13. The Defects Liability Period is the one year period between contract
completion and final acceptance within which the Contractor assumes
the responsibility to undertake the repair of any damage to the Works
at his own expense.
46
1.14. Drawings are graphical presentations of the Works. They include all
supplementary details, shop drawings, calculations, and other
information provided or approved for the execution of this Contract.
1.16. The Intended Completion Date refers to the date specified in the
SCC when the Contractor is expected to have completed the Works. The
Intended Completion Date may be revised only by the Procuring Entity’s
Representative by issuing an extension of time or an acceleration order.
1.18. The Notice to Proceed is a written notice issued by the Procuring Entity
or the Procuring Entity’s Representative to the Contractor requiring the
latter to begin the commencement of the work not later than a specified
or determinable date.
1.19. Permanent Works all permanent structures and all other project
features and facilities required to be constructed and completed in
accordance with this Contract which shall be delivered to the Procuring
Entity and which shall remain at the Site after the removal of all
Temporary Works.
1.20. Plant refers to the machinery, apparatus, and the like intended to form
an integral part of the Permanent Works.
1.21. The Procuring Entity is the party who employs the Contractor to carry
out the Works stated in the SCC.
1.23. The Site is the place provided by the Procuring Entity where the Works
shall be executed and any other place or places which may be
designated in the SCC, or notified to the Contractor by the Procuring
Entity’s Representative as forming part of the Site.
1.24. Site Investigation Reports are those that were included in the
Bidding Documents and are factual and interpretative reports about the
surface and subsurface conditions at the Site.
47
between the scheduled and actual accomplishment of the Work by the
Contractor as established from the work schedule. This is actually
described as a percentage of the whole Works.
1.27. The Start Date, as specified in the SCC, is the date when the Contractor
is obliged to commence execution of the Works. It does not necessarily
coincide with any of the Site Possession Dates.
2. Interpretation
In interpreting the Conditions of Contract, singular also means plural, male also
means female or neuter, and the other way around. Headings have no
significance. Words have their normal meaning under the language of
this Contract unless specifically defined. The Procuring Entity’s
Representative will provide instructions clarifying queries about the
Conditions of Contract.
48
documents pertaining to this Contract which are exchanged by the
parties shall be written in English.
This Contract shall be interpreted in accordance with the laws of the Republic
of the Philippines.
4. Communications
Communications between parties that are referred to in the Conditions shall be
effective only when in writing. A notice shall be effective only when it is
received by the concerned party.
5. Possession of Site
On the date specified in the SCC, the Procuring Entity shall grant the Contractor
possession of so much of the Site as may be required to enable it to
proceed with the execution of the Works. If the Contractor suffers delay
or incurs cost from failure on the part of the Procuring Entity to give
possession in accordance with the terms of this clause, the Procuring
Entity’s Representative shall give the Contractor a Contract Time
Extension and certify such sum as fair to cover the cost incurred, which
sum shall be paid by Procuring Entity.
If possession of a portion is not given by the date stated in the SCC Clause 0,
the Procuring Entity will be deemed to have delayed the start of the
relevant activities. The resulting adjustments in contact time to address
such delay shall be in accordance with GCC Clause 47.
The Contractor shall bear all costs and charges for special or temporary right-
of-way required by it in connection with access to the Site. The
Contractor shall also provide at his own cost any additional facilities
outside the Site required by it for purposes of the Works.
The Contractor shall allow the Procuring Entity’s Representative and any person
authorized by the Procuring Entity’s Representative access to the Site
and to any place where work in connection with this Contract is being
carried out or is intended to be carried out.
The Contractor shall commence execution of the Works on the Start Date and
shall carry out the Works in accordance with the Program of Work
submitted by the Contractor, as updated with the approval of the
49
Procuring Entity’s Representative, and complete them by the Intended
Completion Date.
The Contractor shall be responsible for the safety of all activities on the Site.
The Contractor shall carry out all instructions of the Procuring Entity’s
Representative that comply with the applicable laws where the Site is
located.
The Contractor shall employ the key personnel named in the Schedule of Key
Personnel, as referred to in the SCC, to carry out the supervision of the
Works. The Procuring Entity will approve any proposed replacement of
key personnel only if their relevant qualifications and abilities are equal
to or better than those of the personnel listed in the Schedule.
The Contractor shall submit to the Procuring Entity for consent the name and
particulars of the person authorized to receive instructions on behalf of
the Contractor.
The Contractor shall cooperate and share the Site with other contractors, public
authorities, utilities, and the Procuring Entity between the dates given in
the schedule of other contractors particularly when they shall require
access to the Site. The Contractor shall also provide facilities and
services for them during this period. The Procuring Entity may modify
the schedule of other contractors, and shall notify the Contractor of any
such modification thereto.
7. Performance Security
Within ten (10) calendar days from receipt of the Notice of Award from the
Procuring Entity but in no case later than the signing of the contract by
both parties, the Contractor shall furnish the performance security in any
the forms prescribed in ITB Clause 0.
50
The performance security posted in favor of the Procuring Entity shall be
forfeited in the event it is established that the Contractor is in default in
any of its obligations under the Contract.
The performance security shall remain valid until issuance by the Procuring
Entity of the Certificate of Final Acceptance.
The performance security may be released by the Procuring Entity and returned
to the Contractor after the issuance of the Certificate of Final Acceptance
subject to the following conditions:
(a) There are no pending claims against the Contractor or the surety
company filed by the Procuring Entity;
(b) The Contractor has no pending claims for labor and materials filed
against it; and
Unless otherwise indicated in the SCC, the Contractor, by entering into the
Contract with the Procuring Entity, acknowledges the right of the
Procuring Entity to institute action pursuant to Act 3688 against any
subcontractor be they an individual, firm, partnership, corporation, or
association supplying the Contractor with labor, materials and/or
equipment for the performance of this Contract.
8. Subcontracting
Unless otherwise indicated in the SCC, the Contractor cannot subcontract
Works more than the percentage specified in ITB Clause 0.
51
Subcontracting of any portion of the Works does not relieve the Contractor of
any liability or obligation under this Contract. The Contractor will be
responsible for the acts, defaults, and negligence of any subcontractor,
its agents, servants or workmen as fully as if these were the Contractor’s
own acts, defaults, or negligence, or those of its agents, servants or
workmen.
9. Liquidated Damages
The Contractor shall pay liquidated damages to the Procuring Entity for each
day that the Completion Date is later than the Intended Completion
Date. The applicable liquidated damages is at least one-tenth (1/10) of
a percent of the cost of the unperformed portion for every day of delay.
The total amount of liquidated damages shall not exceed ten percent
(10%) of the amount of the contract. The Procuring Entity may deduct
liquidated damages from payments due to the Contractor. Payment of
liquidated damages shall not affect the Contractor. Once the cumulative
amount of liquidated damages reaches ten percent (10%) of the amount
of this Contract, the Procuring Entity shall rescind this Contract, without
prejudice to other courses of action and remedies open to it.
52
be fully responsible for the safety, protection, security, and convenience
of his personnel, third parties, and the public at large, as well as the
Works, Equipment, installation, and the like to be affected by his
construction work.
The defects liability period for infrastructure projects shall be one year from
contract completion up to final acceptance by the Procuring Entity.
During this period, the Contractor shall undertake the repair works, at
his own expense, of any damage to the Works on account of the use of
materials of inferior quality within ninety (90) days from the time the
Head of the Procuring Entity has issued an order to undertake repair. In
case of failure or refusal to comply with this mandate, the Procuring
Entity shall undertake such repair works and shall be entitled to full
reimbursement of expenses incurred therein upon demand.
Unless otherwise indicated in the SCC, in case the Contractor fails to comply
with the preceding paragraph, the Procuring Entity shall forfeit its
performance security, subject its property(ies) to attachment or
garnishment proceedings, and perpetually disqualify it from participating
in any public bidding. All payables of the GOP in his favor shall be offset
to recover the costs.
After final acceptance of the Works by the Procuring Entity, the Contractor shall
be held responsible for “Structural Defects”, i.e., major
faults/flaws/deficiencies in one or more key structural elements of the
project which may lead to structural failure of the completed
elements or structure, or “Structural Failures”, i.e., where one or more
key structural elements in an infrastructure facility fails or collapses,
thereby rendering the facility or part thereof incapable of withstanding
the design loads, and/or endangering the safety of the users or the
general public:
53
not approving or acting on proposed changes to noted defects or
deficiencies in the design and/or specifications; and the use of
substandard construction materials in the project;
(d) Third Parties - Third Parties shall be held liable in cases where
Structural Defects/Failures are caused by work undertaken by
them such as leaking pipes, diggings or excavations, underground
cables and electrical wires, underground tunnel, mining shaft and
the like, in which case the applicable warranty to such structure
should be levied to third parties for their construction or
restoration works.
Minimum Amount in
Form of Warranty Percentage (%) of Total
Contract Price
(f) Cash or letter of credit issued by
Universal or Commercial bank:
provided, however, that the letter
of credit shall be confirmed or Five Percent (5%)
authenticated by a Universal or
Commercial bank, if issued by a
foreign bank
(g) Bank guarantee confirmed by
Universal or Commercial bank:
provided, however, that the letter
of credit shall be confirmed or Ten Percent (10%)
authenticated by a Universal or
Commercial bank, if issued by a
foreign bank
(h) Surety bond callable upon
demand issued by GSIS or any Thirty Percent (30%)
surety or insurance company duly
54
certified by the Insurance
Commission
The warranty security shall be stated in Philippine Pesos and shall remain
effective for one year from the date of issuance of the Certificate of Final
Acceptance by the Procuring Entity, and returned only after the lapse of
said one year period.
(b) The risk of damage to the Works, Plant, Materials, and Equipment
to the extent that it is due to a fault of the Procuring Entity or in
the Procuring Entity’s design, or due to war or radioactive
contamination directly affecting the country where the Works are
to be executed.
55
15. Insurance
The Contractor shall, under his name and at his own expense, obtain and
maintain, for the duration of this Contract, the following insurance
coverage:
The Contractor shall notify the insurers of changes in the nature, extent, or
program for the execution of the Works and ensure the adequacy of the
insurances at all times in accordance with the terms of this Contract and
shall produce to the Procuring Entity’s Representative the insurance
policies in force including the receipts for payment of the current
premiums.
If the Contractor fails to obtain and keep in force the insurances referred to
herein or any other insurance which he may be required to obtain under
the terms of this Contract, the Procuring Entity may obtain and keep in
force any such insurances and pay such premiums as may be necessary
for the purpose. From time to time, the Procuring Entity may deduct the
amount it shall pay for said premiums including twenty five percent
(25%) therein from any monies due, or which may become due, to the
Contractor, without prejudice to the Procuring Entity exercising its right
to impose other sanctions against the Contractor pursuant to the
provisions of this Contract.
In the event the Contractor fails to observe the above safeguards, the Procuring
Entity may, at the Contractor’s expense, take whatever measure is
deemed necessary for its protection and that of the Contractor’s
personnel and third parties, and/or order the interruption of dangerous
Works. In addition, the Procuring Entity may refuse to make the
56
payments under GCC Clause 40 until the Contractor complies with this
Clause.
(v) Where reasonable grounds exist that the insurer may not
be able, fully and promptly, to fulfill its obligation under
the insurance policy.
Due to the Contractor’s fault and while the project is on-going, it has incurred
negative slippage of fifteen percent (15%) or more in accordance with
Presidential Decree 1870, regardless of whether or not previous
warnings and notices have been issued for the Contractor to improve his
performance;
Due to its own fault and after this Contract time has expired, the Contractor
incurs delay in the completion of the Work after this Contract has
expired; or
The Contractor:
(b) does not actually have on the project Site the minimum essential
equipment listed on the Bid necessary to prosecute the Works in
57
accordance with the approved Program of Work and equipment
deployment schedule as required for the project;
(c) does not execute the Works in accordance with this Contract or
persistently or flagrantly neglects to carry out its obligations
under this Contract;
All materials on the Site, Plant, Equipment, and Works shall be deemed to be
the property of the Procuring Entity if this Contract is rescinded because
of the Contractor’s default.
(b) The prosecution of the Work is disrupted by the adverse peace and order
situation, as certified by the Armed Forces of the Philippines Provincial
Commander and approved by the Secretary of National Defense.
The Procuring Entity or the Contractor may terminate this Contract if the other
party causes a fundamental breach of this Contract.
Fundamental breaches of Contract shall include, but shall not be limited to, the
following:
(a) The Contractor stops work for twenty eight (28) days when no
stoppage of work is shown on the current Program of Work and
58
the stoppage has not been authorized by the Procuring Entity’s
Representative;
(c) The Procuring Entity shall terminate this Contract if the Contractor
is declared bankrupt or insolvent as determined with finality by a
court of competent jurisdiction. In this event, termination will be
without compensation to the Contractor, provided that such
termination will not prejudice or affect any right of action or
remedy which has accrued or will accrue thereafter to the
Procuring Entity and/or the Contractor. In the case of the
Contractor's insolvency, any Contractor's Equipment which the
Procuring Entity instructs in the notice is to be used until the
completion of the Works;
(g) The Contractor has delayed the completion of the Works by the
number of days for which the maximum amount of liquidated
damages can be paid, as defined in the GCC Clause 9; and
59
(iv) any other act analogous to the foregoing.
The Funding Source or the Procuring Entity, as appropriate, will seek to impose
the maximum civil, administrative and/or criminal penalties available
under the applicable law on individuals and organizations deemed to be
involved with corrupt, fraudulent, or coercive practices.
When persons from either party to this Contract gives notice of a fundamental
breach to the Procuring Entity’s Representative in order to terminate the
existing contract for a cause other than those listed under GCC Clause
0, the Procuring Entity’s Representative shall decide whether the breach
is fundamental or not.
If this Contract is terminated, the Contractor shall stop work immediately, make
the Site safe and secure, and leave the Site as soon as reasonably
possible.
(c) Within a period of seven (7) calendar days from receipt of the
Notice of Termination, the Contractor shall submit to the Head of
60
the Procuring Entity a verified position paper stating why the
contract should not be terminated. If the Contractor fails to show
cause after the lapse of the seven (7) day period, either by
inaction or by default, the Head of the Procuring Entity shall issue
an order terminating the contract;
(d) The Procuring Entity may, at any time before receipt of the
Bidder’s verified position paper described in item (c) above
withdraw the Notice to Terminate if it is determined that certain
items or works subject of the notice had been completed,
delivered, or performed before the Contractor’s receipt of the
notice;
(h) Failure by the contractor to fully and faithfully comply with its
contractual obligations without valid cause, or failure by the
contractor to comply with any written lawful instruction of the
procuring entity or its representative(s) pursuant to the
implementation of the contract. For the procurement of
infrastructure projects or consultancy contracts, lawful
instructions include but are not limited to the following:
61
(i) Employment of competent technical personnel, competent
engineers and/or work supervisors;
62
20. Force Majeure, Release From Performance
For purposes of this Contract the terms “force majeure” and “fortuitous event”
may be used interchangeably. In this regard, a fortuitous event or force
majeure shall be interpreted to mean an event which the Contractor
could not have foreseen, or which though foreseen, was inevitable. It
shall not include ordinary unfavorable weather conditions; and any other
cause the effects of which could have been avoided with the exercise of
reasonable diligence by the Contractor.
If the event continues for a period of eighty four (84) days, either party may
then give notice of termination, which shall take effect twenty eight (28)
days after the giving of the notice.
(a) any sum to which the Contractor is entitled under GCC Clause
28;
The net balance due shall be paid or repaid within a reasonable time period
from the time of the notice of termination.
63
Any and all disputes arising from the implementation of this Contract covered
by the R.A. 9184 and its IRR shall be submitted to arbitration in the
Philippines according to the provisions of Republic Act No. 876,
otherwise known as the “ Arbitration Law” and Republic Act 9285,
otherwise known as the “Alternative Dispute Resolution Act of 2004”:
Provided, however, That, disputes that are within the competence of the
Construction Industry Arbitration Commission to resolve shall be referred
thereto. The process of arbitration shall be incorporated as a provision
in this Contract that will be executed pursuant to the provisions of the
Act and its IRR: Provided, further, That, by mutual agreement, the
parties may agree in writing to resort to other alternative modes of
dispute resolution.
(b) If the Contractor has not received sums due it for work already done
within forty five (45) days from the time the Contractor’s claim for
payment has been certified by the Procuring Entity’s Representative, the
Contractor may immediately issue a suspension of work notice in
accordance with GCC Clause 0.
The Procuring Entity’s Representative may delegate any of his duties and
responsibilities to other people, except to the Arbiter, after notifying the
Contractor, and may cancel any delegation after notifying the
Contractor.
64
The Procuring Entity’s Representative’s approval shall not alter the Contractor’s
responsibility for design of the Temporary Works.
The Contractor shall obtain approval of third parties to the design of the
Temporary Works, when required by the Procuring Entity.
The Procuring Entity’s Representative shall decide whether and by how much
to extend the Intended Completion Date within twenty one (21) days of
the Contractor asking the Procuring Entity’s Representative for a decision
thereto after fully submitting all supporting information. If the
Contractor has failed to give early warning of a delay or has failed to
cooperate in dealing with a delay, the delay by this failure shall not be
considered in assessing the new Intended Completion Date.
65
(c) in the absence of appropriate rates, the rates in this Contract shall
be used as the basis for valuation; or failing which
29. Dayworks
Subject to GCC Clause 43 on Variation Order, and if applicable as indicated in
the SCC, the Dayworks rates in the Contractor’s Bid shall be used for
small additional amounts of work only when the Procuring Entity’s
Representative has given written instructions in advance for additional
work to be paid for in that way.
The Contractor shall be paid for Dayworks subject to obtaining signed Dayworks
forms.
66
31. Program of Work
Within the time stated in the SCC, the Contractor shall submit to the Procuring
Entity’s Representative for approval a Program of Work showing the
general methods, arrangements, order, and timing for all the activities
in the Works.
An update of the Program of Work shall the show the actual progress achieved
on each activity and the effect of the progress achieved on the timing of
the remaining work, including any changes to the sequence of the
activities.
When the Program of Work is updated, the Contractor shall provide the
Procuring Entity’s Representative with an updated cash flow forecast.
The cash flow forecast shall include different currencies, as defined in
the Contract, converted as necessary using the Contract exchange rates.
67
33. Bill of Quantities
The Bill of Quantities shall contain items of work for the construction,
installation, testing, and commissioning of work to be done by the
Contractor.
The Bill of Quantities is used to calculate the Contract Price. The Contractor is
paid for the quantity of the work done at the rate in the Bill of Quantities
for each item.
If the final quantity of any work done differs from the quantity in the Bill of
Quantities for the particular item and is not more than twenty five
percent (25%) of the original quantity, provided the aggregate changes
for all items do not exceed ten percent (10%) of the Contract price, the
Procuring Entity’s Representative shall make the necessary adjustments
to allow for the changes subject to applicable laws, rules, and
regulations.
The Contractor shall permit the Funding Source named in the SCC to inspect
the Contractor’s accounts and records relating to the performance of the
Contractor and to have them audited by auditors appointed by the
Funding Source, if so required by the Funding Source.
68
36. Cost of Repairs
Loss or damage to the Works or Materials to be incorporated in the Works
between the Start Date and the end of the Defects Liability Periods shall be
remedied by the Contractor at the Contractor’s cost if the loss or damage arises
from the Contractor’s acts or omissions.
Every time notice of a defect is given, the Contractor shall correct the notified
defect within the length of time specified in the Procuring Entity’s
Representative’s notice.
The Contractor shall correct the defects which he notices himself before the
end of the Defects Liability Period.
The Procuring Entity shall certify that all defects have been corrected. If the
Procuring Entity considers that correction of a defect is not essential, he
can request the Contractor to submit a quotation for the corresponding
reduction in the Contract Price. If the Procuring Entity accepts the
quotation, the corresponding change in the SCC is a Variation.
The use of a third party to correct defects that are uncorrected by the
Contractor will in no way relieve the Contractor of its liabilities and
warranties under the Contract.
The advance payment shall be made only upon the submission to and
acceptance by the Procuring Entity of an irrevocable standby letter of
69
credit of equivalent value from a commercial bank, a bank guarantee or
a surety bond callable upon demand, issued by a surety or insurance
company duly licensed by the Insurance Commission and confirmed by
the Procuring Entity.
The contractor may reduce his standby letter of credit or guarantee instrument
by the amounts refunded by the Monthly Certificates in the advance
payment.
The Procuring Entity will provide an Advance Payment on the Contract Price as
stipulated in the Conditions of Contract, subject to the maximum amount
stated in SCC Clause 0.
The Procuring Entity shall deduct the following from the certified gross amounts
to be paid to the contractor as progress payment:
(a) Cumulative value of the work previously certified and paid for.
The first progress payment may be paid by the Procuring Entity to the
Contractor provided that at least twenty percent (20%) of the work has
been accomplished as certified by the Procuring Entity’s Representative.
70
Items of the Works for which a price of “0” (zero) has been entered will not be
paid for by the Procuring Entity and shall be deemed covered by other
rates and prices in the Contract.
(b) comprise the value of the quantities of the items in the Bill of
Quantities completed; and
42. Retention
The Procuring Entity shall retain from each payment due to the Contractor an
amount equal to a percentage thereof using the rate as specified in ITB
Sub-Clause 0.
The total “retention money” shall be due for release upon final acceptance of
the Works. The Contractor may, however, request the substitution of
the retention money for each progress billing with irrevocable standby
letters of credit from a commercial bank, bank guarantees or surety
bonds callable on demand, of amounts equivalent to the retention
money substituted for and acceptable to the Procuring Entity, provided
that the project is on schedule and is satisfactorily undertaken.
71
Otherwise, the ten (10%) percent retention shall be made. Said
irrevocable standby letters of credit, bank guarantees and/or surety
bonds, to be posted in favor of the Government shall be valid for a
duration to be determined by the concerned implementing office/agency
or Procuring Entity and will answer for the purpose for which the ten
(10%) percent retention is intended, i.e., to cover uncorrected
discovered defects and third party liabilities.
An Extra Work Order may be issued by the Procuring Entity to cover the
introduction of new work necessary for the completion, improvement or
protection of the project which were not included as items of Work in
the original contract, such as, where there are subsurface or latent
physical conditions at the site differing materially from those indicated
in the contract, or where there are duly unknown physical conditions at
the site of an unusual nature differing materially from those ordinarily
encountered and generally recognized as inherent in the Work or
character provided for in the contract.
Any cumulative Variation Order beyond ten percent (10%) shall be subject of
another contract to be bid out if the works are separable from the
original contract. In exceptional cases where it is urgently necessary to
complete the original scope of work, the Head of the Procuring Entity
may authorize a positive Variation Order go beyond ten percent (10%)
but not more than twenty percent (20%) of the original contract price,
subject to the guidelines to be determined by the GPPB: Provided,
72
however, That appropriate sanctions shall be imposed on the designer,
consultant or official responsible for the original detailed engineering
design which failed to consider the Variation Order beyond ten percent
(10%).
In claiming for any Variation Order, the Contractor shall, within seven (7)
calendar days after such work has been commenced or after the
circumstances leading to such condition(s) leading to the extra cost, and
within twenty-eight (28) calendar days deliver a written communication
giving full and detailed particulars of any extra cost in order that it may
be investigated at that time. Failure to provide either of such notices in
the time stipulated shall constitute a waiver by the contractor for any
claim. The preparation and submission of Variation Orders are as
follows:
(d) If, after review of the plans, quantities and estimated unit cost of
the items of work involved, the proper office of the procuring
entity empowered to review and evaluate Change Orders or Extra
Work Orders recommends approval thereof, Head of the
Procuring Entity or his duly authorized representative, believing
the Change Order or Extra Work Order to be in order, shall
approve the same.
73
(e) The timeframe for the processing of Variation Orders from the
preparation up to the approval by the Head of the Procuring Entity
concerned shall not exceed thirty (30) calendar days.
The Contractor or its duly authorized representative shall have the right to
suspend work operation on any or all projects/activities along the critical
path of activities after fifteen (15) calendar days from date of receipt of
written notice from the Contractor to the district engineer/regional
director/consultant or equivalent official, as the case may be, due to the
following:
74
(d) There is failure on the part of the Procuring Entity to deliver
government-furnished materials and equipment as stipulated in
the contract.
The net balance due shall be paid or repaid within twenty eight (28) days from
the notice of termination.
If the Contractor has terminated the Contract under GCC Clauses 17 or 18, the
Procuring Entity shall promptly return the Performance Security to the
Contractor.
75
an extension of contract time, the Procuring Entity shall determine the
amount of such extension; provided that the Procuring Entity is not
bound to take into account any claim for an extension of time unless the
Contractor has, prior to the expiration of the contract time and within
thirty (30) calendar days after such work has been commenced or after
the circumstances leading to such claim have arisen, delivered to the
Procuring Entity notices in order that it could have investigated them at
that time. Failure to provide such notice shall constitute a waiver by the
Contractor of any claim. Upon receipt of full and detailed particulars, the
Procuring Entity shall examine the facts and extent of the delay and shall
extend the contract time completing the contract work when, in the
Procuring Entity’s opinion, the findings of facts justify an extension.
Extension of contract time may be granted only when the affected activities fall
within the critical path of the PERT/CPM network.
76
request of the Contractor for extension of contract time and submitted
to the Procuring Entity for consideration and the validity of the
Performance Security shall be correspondingly extended.
49. Completion
The Contractor shall request the Procuring Entity’s Representative to issue a
certificate of Completion of the Works, and the Procuring Entity’s
Representative will do so upon deciding that the work is completed.
If the Contractor does not supply the Drawings and/or manuals by the dates
stated in the SCC, or they do not receive the Procuring Entity’s
Representative’s approval, the Procuring Entity’s Representative shall
withhold the amount stated in the SCC from payments due to the
Contractor.
77
Section V. Special Conditions of Contract
78
Special Conditions of Contract
GCC Clause
1.16 The Intended Completion Date is Two Hundred Ten Calendar
Days (210 CD) from the effectivity of the contract.
1.21 The Procuring Entity is Department of Public Works and
Highways, Surigao del Sur 2nd Engineering District, Bislig City,
Surigao del Sur.
1.22 The Procuring Entity’s Representative is
NOEL R. OCLARIT
District Engineer
Surigao del Sur 2ndDistrict Engineering Office
Bislig City, Surigao del Sur
0 The Procuring Entity shall give possession of all parts of the Site to
the Contractor UPON ISSUANCE OF NOTICE TO PROCEED.
T E C H N I C A L
MANPOWER REQUIRED
PERSONNEL NUMBER
Foreman 1
Electrician 1
Skilled 1
Welder 1
I. Technology 2
A.C. Technician 1
Laborer 4
79
0 In case of semi-permanent structures, such as buildings of types 1, 2,
and 3 as classified under the National Building Code of the Philippines,
concrete/asphalt roads, concrete river control, drainage, irrigation lined
canals, river landing, deep wells, rock causeway, pedestrian overpass,
and other similar semi-permanent structures: Five (5) years.
13 No additional provision. , if the Contractor is a joint venture, “A
18.3(h)(i) No further instructions.
0 The Arbiter is: Construction Industry Arbitration Commission
0 No days’ work are applicable to the contract.
0 The Contractor shall submit the Program of Work to the Procuring
Entity’s Representative within ten (10) days of delivery of the Letter of
Acceptance.
0 The Funding Source is the Government of the Philippines.
0 The amount of the advance payment is 15% OF THE CONTRACT COST.
0 Materials and equipment delivered on the site but not completely put in
place shall NOT be included for payment.
0 The date by which operating and maintenance manuals are required is
not applicable
The date by which “as built” drawings are required is Thirty (30) days
from completion.
80
Section VI. Specifications
Notes on Specifications
A set of precise and clear specifications is a prerequisite for Bidders to respond realistically and
competitively to the requirements of the Procuring Entity without qualifying or conditioning their
Bids. In the context of international competitive bidding, the specifications must be drafted to
permit the widest possible competition and, at the same time, present a clear statement of the
required standards of workmanship, materials, and performance of the goods and services to
be procured. Only if this is done will the objectives of economy, efficiency, and fairness in
procurement be realized, responsiveness of Bids be ensured, and the subsequent task of Bid
evaluation facilitated. The specifications should require that all goods and materials to be
incorporated in the Works be new, unused, of the most recent or current models, and
incorporate all recent improvements in design and materials unless provided otherwise in the
Contract.
Samples of specifications from previous similar projects are useful in this respect. The use of
metric units is mandatory. Most specifications are normally written specially by the Procuring
Entity or its representative to suit the Works at hand. There is no standard set of Specifications
for universal application in all sectors in all regions, but there are established principles and
practices, which are reflected in these PBDs.
There are considerable advantages in standardizing General Specifications for repetitive Works
in recognized public sectors, such as highways, ports, railways, urban housing, irrigation, and
water supply, in the same country or region where similar conditions prevail. The General
Specifications should cover all classes of workmanship, materials, and equipment commonly
involved in construction, although not necessarily to be used in a particular Works Contract.
Deletions or addenda should then adapt the General Specifications to the particular Works.
Care must be taken in drafting specifications to ensure that they are not restrictive. In the
specification of standards for goods, materials, and workmanship, recognized international
standards should be used as much as possible. Where other particular standards are used,
whether national standards or other standards, the specifications should state that goods,
materials, and workmanship that meet other authoritative standards, and which ensure
substantially equal or higher quality than the standards mentioned, will also be acceptable. The
following clause may be inserted in the SCC.
81
Section VII. Drawings
Insert here a list of Drawings. The actual Drawings, including site plans,
should be attached to
82
Section VIII. Bill of Quantities
83
Department of Public Works and Highways
1. Part No. - Enter the “Part No.” for each section of the BOQ where unit prices are
entered.
2. Part Description – Enter the “Part Description” corresponding to the “Part No.”
3. Total Amount – Enter the “Total Amount” in Pesos for all pages having the same “Part
Description”
84
Bill of Quantities
(Columns8:33 (1), (2), (3), and (4) are (Columns (5) and (6) are
to be filled up by the Procuring Entity to be filled up by the Bidder)
Pay
Unit Price Amount
Item Description Unit
Quantity (Pesos) (Pesos)
No.
85
In Figures: Php
In words: Pesos
Submitted by:
Date:
Name of the Representative of the Bidder
86
Position
87
Section IX. Bidding Forms
88
TABLE OF CONTENTS
89
Department of Public Works and Highways (DPWH)
Contract ID:
Contract Name:
Location of the Contract:
Bid Form
Date:
(a) We have examined and have no reservation on the Bidding Documents (BDs),
including Supplemental/Bid Bulletins, for the above stated Contract;
(b) We offer to execute the Works for this Contract in accordance with the said BDs,
including the Bid Data Sheet, General and Special Conditions of Contract,
Specifications and Drawings therein;
(c) we present our Bid to execute the Works, consisting of our Technical Proposal
(Annex “A”) and our Financial Proposal (Annex “B”);
(1) Bid Security in the required form, amount and validity period, using Form
DPWH-INFR-09,10, or 11, as applicable (Annex “A-1”)
(2) Organizational Chart for the Contract, using Form DPWH-INFR-13 (Annex "A-3”)
(3) Contractor’s Certification on Key Personnel for the Contract, with the Key
Personnel’s Affidavits of Commitment to Work on the Contract, using form DPWH-
INFR-14 (Annex “A-4”)
(4) List of Contractor’s Major Equipment Pledged for the Contract, using the DPWH-
INFR-15 (Annex “A-6);
(2) Bid prices in the Bill of Quantities Form, using the Forms DPWH-INFR-17 and
18 (Annex “B-2”)
(4) Cash flow by the quarter, using Form DPWH-INFR- 19 (Annex “B-4”);
90
(f) The total price of our Bid for this Contract based on the unit prices in the said
Bill of Quantities, excluding any discounts offerd in item (g) below, is: Total Bid
price in words and in figures;
(g) The discounts we offer and the methodology for their application for this
Contract are: __________________;
(h) Our Bid shall be valid for a period of ___________________ days from the date
fixed for the opening of bids in accordance with the Bidding Documents, and it
shall remain binding upon us and may be accepted by you at any time before
the expiration of that period;
(i) If our Bid is accepted and we receive from you a Notice of Award, we commit,
within ten (10) calendar days from our receipt of the said Notice, (1) to submit
to you the required Performance Security and other documents prescribed in the
Bidding Documents, and (2) to sign the Contract Agreement;
(j) We understand that, if the contract is awarded to us, this Bid, together with your
written acceptance thereof through your Notice of Award, shall constitute a
binding contract between us, until a formal Contract Agreement is prepared and
executed;
(k) We understand that you are not bound to accept the Lowest Calculated Bid or
any other Bid that you may receive;
(l) We acknowledge that failure to sign each page of this form of Bid and the
accomplished Bill of Quantities shall be a ground for the rejection of our Bid; and
(m) We likewise certify/confirm that the undersigned is the duly authorized
representative of the Bidder, and granted full power and authority to do, execute
and perform any and all acts necessary to participate, submit the Bid, and to
sign and execute the appropriate contract documents for the abovementioned
Contract.
Name:
In the capacity of:
Signed:
Duly authorized to sign the Bid for and on behalf of:
Date: ___________
91
Department of Public Works and Highways (DPWH)
Contract ID:
Contract Name:
Location of the Contract:
This CONTRACT AGREEMENT, made this ___ day of _month_, _year, by and
between:
-and-
WITNESSETH:
NOW, THEREFORE, for and consideration of the foregoing premises, the parties
hereto agree as follows:
2. The following documents shall be attached, deemed to form, and be read and
construed as part of this CONTRACT AGREEMENT, and shall be interpreted
in the following order of priority:
92
Department of Public Works and Highways (DPWH)
Contract ID:
Contract Name:
Location of the Contract:
(7) Specifications
(8) Drawings
93
Department of Public Works and Highways (DPWH)
Contract ID:
Contract Name:
Location of the Contract:
IN WITNESS WHEREOF, the parties hereto set their respective hands on the day,
month and year first above written.
______________________ _____________________
Witnessed by:
______________________ _____________________
94
Department of Public Works and Highways (DPWH)
Contract ID:
Contract Name:
Location of the Contract:
AFFIDAVIT
95
Department of Public Works and Highways (DPWH)
Contract ID:
Contract Name:
Location of the Contract:
5. [Name of Bidder] is authorizing the Head of the Procuring Entity or its duly
authorized representative(s) to verify all the documents submitted;
96
Department of Public Works and Highways (DPWH)
Contract ID:
Contract Name:
Location of the Contract:
c) Make an estimate of the facilities available and needed for the contract to
be bid, if any; and
9. [Name of Bidder] did not give or pay directly or indirectly, any commission,
amount, fee, or any form of consideration, pecuniary or otherwise, to any person
or official, personnel or representative of the government in relation to any
procurement project or activity.
IN WITNESS WHEREOF, I have hereunto set my hand this __ day of ___, 20__
at ____________, Philippines.
____________________________________
[Bidder’s Representative/Authorized Signatory]
97
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
Contract ID :
Contract Name :
98
SUBSCRIBED AND SWORN to before me this day of at
, affiant exhibiting to me his Residence Certificate No. issued on
at .
Doc. No.
Page No. ___________________
Book No.
Series of
99
100