Calibration Procedure For Melting Point Apparatus: IA 9100, 9200 and 9300
Calibration Procedure For Melting Point Apparatus: IA 9100, 9200 and 9300
Calibration must be carried out annually, or whenever the performance of the apparatus is suspected,
e.g. when similar successive test produce markedly divergent results.
The apparatus must either be returned to the dealer for calibration, or calibration must be carried out in
the following manner, using Calibration Kit AZ6730 and the standard chemicals Carbazole (AZ9118)
and P-nitrotoluene (AZ9218).
a) Switch the unit on and ensure the instrument components are in the stable condition
b) Perform a melt with each standard chemical and note the reading
c) Compare the results obtained with the melting points shown on the certificates supplied
with each chemical and ascertain whether the unit performs within acceptable limits
3. Invert the unit and remove the three screws securing the base plate to the body
4. Place the unit on the bench the correct way up taking care not to let the base fall from the unit. Lift
the body from the base plate
5. Turn the body on its side and placed it on the bench to the right of the base plate
6. Remove the two pin connector from PL1 2A on the printed circuit board
10. Allow the instrument to re-stabilise. It should not be necessary to go through the ‘Set-point’
procedure again at this stage. 2 to 3 minutes should suffice to ensure stabilisation.
11. Adjust the LO knob until the display shows the actual melting point obtained in b) above for the
standard sample of p-nitrotoluene.
13. Adjust the HI knob until the display shows the actual melting point obtained in b) above for the
standard sample of Carbazole
14. Adjust VR1 on the PCB with the trim tool provided untilt the display reads the melting point o
Carbazole as quoted on the Calibration Certificate provided with the sample.
16. Adjust VR3 on the PCB with eth trim tool until the display reads the melting point of p-nitrotoluene
as quoted on the Calibration Certificate provided with the sample
17. Repeat steps 14 to 18 until no further adjustment to VR1 and VR3 are required when the switch is
changed from Hi to LO
19. Unplug the calibration Box PL12A and replace the connector removed in stage 6
20. Remove the power supply plug and replace the base. Check the calibration again using Standard
Chemicals as in b) and c) and repeat the procedure if necessary