Figure 1: Auto-Schedule Tool
Figure 1: Auto-Schedule Tool
Apparatus
MS Project
This tool contains a list which allows us to perform any operation like Gantt Chart,
Network Diagram or Resource Sheet.
Different columns can be generated by clicking the bar above such as Free Slack
and Critical
Procedure
1. Start with the entering the Task Name in the given Column
Figure 6: Predecessors
Figure 7: PERT
4. Columns are completed with predecessors, free slack and critical activities.
Figure 8: Duration
Start: Tue 12/11/19ID: 1 Start: Tue 03/12/19ID: 3 Start: Mon 06/01/20 ID: 4 Start: Mon 03/02/20 ID: 8 Start: Mon 09/03/20ID: 12
Finish: Mon 02/12/19
Dur: 15 days Finish: Fri 03/01/20Dur: 24 days Finish: Fri 31/01/20Dur: 20 days Finish: Fri 06/03/20Dur: 25 days Finish: Tue 17/03/20
Dur: 7 days
Res: Res: Res: Res: Res:
G-Train Marketing Personnel N-Release advertising to print media Q-Run Media Advertising, mailings
Start: Wed 05/02/20ID: 7 Start: Wed 18/03/20ID: 14 Start: Tue 24/03/20ID: 17
Finish: Tue 03/03/20
Dur: 20 days Finish: Mon 23/03/20
Dur: 4 days Finish: Tue 21/04/20
Dur: 21 days
Res: Res: Res:
5. Network Diagram is chosen from the Button at the top left corner.
Discussions and Conclusion
MS Project is a very important tool which contains features like Gantt chart,
Resource Sheet and Network Diagram. In Problem we had to identify the critical path
of the Activities as described in the problem statement. It is very easy and simplified
tool to use all these features. Optimistic, most likely and pessimistic time durations
are given. Estimated time duration is calculated using the PERT Technique. Free
Slack is also calculated in one column, for instance 52 Days is assigned to the
Activity B which means that ‘B’ can be started after 52 Days. Critical Path is
ACDJKNQ.