Lead time: 2 weeks Week 1 2 3 4 5 6 7 Gross requirements 100 500 300 Stock on order 100 Current stock Net requirements 0 500 300 Place order 500 300 Scheduled deliveries 500 300
Level 2: D Lot size: L4L
Lead time: 1 week Week 1 2 3 4 5 6 7 Gross requirements 500 300 Stock on order Current stock 50 50 Net requirements 450 300 Place order 450 300 Scheduled deliveries 450 300
Level 1,2: C Lot size: 800
Lead time: 1 week Week 1 2 3 4 5 6 7 Gross requirements 1050 850 150 Stock on order 300 Current stock 120 170 170 120 120 770 770 Net requirements 630 680 30 Place order 800 800 800 Scheduled deliveries 800 800 800 Level 0 - X Lot size: L4L Lead time: 2 period Week 1 2 3 4 5 6 7 8 Gross requirements 480 Stock on order Current stock 180 180 180 180 180 180 180 180 Net requirements 300 Start assembly 300 100 Scheduled completion 300
Level 1: A Lot size: Periodic order quantity (2 weeks)
Lead time: 2 weeks Week 1 2 3 4 5 6 7 8 Gross requirements 600 200 Stock on order Current stock 100 100 100 100 100 200 200 0 Net requirements 500 0 Place order 700 Scheduled deliveries 700
Level 1: B Lot size: 100
Lead time: 2 weeks Week 1 2 3 4 5 6 7 8 Gross requirements 300 100 Stock on order Current stock 50 50 50 50 50 50 50 50 Net requirements 250 50 Place order 300 100 Scheduled deliveries 300 100
Level 1: C Lot size: 200
Lead time: 1 week Week 1 2 3 4 5 6 7 8 Gross requirements 900 300 Stock on order Current stock 50 50 50 50 50 150 50 50 Net requirements 850 150 Place order 1000 200 Scheduled deliveries 1000 200
Level 1,2: D Lot size: 400
Lead time: 2 week Week 1 2 3 4 5 6 7 8 Gross requirements 1400 300 100 Stock on order Current stock 50 50 50 250 250 350 350 250 Net requirements 1350 50 0 Place order 1600 400 Scheduled deliveries 1600 400 9 100