This mechanical data sheet provides specifications for a fuel gas filter including: 1. Process design conditions such as flow rate, pressure drop, and filtration efficiency requirements. 2. Operating conditions like design and operating pressures and temperatures. 3. Materials of construction including carbon steel and internal coating. 4. Connection details listing the required number of connections, sizes, ratings, and facing types including inlet, outlet, and drain connections.

Uploaded by

sudjono
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
1K views4 pages

Mechanical Data Sheet For Fuel Gas Filters

This mechanical data sheet provides specifications for a fuel gas filter including: 1. Process design conditions such as flow rate, pressure drop, and filtration efficiency requirements. 2. Operating conditions like design and operating pressures and temperatures. 3. Materials of construction including carbon steel and internal coating. 4. Connection details listing the required number of connections, sizes, ratings, and facing types including inlet, outlet, and drain connections.

Uploaded by

sudjono
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 4

DOCUMENT NO:

MECHANICAL DATA SHEET


IPB-OCS-KEA-MEC-DAT-0008
FUEL GAS FILTER OCS JOB NO. R1948
REFERENCE DRAWING NO :
KRISENERGY (APSARA) LTD Rev. Date Prep'd Revision
A 27/12/18 ES ISSUED FOR REVIEW PID No. IPB-OCS-KEA-PRO-P
0 01/02/19 ES ISSUED FOR CONSTRUCTION
PREP'D CHK'D APP'D

ES SS RR

Client : KRISENERGY (APSARA) LTD Project Title : INGENIUM II - PRODUCTION BARGE No Required : 2 Serial No. :
Location : Cambodia Apsara Block A Service : FUEL GAS Sheet No. : 3 of 3
Tag No : 45-F-01 A/B Vendor : Purchase Order No. :
PROCESS DESIGN CONDITIONS
1 CODE : ASME Section VIII Div. 1 7 DUTY : INTERMIT
2 SERVICE : Fuel Gas 8 PRESS. DROP MAX. ALLOW (CLEAN) psig
3 FLUID TYPE :
Gas 9 PRESS. DROP MAX. ALLOW (DIRTY) psig
4 FLOW RATE mmscfd 2 10 OVERALL MOLECULAR WEIGHT
5 FILTRATION EFFICIENCY REQ'D % 100 11 OVERALL DENSITY kg/m3 3.71
6 FILTRATION EFFICIENCY OFFERED % Note 1 12
LIQUID VISCOSITY cP 0.0123
OPERATING CONDITIONS
13 DESIGN PRESSURE barg 6.9 24 VESSEL SPECIFICATION IPB-OCS-KEA
14 DESIGN TEMPERATURE o
C 121 25 WELDING SPECIFICATION ASME
15 OPERATING PRESSURE barg 2.9 26 PAINT/COATING SPEC IPB-OCS-KEA
16 OPERATING TEMPERATURE C
o
73.2 27 LIFTING PROVISION REQ
17 FLUID FLOW mmscfd 2 28 VESSEL ORIENTATION VER
18 PERCENTAGE SOLIDS IN FLUID Note 1 29 DIMENSIONS :
19 NATURE OF SOLIDS Note 1 30 INSIDE DIAMETER mm N
20 SIEVE ANALYSIS OF SOLIDS Note 1 31 T/T LINE mm N
21 SETTLING VELOCITY OF SOLIDS m/s Note 1 32 THICKNESS mm N
22 PARTICLE SIZE microns 10 33 LIFTING & GROUNDING LUGS REQ
23 LIQUID REMOVAL EFFICIENCY % Note 1 34 LEGS & BASE PLATE SKIR
MECHANICAL DESIGN
35 MATERIALS OF CONSTRUCTION Carbon Steel 41 GASKETS YES
36 CORROSION ALLOWANCE mm 1.6 42 COVER YES
37 EXTRERNAL & INTERNAL COATING IPB-OCS-KEA-PIP-SPE-0006 43 COVER BOLTS & NUTS YES
38 INTERNAL TYPE & MATERIAL Note 1 44 LIFTING LUGS YES
39 SUPPORT TYPE BY SELF (NOZZLES) 45 GROUNDING LUGS YES
40 PIPING CONNECTION IPB-OCS-KEA-PIP-SPE-0001 46 NAME PLATE YES
CONNECTION SCHEDULE SKETCH
47 Mark Reqd. Size. Rating Facing
SCH SERVICE
48 No No. (inch) (#) Type
49 N1 1 4 150 RF WN 40 FUEL GAS INLET
50 N2 1 4 150 RF WN 40 FUEL GAS OUTLET
51 N3 1 2 150 RF WN 80 CLOSED DRAIN N7
52 N4 1 2 150 RF WN 80 CLOSED DRAIN
53 N5 1 2 150 RF WN 80 BRIDLE LG & LT
54 N6 1 2 150 RF WN 80 BRIDLE LG & LT
N8
55 N7 1 2 150 RF WN 80 BRIDLE LG & LT
56 N8 1 2 150 RF WN 80 BRIDLE LG & LT
57 N9 1 2 150 RF WN 80 PDT
N3
58 N10 1 2 150 RF WN 80 PDT
59 N11 1 2 150 RF WN 80 OPEN DRAIN
60 N12 1 2 150 RF WN 80 SS TUBING
N1
61 N13 1 2 150 RF WN 80 UC
62 N14 1 2 150 RF WN 80 SPARE
63 X1 1 2 - - STD VENT N13
N12
64 X2 1 24 - - STD ACCESS OPENING
65 M1 1 HOLD - - STD MANWAY C/W COVER, DAVIT & HINGE

N4
DOCUMENT NO:
MECHANICAL DATA SHEET
IPB-OCS-KEA-MEC-DAT-0008
FUEL GAS FILTER OCS JOB NO. R1948
REFERENCE DRAWING NO :
KRISENERGY (APSARA) LTD Rev. Date Prep'd Revision
A 27/12/18 ES ISSUED FOR REVIEW PID No. IPB-OCS-KEA-PRO-P
0 01/02/19 ES ISSUED FOR CONSTRUCTION
PREP'D CHK'D APP'D

ES SS RR

X1
NOTES:
1 Vendor to confirm and advise
2 Vendor to determine and verify the thickness and guarantee them on strength.
X2
3 Vendor to determine type and material as per ASTM Standard.
4 Vendor to determine type of internals (i.e filter, etc) required by the process.
5 For the detail information of the vessel, Vendor shall comply to reference specification and international
codes and standard.
6 Vendor to provide quick release mechanism i.e bandlock
REV.

IPB-OCS-KEA-MEC-DAT-0008 0

OCS JOB NO. R1948

PID No. IPB-OCS-KEA-PRO-PID-4510

APP'D CLIENT
DAVE/MARC/
RR
ROB
Serial No. :

DESIGN CONDITIONS
INTERMITEN
TBA
Note 1
25.72
at 57.3 oC
at 57.3 oC
ING CONDITIONS
IPB-OCS-KEA-MEC-SPE-0001
ASME Section IX
IPB-OCS-KEA-PIP-SPE-0006
REQUIRED
VERTICAL

Note 1
Note 1
Note 2
REQUIRED
SKIRT TYPE
ANICAL DESIGN
NO
NO
NO
NO
NO
NO
SKETCH

N14

N2

N9

N10

N5

N6
REV.

IPB-OCS-KEA-MEC-DAT-0008 0

OCS JOB NO. R1948

PID No. IPB-OCS-KEA-PRO-PID-4510

APP'D CLIENT
DAVE/MARC/
RR
ROB
N6

N14

You might also like