The document provides a method statement for installing various doors as part of a proposed new mosque construction project in Bandar Universiti, Seri Iskandar, Perak. It outlines 5 tasks involving installing reinforced concrete lintels, wood panel doors, phenolic panel doors of various sizes. The tasks will take an estimated total of 4 days to complete using skilled and general laborers with hand and power tools.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0 ratings0% found this document useful (0 votes)
121 views5 pages
Door Tandas
The document provides a method statement for installing various doors as part of a proposed new mosque construction project in Bandar Universiti, Seri Iskandar, Perak. It outlines 5 tasks involving installing reinforced concrete lintels, wood panel doors, phenolic panel doors of various sizes. The tasks will take an estimated total of 4 days to complete using skilled and general laborers with hand and power tools.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 5
UNION SIX CONSTRUCTION SDN. BHD.
METHOD STATEMENT FORM
TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI, SERI ISKANDAR, PERAK. PREPARED BY: SHARIFAH NUR ATIQAH DATE: 08/11/2019 ELEMENT: DOOR PAGE NO: 1/5
NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION
TOOL LABOUR 1. Vibrated reinforced concrete, 125mm x 32m Hammer drill 1 skilled labor Workers 1 days 200mm high as output = 2m/h described lintol Mash hammer 2 general labor reinforcement with and 2x3=6 including 4 nos. 10mm Masonry chisel diameter high tensile bar (32m / 6m/h) / Tape measure 8 hours = reinforcement hooked at both ends with 6mm 0.66 days Trowel diameter mild steel bar reinforcement as described stirrups at stirrups at 150mm center including formwork. UNION SIX CONSTRUCTION SDN. BHD.
METHOD STATEMENT FORM
TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI, SERI ISKANDAR, PERAK. PREPARED BY: SHARIFAH NUR ATIQAH DATE: 08/11/2019 ELEMENT: DOOR PAGE NO: 2/5
NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION
TOOL LABOUR 2. 1400mm x 2100mm double leaves wood 1 no’s Measuring 1 skilled labor Workers 1 day panel door and c/w tape output = ironmongeries to 1 general labor 0.8m/h Architect's approval. (D2) Hammer 2 x 0.8 = 1.6 Screw driver (1m / 1.6m/h) / Driller 8 hours = 0.78 days UNION SIX CONSTRUCTION SDN. BHD.
METHOD STATEMENT FORM
TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI, SERI ISKANDAR, PERAK. PREPARED BY: SHARIFAH NUR ATIQAH DATE: 08/11/2019 ELEMENT: DOOR PAGE NO: 3/5
NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION
TOOL LABOUR 3. 900mm x 2100mm single leaves wood panel door 4 no’s Measuring 1 skilled labor Workers 1 day door and c/w tape output = ironmongeries to 1 general labor 0.8m/h Architect's approval Hammer 2 x 0.8 = 1.6 Screw driver (4m / 1.6m/h) / Driller 8 hours = 0.31 days UNION SIX CONSTRUCTION SDN. BHD.
METHOD STATEMENT FORM
TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI, SERI ISKANDAR, PERAK. PREPARED BY: SHARIFAH NUR ATIQAH DATE: 08/11/2019 ELEMENT: DOOR PAGE NO: 4/5
NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION
TOOL LABOUR 4. 750mm x 2100mm Asuwaris Phenolic panel 10 no’s Measuring 1 skilled labor Workers 1 day door and c/w tape output = ironmongeries to 1 general labor 0.8m/h Architect's approval. Hammer 2 x 0.8 = 1.6 Screw driver (10m / 1.6m/h) Driller / 8 hours = 0.78 days UNION SIX CONSTRUCTION SDN. BHD.
METHOD STATEMENT FORM
TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI, SERI ISKANDAR, PERAK. PREPARED BY: SHARIFAH NUR ATIQAH DATE: 08/11/2019 ELEMENT: DOOR PAGE NO: 5/5
NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION
TOOL LABOUR 5. 1000mm x 2100mm Asuwaris Phenolic panel 2 no’s Measuring 1 skilled labor Workers 1 day door and c/w tape output = ironmongeries to 1 general labor 0.8m/h Architect's approval Hammer 2 x 0.8 = 1.6 Screw driver (2m / 1.6m/h) / Driller 8 hours = 0.16 days