Red Zuma Project - Part-1

The Red Zuma Project has a planned completion date of January 8, 2016 after 260 days. The critical path activities are 2-3-5-8-9-11-12-13-15-16-17. Activity 6 has the most slack at 179 days. The network diagram shows a single critical path, so it is not very sensitive to delays. Activities 5 and 12 are key milestones.

Uploaded by

Zeeshan Ali
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (2 votes)
2K views5 pages

Red Zuma Project - Part-1

The Red Zuma Project has a planned completion date of January 8, 2016 after 260 days. The critical path activities are 2-3-5-8-9-11-12-13-15-16-17. Activity 6 has the most slack at 179 days. The network diagram shows a single critical path, so it is not very sensitive to delays. Activities 5 and 12 are key milestones.

Uploaded by

Zeeshan Ali
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 5

RED ZUMA PROJECT

PART-1

1- The Project shall take 260 days to get completed. The expected completion of the Project is 8th January
2016.
2- The critical activities on the critical path is 2-3-5-8-9-11-12-13-15-16-17
3- The activity 6 has the utmost slack period.
4- Network is less sensitive as there is only one critical path.
5- Activity 5 and 12 has been known milestones as they are key activities as many activities are dependent on
these activities to finalize for completion of this project.
 A GANTT CHART
 A NETWORK DIAGRAM HIGHLIGHTING THE CRITICAL PATH
 A SCHEDULE TABLE REPORTING ES, LS, EF, LF & SLACK

Activity ID Duration ES LS EF LF SL
2 25 0 0 25 25 0
3 30 25 25 55 55 0
4 20 25 35 45 55 10
5 10 55 55 65 65 0
6 15 65 244 80 259 179
7 30 65 120 95 150 55
8 45 65 65 110 110 0
9 25 110 110 135 135 0
10 10 135 140 145 150 5
11 15 135 135 150 150 0
12 20 150 150 170 170 0
13 10 170 170 180 180 0
14 7 170 194 177 204 27
15 14 180 180 194 194 0
16 35 224 224 259 259 0
17 1 259 259 260 260 0
PART-2

PART-A

1- Marketing specialists, Design engineers, Industrial engineers and Test riders resources are
overallocated.