Linear Programming Cases
Linear Programming Cases
Petroleum Blending
We have two types of crudes that can be blended to form premium
and regular type of petrol. This can be done by two processes.
The output depends on the number of times each process is run.
The requirements and outputs for each of the two processes for
each run are given below:
Requirement/Run Output/Run
Process
Crude A Crude B Premium Regular
I 1 3 5 2
II 4 2 3 8
Availability 1000 1500
Minimum Demand 800 700
Profit/Unit 3000 2500
These four raw materials cost Rs 12/-, 15/-, 6/- and 0.50/- per
unit. Company can arrange maximum of 1200, 1500, 2400 and 20000
units of raw materials respectively for production purpose.
Nagpur Pune
R1 300 400
R2 250 450
R3 500 720
Nagpur Pune
Labour cost (Rs/ton) 50 45
Capacity(tons) 450 600
In the above problem the warehouses are not setup and we need
to setup those too. Each warehouse can handle 400 Pallets. The
cost of setting up a warehouse at each of the location is
given below (In Rupees Crores):
Warehouse Nagpur Pune Nashik Kolhapur Latur
Cost 1.25 1.2 0.8 1 0.9
The employees would come and join at the start of any slot, but
would continue for 8 hours (2 slots). We have to assist the call
centre in manpower planning and scheduling.
What should we do?