RINCIAN BIAYA KONTRAK

Satuan Kerja : Dinas Pekerjaan Umum Provinsi Maluku


Pekerjaan : Analisa Dampak Lingkungan (AMDAL) Jalan Laha - Negeri Lima
Lokasi : Prov. Maluku 770,000,000
Tahun Anggaran : 2016 762,410,000
7,590,000
II. BIAYA LANGSUNG NON PERSONIL

KONTRAK AWAL

Harga Satuan
No Uraian Vol Satuan Total (Rp.)
(Rp.)

II.1 Biaya Operasional Kantor


1 Biaya Komunikasi 0.50 Bulan Rp 2,500,000 1,250,000.00
2 Biaya Peralatan Kantor
- Alat Tulis Kantor 0.50 Bulan Rp 1,500,000 750,000.00
- Sewa Komputer + Printer 0.50 Bulan Rp 2,500,000 1,250,000.00
- Sewa Kantor 0.50 Bulan Rp 2,500,000 1,250,000.00
- Sewa Kendaraan Roda 4 & Operasional 6.00 BH Rp 1,000,000 6,000,000.00
- Biaya Penggandaan Surat 1.00 Ls Rp 100,000 100,000.00
- Biaya Pengiriman Dokumen AMDAL atau Formulir UKL-UPL 1.00 Ls Rp 250,000 250,000.00
- Biaya Pengiriman Surat Undangan 1.00 Ls Rp 250,000 250,000.00
- Biaya Pengiriman Surat Keputusan 1.00 Ls Rp 250,000 250,000.00
3 Biaya Administrasi Lainnya
- Biaya Pengumuman Permohonan Izin Lingkungan 1.00 Ls Rp 1,500,000 1,500,000.00
Harga Satuan
No Uraian Vol Satuan Total (Rp.)
(Rp.)

- Biaya Pengumuman Penerbitan Izin Lingkungan 1.00 Ls Rp 1,500,000 1,500,000.00


- Administrasi Penerbitan Keputusan Kelayakan / Ketidaklayakan 1.00 Ls Rp 1,500,000 1,500,000.00
- Administrasi Penerbitan Rekomendasi UKL-UPL 1.00 Ls Rp 2,500,000 2,500,000.00
4 Perlengkapan K3 (Safety Health)
- Baju + Rompi + Sarung Tangan + Topi + Helm + Sepatu + Mantel Hujan 39 Orang Rp 650,000 25,350,000.00

Sub Total II.1. 43,700,000.00


Harga Satuan
No Uraian Vol Satuan Total (Rp.)
(Rp.)

II.2. Biaya Sosialisasi dan Pembahasan


1 Pengumuman (Public Expose) 1.00 Ls Rp 3,500,000 3,500,000.00
2 Kegiatan Sosialisasi Warga
- Sewa Gedung ( 1 unit x 1 hari ) 1 UH 3,500,000.00 3,500,000.00
- Konsumsi ( 40 orang x 1 hari ) 40 OH 200,000.00 8,000,000.00
- Uang Transport Warga ( 40 orang x 1 hari ) 40 OH 250,000.00 10,000,000.00
- Honor Narasumber ( 1 orang x 1 hari ) 1 OH 2,500,000.00 2,500,000.00
- Honor Perangkat Daerah ( 5 orang x 1 hari ) 5 OH 1,500,000.00 7,500,000.00
- Sewa Infocus ( 1 unit x 1 kali ) 1 OH 500,000.00 500,000.00
- Spanduk dan Banner 1 Ls 1,500,000.00 1,500,000.00
- Meeting Kits ( 40 orang x 1 hari ) 40 OH 150,000.00 6,000,000.00
3 Pembahasan KA ANDAL
- Honor Tim Komisi ( 10 orang x 1 kali ) 10 OH 2,500,000.00 25,000,000.00
- Honor Tim Teknis (5 orang x 1 kali ) 5 OH 2,000,000.00 10,000,000.00
- Uang Transport tokoh masyarakat & LSM ( 10 orang x 1 kali ) 10 OH 350,000.00 3,500,000.00
- Konsumsi Peserta ( 40 orang x 1 kali ) 40 OH 200,000.00 8,000,000.00
- Sewa Gedung ( 1 unit x 1 kali ) 1 OH 3,500,000.00 3,500,000.00
- Sewa Infocus ( 1 unit x 1 kali ) 1 OH 500,000.00 500,000.00
4 Pembahasan ANDAL, RKL - RPL
- Honor Tim Komisi ( 10 orang x 2 kali ) 20 OH 2,500,000.00 50,000,000.00
- Honor Tim Teknis (5 orang x 2 kali ) 10 OH 2,000,000.00 20,000,000.00
- Uang Transport tokoh masyarakat & LSM ( 10 orang x 2 kali ) 20 OH 350,000.00 7,000,000.00
- Konsumsi Peserta ( 40 orang x 2 kali ) 80 OH 200,000.00 16,000,000.00
- Sewa Gedung ( 1 unit x 2 kali ) 2 OH 3,500,000.00 7,000,000.00
- Sewa Infocus ( 1 unit x 2 kali ) 2 OH 500,000.00 1,000,000.00
5 Biaya Pengecekan Kebenaran atau Kesesuaian atas hasil
perbaikan dokumen AMDAL 1 Ls 5,000,000.00 5,000,000.00
Harga Satuan
No Uraian Vol Satuan Total (Rp.)
(Rp.)

Sub Total II.2. 199,500,000.00


Harga Satuan
No Uraian Vol Satuan Total (Rp.)
(Rp.)

II.3. Biaya Sampling dan Analisa Laboratorium


1 Analisa Kualitas Air Tanah 3 sampel Rp 500,000 1,500,000.00
2 Analisa Kualitas Lingkungan 3 sampel Rp 500,000 1,500,000.00
3 Analisa Kualitas Udara 3 sampel Rp 500,000 1,500,000.00
4 Data Sosial Ekonomi Budaya dan Kesmas 3 sampel Rp 500,000 1,500,000.00
5 Data Sekunder 3 sampel Rp 500,000 1,500,000.00

Sub Total II.3. 7,500,000.00

II.4. Biaya Laporan


1 Laporan Pendahuluan 3 buku Rp 250,000 750,000.00
2 Laporan Bulanan 3 buku Rp 250,000 750,000.00
3 Laporan Antara 3 buku Rp 350,000 1,050,000.00
4 Draft Kerangka Acuan ANDAL 10 buku Rp 300,000 3,000,000.00
5 Final Kerangka Acuan ANDAL 10 buku Rp 350,000 3,500,000.00
6 Draft Analisa Dampak Lingkungan ANDAL, RKL - RPL 10 buku Rp 300,000 3,000,000.00
7 Final Analisa Dampak Lingkungan ANDAL, RKL - RPL 10 buku Rp 350,000 3,500,000.00
8 Rencana Pengelolaan Lingkungan (RKL) 10 buku Rp 350,000 3,500,000.00
9 Rencana Pemantauan Lingkungan (RPL) 10 buku Rp 350,000 3,500,000.00
10 Draft Laporan Akhir 3 buku Rp 400,000 1,200,000.00
11 Laporan Akhir 3 buku Rp 450,000 1,350,000.00
12 Flash Disc 3 Bh Rp 225,000 675,000.00

Sub Total II.4. 25,775,000.00


Harga Satuan
No Uraian Vol Satuan Total (Rp.)
(Rp.)

SUB TOTAL II. 276,475,000.00


-
-
-

KONTRAK ADDENDUM 01

Harga Satuan
Vol Satuan Total (Rp.)
(Rp.)

12.00 Bulan Rp 500,000 6,000,000.00

12.00 Bulan Rp 500,000 6,000,000.00


0.00 Bulan Rp 2,500,000 -
0.00 Bulan Rp 2,500,000 -
0.00 BH Rp 1,000,000 -
1.00 Ls Rp 100,000 100,000.00
1.00 Ls Rp 250,000 250,000.00
1.00 Ls Rp 250,000 250,000.00
1.00 Ls Rp 250,000 250,000.00

1.00 Ls Rp 1,500,000 1,500,000.00


Harga Satuan
Vol Satuan Total (Rp.)
(Rp.)

1.00 Ls Rp 1,500,000 1,500,000.00


1.00 Ls Rp 1,500,000 1,500,000.00
1.00 Ls Rp 2,500,000 2,500,000.00

8 Orang Rp 650,000 5,200,000.00

25,050,000.00
Harga Satuan
Vol Satuan Total (Rp.)
(Rp.)

1.00 Ls Rp 3,500,000 3,500,000.00

1 UH 3,500,000.00 3,500,000.00
40 OH 100,000.00 4,000,000.00
40 OH 100,000.00 4,000,000.00
1 OH 1,000,000.00 1,000,000.00
5 OH 1,000,000.00 5,000,000.00
1 OH 500,000.00 500,000.00
1 Ls 1,280,000.00 1,280,000.00
40 OH 100,000.00 4,000,000.00

10 OH 1,500,000.00 15,000,000.00
5 OH 1,000,000.00 5,000,000.00
10 OH 100,000.00 1,000,000.00
40 OH 100,000.00 4,000,000.00
1 OH 3,500,000.00 3,500,000.00
1 OH 500,000.00 500,000.00

20 OH 1,500,000.00 30,000,000.00
10 OH 1,000,000.00 10,000,000.00
20 OH 100,000.00 2,000,000.00
80 OH 100,000.00 8,000,000.00
2 OH 3,500,000.00 7,000,000.00
2 OH 500,000.00 1,000,000.00

1 Ls 5,000,000.00 5,000,000.00
Harga Satuan
Vol Satuan Total (Rp.)
(Rp.)

118,780,000.00
Harga Satuan
Vol Satuan Total (Rp.)
(Rp.)

3 sampel Rp 500,000 1,500,000.00


3 sampel Rp 500,000 1,500,000.00
3 sampel Rp 500,000 1,500,000.00
3 sampel Rp 500,000 1,500,000.00
3 sampel Rp 500,000 1,500,000.00

7,500,000.00

3 buku Rp 250,000 750,000.00


3 buku Rp 250,000 750,000.00
3 buku Rp 350,000 1,050,000.00
10 buku Rp 300,000 3,000,000.00
10 buku Rp 350,000 3,500,000.00
10 buku Rp 300,000 3,000,000.00
10 buku Rp 350,000 3,500,000.00
10 buku Rp 350,000 3,500,000.00
10 buku Rp 350,000 3,500,000.00
3 buku Rp 400,000 1,200,000.00
3 buku Rp 450,000 1,350,000.00
3 Bh Rp 225,000 675,000.00

25,775,000.00
Harga Satuan
Vol Satuan Total (Rp.)
(Rp.)

177,105,000.00
RINCIAN BIAYA KONTRAK

Satuan Kerja : Dinas Pekerjaan Umum Provinsi Maluku


Pekerjaan : Analisa Dampak Lingkungan (AMDAL) Jalan Laha - Negeri Lima
Lokasi : Prov. Maluku
Tahun Anggaran : 2016

I. BIAYA LANGSUNG PERSONIL

KONTRAK AWAL

Pengl Jml. Penugasan Org / Billing


No Uraian Gol
(Thn) Personil (bln) Bulan Rate (Rp)

I.1 Tenaga Ahli / Profesional Staf


1 Ketua Tim Penyusun AMDAL (KTPA) S1 3 1 0.5 0.5 Rp 23,500,000
2 Ahli Teknik Jalan Raya S1 2 5 0.5 2.5 Rp 21,750,000
3 Ahli Lingkungan S1 2 5 0.5 2.5 Rp 21,750,000
4 Ahli Sosial S1 2 5 0.5 2.5 Rp 21,750,000
5 Ahli Kehutanan S1 2 3 0.5 1.5 Rp 21,750,000
6 Ahli Hidrologi S1 2 5 0.5 2.5 Rp 21,750,000
7 Ahli Geologi S1 2 5 0.5 2.5 Rp 21,750,000
8 Ahli Biologi S1 2 3 0.5 1.5 Rp 21,750,000

Sub Total I.1.

I.2 Tenaga Pendukung / Supporting Staf


1 Sekretaris D3 1 1 0.5 0.5 Rp 5,500,000
2 Operator Komputer D3 1 7 0.5 3.5 Rp 7,500,000
3 Drafter / Asisten Tenaga Ahli D3 1 7 0.5 3.5 Rp 7,500,000
4 Office Boy (OB) SLTA 1 4 0.5 2 Rp 2,500,000
5 Pengemudi SLTA 1 6 0.5 3 Rp 2,500,000

Sub Total I.2.

SUB TOTAL I.
KONTRAK ADDENDUM 01

TOTAL Jml. Penugasan Org / Billing TOTAL

(Rp) Personil (bln) Bulan Rate (Rp) (Rp)

11,750,000 1 12 12 Rp 15,000,000 180,000,000


54,375,000 1 11 11 Rp 12,000,000 132,000,000
54,375,000 1 3 3 Rp 12,000,000 36,000,000
54,375,000 1 3 3 Rp 12,000,000 36,000,000
32,625,000 1 1 1 Rp 12,000,000 12,000,000
54,375,000 1 1 1 Rp 12,000,000 12,000,000
54,375,000 1 1 1 Rp 12,000,000 12,000,000
32,625,000 1 1 1 Rp 12,000,000 12,000,000

348,875,000 432,000,000

2,750,000 1 12 12 Rp 3,500,000 42,000,000


26,250,000 1 12 12 Rp 3,500,000 42,000,000
26,250,000 0 0 0 Rp 5,000,000 -
5,000,000 0 0 0 Rp 2,500,000 -
7,500,000 0 0 0 Rp 2,500,000 -

67,750,000 84,000,000

416,625,000 516,000,000
REKAPITULASI RINCIAN BIAYA KONTRAK

Satuan Kerja : Dinas Pekerjaan Umum Provinsi Maluku


Pekerjaan : Analisa Dampak Lingkungan (AMDAL) Jalan Laha - Negeri Lima
Lokasi : Prov. Maluku
Tahun Anggaran : 2016

KONTRAK AWAL KONTRAK ADDENDUM 01


NO. URAIAN
TOTAL TOTAL

I. BIAYA LANGSUNG PERSONIL


I.1 Tenaga Ahli / Profesional Staf Rp. 348,875,000 Rp. 432,000,000
I.2 Tenaga Pendukung / Supporting Staf Rp. 67,750,000 Rp. 84,000,000
TOTAL I. Rp. 416,625,000 Rp. 516,000,000

II. BIAYA LANGSUNG NON PERSONIL


II.1 Biaya Operasional Kantor Rp. 43,700,000 Rp. 25,050,000
II.2. Biaya Sosialisasi dan Pembahasan Rp. 199,500,000 Rp. 118,780,000
II.3. Biaya Sampling dan Analisa Laboratorium Rp. 7,500,000 Rp. 7,500,000
II.4. Biaya Laporan Rp. 25,775,000 Rp. 25,775,000
TOTAL II Rp. 276,475,000 Rp. 177,105,000

TOTAL I + II Rp. 693,100,000 Rp. 693,105,000

PPN 10 % Rp. 69,310,000 Rp. 69,310,500

JUMLAH Rp. 762,410,000 Rp. 762,415,500

JUMLAH TOTAL Rp. 762,410,000 Rp. 762,410,000

TERBILANG = TUJUH RATUS ENAM PULUH DUA JUTA EMPAT RATUS SEPULUH RIBU RUPIAH

Untuk dan atas nama Untuk dan atas nama Untuk dan atas nama
Satuan Kerja Perangkat Daerah Penyedia Jasa Penyedia Jasa
Dinas Pekerjaan Umum Provinsi Maluku
Pejabat Pembuat Komitmen

Ir. Ismail Usemahu, MT Ir. Kurdi Ikhsan Ir. Kurdi Ikhsan


NIP. 19650413 199303 1 009 Direktur Utama Direktur Utama

You might also like