Installation Standard For SPP
Installation Standard For SPP
Note:
The purpose of Installation standard is to implement the correct practices for
installation of Solar Power Plant.
1. Preparation Work
a. Drawings showing Longitude & Latitude co-ordination, True North etc. shall be
available at site for start-up.
b. Checkout and ensure the tools & tackles required are sufficient at site location.
c. Check the structural elements as per the drawings especially the dimensional
aspects, holes, etc.
d. Foundation area where the structure to be shifted should be cleaned.
2. Installation
1) Before start installation work marking should be done for Legs, As per the
drawing
2) Check the Legs and ground clearance, Leg to Leg Distance as per
dimensions mentioned in design drawings.
3) The leg structure is gently locked with the stand with appropriate Nut/Bolts.
Care shall be taken that all Bolts are inserted in the same direction taking
care of the length. Two/Three threads on the bolt shall be left after the
complete Nut / Washer / Bolt assembly is done.
4) Alignment should be done as per dimensions given in drawing. Each nut shall
be tightened with a continuous smooth action using a calibrated torque device, for
Tightening torque refer given below standard table 1.1.
Installation Standard for Solar PV Plant
Table 1.1
5) The ration of cement, sand and aggregate should be as per the details mentioned
in design. Allow 12 hours of curing time for the cement concrete.
6) Crimping of MC4 connecter lugs must be done with MC4 Crimping tool.
9) Proper lugs must be used as per the connection type i.e. Bootless lugs
used for inverter, Pin type lugs used for MCB, ring type lug used for
Erthing and MCCB lugging purpose, and crimping of lugs must be
done with suitable crimping tool.
10) For installation of inverter choose location at which we can avoid constant
contact with water, direct solar irradiation, dust and ammonia gases,
flammable surface etc.
Location selected at which inverter get adequate air flow.
1) Installation carried out as per SCPL approved drawing only. Any change in
layout must be informed to design department for approval before installation.
2) Structure material must be as per approved BOM only. Any change in BOM
must be informed to design department for approval before installation.
3) All rules and regulations must be followed strictly as per site’s security
procedure and at customer location also. Any harsh behavior from any labor or
supervisor is strictly not allowed.
4) In case of any query, contractor must not communicate directly with customer.
Contractor should inform SCPL site engineer/supervisor in case of any query,
information.
If the contractor does not follow any of the standard/Guideline as mention above than
penalty or Rework will be in the scope of the contractor.