The document appears to describe test procedures and formats for commissioning a P643 transformer differential relay. It involves mechanical checks, electrical function tests, secondary injection tests of inputs and outputs, and testing of protection elements like restricted earth fault.

The equipment being tested is a P643 transformer differential relay with the designation P643 TRANSFORMER DIFFERENTIAL.

The types of tests being performed include mechanical checks, electrical function tests, secondary injection tests of inputs and outputs, testing of protection elements like transformer differential, restricted earth fault, and CBF.

Commissioning Service Department

Commissioning Standard Test Formats

Description: P643 TRANSFORMER DIFFERENTIAL


Equip. No. Drawing ref.: CD- Page 1 of 20
Contractor: Contract no.: Substation No :

1. GENERAL DATA & INFORMATION

Panel No. = CT Ratio HV


Panel Name CT Ratio LV
Manufacturer Transf. MVA
Serial No Transf. HV
Order No. Transf. LV
Frequency Fn 60 HZ DC. Aux. Voltage 125 VDC

2. MECHANICAL CHECKS AND VISUAL INSPECTION


As per TCS –P–105 Rev -1, Item no 4.1& 4.12.1.1

ITEM DESCRIPTION REMARKS


1 Inspect for any physical damage or defects.  Yes  N/A
2 Verify connections and ferrules as per approved drawings  Yes  N/A
3 Check tightness of all the connections.  Yes  N/A
4 Check Apparatus List  Yes  N/A
5 Check relay version and switching elements on printed circuit board  Yes  N/A

3. ELECTRICAL TESTS
As per TCS –P–105 Rev -1, Item no 4.2& 4.12.1.2
3.1. FUNCTION TEST

ITEM DESCRIPTION REMARKS


Date & Time - Set clock to local time.
1  Yes  N/A
- Time maintained when Aux. Supply removed.
Alarm (yellow) LED – to check make Test Mode enable under
2  Yes  N/A
Commissioning Test menu.
Out of service (yellow) LED – to check make Test Mode enable under
3  Yes  N/A
Commissioning Test menu.
4 Trip (red) LED – apply any fault to produce any trip condition  Yes  N/A
8 + 10 function key programmable LEDs – apply Test LEDs under
5  Yes  N/A
Commissioning test menu.
6 Output Relays Checked  Yes  N/A

7 Test switch / plug checked for correct function.  Yes  N/A

Tested by: ENG. Witnessed by: ENG.

Signature & Date: Signature & Date:


Commissioning Service Department
Commissioning Standard Test Formats

Description: P643 TRANSFORMER DIFFERENTIAL


Equip. No. Drawing ref.: CD- Page 2 of 20
Contractor: Contract no.: Substation No :

3.2. OPERATING DC SUPPLY CURRENT

DC voltage DC current w/o fault DC current with Max. calculated


(V) (mA) fault (mA) watt (W)
125

Limit: DC burden 15/20 VA. (Refer to the reference technical manual).

3.3. WATCH DOG CHECK

SUPPLY OFF
TERMINALS (CLOSED) - (J11, J12) :
TERMINALS (OPEN) - (J13, J14) :
SUPPLY ON
TERMINALS (CLOSED) - (J13, J14) :
TERMINALS (OPEN) - (J11, J12) :

3.4. TIME AND DATE CHECK

To check time & date go to main menu on the display for MiCOM P643 then open system
time and adjust time & date.
To test keeping time and date setting this, remove the auxiliary supply from the relay for
approximately 30 seconds, then restoring the auxiliary supply, the time and date setting
should not be lost.
Result: ____________

Tested by: ENG. Witnessed by: ENG.

Signature & Date: Signature & Date:


Commissioning Service Department
Commissioning Standard Test Formats

Description: P643 TRANSFORMER DIFFERENTIAL


Equip. No. Drawing ref.: CD- Page 3 of 20
Contractor: Contract no.: Substation No :

3.5. SECONDARY INJECTION TESTS

1. INPUT OPTO-ISOLATORS CHECKS (With Relay Energized):


Note: Go to Commissioning Test, Test mode (test mode), then go to system data column to check the status
of the binary inputs.

TEST METHOD RESULT


OPTO INPUT
(Energize only one at a time with 125V DC Station Display 0 to REMARKS
NO.
Battery voltage) 1
OPTO 1 ENERGIZE TB NO. D2-D1 1 SPARE

OPTO 2 ENERGIZE TB NO. D4-D3 1 SPARE

OPTO 3 ENERGIZE TB NO. D6- D5 1 SPARE


TRAFO VT MCB
OPTO 4 ENERGIZE TB NO. D8-D7 1
TRIP
LV CBF
OPTO 5 ENERGIZE TB NO. D10-D9 1
INITIATION
OPTO 6 ENERGIZE TB NO. D12-D11 1 SPARE

OPTO 7 ENERGIZE TB NO. D14-D13 1 SPARE

OPTO 8 ENERGIZE TB NO. D16-D15 1 SPARE

OPTO 9 ENERGIZE TB NO. F2-F1 1 87T2 PROTN IN

OPTO 10 ENERGIZE TB NO. F4-F3 1 87T2 PROTN OUT


RESET DC SUP
OPTO 11 ENERGIZE TB NO. F6-F5 1
FAIL
OPTO 12 ENERGIZE TB NO. F8-F7 1 IND DC SUP FAIL

OPTO 13 ENERGIZE TB NO. F10-F9 1 AC SUPPLY FAIL

OPTO 14 ENERGIZE TB NO. F12-F11 1 SPARE

OPTO 15 ENERGIZE TB NO. F14-F13 1 SPARE

OPTO 16 ENERGIZE TB NO. F16-F15 1 SPARE

TEST METHOD RESULT


OPTO INPUT
(Energize only one at a time with 125V DC Station Display 0 to REMARKS
NO.
Battery voltage) 1
OPTO 17 ENERGIZE TB NO. B2-B1 1 IN/OUT DC FAIL

OPTO 18 ENERGIZE TB NO. B4-B3 1 94T2 OPTD

Tested by: ENG. Witnessed by: ENG.

Signature & Date: Signature & Date:


Commissioning Service Department
Commissioning Standard Test Formats

Description: P643 TRANSFORMER DIFFERENTIAL


Equip. No. Drawing ref.: CD- Page 4 of 20
Contractor: Contract no.: Substation No :

OPTO 19 ENERGIZE TB NO. B6- B5 1 86T2 OPTD

OPTO 20 ENERGIZE TB NO. B8-B7 1 SPARE

OPTO 21 ENERGIZE TB NO. B10-B9 1 SPARE

OPTO 22 ENERGIZE TB NO. B12-B11 1 SPARE

OPTO 23 ENERGIZE TB NO. B14-B13 1 SPARE

OPTO 24 ENERGIZE TB NO. B16-B15 1 SPARE

2. OUTPUT RELAYS CHECKS (With Relay Energized):


Note: Go to Commissioning Test, Test mode (blocked), Test Pattern mode and select each relay to be
tested and Apply Contact Test, after test; apply remove test to de-energize the relay.
TEST METHOD RESULT
OUTPUT RELAY
No.
(Energize only one relay at a time by Contact REMARKS
‘Contact Test in ‘Apply Test Mode’) Checked

RL1 CONTACT OPERATED H1-H2 (N/O) SPARE

RL2 CONTACT OPERATED H3-H4 (N/O) SPARE

RL3 CONTACT OPERATED H5-H6 (N/O) SPARE

RL4 CONTACT OPERATED H7-H8 (N/O) SPARE

RL5 CONTACT OPERATED H9- H10 (N/O) SPARE

RL6 CONTACT OPERATED H11-H12 (N/O) SPARE

RL7 CONTACT OPERATED H13-H14-H15 (C/O) SPARE

RL8 CONTACT OPERATED H16-H17-H18 (C/O) SPARE

RL9 CONTACT OPERATED G1-G2 (N/O) 87T2

RL10 CONTACT OPERATED G3-G4 (N/O) 64NP

RL11 CONTACT OPERATED G5-G6 (N/O) 64NS

RL12 CONTACT OPERATED G7-G8 (N/O) 50/51P

RL13 CONTACT OPERATED G9-G10 (N/O) 50/50NP

RL14 CONTACT OPERATED G11-G12 (N/O) 51/51NS

RL15 CONTACT OPERATED G13-G14-G15 (C/O) 51/51NS

RL16 CONTACT OPERATED G16-G17-G18 (C/O) SPARE


* After output relay test; select test mode to be disable.

Tested by: ENG. Witnessed by: ENG.

Signature & Date: Signature & Date:


Commissioning Service Department
Commissioning Standard Test Formats

Description: P643 TRANSFORMER DIFFERENTIAL


Equip. No. Drawing ref.: CD- Page 5 of 20
Contractor: Contract no.: Substation No :
3. LED CHECKS

RESULT
LED’S FUNCTION REMARKS
Checked

LED 1 I DIFF OPTD -

LED 2 REF OPTD HV -

LED 3 REF OPTD LV -

LED 4 O/C OPTD HV -

LED 5 O/C OPTD LV -

LED 6 E/F OPTD HV -

LED 7 E/F OPTD LV -

LED 8 PROT. OUT -

F.key LED 1 2ND HARMONICS -

F.key LED 2 5TH HARMONICS -

F.key LED 3 R-PHASE OPTD -

F.key LED 4 Y-PHASE OPTD -

F.key LED 5 B-PHASE OPTD -

F.key LED 6 HIGH SET OPTD -

F.key LED 7 CBF LV OPTD -

F.key LED 8 NEUTRAL ALARM -

F.key LED 9 STANDBY EF -

F.key LED 10 RESET LED -

Tested by: ENG. Witnessed by: ENG.

Signature & Date: Signature & Date:


Commissioning Service Department
Commissioning Standard Test Formats

Description: P643 TRANSFORMER DIFFERENTIAL


Equip. No. Drawing ref.: CD- Page 6 of 20
Contractor: Contract no.: Substation No :

3.6. CURRENT INPUTS CHECK:

3.6.1. HIGH SIDE:

I diff= I1*CT matching factor + I2*CT matching factor


I rest =0.5* ( I1*CT matching factor + I2*CT matching factor)

Transformer Rated Current In = MVA/ {√3 * (KVN-HVS)}


KVN - HVS = 132KV
CT Ratio = 800/1 A Transf. In = 437 A
Calculated 1ph I diff= I1*CT matching factor + I2*CT matching factor / 1.5
Calculated 1ph I rest= 0.5 (I1*CT matching factor + I2*CT matching factor) / 1.5
HV CT matching factor-1.830, LV CT matching factor-1.143

Injected Measuring From Relay Calculated Values


Phase Current
(A) IPrim. (A) Isec (A) I diff I rest I diff I rest

L1
L2
L3

3.6.2. LOW SIDE:

I diff= I1*CT matching factor + I2*CT matching factor


I rest =0.5* ( I1*CT matching factor + I2*CT matching factor)

Transf. In =MVA/ {√3 * (kVn-LVS)}


KVn - LVS =33 kV
CT Ratio= 2000/1 A, Transf. In = 1750 A
Calculated 1ph I diff= I1*CT matching factor + I2*CT matching factor / 1.5
Calculated 1ph I rest= 0.5 (I1*CT matching factor + I2*CT matching factor) / 1.5
HV CT matching factor-1.830, LV CT matching factor-1.143

Measuring From Relay Calculated Values


Injected
Phase Current
(A) I Prim. (A) ISec(A) I diff. I rest I diff I rest

L1

L2

L3

Tested by: ENG. Witnessed by: ENG.

Signature & Date: Signature & Date:


Commissioning Service Department
Commissioning Standard Test Formats

Description: P643 TRANSFORMER DIFFERENTIAL


Equip. No. Drawing ref.: CD- Page 7 of 20
Contractor: Contract no.: Substation No :

3.7. VOLTAGE INPUT CHECK:

Phase injected Voltage read on relay display (kV)


voltage injected
(volt)
Relay 1 RN YN BN RY YB BR

L1-E 66.39

L2-E 66.39

L3-E 66.39

L1-L2-L3 76.42

3.8. TEST DONE W/O ZERO SEQUENCE

High Side (132kV) Low Side (33kV)

Phase Fault Trip Trip


Calculate Actual DROP Time at Calculate Actual DROP Time at
d P/U P/U OFF 2I d P/U P/U OFF 2I
trip (ms) trip (ms)
L1-N

L2-N

L3-N

L1-L2-L3

* Pick-up: formula ±5%


* Drop-off: 95% of formula ±5% (see technical manual P64×_112 page no: 40)

3.9. DIFFERENTIAL PICKUP TEST.


Settings:
IS1 0.4 PU
K1 30 %
Is2 4 PU
K2 80 %
tDIFF 0.0 Sec
IS-HS1 8 PU
IS-HS2 12 PU

Tested by: ENG. Witnessed by: ENG.

Signature & Date: Signature & Date:


Commissioning Service Department
Commissioning Standard Test Formats

Description: P643 TRANSFORMER DIFFERENTIAL


Equip. No. Drawing ref.: CD- Page 8 of 20
Contractor: Contract no.: Substation No :

HV Calculated pickup - Is1*HV Full load current


LV Calculated pickup - Is1*LV Full load current

3.10. HIGH SET CHECK:

IS-HS1=8 PU = 8 x I rated/CTR
HIGH SIDE: 8*437/800 LOW SIDE: 8*1750/2000
3.10.1. ZERO SEQUENCE FILTER FUNCTION DISABLED IN SYSTEM CONFIGURATION.

High Side (132kv) Low Side (33kV)

Phase fault Trip Trip


Calculate Actual DROP Time at Calculate Actual DROP Time at
d P/U P/U OFF 2I d P/U P/U OFF 2I
trip (ms) trip (ms)
L1-N

L2-N

L3-N

L1-L2-L3

IS-HS2 =12 PU = 12 I rated/CTR


IS-HS2=12 PU

High Side (132kv) Low Side (33kV)

Phase fault Trip Trip


Calculate Actual DROP Time at Calculate Actual DROP Time at
d P/U P/U OFF 15A d P/U P/U OFF 15A
trip (ms) trip (ms)
L1-N

L2-N

L3-N

L1-L2-L3

* Pick-up: formula ±5%


* Drop-off: 95% of formula ±5% (see technical manual P64×_112 page no: 40)

Tested by: ENG. Witnessed by: ENG.

Signature & Date: Signature & Date:


Commissioning Service Department
Commissioning Standard Test Formats

Description: P643 TRANSFORMER DIFFERENTIAL


Equip. No. Drawing ref.: CD- Page 9 of 20
Contractor: Contract no.: Substation No :

3.11. BIAS CHARACTERISTIC CHECK:

3.11.1. LOWER SLOPE TEST:


- IS1: Basic Diff Current Setting.
- K1: Lower Percentage Bias Setting.
- Id Calculated = I diff> K1 * Ibias

IS1 0.4 A
K1 30 %
Is2 4 A
K2 80 %
tDIFF 0.0 Sec
IS-HS1 8 A
IS-HS2 12 A

Tested by: ENG. Witnessed by: ENG.

Signature & Date: Signature & Date:


Commissioning Service Department
Commissioning Standard Test Formats

Description: P643 TRANSFORMER DIFFERENTIAL


Equip. No. Drawing ref.: CD- Page 10 of 20
Contractor: Contract no.: Substation No :

CALCULATED VALUE MEASURED VALUE


APPLIED APPLIED
CURRENT(A) CURRENT(A) SLOPE
PHASE HV SIDE LV SIDE I DIFF I BIAS I DIFF I BIAS IN %

1.5
R
2.0
1.5
Y
2.0
1.5
B
2.0
K1-30% Is1-0.4

* Pick-up: formula ±5%


* Drop-off: 95% of formula ±5% (see technical manual P64×_112 page no: 40)

ID----I DIFF IB----IBIASE SLOPE = (ID2-ID1)/ (IB2-IB1)

B- Upper Slope Test:


- IS2: Basic Diff Current Threshold Setting.
- K2: High Percentage Bias Setting.
- Id Calculated = I diff> K1 * Is2 + K2 ( Ibias – Is2 )

CALCULATED VALUE MEASURED VALUE


APPLIED APPLIED
PHASE CURRENT CURRENT
(A) HV (A) LV SIDE SLOPE
I DIFF I BIAS I DIFF I BIAS
SIDE IN %

Differential Setting (Is1=0.4 , Is2=2 , K1= 30%, K2=60%). K1-30%


* Pick-up: formula ±5%
* Drop-off: 95% of formula ±5% (see technical manual P64×_112 page no: 40)

Tested by: ENG. Witnessed by: ENG.

Signature & Date: Signature & Date:


Commissioning Service Department
Commissioning Standard Test Formats

Description: P643 TRANSFORMER DIFFERENTIAL


Equip. No. Drawing ref.: CD- Page 11 of 20
Contractor: Contract no.: Substation No :

3.12. HARMONICS CHECK

3.12.1. 2ND HARMONIC RESTRAIN CHECK:

Pass criteria:
Measured second harmonic threshold for blocking of differential element should be +/-10% of set value.

TEST PROCEDURE: -
1. From general mode page (7/7) change the frequency setting from (All Equal) to (Free Frequency).
2. From page (7/7) select the frequency of phase (R) as fundamental (60 HZ) and Phase (Y) as 2nd
harmonics (120 HZ).
3. From page (1/7) select the current injection value according to the setting of the differential relay
operating current we can select phase (R) as (1A) and angle (0) and phase (Y) (1A) Current and angle (0)
3-After that click START the relay will pick up then slowly reduce the current in phase (Y) Until relay
trip depend on relay setting.
4. If the ratio of (IY/IR) mean (I (2fn)/I (1fn > Setting (in our case setting is 15%)
5. Relay will BLOCK.

CONNECTION: -

Current Observed 2nd Harmonics


Harmonic Normal
Winding Injected
Setting current (A)
In phase Blocking Expected Blocking Measured

AN 15% 1 0.150

HV BN 15% 1 0.150

CN 15% 1 0.150

AN 15% 1 0.150

LV BN 15% 1 0.150

CN 15% 1 0.150

Tested by: ENG. Witnessed by: ENG.

Signature & Date: Signature & Date:


Commissioning Service Department
Commissioning Standard Test Formats

Description: P643 TRANSFORMER DIFFERENTIAL


Equip. No. Drawing ref.: CD- Page 12 of 20
Contractor: Contract no.: Substation No :

3.12.2. 5TH HARMONIC RESTRAINT CHECK: -

TEST PROCEDURE: -
6. From general mode page (7/7) change the frequency setting from (All Equal) to (Free Frequency).
7. From page (7/7) select the frequency of phase (R) as fundamental (60 HZ) and Phase (Y) as 5th harmonics
(300 HZ).
8. From page (1/7) select the current injection value according to the setting of the differential relay
operating current we can select phase (R) as (1A) and angle (0) and phase (Y) (1A) Current and angle (0)
3-After that click START the relay will pick up then slowly reduce the current in phase (Y) Until relay
trip depend on relay setting.
9. If the ratio of (IY/IR) mean (I (5fn)/I (1fn > Setting (in our case setting is 25%)
10. Relay will BLOCK.

CONNECTION: -

Current Observed 5th Harmonics


Harmonic Normal
Winding Injected
Setting current (A)
In phase Blocking Expected Blocking Measured

AN 25% 1 0.250

HV BN 25% 1 0.250

CN 25% 1 0.250

AN 25% 1 0.250

LV BN 25% 1 0.250

CN 25% 1 0.250

Tested by: ENG. Witnessed by: ENG.

Signature & Date: Signature & Date:


Commissioning Service Department
Commissioning Standard Test Formats

Description: P643 TRANSFORMER DIFFERENTIAL


Equip. No. Drawing ref.: CD- Page 13 of 20
Contractor: Contract no.: Substation No :

3.13. HV OVER CURRENT AND EARTH FAULT:

3.13.1. OVER CURRENT PICK UP / RESET RESULT: In=0.77 In CURVE:NI

PICK UP MEASURED MEASURED


PHASE
SETTING PICK UP(A) DROP OFF (A)

PHASE – R 0.77

PHASE –Y 0.77

PHASE - B 0.77

Note: pick up error =±5% Drop off Level = >95% of pick up

3.13.2. OVER CURRENT CHARACTERISTIC:

Normal inverse Is =1.2In Tm : 0.3


T = (0.14*Tm) / ( (I/I s) ^ 0.02 – 1 )) sec.

2 * IS
PHASE
EXP sec ACT sec.
PHASE-R

PHASE-Y

PHASE-B

3.13.3. EARTH FAULT PICK UP / RESET RESULT: In=0.13In CURVE:NI

PICK UP MEASURED MEASURED


PHASE
SETTING PICK UP(A) DROP OFF (A)

PHASE – R 0.13

Note: pick up error =±5% Drop off Level = >95% of pick up

Tested by: ENG. Witnessed by: ENG.

Signature & Date: Signature & Date:


Commissioning Service Department
Commissioning Standard Test Formats

Description: P643 TRANSFORMER DIFFERENTIAL


Equip. No. Drawing ref.: CD- Page 14 of 20
Contractor: Contract no.: Substation No :

3.13.4. EARTH FAULT CHARACTERISTIC:

Normal inverse Is =0.2In Tm : 0.3


T = (0.14*Tm) / ( (I/I s) ^ 0.02 – 1 )) sec.

2 * IS
PHASE
EXP sec ACT sec.
PHASE-R

3.14. LV OVER CURRENT AND EARTH FAULT:

3.14.1. OVER CURRENT PICK UP / RESET RESULT: In= 1.23 In CURVE:NI

PICK UP MEASURED MEASURED


PHASE
SETTING PICK UP(A) DROP OFF (A)

PHASE – R 1.23
PHASE –Y 1.23
PHASE - B 1.23

Note: pick up error =±5% Drop off Level = >95% of pick up

3.14.2. OVER CURRENT CHARACTERISTIC:

Normal inverse Is =1.0In Tm : 0.3


T = (0.14*Tm) / ( (I/I s) ^ 0.02 – 1 )) sec.

2 * IS
PHASE
EXP sec ACT sec.
PHASE-R

PHASE-Y

PHASE-B

Tested by: ENG. Witnessed by: ENG.

Signature & Date: Signature & Date:


Commissioning Service Department
Commissioning Standard Test Formats

Description: P643 TRANSFORMER DIFFERENTIAL


Equip. No. Drawing ref.: CD- Page 15 of 20
Contractor: Contract no.: Substation No :

3.14.3. EARTH FAULT PICK UP / RESET RESULT: In=0.2In CURVE:NI

PICK UP MEASURED MEASURED


PHASE
SETTING PICK UP(A) DROP OFF (A)

PHASE – R 0.2

Note: pick up error =±5% Drop off Level = >95% of pick up

3.14.4. EARTH FAULT CHARACTERISTIC:

Normal inverse Is =0.1In Tm : 0.3


T = (0.14*Tm) / ( (I/I s) ^ 0.02 – 1 )) sec.

2 * IS
PHASE
EXP sec ACT sec.
PHASE- E/F

3.15. STANDBY EARTH FAULT:

PICK UP TEST: Is =0.15In Tm : 0.1

PICK UP MEASURED MEASURED


PHASE
SETTING PICK UP(A) DROP OFF (A)

PHASE – R 0.15

Note: pick up error =±5% Drop off Level = >95% of pick up

120 × Tp
Long Inverse t (s) = ---------------------------
(I/I p)^ 1 - 1

10 * IS
2 * IS 5 * IS
PHASE
EXP sec ACT sec. EXP sec. ACT sec. EXP sec ACT sec
PHASE-E/F

Tested by: ENG. Witnessed by: ENG.

Signature & Date: Signature & Date:


Commissioning Service Department
Commissioning Standard Test Formats

Description: P643 TRANSFORMER DIFFERENTIAL


Equip. No. Drawing ref.: CD- Page 16 of 20
Contractor: Contract no.: Substation No :

3.16. LV NUTRAL CUREENT ALARM:

SET PICK UP
SET TIME (s) DROP OFF (A) OPTD TIME (s)
CURRENT (A) CURRENT (A)

0.100 5 sec

Note: pick up error =±5% Drop off Level = >95% of pick up

3.17. RESTRICTED EARTH FAULT PROTECTION (REF):

3.17.1. HV SIDE
REF Pickup Test.
Settings:
IS1 0.1 A
K1 0 %
Is2 0.9 A
K2 150 %
tDIFF 0.0 Sec
* Limits: Pick up 10 %.

Trip Time at
set value (A) Actual P/U (A) DROP OFF (A)
2I trip (ms)

0.1

3.17.2. BIAS CHARACTERISTIC CHECK:

A- Lower Slope Test:


- IS1: Basic Diff Current Setting.
- K1: Lower Percentage Bias Setting.
- Id Calculated = I diff> K1 * Ibias ( here settings k1-0% so using below formula)
- Id Calculated = I diff> I1-I2

Tested by: ENG. Witnessed by: ENG.

Signature & Date: Signature & Date:


Commissioning Service Department
Commissioning Standard Test Formats

Description: P643 TRANSFORMER DIFFERENTIAL


Equip. No. Drawing ref.: CD- Page 17 of 20
Contractor: Contract no.: Substation No :

REF SLOPE SETTINGS:

IS1-0.1 PU, IS2- 1 PU, K1-0%, K2-150%, tREF- 0 SEC

 First change the settings in secondary value in measurement setup.

CALCULATED VALUE MEASURED VALUE


APPLIED APPLIED
PHASE CURRENT(A) CURRENT (A) SLOPE
HV SIDE NEUTRAL SIDE I DIFF I BIAS I DIFF I BIAS IN %

0.5
R
0.8

Tested by: ENG. Witnessed by: ENG.

Signature & Date: Signature & Date:


Commissioning Service Department
Commissioning Standard Test Formats

Description: P643 TRANSFORMER DIFFERENTIAL


Equip. No. Drawing ref.: CD- Page 18 of 20
Contractor: Contract no.: Substation No :

K1-0% Is1-0.1
B- Upper Slope Test:
- IS2: Basic Diff Current Threshold Setting.
- K2: High Percentage Bias Setting.
- Id Calculated = I diff> K1 * Is2 + K2 ( Ibias – Is2 )

CALCULATED VALUE MEASURED VALUE


APPLIED APPLIED
PHASE CURRENT(A) CURRENT (A) SLOPE
HV SIDE NEUTRAL SIDE I DIFF I BIAS I DIFF I BIAS IN %

1
R
2

Differential Setting (Is1=0.1 , Is2=0.9 , K1= 0%, K2=150%).

3.17.3. LV SIDE
Restricted earth fault protection:

REF Pickup Test.

Settings:

IS1 0.1 A
K1 0 %
Is2 0.9 A
K2 150 %
tDIFF 0.0 Sec

* Limits: Pick up 10 %.
* Limits: Pick up 10 %.

Trip Time at
set value (A) Actual P/U (A) DROP OFF (A)
2I trip (ms)

0.1

Tested by: ENG. Witnessed by: ENG.

Signature & Date: Signature & Date:


Commissioning Service Department
Commissioning Standard Test Formats

Description: P643 TRANSFORMER DIFFERENTIAL


Equip. No. Drawing ref.: CD- Page 19 of 20
Contractor: Contract no.: Substation No :

3.17.4. BIAS CHARACTERISTIC CHECK:

A- Lower Slope Test:


- IS1: Basic Diff Current Setting.
- K1: Lower Percentage Bias Setting.
- Id Calculated = I diff> K1 * Ibias ( here settings k1-0% so using below formula)
- Id Calculated = I diff> I1-I2
 First change the settings in secondary value in measurement setup.

CALCULATED MEASURED
APPLIED APPLIED
VALUE VALUE
PHASE CURRENT CURRENT (A) SLOPE
(A) NEUTRAL IN %
HV SIDE SIDE I DIFF I BIAS I DIFF I BIAS

0.5
R 0.8

K1-0% Is1-0.1

* Pick-up: formula ±5%


* Drop-off: 95% of formula ±5%

B- Upper Slope Test:


- IS2: Basic Diff Current Threshold Setting.
- K2: High Percentage Bias Setting.
- Id Calculated = I diff> K1 * Is2 + K2 ( Ibias – Is2 )

APPLIED CALCULATED VALUE MEASURED VALUE


APPLIED
CURRENT
CURRENT SLOPE
PHASE (A)
(A) IN %
NEUTRAL I DIFF I BIAS I DIFF I BIAS
HV SIDE
SIDE

1
R
2

Differential Setting (Is1=0.1 , Is2=0.9 , K1= 0%, K2=100%).


* Pick-up: formula ±5%
* Drop-off: 95% of formula ±5%

Tested by: ENG. Witnessed by: ENG.

Signature & Date: Signature & Date:


Commissioning Service Department
Commissioning Standard Test Formats

Description: P643 TRANSFORMER DIFFERENTIAL


Equip. No. Drawing ref.: CD- Page 20 of 20
Contractor: Contract no.: Substation No :

3.18. CBF LV SIDE:


Current (A) Stage 1
Phase
Set Pickup Drop-off Set OPTD (ms)
R
Y 10% In 150 ms
B

Limits:
I > Pick-up: Setting ±5% or 20 mA
I > Drop-off: 100%of setting ±5% or 20 mA
Timers: ± 2% or 50 ms whichever is greater

Tested by: ENG. Witnessed by: ENG.

Signature & Date: Signature & Date: