Red Zuma Project - Part-1
Red Zuma Project - Part-1
PART-1
1- The Project shall take 260 days to get completed. The expected completion of the Project is 8th January
2016.
2- The critical activities on the critical path is 2-3-5-8-9-11-12-13-15-16-17
3- The activity 6 has the utmost slack period.
4- Network is less sensitive as there is only one critical path.
5- Activity 5 and 12 has been known milestones as they are key activities as many activities are dependent on
these activities to finalize for completion of this project.
A GANTT CHART
A NETWORK DIAGRAM HIGHLIGHTING THE CRITICAL PATH
A SCHEDULE TABLE REPORTING ES, LS, EF, LF & SLACK
Activity ID Duration ES LS EF LF SL
2 25 0 0 25 25 0
3 30 25 25 55 55 0
4 20 25 35 45 55 10
5 10 55 55 65 65 0
6 15 65 244 80 259 179
7 30 65 120 95 150 55
8 45 65 65 110 110 0
9 25 110 110 135 135 0
10 10 135 140 145 150 5
11 15 135 135 150 150 0
12 20 150 150 170 170 0
13 10 170 170 180 180 0
14 7 170 194 177 204 27
15 14 180 180 194 194 0
16 35 224 224 259 259 0
17 1 259 259 260 260 0
PART-2
PART-A
1- Marketing specialists, Design engineers, Industrial engineers and Test riders resources are
overallocated.
2-