Week 1 Site Investigation
Week 1 Site Investigation
Construction technology
Week 1
• Lecture
• Monday, 10 – 11 am, BK17
• Wednesday, 4 – 6 pm, BK17
• Consultation hours
• Wednesday, 9 – 11 am
• Or through appointment
Course Overview (con`t)
• Teaching Plan
• Site location and investigation (3 hours)
• Choice of methods and plants (6 hours)
• Earthworks (5 hours)
• Types of piles and piling methods (5 hours)
• Concrete technology (4 hours)
• Special structures (5 hours)
• Temporary works (4 hours)
• Industrialized building system (IBS) (7 hours)
• Seminar by professional practitioner (3 hours)
Course overview (con`t)
• Assessment
• Test 1 – 20%
• Test 2 – 20%
• 9 x Assignments – 20%
• Final Exam – 40%
2. Accessibility
• Approach and site access roads, width, gradient, bends, sharp corners, condition
and construction relative to transport of heavy plant and equipment
• Bridges strength, width and clearance height
• Temporary roads, rolled metal tracts or consider preparing sub-base for new
roads as temporary access
3. Availability of space
• Site offices, canteen, stores and compound
• Material storage and handling
• Construction area and assembly areas
• Plant location
4. Services
• Water, drainage, electricity, gas & telephone
5. Ground composition
• Required to determine:
• Changes in strata
• Strength of subsoil
• Toxicity of subsoil
• Stability of excavation
• Water table (depth below surface)
• Geology: exposures of soils and rocks which can be examined and sampled
• Surface water and ground water: signs of flooding; springs; water logging
• Vegetation: signs of vegetation die-back or restricted vegetation as a result of
contamination of the ground; presence of invasive species such as Japanese Knotweed;
trees which may cause shrinkage and swelling of clay soils
• Contamination: indications of spills, disturbed ground, areas of fill or spoil heaps, old
fuel or oil tanks
• Local knowledge: anecdotal information on past uses of the site or past problems in
the area
• Access and services: information such as access for site equipment and location of
buried or overhead services
Detailed exploration/ Ground Investigation
(gi)
• The principal objective of the detailed soil test/ ground investigation
are as follows:
• To carry out tests to determine the mechanical properties of the soil in-situ
• Information required from GI
• Depth to bedrock
• Three principal methods of investigating the ground conditions:
• Excavating a hole large enough for a person to work in and revealing the soil strata for
examining and sampling
• Used extensively at the surface for block sampling and detection of service prior to
borehole excavation
• Only suitable in dry areas, as they allow hand cut samples to be taken which minimize
the disturbance of sample
• Most suitable to be used in exploring back filled area and sites overlain by variable
natural deposits
Example of trial pit dimension
• Boreholes
• Refer to MS2038
• Principal method for detailed ground investigations
• Used to determine the nature of the ground in a qualitative manner
• Recover undisturbed samples for quantitative examination
• The greater the number of boreholes, the more certain it is possible to be of the
correlation and thus to trust in the results
• Includes coring, sampling, in-situ testing and water table observation
• Drill through soils and core through rocks
• Two commonly used method
• Rotary drilling method
• Rotary wash boring
• Rock coring
Typical Rotary Drilling Rig
• Care in sampling
• Standard Penetration tests
• According to MS1056
• Hammer weight = 65 kg
• Total penetration is 450 mm and the number of blows for the last 300 mm is the SPT’N’
value
• Water table elevation determination
• Measure down the hole to the water table as water fills the hole
• McMullen (1998)
• Constraints with lesser impact
• Constraints with greater impact
• Economic constraints
• Budget limit
• Adopted construction system may not be the best for achieving goal and quality
• Allocation of money
• Will affect the quality of product and performance of project
• Legal constraints
• Mainly related to work law, safety regulations and supervision plan
• May affect schedule and lead to project delay
• E.g. traffic diversion requiring immediate decision
• May affect planning and progress of the project
• E.g. traffic ordinance and excavation permit
• Environmental constraints
• Public concerns and regulations requiring the environment to be protected
• E.g. air protection, tree preservation, traffic limit, noise control etc
• If the approval is not obtained on time, will affect the progress of the project
• Technical constraints may also arise from environmental constraints
• Technical constraints
• The ability and competency of local engineers to design and construct the project,
especially when dealing with state-of-the-art projects
• Usage of international expatriates
• May also arise from other type of constraints
• Social constraints
• May appear minor and insignificant, but is very complicated to deal with
• Sometimes may bring big problems for the project, and affect the progress of the project
• E.g. compensation of properties, dirty and faulty roads, proper use of public money etc.
END OF CHAPTER 1