CPM Model Question
CPM Model Question
MODEL EXAM
AR 6012 CONSTRUCTION AND PROJECT MANAGEMENT
PART-A DATE: 14.10.2019
ANSWER ALL THE QUESTIONS
1. Explain the drawbacks of bar chart.
2. What is meant by WBS?
3. Explain PERT.
4. Explain project cost.
5. Explain the concept of network crashing.
6. What do you understand my most likely time.
7. Explain the concept of critical path.
8. Give any two comparison between PERT and CPM.
9. What do you understand by project updating?
10. Explain cost slope.
PART-B
11 A. FOLLOWING TABLE SHOWS THE DETAILS OF CONSTRUCTION PROJECT.
B. A PERT network consists of seven activities. The optimistic time (t0), most likely (tm) and
pessimistic time (tp) as estimated for different activities in weeks are given below in table
Below.