Department of Public Works and Highways: Lower Kalinga District Engineering Office

This document provides the contractual data for the construction project of a two-story, four-classroom workshop building at the Kalinga National High School in Tabuk City, Kalinga. The original contractor was J.Q.G Construction with an original contract amount of PHP 13.5 million, later revised to PHP 12.3 million. Several time extensions and a work suspension have resulted in a revised completion date of September 8, 2018. As of June 30, 2018 the project's physical accomplishments were 63.12% completed, behind the scheduled accomplishment by 3.61%.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
31 views1 page

Department of Public Works and Highways: Lower Kalinga District Engineering Office

This document provides the contractual data for the construction project of a two-story, four-classroom workshop building at the Kalinga National High School in Tabuk City, Kalinga. The original contractor was J.Q.G Construction with an original contract amount of PHP 13.5 million, later revised to PHP 12.3 million. Several time extensions and a work suspension have resulted in a revised completion date of September 8, 2018. As of June 30, 2018 the project's physical accomplishments were 63.12% completed, behind the scheduled accomplishment by 3.61%.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Republic of the Philippines

DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS


LOWER KALINGA
DISTRICT ENGINEERING OFFICE
CORDILLERA ADMINISTRATIVE REGION
Bulanao, Tabuk City, Kalinga

COMPLETE CONTRACTUAL DATA

CONTRACT ID : 17PL0272
PROJECT NAME : CONSTRUCTION OF TWO(2) STOREY FOUR(4)
CLASSROOMS WORKSHOP BUILDING-1, KALINGA
NATIONAL HIGH SCHOOL, TABUK CITY, KALINGA
CONTRACTOR : J.Q.G CONSTRUCTION
ORIGINAL CONTRACT AMOUNT
a) Original : Php 13,506,764.08
b) Revised due to V.O No. 1 : Php 12,382,431.61

EFFECTIVITY OF CONTRACT : January 14, 2018

CONTRACT DURATION
a) Original : 180 Calendar Days
b) Revised due to T.E No. 1 : 210 Calendar Days
c) Revised due to V.O No. 1 : 238 Calendar Days (this request)

APPROVED TIME EXTENSION


a) Time Extension No. 1 : 30 Calendar Days

APPROVED WORK SUSPENSION NO. 1


a) Effectivity date : January 14, 2018
b) No. of suspended days : 30 Calendar Days

TIME EXTENSION IF THE PROPOSED


a) V.O No. 1 is approved : 28 Calendar Days (this request)

COMPLETION DATE
a) Original : July 12, 2018
b) Revised due to TE No. 1 : August 11, 2018
c) Revised due to V.O No. 1, : September 8, 2018 (this request)
SCOPE OF WORK : School Building
IMPLEMENTING OFFICE : DPWH – Lower Kalinga District Engineering Office
SOURCE OF FUNDS : BEFF 2017
STATUS OF PROJECT : On-going

Physical Accomplishments as of June 30, 2018:


Actual Accomplishment : 63.12%
Scheduled Accomplishment as per approved : 66.73%
Slippage : -3.61% (Beyond Schedule)

ADOLFO R. CARBONELL
Project Engineer
DPWH-LKDEO