PJM Study
PJM Study
May 2002
Docs#139461
Confidential 1
Table of Contents
Introduction Pages 3 - 5
Milestone Schedule Page 4
Scope of Interconnection Customer’s Work Page 4
Scope of Pepco’s Work Page 4
Confidential 2
INTRODUCTION
Description of Project
Mirant Project #A7 / #B1 is located at the existing Dickerson (Station H) Generation Station in
Montgomery County, Maryland. The projects originally consisted of (#A7 – 120MW) installing
one steam turbine generator to build out to a combined cycle with two existing Unit #4
combustion turbine generators; and (#B1 – 398MW) a new combined cycle, named Unit #5,
consisting of two combustion turbine generators and one steam turbine generator. The Impact
Studies for #A7 and #B1 were performed with the new generation addition as described above.
Projects #A7 and #B1, as currently defined, consists of two 160MW combustion turbine
generators scheduled for commercial operation in May 2004, and build out to a combined cycle
arrangement with the addition of a 222MW steam turbine generator in May 2006.
The total MW capacity (summer) request for the original #A7 and #B1 is 518MW. The
redefined #A7 and #B1 MW (summer) capability is 542MW. The new arrangement will have
24MW which will not qualify for Capacity Interconnection Rights under the #A7 and #B1
requests. The Interconnection Customer also has an additional Queue #G2 generator
interconnection request for 234MW. #G2 will be used to qualify the excess 24MW from the
redefined #A7 / #B1 projects, and to interconnect a new 210MW steam turbine generator to build
out unit #4 into a combined cycle. #G2 MWs are also planned to be commercial in May 2006.
This report will not address Queue position #G2.
A simplified one line diagram shown below illustrates the connection and relationship of Queues
A7, B1, and G2 at Dickerson.
Eastalco Monocacy
Lovettsville Eastalco
Ringgold
Ringgold
Doubs
Potomac Edison (AP)
Bedington Brighton
Mt Storm Loudoun
500 kV
23102
23101 230 kV
SPARE SPARE
50 MW MCRRF
5 4
SPARE (Montgomery County
Resource Recovery Facility)
23032
23034
Quince
Orchard
23111
23033
23035
to Pleasant View
(Virginia Power)
Confidential 3
At present, there are two combustion turbines (Unit #4) and the 50 MW MCRRF generating
facility connected to the Station H 230 kV bus. A steam turbine unit is planned to be added and
will be connected between breakers 45A and 45B as part of the Queue #G2 interconnection
request. There are four generating units presently connected to the Dickerson Station D 230 kV
bus. In addition to generating connections, there are four Dickerson – Quince Orchard 230 kV
circuits, two Dickerson – Doubs 230 kV circuits and one Dickerson – Pleasant View 230 kV
circuit connected to the existing station.
Milestone Schedule
The following milestone dates have been established for Project A7/B1:
Note: Preliminary results indicate that Interconnection Customer’s schedule does not
align with Pepco’s estimated date for completion of all switchyard work at Stations
H and D.
Confidential 4
Thirteen (13) 230 kV breakers at Dickerson Station “D” with 50 kA short circuit interrupting
rating will require replacement with 63 kA rated units. Breakers 4A and 4B are presently oil
circuit breaker units rated at 63 kA and will not require replacement. Select breaker isolating
breaker switches, breaker taps, potential transformer / current transformer units, bus taps, bus
supports and instrument transformer taps will also require replacement to ensure a 63 kA short
circuit rating.
Thirteen (13) 230 kV gas breakers in the Station “H” switchyard will require the addition of
external capacitors to attain a 63 kA short circuit interruption rating.
Protection Systems
Station “D” stuck breaker protection will be modified such that catastrophic loss of gas on any
breaker will initiate stuck breaker protection to isolate the affected breaker. This stuck breaker
scheme was not used for the existing oil breakers. Although not required, it is recommended that
the existing Station “D” circuit breaker overcurrent relays on CBs 1A, 1B, 1C, 2A, 2B, 2C, 3A,
3B, 3C and 7A be replaced with a GE Universal, multifunction type F-60 relay. Many of these
pre-existing relays are on generator positions and are unreliable.
At Station “H”; bus differential, cable differential, and stuck breaker protection systems will be
required for the direct connection circuit and addition of circuit breakers #48A and #48B.
Other Facilities
Adequacy of Station “D’ and Station “H” AC Station Service and 125Vdc systems must be
verified after selection of circuit breakers and switches. Substation shield wires and grounding
grid upgrades will be determined as part of the detailed design.
See Attachment #1 for a list of required material, and Attachment #2 for a list of affected Pepco
drawings. Finished design drawings are available to Interconnection Customer upon request.
Permits Required
Building permits will be required for breaker foundation additions at Dickerson Sta. H.
Building permits will not be required for additions at Dickerson Sta. D.
Confidential 5
FACILITY STUDY RESULTS
SUBSTATIONS
A sensitivity analysis was conducted to determine the requirements for other facilities at
Dickerson Station “D”. The sensitivity analysis included bus design calculations at fault
levels between 50kA and 63kA. At 63kA five additional bus supports and 28 additional
station post insulators are required. At fault levels between 50 and 55kA, the number of
bus supports to be added can be reduced from five to three and the number of station post
insulators can be reduced from 28 to 26 as compared to the design at 63 kA. It is also
important to remember that other PJM and PJM West generation interconnections up to
and including Queue #G2 can add as much as 5kA to the expected fault duties. Based on
Confidential 6
the relatively minor change in work scope it would be prudent to design the entire
switchyard for a 63kA fault current level.
Circuit Breaker Specification
· Dead tank, group operated
· Rated maximum voltage: 242 kV
· Rated voltage range factor, K-1.0
· Rated full wave impulse withstand: 900 kV
· Rated capacitance switching current: Definite purpose
· Rated continuous current: 3000a
· Duty cycle: OCO
· Rated short circuit current: 63 kA
· Closing and Latching capability: 164 kA peak
· Rated Interrupting time: 3 cycles
· Rated permissible tripping delay, Y: 1 second
· Rated reclosing time: 20 cycles
· Adjustable reclosing time: 20 cycles
· Tripping logic for low SF-6 gas: Trip and block close
· Bushing data: Basic Impulse level: 900 kV, minimum creepage distance: 140”
· Color: ANSI 70 gray
· Nominal station service voltage: 480/277v
· Breaker closing: one coil rated 125vdc, breaker tripping: two coils rated at 125vdc
· Current transformer requirements: ( 3 ), C800, 3000/5 current transformers per
bushing
Confidential 7
· Impulse withstand voltage (BIL ): 900 kV peak
· Voltage rating: 138 kV/115-69 V (Each phase)
· Current rating: 3000 A continuous
· Thermal rating: 7000 va
· Ratio : 2000/1200/1 (Potential transformer), 2000/5 (Current transformer)
· Accuracy: 0.3 %
· Burden: 400ZZ (Potential transformer), 1.8 (Current transformer)
· CT mechanical Rating: 63 kA
· CT Short Time Thermal Current Rating: 63 kA
Design Requirements
The general design requirements are as follows:
Confidential 8
Rigid & Strain Bus Design
Pepco’s preferred bus conductors are 4” schedule 80 aluminum tube for rigid bus and two
1590 MCM wires per phase for strain bus. The rigid bus will be designed for a maximum
deflection of one pipe outer diameter without ice. Porcelain station post insulators will be
used on all bus supports and disconnect switches, and the mechanical ratings will be
determined during the detailed design.
The rigid bus design will be designed in accordance with the following loading cases:
Loading Case 1
NESC Heavy Loading, 40 mph wind, 0.5 “ radial ice and 63 kA short circuit force
applied simultaneously. Overload Factors: 2.5 wind, 1.565 short circuit and 2.5 vertical.
Loading Case 2
Extreme Ice Loading, 0 mph wind, 1.0” radial ice and 63 kA short circuit force applied
simultaneously. Overload Factors: 2.5 wind, 1.565 short circuit and 2.5 vertical.
Loading Case 3
Extreme Wind Loading, 80 mph wind and 63 kA short circuit force loads applied
simultaneously. Overload Factors: 2.5 wind, 1.565 short circuit and 2.5 vertical.
Structural Design
Steel structures as required will be designed and fabricated in accordance with the latest
edition of the AISC “ Manual of Steel Construction”, ASCE 7-98 and the Uniform
Building Code. The bus, insulators, switch and equipment supports will be designed to
withstand the following loads.
Loading Case 1- NESC Heavy
Structures will be loaded with all equipment loads and the weight of the structure. A wind
pressure of 4psf will be applied as well as a simultaneous radial ice load associated with
½”. Overload factors of 2.5 for transverse wind, 1.25 for wire tension and 1.5 for vertical
loads will be applied.
Confidential 9
Loading Case 3- Extreme Wind
Structures will be loaded with all equipment loads and the weight of the structure. A wind
of 80 mph will be applied. Overload factors of 1.25 will be applied for all loads.
Loading Case 4- Short Circuit and High Wind
A horizontal loading associated with a short circuit of 63 kA magnitude will be applied to
the bus elevations. Simultaneously, a wind force associated with an 80 mph wind force
will be applied. Overload factors of 1.565 will be used for the short circuit force and 1.0
for the wind loads.
Grounding System
The grounding grid upgrade will be designed in accordance with ANSI/IEEE 80. The
grounding grid is based on a 63 kA short circuit with 50% of available short circuit
current being contributed by remote sources. A fault duration of 0.407 seconds is used for
sizing of the grid conductor. Fault duration for determination of step and touch potentials
is 0.07 seconds.
The existing bus, protection, line protection, and generator protection will remain
unchanged as a result of the breaker replacements. Existing stuck breaker protection will
be modified such that catastrophic loss of gas on any breaker will initiate stuck breaker
protection to isolate the affected breaker. This stuck breaker scheme is not used for oil
breakers. Existing breaker overcurrent relays for breakers 1A, 1B, 1C, 2A, 2B, 2C, 3A,
3B, 3C and 7A will be replaced with a GE Universal, multifunction type F-60 relay.
Many of these relays are on generator positions and are unreliable and could lead to
possible generator outages.
Confidential 10
Note: Replacement of overcurrent relays, with pre-existing reliability concerns, will be
done at Pepco cost.
Confidential 11
B. DICKERSON STATION “H”
1. Add 230kV circuit breakers 48A and 48B, three 230 kV disconnect
switches, instrument transformers, associated protective relaying,
miscellaneous bus work and support structures, including the
termination for the A7/B1 Direct Connection circuit.
Confidential 12
· Number of poles: three
· Switch Phase Spacing: 180”
· Motor operator control voltage: 120 vac
· Manual operator: Worm gear type
· Manual operator cam operated type auxiliary switch contacts, number of “a” contacts:
8, number of “b” contacts: 8
Metering Specifications
Metering equipment for the generating units installed at Station “H” will be the
responsibility of the developer and will not be included in this Facility Study report.
Confidential 13
Protective Relaying
The relaying equipment for protection of the Direct Connection circuit and for protection
of circuit breakers 48 A&B is listed below. The equipment will be located in the existing
Pepco control house.
Bus Differential Relaying
Breaker 48A will be incorporated into the bus differential schemes for existing 230 kV
Bus #1. The relays used for both schemes will be GE type SBD11 relays. Tripping
functions will be performed by ABB type AR relays and lockout functions will be
performed by Electroswitch auxiliary type LOR relays. Reclosing will be delayed on the
affected breakers, and stuck breaker protection will be initiated by a bus differential
operation. Breakers 48B will be incorporated into bus differential schemes for existing
230 kV Bus #2. The relays used for both schemes will be GE type SBD11 relays.
Tripping functions will be performed by ABB type AR relays and lockout functions will
be performed by Electroswitch auxiliary type LOR relays. Reclosing will be delayed on
the affected breakers and stuck breaker protection will be initiated by a bus differential
operation.
Confidential 14
RTU located in the control house and remotely from the Pepco Control Center. Metering
equipment to provide amp, watt, var and volt information on breakers 48 A&B will be
installed.
Communications
Pepco will utilize existing telecommunications optical fiber circuits for the transmittal of
all required metering and protection information. Extension of fiber cables may be
required into the new areas of the proposed generating units and the generator control
room. This will be determined during detailed design and will require close coordination
with Mirant.
Confidential 15
Circuit Breaker TRV Capacitor Specification (for upgrade of 13 circuit breakers)
Capacitor upgrade will use ABB Model #206D53801 capacitor upgrade. A minimum of
three will be required for esch circuit breaker, some breakers may require two sets of
three each.
Design Requirements
Same as Dickerson Station “D”. See Station “D” Design Requirements on pages 8
through 10.
Confidential 16
Grounding System
The grounding grid upgrade will be designed in accordance with ANSI/IEEE 80. The
grounding grid is based on a 63 kA short circuit with 50% of available short circuit
current being contributed by remote sources. A fault duration of 0.407 seconds is used for
sizing of the grid conductor. Fault duration for determination of step and touch potentials
is 0.07 seconds.
Confidential 17
488 A-H and charger no. 1 is 100 A, battery no. 2 is 320 AH and charger no. 2 is 50 A.
The batteries and chargers were sized using IEEE 485 and the criteria listed below.
Nominal battery voltage: 125 VDC
Number of Cells: 58
Emergency Operating Time: 8 hours
Minimum cell voltage: 1.81v
Lowest expected electrolyte
Temperature: 65 degree F
Specific gravity at rated capacity 1.215
Plate type: Lead Calcium
Recharge Time at Design Load: 8 hours
Battery load profiles at Station H switchyard are based on a double contingency event
consisting of a main bus fault with a circuit breaker failure contingency. The adequacy of
the existing battery and charger systems will be verified during the detailed design phase
as a result of the additional equipment loading on the 125 VDC system.
Confidential 18
STATION “D” COST ESTIMATE
The costs for the work at the Dickerson Sta. D switchyard are estimated to be $8.0
million. This estimate includes replacing (13) 50 kA breakers with 63 kA units, and
replacing associated disconnect switches, bus structures and bus support structures to
ensure a 63 kA rating.
These costs are entirely associated with the requirement to upgrade the short circuit rating
of the Station “D” switchyard. The cost will be divided evenly among the thirteen breaker
positions. Thus each breaker position is responsible for $615,385 worth of network
upgrades. This estimate does not include CIAC tax Gross-up which is 34%.
The estimate can be broken down as follows:
Labor Direct $ 1,789,000
Labor Indirect $ 2,065,000
Material Direct $ 3,452,000
Material indirect $ 694,000
Subtotal $ 8,000,000
CIAC Tax (if required) $ 2,720,000
Total $10,720,000
Confidential 19
ENGINEERING DESIGN SCHEDULE
Activity Start Finish
Single Line Diagram 3/15/02 4/30/02
Functional Diagram 4/01/02 6/01/02
Three line diagrams 4/01/02 6/01/02
AC Schematics 6/01/02 7/01/02
AC/DC station service drawings 6/01/02 10/01/02
Control/Relay panel diagrams 7/01/02 8/01/02
DC Schematic diagrams 7/01/02 9/01/02
Interconnection diagrams 9/01/02 10/01/02
Rigid Bus design calculations 5/01/02 7/15/02
Lightning shielding calculations 5/01/02 7/15/02
Bus & equipment arrangement drawings 7/01/02 9/01/02
Raceway drawings 7/01/02 9/01/02
Grounding calculations 5/01/02 7/01/02
Battery & charger calculations 5/01/02 7/01/02
Steel structure verification 6/01/02 8/01/02
Foundation design calculations 6/01/02 8/01/02
Foundation drawings 8/01/02 10/01/02
Grading Drawings (verification) 8/01/02 10/01/02
Storm Water & erosion control verification 10/01/02 12/01/02
Relay Settings 10/01/02 1/02/03
Confidential 20
Note: It is envisioned that the work at Sta. D and Sta. H will proceed essentially
simultaneously. It is also assumed that outages will not generally be granted in January,
February, June, July, August or September of any calendar year. It is also assumed that
outages on individual transmission circuits and generator units will be granted during the
proposed construction period. Outages that may be required for other PJM Queue
projects on the Pepco system may alter the above schedule.
Confidential 21
ATTACHMENTS
Confidential 22
ATTACHMENT #1
Material List
230 kV Breaker- Quantity: 15 (13 for Sta. “D”, 2 for Sta. “H”)
1) 230 kV
2) 3000 A Continuous
3) 63 kA Capability Short Circuit Interrupting
4) (6) Sets of C800 CTs
5) Two Sets of Trip Coils
6) 9 (a) and 9 (b) Auxiliary Breaker Contacts
7) 125 vdc Trip and Close
8) 480/277 vac Auxiliary Power
230 kV Disconnect Switch- Quantity: 29 (26 for Sta. “D”, 3 for Sta. “H”)
1) 230 kV
2) 3000 Continuous
3) 100 kA Asymmetrical Current Withstand Capability
4) Motor operated
5) Ground Switch Manual, Jaw End (ten units – Sta. “D”, three units – Sta. “H”)
6) 9 (a) and 9 (b) Auxiliary Breaker Contacts
7) Insulators, High Strength, ANSI Grey
8) Shipped Assembled
Confidential 23
28 for Sta. “D” (18 high strength, 10 extra high strength) (23 mounted on existing structures)
105 for Sta. “H” (15 high strength, 90 extra high strength) (69 mounted on existing
structures)
3) 4 " Schedule 80 Aluminum Bus, Vincent Metals- Quantity: 600 ft. (Sta. “H”)
4) 2/c Welded Aluminum Terminal, Alcoa 1546.150- Quantity:
5) Terminal Pad, 4", Sch. 80, Dossert WTPI-4000E-4N4F-AA- Quantity:
6) Bus Support Clamp, 4", Sch 80, 5" BC, Anderson- Quantity:
7) 2/C Spacer Clamp, Anderson APCS 16-12- Quantity:
8) Compression Terminal, Anderson VPUL-4/0-2N- Quantity:
9) Tee Tap, 1590 MCM, Alcoa 28393.18EHV- Quantity:
10) 230 kV Arrester Tap, Alcoa 2010.18EHV- Quantity
11) Welded Aluminum Terminal, 1590 MCM, Alcoa 1526 150D- Quantity:
Grounding Material
1) Terminal Pad, 500 MCM, Burndy YA34-2N- Quantity:
2) Tee Connector, 500 MCM, Dossert CRT 50-50- Quantity:
3) Wire Copperweld, 500MCM, Quantity:
4) Ground Mat, 12" Mesh, #6 Solid, Erico- Quantity:
5) Ground Rod, 5/8"x 8', Mcgraw WDN3C8- Quantity:
6) Mold, Cable-Gnd Rod, Erico GYJ-169J- Quantity:
7) Handle Clamp, 4" Wide Molds, Erico L159- Quantity:
8) Cartridge, Grounding, Erico 250- Quantity:
9) Cartridge Grounding, Erico 150- Quantity:
10) Handle Clamp, 3" Molds, Cadweld L160- Quantity:
11) Mold, Cable to Cable, Cadweld TAC-9J9J- Quantity:
12) Ground Clamp, 500 MCM, Burndy GB 34- Quantity:
13) Mold, Cable to Cable, 500 MCM -#6, Erico PTC- 1G9J- Quantity:
Confidential 24
17) Terminal Block, 8 Pole, Marathon # 1508- Quantity:
18) Coupling, 4", AET 45- Quantity:
19) Bushing, Conduit, 4", T&B # 519- Quantity:
20) Connector, 1 1/2" Flexible Conduit, Sepco C31- Quantity:
21) Wire, 4 Copperweld, Quantity:
22) Conduit, Flexible, 1 1/2", Quantity:
23) Cable Tie, T&B # TY527MK- Quantity:
24) Conduit, Rigid Aluminum, 1 1/2"- Quantity:
25) Conduit Clamp, 1 1/2" Aluminum, Quantity:
26) Coupling, 1 1/2" Rigid Conduit- Quantity:
27) Coupling, PVC, 1 1/2", AET# TF 150- Quantity:
28) Coupling, PVC 2", AET # TF 200- Quantity:
29) Conduit, 2" Flexible, AET- Quantity:
30) Conduit, 3" Flexible, AET- Quantity:
31) Coupling, 3" Underground, AET # TF 300- Quantity:
Substation Structures
1) A-frame take-off tower – Quantity: 1 (Sta. “H”)
2) 230 kV switch stand – Quantity: 3 (Sta. “H”)
3) 230 kV switch stand modified for use as a bus support str. – Quantity: 1 (Sta. “H”)
4) 230 kV single phase bus support str. – Quantity: 26 (21 Sta. “H”, 5 Sta. “D”)
5) 230 kV CT/PT stand – Quantity: 6 (Sta. “H”)
Cable Requirements
1) 4/C #9, 1000v, Copper, Shielded- Quantity:
2) 12/C # 9, 1000v, Copper, Shielded- Quantity:
3) 4/C # 9, 1000v, Copper, Non-Shielded- Quantity:
4) 12/C # 12, 1000v, Copper, Shielded- Quantity:
5) 7/C # 12, 1000v, Copper, Shielded- Quantity:
6) 12/C # 12, 1000v, Copper, Non-Shielded- Quantity:
7) 7/C # 12, 1000v, Copper, Non-Shielded- Quantity:
8) 4/C # 12, 1000v, Copper, Non-Shielded- Quantity:
9) 2/C #12, 1000v, Copper, Non-Shielded- Quantity:
Confidential 25
3) Auxiliary Lockout Relay, Electroswitch # 7803D- Quantity: 1
4) Miscellaneous lot of equipment to include test switches, auxiliary relays, switchboard
plates, etc. Quantities to be determined during detailed design phase of the project.
Confidential 26
ATTACHMENT #2
Drawing List
(DICKERSON STATION “D” 230KV SWYD., 230KV EQUIPMENT UPGRADE ASSOCIATED DRAWINGS)
Confidential 27
7E-GSD-467 A.C. ELEM DIAG BUS #2 DIFF REL'S #1
7E-GSD-468 A.C. ELEM DIAG BUS #2 DIFF REL'S #2
7E-GSD-469 A. C. ELEM DIAG BAY #1 STK. BKR. REL'S #2 OCB'S 1A, 1B & 1C
7E-GSD-470 A. C. ELEM DIAG BAY #2 STK. BKR. REL'S #2 OCB'S 2A, 2B & 2C
7E-GSD-471 A. C. ELEM DIAG BAY #3 STK. BKR. REL'S #2 OCB'S 3A, 3B & 3C
7E-GSD-472 A. C. ELEM DIAG BAYS #5,6,7 & 9 STK. BKR. REL'S #2
7E-GSD-620 230KV SUBST A.C. ELEM DIAG O.C. REL,S 1A1 &1B1
7E-GSD-621 230KV SUBST A.C. ELEM DIAG O.C. REL,S 2A1 &2B1
7E-GSD-622 230KV SUBST A.C. ELEM DIAG O.C. REL,S 3A1 &3B1
7E-4845 230KV SUB STA ELEM CONTROL DIAG MICROWAVE ALARMS
7E-GSD-423 230KV CONTROL DIAG. BUS #1 & #2 POT. TRANSF. & BUS DIFF.
C.T CAB. 2
7E-GSD-476 CONTROL DIAG. SWBD. OCB STK. BKR. REL'S 1A2, 1B2 &1C2
7E-GSD-477 CONTROL DIAG. SWBD. OCB STK. BKR. REL'S 2A2, 2B2 & 2C2
7E-GSD-478 CONTROL DIAG. SWBD. OCB STK. BKR. REL'S 3A2, 3B2 & 3C2
7E-GSD-479 CONTROL DIAG. SWBD. OCB 5A STK. BKR. REL'S 5A2
7E-GSD-480 CONTROL DIAG. SWBD. OCB 6C STK. BKR. REL'S 6C2
7E-GSD-481 CONTROL DIAG. SWBD. OCB 7A STK. BKR. REL'S 7A2
7E-GSD-482 CONTROL DIAG. SWBD. OCB 9A STK. BKR. REL'S 9A2
7E-GSD-487 CONTROL DIAG. SWBD. OCB STK. BKR. REL'S 4A2, 4B2, & FUT.
4C2
7E-GSD- 488 CONTROL DIAG. SWBD. BUS #1 DIFF. REL'S #1
7E-GSD- 489 CONTROL DIAG. SWBD. BUS #1 DIFF. REL'S #2
7E-GSD- 490 CONTROL DIAG. SWBD. BUS #2 DIFF. REL'S #1
7E-GSD- 491 CONTROL DIAG. SWBD. BUS #2 DIFF. REL'S #2
7E-GSD- 492 CONTROL DIAG. SWBD. MISC. ALARM PNL. SOUTH
7E-GSD- 581 A.C. CONTROL DIAG. BAY #4 STK BKR REL,S #1 OCB ,S 4A, 4B &
FUT 4C
7E-GSD- 582 A.C. CONTROL DIAG. BAY #4 STK BKR REL,S #2 OCB ,S 4A, 4B &
FUT 4C
7E-GSD- 583 CONTROL SW. OCB 4A
7E-GSD- 584 CONTROL SW. OCB 4B
7E-GSD- 587 CONTROL DIAG SWBD STK BKR REL,S 4A2, 4B2 & FUT 4C2
7E-GSD- 619 230KV CONTROL HSE CONTROL DIAG OCB'S 1A, 1B, 2A, 2B, 3A,
3B, 4A, & 4B MET. AUX C.T.,S
3E- GSD- 499 SHTS. 5 - 22 230KV CONTROL HSE CONDUIT & WIRE SCHEDULE
7E-3275 230KV CONTROL DIAG. OCB'S 1A & 2A
347-E-321 230KV CONTROL DIAG. OCB'S 3B & 3C
7E-3279 CONTROL DIAG. SWBD. OCB 7A & FDR CKT 7HF
7E-4802 CONTROL DIAG. OCB 6C & FDR CKT 6HF
7E-4803 CONTROL DIAG. SWBD. OCB 6C & FDR CKT 6HF (6E1)
7E-4846 230KV SUB STA CONTROL DIAG MICROWAVE TRANSMITTER
RELAY RACK
7E- 4849 230KV SUB STA CONTROL DIAG MICROWAVE TEST PANEL
7E-5940 CONTROL DIAG. DIGITAL FAULT RECORDER SYSTEM
7E-5941 CONTROL DIAG. DISTR. RECORDER EQUIPMENT (SER)
Confidential 28
7E-2776 230KV SWYD CONTROL CONDUITS, TRENCH & GROUNDING
PLAN
7E-6037 CONTROL DIAG. SWBD. STK. BKR. OCB 4A1, 4B1 & 9A1
7E-7059 RTU INTERFACE BOX
7E-7079 TRU 230KV YARD INTERFACE BOX
3E- 7158 230KV SUBST CONDUIT & WIRE SCHEDULE
7E-8022 CONTROL DIAG. OCB 1A,2A & 3A RECLOSERS
7E-8028 230KV SUB CONTROL DIAG TOGGLE SW. ALARMS (RTU)
4E-3850 230KV SUB STA CONDUIT & WIRE SCHEDULE MICROWAVE
9862`-RE-3H CONTROL DIAG. OCB,S 1B & 1C
9862`-RE-3J CONTROL DIAG. OCB,S 2B & 2C
Confidential 29
9862-FE-9C 230KV SWYD EQUIP PLAN
E-35 230KV SWYD EQUIP PLAN
E-64 RELAY BOARD ARRANGEMENTS & DETAILS
E-73 RELAY BOARD ARRANGEMENTS - 230KVSWBD - RELAY HOUSE
E-81 GROUNDING SYSTEM PLAN
E-83 GROUNDING DETAILS
E-84 GROUNDING PLAN 230KV SWYD
E-85 GROUNDING DETAILS - 230KV SWYD
E-86 GROUNDING SYSTEM - GENERAL ARRANGEMENT PLAN
7E-GSD-374 230KV SWTYD CABLE & DIRECT BURIAL TRENCH KEY PLAN
7E-GSD-612 230KV STA. SWTYD ELECTRICAL ARRANGEMENT MISC
ASSEMBLIES & DETAILS
7E-GSD- 608 SH. 1 230KV SUBST. FUNCTIONAL DIAG. RELAYING & METERING
7E-GSD- 608 SH. 2 230KV SUBST. FUNCTIONAL DIAG. RELAYING & METERING
Confidential 30
7E-GSD- 608 SH.3 230KV SUBST. FUNCTIONAL DIAG. RELAYING & METERING
7E-GSD- 608 SH.4 230KV SUBST. FUNCTIONAL DIAG. RELAYING & METERING
7E-GSD- 608 SH5 230KV SUBST. FUNCTIONAL DIAG. RELAYING & METERING
7E-GSD- 608 SH6 230KV SUBST. FUNCTIONAL DIAG. RELAYING & METERING
7E-GSD- 608 SH7 230KV SUBST. FUNCTIONAL DIAG. RELAYING & METERING
GSD-EU4-800 230KV FUNCTIONAL DIAG. BAYS 1,2 & 3
GSD-EU4-801 230KV FUNCTIONAL DIAG. BAYS 4,5 & 6
7E-GSH--615 SH .05 230KV FUNC DIAG RELAYING & METERING CIR 48D
Confidential 31
7E-GSH--615 SH. 11 230KV FUNC DIAG STUCK BKR RELAYING BAYS NOS 6, 7 & 8
7E-GSH--615 SH. 19 230KV FUNC DIAG METERING & MONITORING BAY NO. 8
Confidential 32
7E-GSH-042- SH. 05 230KV ELECT ARRANGEMENT, PLAN & ELEV BAY3
7E-GSH-042- SH. 06 230KV ELECT ARRANGEMENT, PLAN & ELEV BAY4
7E-GSH-042- SH. 07 230KV ELECT ARRANGEMENT, PLAN & ELEV BAY5
7E-GSH-042- SH. 08 230KV ELECT ARRANGEMENT, PLAN & ELEV BAY6
7E-GSH-042- SH. 09 230KV ELECT ARRANGEMENT, PLAN & ELEV BAY7
7E-GSH-042- SH. 10 230KV ELECT ARRANGEMENT, PLAN & ELEV BAY8
7E-GSH-042- SH. 11 230KV ELECT ARRANGEMENT, PLAN & ELEV BAY9
7E-GSH-042- SH. 12 230KV ELECT ARRANGEMENT, PLAN & ELEV BAY10
7E-GSH-042- SH. 13 230KV ELECT ARRANGEMENT, PLAN & ELEV BAY11
7E-GSH-042- SH. 14 230KV ELECT ARRANGEMENT, PLAN & ELEV BAY12
7E-GSH-042- SH. 15 230KV ELECT ARRANGEMENT, PLAN & ELEV MAIN BUS 1
7E-GSH-042- SH. 16 230KV ELECT ARRANGEMENT, PLAN & ELEV MAIN BUS2
7E-GSH-042- SH. 17 230KV ELECT ARRANGEMENT, PLAN & ELEV MAIN BUS2
7E-GSH-044- SH. 1 230KV SWYD DETAILS
7E-GSH-044- SH. 2 230KV SWYD DETAILS
7E-GSH-048- SH. 01 GROUNDING, PLAN, SITE
7E-GSH-048- SH. 02 GROUNDING, 230KV SOUTH YARD
7E-GSH-048- SH. 03 GROUNDING, 230KV NORTH YARD
7E-GSH-050 CONTROL HOUSE GENERAL ARRANGEMENT PLAN
7E-GSH-202 -SH. 06 230KV SWYD RACEWAY PLAN
7E-GSH-202 -SH. 07 230KV SWYD RACEWAY PLAN
7E-GSH-202 -SH. 08 230KV SWYD RACEWAY PLAN
7E-GSH-202 -SH. 09 230KV SWYD RACEWAY PLAN
7E-GSH-202 -SH.11 230KV SWYD RACEWAY PLANS, SECT & DETAILS
7E-GSH-400 -SH.01 CONTROL HOUSE CABLE TRAY PLAN
7E-GSH-400 -SH.02 CONTROL HOUSE CABLE TRAY SUPTS PLAN, SECT & DETAILS
7E-GSH-400 -SH.03 CONTROL HOUSE CABLE TRAY SECTIONS & DETAILS
Confidential 33
7E-GSH-005- SH. 08 FOUNDATION LAYOUT
7E-GSH-005- SH. 09 FOUNDATION LAYOUT
7E-GSH-006- SH. 01 FOUNDATION DETAILS
7E-GSH-006- SH. 02 FOUNDATION DETAILS
7E-GSH-006- SH. 03 FOUNDATION DETAILS
7E-GSH-006- SH. 04 FOUNDATION DETAILS
7E-GSH-006- SH. 05 FOUNDATION DETAILS
7E-GSH-006- SH. 05 FOUNDATION DETAILS
7E-GSH-006- SH. 07 FOUNDATION DETAILS
7E-GSH-006- SH. 08 EQUIPMENT FOUNDATION DETAILS
7E-GSH-007- SH. 01 CONTROL HOUSE FOUNDATION
7E-GSH-007- SH. 02 CONTROL HOUSE FOUNDATION
7E-GSH-007- SH. 03 CONTROL HOUSE ROOF- PLAN,SECTS & DETS
7E-GSH-007- SH. 04 CONTROL HOUSE ROOF- PLAN,SECTS & DETS
7E-GSH-008- SH. 01 EQUIPMENT STEEL STRUCTURES
7E-GSH-008- SH. 02 EQUIPMENT STEEL STRUCTURES
7E-GSH-008- SH. 03 EQUIPMENT STEEL STRUCTURES
Confidential 34
ATTACHMENT #3
Construction and Outage Sequence
Dickerson Sta. “D”
Dickerson Sta H
Confidential 35
Add TRV Capacitors Breaker 43B 3/10/03 3/14/03
Confidential 36
ATTACHMENT #4
Dickerson Station “D” 230kV single line diagram
Confidential 37
ATTACHMENT #5
Dickerson Station “H” 230kV single line diagram
Confidential 38
ATTACHMENT #6
Dickerson Sta. “D” 230kV three line diagram
Confidential 39
ATTACHMENT #6
Dickerson Sta. “D” 230kV three line diagram
Confidential 40
Sheet 1 of 2
ATTACHMENT #7
Dickerson Sta. “H” 230kV three line diagram
Confidential 41
Sheet 2 of 2
ATTACHMENT #7
Dickerson Sta. “H” 230kV three line diagram
Confidential 42
ATTACHMENT #8
Fault Study Report:
PJM #A7/B1/G2 - Projects at Dickerson, Sta. H.
Description:
The fault study was performed by modeling an Aspen Oneliner File that depicts the proposed
configuration of the A7, B1 and G2 projects at Dickerson Sta. H . The system modeled consisted
of four 13 kV generators (2 Combustion Turbines, 160 MW each and 2 Steam Turbines, 210MW
and 222 MW) each connected to a separate two-winding step-up transformer (230/13 kV). The
high side (230 kV) of each transformer was then connected to the 230 kV bus at Dickerson, Sta.
H which is labeled as DICKH230, Bus No. 7002. The 230 kV bus at Dickerson, Sta. H is part of
the Pepco Base Case Aspen Oneliner file that depicts the entire transmission and distribution
system.
Assumption:
Modeling Tool:
The tool used to model this project was Aspen Oneliner version 2000F. This is
a PC-based short-circuit and relay coordination program. The short circuit
program simulates all types of classical faults, such as, bus, line-end, line-out,
intermediate and simultaneous faults.
Analysis:
Existing The short-circuit program was used to determine the three-phase and single-phase
Condition fault duties at the 230 kV bus (Bus No. 7001) at Dickerson, Sta. D and at the
230 kV bus (Bus No. 7002) at Dickerson, Sta. H. The ANSI X/R Ratio was
determined.
(No Additional Generation)
A7 The short-circuit program was used to determine the three-phase and single-phase
fault duties at the 230 kV bus (Bus No. 7001) at Dickerson, Sta. D and at the
230 kV bus (Bus No. 7002) at Dickerson, Sta. H, when one 160 MW combustion
turbine (1 CT) is connected to the 230 kV bus (Bus No. 7002) at Dickerson,
Sta. H. The ANSI X/R Ratio was determined.
(1 CT, 160 MW)
Confidential 43
A7/B1 The short-circuit program was used to determine the three-phase and single-phase
fault duties at the 230 kV bus (Bus No. 7001) at Dickerson, Sta. D and at the
230 kV bus (Bus No. 7002) at Dickerson, Sta. H, when in addition to project A7,
one 160 MW combustion turbine (1 CT) and one 210 MW steam turbine (1 ST)
are connected to the 230 kV bus (Bus No. 7002) at Dickerson, Sta. H. The ANSI
X/R Ratio was determined.
(2 CTs & 1 ST, Total 530 MW)
A7/B1/G2 The short-circuit program was used to determine the three-phase and single-phase
fault duties at the 230 kV bus (Bus No. 7001) at Dickerson, Sta. D and at the
230 kV bus (Bus No. 7002) at Dickerson, Sta. H, when in addition to projects A7
and B1, one 222 MW steam turbine (1 ST) is connected to the 230 kV bus
(Bus No. 7002) at Dickerson, Sta. H.The ANSI X/R Ratio was determined.
(2 CTs & 2 STs, Total 752 MW)
Confidential 44
Station Name: Dickerson, Sta. D
Estimated Breaker
Case Actual Duty ANSI Adjusted Nameplate
Three Phase X/R Duty Rating
(A) Ratio (A) (A)
Existing
Condition 45710.1 21.5 45710
50,000
A7/B1 51527.8 21.0 51530
Estimated Breaker
Case Actual Duty ANSI Adjusted Nameplate
Single Phase X/R Duty Rating
(A) Ratio (A) (A)
Existing
Condition 43583.5 24.2 46200
Confidential 45
Station Name: Dickerson, Sta. H
Estimated Breaker
Case Actual Duty ANSI Adjusted Nameplate
Three Phase X/R Duty Rating
(A) Ratio (A) (A)
Existing
Condition 45747.6 21.2 45750
50,000
A7/B1 51813.3 21.6 51810
Estimated Breaker
Case Actual Duty ANSI Adjusted Nameplate
Single Phase X/R Duty Rating
(A) Ratio (A) (A)
Existing
Condition 43871.6 26.1 47160
Confidential 46