4national Grid Code For Power Transmission
4national Grid Code For Power Transmission
DRAFT
February 2018
CONTENTS
1 PREAMBLE …………………………………………………………………………………………………………………19
1.1 INTRODUCTION ................................................................................................................... 19
1.2 STRUCTURE OF THE ENTGC ................................................................................................... 20
1.2.1 Preamble ........................................................................................................................ 20
1.2.2 Glossary and Definitions.................................................................................................. 20
1.2.3 General Conditions.......................................................................................................... 20
1.2.4 Governance Chapter ....................................................................................................... 20
1.2.5 Planning Chapter ............................................................................................................ 21
1.2.6 Connections Chapter ....................................................................................................... 21
1.2.7 Renewable Power Plant Chapter ..................................................................................... 21
1.2.8 Operations Chapters ....................................................................................................... 21
1.2.8.1 Operational Planning ...................................................................................................... 21
1.2.8.2 Operational Security ....................................................................................................... 22
1.2.8.3 Emergency Operations .................................................................................................... 22
1.2.8.4 Incident Reporting .......................................................................................................... 22
1.2.8.5 Demand Control.............................................................................................................. 22
1.2.8.6 System Tests ................................................................................................................... 23
1.2.9 Interchange Scheduling and Balancing Chapters.............................................................. 23
1.2.9.1 Interchange Scheduling ................................................................................................... 23
1.2.9.2 Balancing and Frequency Control .................................................................................... 23
1.2.9.3 Ancillary Services ............................................................................................................ 24
1.2.10 Ethiopia Metering Chapter .............................................................................................. 24
1.2.11 Interconnection Metering Chapter................................................................................... 25
1.2.12 Data Exchange Chapter................................................................................................... 25
1.2.13 Information Exchange Chapter ........................................................................................ 25
1.2.14 Cyber Security Chapter .................................................................................................... 25
1.2.15 System Operator Training Chapter .................................................................................. 26
1.3 SCOPE OF THE ENTGC .......................................................................................................... 26
2 GLOSSARY AND DEFINITIONS ......................................................................................27
2.1 INTRODUCTION ................................................................................................................... 27
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT ii
Contents
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT iii
Contents
4.6 MEETINGS.......................................................................................................................... 64
4.6.1 Date and Venue .............................................................................................................. 64
4.6.2 Further Meetings ............................................................................................................ 64
4.6.3 Notice of Meetings.......................................................................................................... 64
4.6.3.1 Notice by Chairperson ..................................................................................................... 64
4.6.3.2 Details in Notice.............................................................................................................. 64
4.6.3.3 Failure to Give Notice ...................................................................................................... 64
4.6.3.4 Proposal for Agenda ....................................................................................................... 64
Proceedings at Meetings ................................................................................................. 65
4.6.4 65
4.6.4.1 Quorum .......................................................................................................................... 65
4.6.4.2 Inquorate Meetings ........................................................................................................ 65
4.6.5 Agenda ........................................................................................................................... 65
4.6.6 Validity of Acts ................................................................................................................ 65
4.6.7 Meeting Attendance ....................................................................................................... 65
4.6.8 Minutes .......................................................................................................................... 65
4.6.8.1 Circulation ...................................................................................................................... 65
4.6.8.2 Approval of Minutes........................................................................................................ 65
4.6.8.3 Amendments .................................................................................................................. 66
4.6.9 Guidance from the ENTGCRC........................................................................................... 66
4.6.10 Sub-Committees and Working Groups ............................................................................. 66
4.6.10.1 Sub-Committees.............................................................................................................. 66
4.6.10.2 Working Groups .............................................................................................................. 66
4.6.10.3 Resolutions ..................................................................................................................... 66
4.7 VACATION OF OFFICE ........................................................................................................... 66
4.8 MEMBER’S RESPONSIBILITIES AND PROTECTIONS ........................................................................ 67
4.8.1 Responsibilities ............................................................................................................... 67
4.8.2 Representation ............................................................................................................... 67
4.8.3 Reliance on Documentation ............................................................................................ 67
4.9 REVISIONS TO THE ENTGC .................................................................................................... 67
4.10 ENTGC AUDITS .................................................................................................................. 67
4.10.1 Customer Request ........................................................................................................... 67
4.10.2 Information Requirements .............................................................................................. 68
4.10.3 Withholding of Information ............................................................................................. 68
4.11 CONTRACTING..................................................................................................................... 68
4.12 REGISTRATION OF LICENSEES .................................................................................................. 68
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT iv
Contents
5 PLANNING 77
5.1 EAPP IC REQUIREMENTS ...................................................................................................... 77
5.1.1 Introduction .................................................................................................................... 77
5.1.2 Objectives ....................................................................................................................... 77
5.1.3 Scope.............................................................................................................................. 78
5.1.4 Principles of the Planning Chapter ................................................................................... 78
5.1.5 Reliability Criteria ........................................................................................................... 78
5.1.6 Planning Process ............................................................................................................. 79
5.1.6.1 Power Balance Statement ...............................................................................................79
5.1.6.2 Transmission System Capability Statement......................................................................80
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT v
Contents
5.2.5 Technical Limits and Targets for Long Term Planning Purposes ........................................ 84
5.2.5.1 Voltage Limits and Targets ..............................................................................................85
5.2.5.2 Other Targets for Long-term Planning Purposes ..............................................................86
5.2.5.3 Reliability Criteria for Long-term Planning Process ...........................................................87
5.2.5.4 Contingency Criteria for Long-term Planning Process .......................................................89
6 CONNECTIONS ............................................................................................................94
6.1 EAPP IC REQUIREMENTS ...................................................................................................... 94
6.1.1 Introduction .................................................................................................................... 94
6.1.2 Objective ........................................................................................................................ 94
6.1.3 Scope.............................................................................................................................. 94
6.1.4 Transmission System Performance Characteristics ........................................................... 94
6.1.4.1 Frequency ......................................................................................................................95
6.1.4.2 Voltage...........................................................................................................................95
6.1.4.3 Harmonics ......................................................................................................................98
6.1.4.4 Phase Unbalance ............................................................................................................98
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT vi
Contents
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT vii
Contents
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT viii
Contents
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT ix
Contents
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT x
Contents
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT xi
Contents
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT xii
Contents
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT xiii
Contents
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT xiv
Contents
17.1.13 Customer Query on Metering Integrity and Metering Data ............................................ 208
18 INTERCONNECTION METERING.................................................................................209
18.1 EAPP IC REQUIREMENTS .................................................................................................... 209
18.1.1 Introduction .................................................................................................................. 209
18.1.2 Objectives ..................................................................................................................... 209
18.1.3 Technical Design and Operational Criteria ..................................................................... 209
18.1.3.1 General Technical Criteria ............................................................................................. 210
18.1.4 Metering Information Register ...................................................................................... 210
18.1.5 Main and Check Metering ............................................................................................. 210
18.1.6 Measurement Parameters............................................................................................. 211
18.1.7 Metering Equipment Standards ..................................................................................... 211
18.1.8 Equipment Accuracy and Error Limits ............................................................................ 211
18.1.8.1 Voltage Transformers (VT) ............................................................................................ 211
18.1.8.2 Current Transformers (CT) ............................................................................................. 212
18.1.8.3 Meters .......................................................................................................................... 212
18.1.9 Inspection, Calibration and Testing................................................................................ 212
18.1.9.1 Initial Calibration .......................................................................................................... 212
18.1.9.2 Periodic Calibration and Testing .................................................................................... 213
18.1.10 Data Collection ............................................................................................................. 213
18.1.11 Security......................................................................................................................... 214
18.1.12 Disputes........................................................................................................................ 214
18.1.13 Meter Data Confidentiality............................................................................................ 214
18.1.14 Operational Metering ................................................................................................... 214
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT xv
Contents
20 INFORMATION EXCHANGE........................................................................................219
20.1 INTRODUCTION ................................................................................................................. 219
20.2 INFORMATION EXCHANGE INTERFACE..................................................................................... 219
20.3 SYSTEM PLANNING INFORMATION ......................................................................................... 219
20.4 OPERATIONAL INFORMATION ............................................................................................... 222
20.4.1 Pre-commissioning Studies ............................................................................................ 222
20.4.2 Commissioning and Notification .................................................................................... 222
20.4.3 General Data Acquisition Information Requirements ..................................................... 223
20.4.4 Unit Scheduling ............................................................................................................. 224
20.4.4.1 Schedules...................................................................................................................... 224
20.4.4.2 File Transfers ................................................................................................................ 225
20.4.5 Inter Control Centre Communication ............................................................................. 225
20.4.6 Communication Facilities Requirements ........................................................................ 225
20.4.6.1 Telecontrol.................................................................................................................... 226
20.4.6.2 Telephone/facsimile...................................................................................................... 226
20.4.6.3 Electronic Mail .............................................................................................................. 226
20.4.7 SCADA and Communication Infrastructure at Points of Supply ....................................... 226
20.4.7.1 Access and Security ....................................................................................................... 226
20.4.7.2 Time Standards ............................................................................................................. 227
20.4.7.3 Integrity of Installation.................................................................................................. 227
20.4.8 Data Storage and Archiving........................................................................................... 227
20.5 POST-DISPATCH INFORMATION ............................................................................................. 228
20.5.1 System and Generating Plant Information ..................................................................... 228
20.5.1.1 Additional Unit Post-dispatch Information ..................................................................... 228
20.5.1.2 Hourly Demand Metering Data ..................................................................................... 229
20.5.2 File Transfers ................................................................................................................ 229
20.5.3 Performance Data......................................................................................................... 229
20.5.3.1 Generating Plant Performance Data .............................................................................. 229
20.5.3.2 Distribution Licensee and End-use User Performance ..................................................... 232
20.5.3.3 TSO Performance .......................................................................................................... 233
20.5.3.4 System Operational Performance Information ............................................................... 235
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT xvi
Contents
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT xvii
Contents
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT xviii
1 PREAMBLE
1.1 INTRODUCTION
The Grid Code, comprised of a document or a set of documents, specifies the rules and
responsibilities for all entities related to electrical power system planning and operations. Its
purpose is to legally establish technical and other requirements for the connection to and use of an
electrical power system by parties in a manner that will ensure reliable, efficient, and safe
operation.
Ethiopia has, for the first time in its history, opened up its electricity generation and distribution
sector to private investors. Privately owned power companies can now invest in the electric power
industry and compete with the state owned utility. The Ethiopian power system, however, lacks a
formal Grid Code document that will ensure reliability, safety, and security of the electric power
system operation. This Preamble provides the rationale for the development of an Ethiopia National
Transmission Grid Code (ENTGC) with a summary of provisions. The ENTGC has gone through a
rigorous approval process as required by the appropriate local authorities.
The objective of the ENTGC is to improve the ability to plan and operate Ethiopia’s power system
safely, reliably, efficiently, and economically, in a transparent and non-discriminatory manner, while
multiple independent parties use the power system. The independent parties must operate within a
framework of rules and regulations, and coordinate with each other and the operators of the
electric system, and the ENTGC will provide this. The ENTGC is intended to establish the reciprocal
obligations of Users of the Ethiopia National Transmission System (ENTS) and operation of the East
African Power Pool.
The ENTGC is based partially on the Eastern Africa Power Pool (EAPP) and East African Community
Interconnection Code (EAPP IC). Furthermore, the EAPP IC imposes certain minimum requirements
on the Member Countries of the EAPP. Thus, the EAPP IC plays an important role in the
development of the ENTGC. This ENTGC follows to the extent possible the organisation and
formatting of the EAPP IC.
Other national grid codes were considered and reviewed in addition to the EAPP IC, including the
South African Grid Code (2012), the South African Grid Connection Code for Renewable Power
Plants (2012), the Namibian Grid Code (2005), the Indian Electricity Grid Code (2010), the Zambian
Grid Code (2006), and the Rwanda Grid Code (2012), the Ethiopian Energy Agency (EEA)’s Draft
Interface Codes for Generation/Interconnection/ Distribution, and the Kenyan Grid Code recently
developed and finalized by Nexant (2015).
In addition, The Final Interim Report Module 1B for “EAPP/EAC Regional Power System Master Plan
(PSMP) & Grid Code Study” (2010) was also reviewed for relevant information.
Addressing exclusively wind power, the Australian Energy Market Operator (AEMO) report “Wind
Integration: International Experience WP2: Review of Grid Codes 2nd October 2011” provided a
review of Grid Codes from the United Kingdom, Germany, Denmark, Spain, Texas, Alberta, Hydro
Quebec, Ontario Independent Electricity System Operator (IESO), and the European Network of
Transmission System Operators for Electricity (ENTSO-E). This review was helpful in preparing the
Renewable Power Plant (RPP) Chapter, one of the Chapters in the ENTGC.
1.2.1 Preamble
This Preamble and summarizes the provisions of the ENTGC.
This Preamble is available to all participants and prospective participants in the ENTS for information
only and does not constitute part of the ENTGC.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 20
CHAPTER 1 Preamble
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 21
CHAPTER 1 Preamble
This Chapter also sets out the procedure for the joint investigation of significant incidents and for
the technical audit of the ENTSO and other TSOs procedures and Plant and Apparatus connected to, or
forming part of, the EAPP Interconnected Transmission System.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 22
CHAPTER 1 Preamble
The Ethiopia and other TSOs shall, after taking all other remedial actions, disconnect customer
demand rather than risk an uncontrolled failure of Plant and or Apparatus or cascading Outages of
the EAPP Interconnected Transmission System.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 23
CHAPTER 1 Preamble
ISBC 2 sets out the procedure, which the ENTSO and other TSOs will use to direct frequency control.
The frequency of the EAPP Interconnected Transmission System will be controlled by:
(a) Automatic response from synchronised Generating Units;
(b) The dispatch of Generating Plants including Automatic Generation Control (AGC);
(c) Response from interconnections with External Systems, and
(d) Demand control.
The operation of the ENTS, other National Systems, and the EAPP Interconnected Transmission
System requires the provision by the ENTSO and other TSOs of the following Ancillary Services
grouped into three major categories:
(a) Frequency Control;
(b) Network Control, and
(c) System Restart Capability.
The above Ancillary Services are the traditional mechanisms to provide the required capability in
relation to:
(a) Operating Reserves;
(b) Demand Control;
(c) Voltage Control;
(d) Power flow control;
(e) Stability control, and
(f) Black-Start.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 24
CHAPTER 1 Preamble
These metering systems are subject to the ENTGC, other National Grid Codes or Regulations, and or
Power Purchase Agreements.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 25
CHAPTER 1 Preamble
wireless, cloud computing, etc.), power systems are vulnerable to cyber-attacks and hackers. In
Ethiopia, the growth in the field of information, communication, and technology (ICT) makes it
imperative to develop a sound cyber security strategy that will ensure confidentiality, integrity, and
availability of public and private sector information across Ethiopia’s ICT infrastructure.
Ethiopia has initiated the effort to define its cyber security strategy as demonstrated in its National
Cyber Security Master Plan draft that has been awaiting implementation. The Cyber Security
Chapter addresses: (i) development of information security management controls and procedures;
(ii) cyber security systems with identity; (iii) access management systems; and (iv) building defense
against threats through training, awareness and monitoring.
The ENTGC shall be read in conjunction with the relevant legislation, including the Proclamation
810/2013, all applicable Energy Operation Regulations and any applicable amendments related to
the administrative authority for the ENTGC. These legislative policies shall be used in conjunction
with the Licences issued to Users and the applicable codes and regulations adopted by the
Regulatory Authority and the Ministry of Water and Irrigation and Energy (MOWIE). All Licences
issued after enactment of the ENTGC shall include the obligation of Parties to comply with the
ENTGC requirements.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 26
2 GLOSSARY AND DEFINITIONS
2.1 INTRODUCTION
The Glossary and Definitions Chapter contains a glossary of terms, a list of abbreviations, and units
used in the Ethiopia ENTGC.
2.2 GLOSSARY
Table 2-1 provides a summary of the terms and definitions used in the ENTGC.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 28
CHAPTER 2 Glossary and Definitions
Conductor A material that allows the flow of electrical current in one or more
directions
Confidential Information which is or has been provided under or, in connection
Information with the Ethiopia National Distribution Grid Code and which is stated
under the Ethiopia National Distribution Grid Code or by the Ethiopian
Energy Authority to be confidential information
Connection Physical link to or through a transmission/distribution network that
will allow the supply of electricity between electrical systems
Connection A bilateral agreement made between the Ethiopia National TSO or a
Agreement TNSP and a User setting out the terms and conditions relating to the
use of the Connection Point and other specific provisions in relation to
that connection
Connection Point The physical point at which a User is connected to the Ethiopia Electric
Transmission System
Constraint A limitation on the capability of a network, load or a generator such
that it is unacceptable to either transfer, consume or generate the
level of electrical power that would occur if the limitation was
removed
Consumer A person or entity obtaining services from a Distribution Licensee
Contingency An unexpected incident, failure or Outage of an interconnected
system component, such as a Generating Plant, transmission line,
circuit breaker, switch or other electrical element. A Contingency may
also include multiple components, which are related by situations
leading to simultaneous component Outages
Control Area An area comprised of an electric system or systems, bounded by
interconnection metering, capable of regulating its generation in order
to maintain its interchange schedule with other electric systems or
Control Areas and to contribute its frequency bias obligation to the
Ethiopia Electric Transmission System.
Control Area Operator The Ethiopia System Operator or another TSO responsible for
operating, monitoring, and ensuring interchange scheduling of its
Control Area
Control Center A physical location from which a TSO exercises control over its
transmission area
Current Transformer An instrument transformer which performs the function of supplying
the protective relays and measuring devices with currents of
magnitude proportional to those of power circuit but sufficiently
reduced in magnitude. It also serves the purpose of isolating the
measuring instruments from high voltage circuits
Customer A person obtaining electricity services from a licensee as defined in the
Energy Proclamation 810/2013
Cut-out Wind Speed The wind speed at which a wind turbine shuts down for protection
against damage
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 29
CHAPTER 2 Glossary and Definitions
Data Collection A computer based system that collects or receives data on a routine
System basis from Metering Equipment
Day Day means calendar day wherever referred to in this document
Defined Metering The DMP is and means The physical location at the Interchange Point
Point within a Control Area where overall accuracy requirements are to be
met. Each single circuit interconnection between Control Areas will
have two DMPs, one in each Control Area
Derogation A waiver to suspend a Transmission Licensee or Distribution Licensee’s
obligations to implement or comply with a provision or provisions of
the ENTGC
Disconnection The operation of switching equipment or other action so as to prevent
the flow of electricity at a connection point
Dispatch The process of precisely matching generation with load in real time
Dispatchable (1) A generating plant that can be turned on or off or can be adjusted
Resource upon request , or, (2) A customer participating as a demand side
resource that can comply with the TSO instructions to reduce
electricity usage
Dispute Any difference between the Ethiopian Energy Authority and any
Transmission Licensee or Distribution Licensee or User in connection
with, or arising out of, the interpretation, implementation or breach of
any provision of the ENTGC
Dispute Notice A written notice issued by either Party to a Dispute outlining the
matter of such Dispute
Distribution The supply of electricity services to customers through medium and
low voltage lines as defined in the Energy Proclamation 810/2013
Distribution Licence A license granted by the Ethiopian Energy Authority to distribute and
sell electricity as defined in the “Council of Ministers Regulation to
Provide for the Regulation of Energy Operations”
Distribution Licensee An entity granted a licence by the Ethiopian Energy Authority to
distribute and sell electricity as defined in the “Council of Ministers
Regulation to Provide for the Regulation of Energy Operations”
Distribution System A distribution network, together with the connection assets associated
with the distribution network, which is connected to another
transmission or distribution system
EAPP Coordination Body established under the guidance of the EAPP Sub-Committee on
Centre Operation responsible for the collection of technical and commercial
information
EAPP Independent Board consisting of nominees of national regulatory boards in the
Regulatory Board EAPP countries that is the regulatory body governing the EAPP IC
EAPP Interconnected The transmission system in Eastern Africa consisting of two or more
Transmission System individual National Systems or Control Areas that normally operate in
synchronism and are physically interconnected via transmission
facilities
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 30
CHAPTER 2 Glossary and Definitions
EAPP Sub-committee EAPP body under the direction of EAPP Steering Committee
on Planning responsible for the coordination of Master Plans and development
programs of EAPP Member utilities
Eastern Africa Power Eastern Africa Power Pool (EAPP) is a regional intergovernmental body
Pool based in Addis Ababa, Ethiopia. Its mission is the pooling of electrical
energy resources in a coordinated and optimized manner to provide
an affordable, sustainable and reliable electricity in the region
Eastern Africa Power The Interconnection Code that sets down the technical rules for the
Pool Interconnection coordinated planning and operation of the EAPP.
Code
Electrical Energy Energy involving the use of electric current which may be produced
either by mechanical, chemical, hydroelectric, wind, photovoltaic or
any other sources as defined in the Energy Proclamation 810/2013.
Electrical Installation Any electrical equipment that is fixed (or to be fixed) in, on, under or
over a Customer's premises.
Electrical Plant Any plant, equipment, apparatus or appliance (other than electrical
supply line, meter, or electrical appliance belonging to a customer)
used for, or for purposes connected with the import, export,
generation, transmission, distribution and supply of electricity.
Electrical Work Work of electrical design, installation, maintenance, testing,
inspection, contracting, or consultancy, electro mechanical activity or
any other electric related business as per the Energy Proclamation
810/2013
End-use User A Customer of the ENTS that contracts for purchase of electrical
energy for his/her own use, not for delivery or supply to another
person
Energy Audit A systematic procedure: (a) to obtain adequate knowledge of the
existing energy consumption profile of a customer; (b) to identify and
quantify cost effective energy saving opportunities; and (c) to report
the findings as defined in the Energy Proclamation 810/2013.
Energy Conservation Reduction in the amount of energy consumed in a process or system
through elimination of waste and economical rational use as defined
in the Energy Proclamation 810/2013
Energy Efficiency Ability to provide the same or higher level of products or services at
lower level of energy consumption as defined in the Energy
Proclamation 810/2013
Ethiopia National Specifies technical requirements for connection to, and use of, the
Transmission Grid National Electricity Transmission System
Code
Ethiopia National The Committee established in accordance with section 4.5.1 of
Transmission Chapter 4 (Governance) and charged with the review of the operation,
Grid Code and revision of the Ethiopia Grid Code. The Ethiopia Electric
Review Committee Transmission Grid Code Review Committee shall be governed by the
Constitution and Rules set out in Section 4.5.of the ENTGC
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 31
CHAPTER 2 Glossary and Definitions
Ethiopia National The electricity transmission system of Ethiopia including all Users
Transmission System connected to that system
Ethiopia National The Committee established in accordance with Chapter 4
Transmission System (Governance) of the Ethiopia National Transmission Grid Code and
Operator charged with providing recommendations to the Ethiopian Energy
Authority on the review and revision of the ENTGC. The Ethiopia
National Transmission Grid Code Review Committee shall be governed
by the provisions set out in Section 4.5 of the ENTGC
Expected Un- The expected amount of energy that cannot supplied by the power
served Energy generating system during the period of observation, due to capacity
deficiency
External System Any electric system outside EAPP that interconnects to the EAPP
Interconnected Transmission System
Fiscal Year Ethiopian fiscal year that starts on July 8th of a year and ends on July
7th of the following year
Force Majeure Causes beyond the reasonable control of and without the fault or
negligence of the Party claiming Force Majeure. It shall include failure
or interruption of the delivery of electric power due to causes beyond
that Party’s control, including Acts of God, wars, sabotage, riots,
hurricanes and other actions of the elements, civil disturbances and
strikes as set out in Section 3.7 of Chapter 3 (General Condition)
Forced Outage Factor Percentage of forced withdrawal of generating plant/unit for service for
upgrade, maintenance and associated reasons from the total capacity
Generating Plant A facility for the generation of electric power comprised of one or
more generating units which are likely to be individually controllable
Generating Unit A specific unit within a Generating Plant that generates electric power
from other sources of energy
Generation License A licence authorising an entity to generate electrical energy
Generation Licensee An entity licensed to operate and maintain generation assets and
generate electricity within the Ethiopia National Transmission System
Generator A device that converts mechanical energy to electrical energy for use
in an external circuit
Governor Automatic control system which maintains the desired system
frequency by adjusting the mechanical power output of the turbine of
a Generating Plant
Grid The network of transmission and distribution systems and connection
points for the movement and supply of electrical energy from
Generating Plants to Customers
Grid Code Revision A Register of all revisions to the Ethiopia Grid Code as set out in
Register Section 4.10.4 of Chapter 4 (Governance)
High Voltage A voltage level above 33,000 volts in accordance with Proclamation
810/2013
Inadvertent Deviation Difference between net actual energy flow and net scheduled energy
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 32
CHAPTER 2 Glossary and Definitions
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 33
CHAPTER 2 Glossary and Definitions
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 34
CHAPTER 2 Glossary and Definitions
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 35
CHAPTER 2 Glossary and Definitions
Reactive Power Instantaneous power derived from the product of voltage and current
and the sine of the voltage- current phase angle, which is measured in
units of var and multiples thereof
Reactive Power Maximum rate at which reactive energy may be transferred from a
Capability Generating Plant to a Connection Point as specified in the connection
agreement
Regional Control A control centre responsible for the operation of the Distribution
Center Network
Regulatory Authority Ethiopian Energy Authority established by the Proclamation 810/2013
and the Council of Ministers Regulation No. 308/2014 replacing
Ethiopian Energy Agency to issue licenses for generation, transmission
and distribution, sale, and import/export of electric energy in Ethiopia
Remaining Capacity The difference between available generating capacity and demand at
the reference dates and calculated under normal climatic conditions
as stated in Chapter 5 (Planning)
Remedial Action Also referred to as Special Protection System, RAS means a protection
Scheme (RAS) system that automatically initiates one or more control actions
following electrical disturbances. Typical examples include tripping
Generating Plants or loads and switching of series capacitors, shunt
capacitors, or shunt reactors
Renewable Power A Generating Plant whose primary energy source is a form of
Plant (RPP) renewable energy, including but not limited to solar energy (for
photovoltaic and concentrated solar plants), small hydro, geothermal,
landfill gas, biomass, biogas, and wind, and whose generation output
is variable in nature
Reserve A measure of available capacity over and above the capacity needed
to meet normal peak demand levels. In case of a Generating Plant, it is
the capacity to generate more or less energy than the system normally
requires. For a transmission company, it is the capacity to handle
additional energy transport if demand levels rise beyond expected
peak levels
Reserve, Regulating A generation reserve that is under central AGC and can respond within
ten seconds and be fully active within ten minutes of activation. This
reserve is used for second-by-second balancing of supply and demand.
This reserve is also used to restore instantaneous reserve within ten
minutes of the disturbance. The provision of Regulating Reserves is a
Secondary Response. Regulation reserve can be up or down
Reserve, Responsive An ancillary service provided by on line generation resources that can
respond to frequency deviations caused by a generating unit trip
Reserve, Spinning Extra generating capacity that is available by increasing the power
output of Generating Plants that are already connected to the power
system. Spinning reserve is generally used for containing the
frequency at acceptable limits following a contingency, such as a unit
trip or a sudden surge in load
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 36
CHAPTER 2 Glossary and Definitions
Reserve, Non-spin Off-line generation capacity that can be ramped to capacity and
synchronized to the grid within a pre-specified time (typically 10 to 30
minutes) of a dispatch instruction by the TSO, and that is capable of
maintaining that output for at least for two hours
Response The provision of a reserve
Response, Primary Refer to Primary Response
Secondary Response Refer to Secondary Response
Rota Disconnection A planned and properly authorised temporary disconnection of
electricity to Customers for a set duration on a rotational basis at
times of a severe shortfall in electricity production
RSA ID RSA ID is a two-factor authentication technology that is used to
protect network resources. The two factors typically are: (i) a
password or PIN; and (ii) an authenticator, could be a hardware token
(such as a USB token, smart card or key fob). The software token is the
RSA Authentication Manager Software that provides the security
engine used to verify authentication requests
System Average SAIDI indicates average minutes of service interruption per customer.
Interruption Duration It is the sum total of customer minutes interrupted divided by the
Index total number of customers served. SAIDI is considered as one of the
best indicators of system stress
System Average The sum total of number of interruptions divided by the total number
Interruption of customers
Frequency Index
Secondary Response Secondary Response is the automatic response to a frequency change
which is fully available by thirty (30) seconds from the time of
frequency change to take over from Primary Response, and which is
sustainable for a period of at least thirty (30) minutes. Secondary
Response is provided by Generating Plants already synchronised to the
ENTS and is normally controlled by the Ethiopia National TSO by AGC
Secretary, Ethiopia The person appointed by the Ethiopian Energy Authority to the
National Transmission Ethiopian National Grid Code Review Committee and named as such
Grid Code Review
Committee
Significant Incident An event which has caused or could have caused injury to persons,
damage to system equipment or operation of the Ethiopia Electric
Transmission System outside the operational security standards
Solar Power A Generating Plant deriving its source of energy from the sun and for
Generating Plant which its generation is variable in nature)
Special Protection Refer to Remedial Action Scheme
Scheme
Steering Committee The body established by EAPP in accordance with the Inter-Government
Memorandum of Understanding and responsible for the Governance of
EAPP
Sub-committee on EAPP body under the direction of EAPP Steering Committee
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 37
CHAPTER 2 Glossary and Definitions
Total Shutdown The situation existing when all generation has ceased within the
Ethiopia Electric Transmission System and there is no supply from
External Systems and, therefore, the Ethiopia Electric Transmission
System has shutdown.
Transmission The operation, management or control of facilities, consisting of high
voltage electric supply lines for movement of electrical energy in bulk
between Generating Plants and transmission substations for the
purposes of enabling supply to Customer.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 38
CHAPTER 2 Glossary and Definitions
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 39
CHAPTER 2 Glossary and Definitions
Works (a) electric supply lines, machinery, lands, buildings, structures, earth
works and water works, and includes any apparatus or things of
whatsoever description, required for the importation, exportation,
generation, transmission, distribution supply and use of electrical
energy; or (b) pipelines, machinery, lands, buildings, structures, earth
works and water works, and includes any apparatus or things of
whatsoever description, required for the importation, exportation,
storage, refining, transportation, dispensing and supply of petroleum;
or (c) machinery, lands, buildings, structures, earth works and water
works, and includes any apparatus or things of whatsoever
description, required for the importation, exportation, storage,
production, transportation, distribution and supply of any other
energy form
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 40
CHAPTER 2 Glossary and Definitions
Abbreviation Description
AC Alternating Current
ACE Area Control Error
AS Ancillary Services
AVR Automatic Voltage Regulator
CC Connections Chapter
CDs Compact Disks
CD Compact Disc
CT Current Transformer
DC Direct Current
DCF Discounted Cash Flow
DR Demand Response
DTE Data Terminal Equipment
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 41
CHAPTER 2 Glossary and Definitions
GC General Conditions
GCR Grid Code Requirement
HV High Voltage
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 42
CHAPTER 2 Glossary and Definitions
PC Planning Chapter
PCC Point of Common Coupling
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 43
CHAPTER 2 Glossary and Definitions
UM Voltage Maximum
UN Voltage Nominal
VT Voltage Transformer
WAN Wide Area Network
Symbol Unit
Amp Ampere
GW Gigawatt (1,000,000,000 W)
GWh Gigawatt-hour
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 44
CHAPTER 2 Glossary and Definitions
Hz Hertz
Kbps Kilobits per second
kV Kilovolt
kVA Kilovolt-ampere
kvar Kilovars
kW Kilowatt
kWh Kilowatt-hour
Mbps Megabits per second
MW Megawatt
MWh Megawatt-hour
s, sec Second
TW Terawatt (1,000,000,000,000 W)
V Volt
W Watt
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 45
3 GENERAL CONDITIONS
3.1 INTRODUCTION
The General Conditions (GC) set out the over-riding principles to be used in the operation of the
ENTS and form the basis for the decisions of a reasonable and prudent operator should specific
events not be covered by the relevant code. The GC describes the provisions necessary for the
overall administration and review of the various aspects of the ENTGC. The GC also deal with those
aspects of ENTGC not covered in other Chapters, including the resolution of Disputes, bilateral
agreements, confidentiality, non-compliance and the revision of the ENTGC through the ENTGCRC.
3.2 SCOPE
These General Conditions apply to the Regulatory Authority, ENTSO, Transmission Licensees,
Distribution Licensees, and Users of the ENTS.
3.3 OBJECTIVE
The Generation Conditions contain provisions, which are of a general nature and apply to all
Chapters of the ENTGC. The objectives of the GC are to ensure, to the extent possible, that the
various Chapters of the ENTGC work together and work in practice for the benefit of the ENTSO,
Transmission Licensees, Distribution Licensees, and Users.
For the above purposes, the Regulatory Authority may, in certain cases, need access to services and
facilities of Users or Transmission Licensees and Distribution Licensees, or to issue instructions to
Users or Transmission Licensees and Distribution Licensees to implement and enforce the ENTGC.
Accordingly, all Users and Transmission Licensees and Distribution Licensees are required not only to
abide by the letter and spirit of the ENTGC, but also to provide the Regulatory Authority with such
rights of access, services and facilities and to comply with any instructions of the Regulatory
Authority.
Each Party shall, at all times, in its dealings with other Parties to the ENTGC act in good faith and in
accordance with Prudent Utility Practice.
Each User and Transmission Licensee or Distribution Licensee shall comply with all instructions given
to it by the Regulatory Authority following such a determination provided the instructions are
consistent with the then current technical parameters of the Transmission Licensee or Distribution
Licensee’s National System. The Regulatory Authority shall, as soon as reasonably practicable
following the unforeseen circumstances, notify all relevant details to the ENTGCRC for consideration
and recommendations in accordance with Chapter 4 (Governance).
Neither Party shall be held to have defaulted in respect of any obligation under the ENTGC if
prevented or delayed from performing that obligation, in whole or in part, because of a Force
Majeure event. If a Force Majeure event prevents or delays a Party from performing any of its
obligations under the ENTGC, that Party shall:
(a) Promptly notify any other Party involved, the Regulatory Authority of the Force Majeure event
and its assessment in good faith of the nature and the effect that the event will have on its
ability to perform any of its obligations and the measures that the Party proposes to take to
alleviate the impact of the Force Majeure event. If the immediate notice is not in writing, it
shall be confirmed in writing as soon as reasonably practicable. The notice shall be posted
on the ENTSO Website
(b) Not be entitled to suspend performance of any of its obligations under the ENTGC to any
greater extent or for any longer time than the Force Majeure event requires it to do
(c) Use its best efforts to mitigate the effects of the Force Majeure event, remedy its inability to
perform, and resume full performance of its obligations
(d) Keep the other Party continually informed of its efforts, and
(e) Provide written notice to the other Party when it resumes performance of any obligations
affected by the Force Majeure event. The notice shall be published on the ENTSO Website
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 47
CHAPTER 3 General Conditions
3.8 COMPLIANCE
(a) All parties shall comply with the ENTGC as updated via Regulatory Authority decisions from
time to time.
(b) Certification of safety compliance by a licensed electrical inspector shall be a pre-requisite
for energizing an electrical installation from the supply line of the licensee
(c) Participants shall inform the Regulatory Authority of any non-compliance report of a
material nature that has been submitted to another participant without delay, but no later
than 30 days after becoming aware of the item unless there is significant risk to the ENTS,
which then must be reported immediately
(d) Failure to comply with the requirements, conditions, or obligations of Certificate of
Competency as stated in Proclamation 810/2013 is punishable with simple imprisonment of
up to three years, or with a fine not more than Birr 15,000 or with both
(e) The Regulatory Authority may require a participant to provide the Regulatory Authority with
information that it deems necessary for the proper administration of the ENTGC. This
information shall be treated as confidential
(f) Upon a report or suspicion of non-compliance the Regulatory Authority may seek to resolve
the issue through negotiation
3.9 NON-COMPLIANCE
If a Transmission Licensee or TNSP or User finds that it is, or will be unable to comply with any
provision of this ENTGC, then that party shall without delay, but not later than 30 days after
discovery, report such non-compliance to the Regulatory Authority.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 48
CHAPTER 3 General Conditions
(c) Failure to implement in time the procedures and information systems required in the ENTGC
established in this Performance Standard.
(d) Failure or unsuitable delays in the execution of the approved remedial actions and plans to
comply with ENTGC provisions following the approval of a Derogation and mitigation plan
3.9.2 Penalties
If the Regulatory Authority determines that the User is in a non-compliance situation for which
Derogation has not been filed, or is in the process of being filed, or for which a Derogation has not
been approved by the Regulatory Authority, or is in violation of the terms of an approved
Derogation, the Regulatory Authoritywill determine and apply a fine penalty for the non-compliance
situation. The Regulatory Authority shall also consider that the Transmission Licensee is in non-
compliance with its licence conditions, and may suspend or revoke the licence. The Regulatory
Authority shall use directives under Item No. 144 (Fine Penalty) under the “Final English Draft Energy
Operation Regulation – Version (2)”, as appropriate, while issuing a fine penalty.
Generation, transmission, distribution, sales, import, export of electricity for commercial purposes;
performing electrical work, energy audit, Energy Efficiency and Energy Conservation contracting or
consultancy service without valid license are punishable as per the Energy Proclamation 810/2013.
The Regulatory Authority shall also consider the following factors while imposing penalties:
(a) Severity of the non-compliance and any environmental, health, and safety impacts
(b) Instances of repeated and deliberate non-compliance
(c) Penalties shall be comparable to those specified in other laws, regulations, and applicable
contracts
(d) Penalties shall be set at a level such that non-compliance will not be economically
preferable to compliance
3.10 DEROGATION
The Regulatory Authority may issue Derogations suspending a Transmission Licensee’s or
Distribution Licensee’s or a User’s obligations to implement or comply with the ENTGC to such an
extent as may be specified in the Derogations.
If a User finds that it is, or will be, unable to comply with any provision of the ENTGC, then they shall,
without delay, report such non-compliance to the Regulatory Authority. The applicant may request
an exemption from the ENTGC requirement, or request additional time to correct the non-
compliance item.
A Party seeking Derogations from any provision in the ENTGC shall make a written request to the
Regulatory Authority containing the following information. Refer also to the sample Request for
Derogation form in Appendix A.
(a) Name of the Party applying for Derogation
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 49
CHAPTER 3 General Conditions
(b) Contact information, name and signature of CEO or other corporate officer delegated by the
CEO
(c) The specific provision of ENTGC (section number and title) against which the present or
predicted non-compliance is identified
(d) The reason for non-compliance
(e) The nature and extent of the non-compliance
(f) The date of non-compliance discovery and reporting of the non-compliance
(g) Identification and description of the system, facility, equipment, process, procedure or
specific connection point in respect of which Derogation is sought
(h) Whether the Derogation sought is permanent exemption or for a delay in achieving
compliance, and If a delay in achieving compliance is being sought, the date by which the
non-compliance will be remedied
(i) A description of any health and safety implications and the associated risk management
measures
(j) A description of the proposal for restoring compliance (where applicable) including details
of actions to:
1. Mitigate risks to customers or other authorized electricity operators
2. Restore compliance (including timetable of works)
(k) A description of the reasonable alternative actions that have been considered
(l) A statement of the expected duration of the non-compliance
(The User is required to justify the Derogation request in terms of both the specific circumstances and
the expected duration. Licensees are advised to give as much notice as possible when making
Derogation requests since Derogation will not be granted unless the Regulatory Authority is satisfied
that the request is justified.)
The Regulatory Authority may initiate at its own initiative a review of any existing Derogations, and
any Derogations under consideration where a relevant and material change in circumstance has
occurred.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 50
CHAPTER 3 General Conditions
The Regulatory Authority may also seek the views and advice of an Independent Expert on the
proposed Derogation, as set out in section 3.11 in this chapter.
It may be the case that not all Plant and Apparatus in use as at the date of adoption of this ENTGC
will be able to meet the requirements of the ENTGC. In some cases, it may not be economically or
technically necessary to upgrade such existing Plant and Apparatus to the required ENTGC
standards. Where this is the case the Regulatory Authority will give consideration to a time bound
Derogation for all or part of the ENTS.
In the event that Derogation is granted, the Transmission Licensee or Distribution Licensee or User
shall take all necessary action to ensure full compliance with the obligation for which the Derogation
has been granted.
Where a material change in circumstances has occurred, a review of any existing Derogation and
any Derogation under consideration may be initiated by the Regulatory Authority.
Upon request from any Transmission Licensee or Distribution Licensee or User, the Regulatory
Authority shall provide a copy of such register of Derogations to such Transmission Licensee or
Distribution Licensee or User.
Transitional Provisions are provisions of the ENTGC approved by the Regulatory Authority that shall
not apply either in whole or in part to some or all Users. They differ from Derogation in that:
(a) The effective date of the ENTGC and its impact on requirements, such as multiple old
Generating Plants that need equipment upgrade in order to reach compliance
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 51
CHAPTER 3 General Conditions
Dispute resolution may include a request to the Regulatory Authority to refer the matter to the
ENTGCRC to consider the disputed ENTGC provisions and offer recommendations on resolution of
the Dispute.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 52
CHAPTER 3 General Conditions
The determination by the Regulatory Authority shall be legally binding on all Parties.
Determinations by the Regulatory Authority are subject to appeal before the Energy Tribunal as
provided under the “COUNCIL OF MINISTERS REGULATION TO PROVIDE FOR THE REGULATION OF
ENERGY OPERATIONS”.
The Independent Expert shall not act as an arbitrator. Provisions of any arbitration legislation shall
not apply and the Regulatory Authority will undertake to treat his determination as binding and
conclusive upon them.
The Independent Expert shall determine the procedure to be followed for preparing an opinion. The
venue for the Independent Expert’s inquiries will be agreed between the Parties to the matter under
consideration. Modern technologies such as videoconferencing may be used to ensure that the
process is as cost efficient and equitable as possible.
The Independent Expert must within fifteen (15) business days of his appointment accept
submissions from the Parties in Dispute and must state his determination of those matters within
sixty (60) business days of his appointment.
Responsibility for the entire cost of the Independent Expert shall be:
(a) In the case of referral pursuant to section 3.9.4 in this chapter, the Party or Parties seeking
revision of the ENTGC shall equally divide the entire cost
(b) In the case of referral pursuant to section 3.10.2 in this chapter, the Party or Parties seeking
Derogation pursuant to section 3.10.1 in this chapter shall equally divide the entire cost
(c) In the case of referral pursuant to section 3.11 in this chapter, the disputing Parties shall
equally divide the entire cost
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 53
CHAPTER 3 General Conditions
3.14 HIERARCHY
In the event of any conflict between the provisions of the ENTGC and any contract, bilateral
agreement or arrangement between a Transmission Licensee, Distribution Licensee, or a User, the
provisions of the ENTGC shall prevail unless the ENTGC expressly provides otherwise.
3.15 CONFIDENTIALITY
All data exchanged relating to connection to, planning, operation and maintenance of the ENTS shall
be treated by all Parties as confidential.
All data relating to and exchanged among Parties concerning the ENTS shall be considered to be
Confidential Information. The Regulatory Authority shall consult with the ENTSO and Users concerning
the publication of any of the data exchanged. Aggregate data may be made available by the ENTSO,
when requested by a User. These data shall be used only for the purpose specified in the request
and shall be treated by the User as confidential. All such disclosure of Confidential Information shall be
subject to a written Confidentiality Agreement duly signed by the ENTSO and User. Such Confidential
Information shall not be disclosed to other parties without the express written consent of the
parties to the Confidentiality Agreement.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 54
CHAPTER 3 General Conditions
3.15.2 Exceptions
This Section does not prevent:
(a) The disclosure, use or reproduction of information if the relevant information is at the time
generally and publicly available other than as a result of breach of confidence by the Party
who wishes to disclose, use or reproduce the information or any person to whom the Party
has disclosed the information
(b) The disclosure, use or reproduction of information to the extent required by law or by a
lawful requirement of:
1. Any government or governmental body, authority or agency having jurisdiction over
a Party or his related bodies corporate; or
(c) The disclosure, use, or reproduction of information if required in connection with legal
proceedings
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 55
CHAPTER 3 General Conditions
3.16.3 Definitions
(a) Terms and expressions printed in italics are listed in the Glossary and Definitions Chapter
and shall, unless the context otherwise requires or is not consistent therewith, bear the
respective meaning set out therein
(b) Terms not herein defined shall have the meaning ascribed thereto in the Oxford English
Dictionary.
(c) Where the Glossary and Definitions refers to any word or term which is more particularly
defined in a part of the ENTGC, the definition in that part of the ENTGC will prevail over the
definition in the Glossary and Definitions in the event of any inconsistency
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 56
CHAPTER 3 General Conditions
3.16.4 Figures
Figures are provided in some Chapters of the ENTGC for convenience and to illustrate a process. In
case of any discrepancy between the text and figures regarding any provision of the ENTGC, the text
shall prevail.
3.16.9 References
References to clauses, provisions or to a particular paragraph, sub-paragraph, or Appendix are,
unless the context otherwise requires, references to that clause, provision, paragraph, sub-
paragraph, or Appendix in or to that part of the ENTGC in which the reference is made.
3.17 LANGUAGE
This ENTGC is written in English. In case of any discrepancies between the English version and a version
translated into any other language, the English version shall prevail.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 57
4 GOVERNANCE
This ENTGC shall be read in conjunction with the relevant legislation including the Proclamation
810/2013 and any applicable amendments related to the administrative authority for the ENTGC.
The ENTGC requirements shall also be applied in conjunction with the licences issued to Generation
Licensees, Transmission companies, TNSPs, and regulations that relate to the ENTS adopted by the
Regulatory Authority and the MOWIE. All Transmission Licences and agreements concluded after
implementation of the ENDGC shall include the obligation of parties to comply with ENTGC
requirements.
This chapter also describes the methodology that will be used to:
a. Ensure that Users are represented in reviewing and making recommendations to the
development and revision of the ENTGC requirements
The functions of the Regulatory Authority under the Proclamation include but are not limited to
issuing competency certification in the areas of inspection, maintenance, testing, design,
consultancy, contracting and electro mechanical activities together with electrical installation work.
The Regulatory Authority functions also include establishing regional regulation framework guiding
the operational arrangements, and practices of electrical works in power generation, transmission,
interconnection, and distribution with well- defined structure that addresses roles and
responsibilities of relevant stakeholders.
The organisations with governance functions include the Regulatory Authority, and the MOWIE,
which oversees the activities of the Regulatory Authority.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 59
CHAPTER 4 Governance
(f) One person representing public Generation Licensees and one person representing private
Generation Licensee
In the case that any of the above categories include more than one entity, the constituents shall
form a caucus and appoint a representative. All appointments are subject to approval by the
Regulatory Authority with regard to required minimum qualifications for Members provided in
Section 4.3.5.
If the ENTGCRC is unable to reach unanimous or consensus agreement on any matter presented
before it, it shall report the cause of disagreement and the views held by the respective Members of
the ENTGCRC to the Regulatory Authority.
4.3.5.1 Chairperson
(a) Minimum of ten (10) years of electric industry experience in a technical capacity
(b) Minimum of seven (7) years of energy sector regulatory compliance oversight experience
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 60
CHAPTER 4 Governance
The Regulatory Authority has the right to modify the term of office during the initial formation of
the ENTGCRC to assure that incumbent member’s terms do not expire at the same time. This will
assure that the Committee has a consistent mix of incumbents and new Members.
Such notifications for re-appointment or appointment must be delivered to the Chairperson at least
twenty one (21) days in advance of the meeting of the ENTGCRC from the person or group of
persons represented by each Member.
4.3.10 Alternates
Each entity shall have the power to appoint any individual to be an Alternate to the Member, and
may at its discretion, remove an alternate Member so appointed. An entity shall not appoint
another Member as an Alternate. Any appointment or removal of an alternate Member shall, unless
the Chairperson otherwise agrees, be effected by notice in writing executed by the appointer and
delivered to the Secretary or tendered at a meeting of the ENTGCRC. If his appointer so requests, an
alternate Member shall be entitled to receive notice of all meetings of the ENTGCRC or of sub-
committees or working groups of which his appointer is a Member. He shall also be entitled to
attend and vote as a Member at any such meeting at which the Member appointing him is not
personally present and at the meeting to exercise and discharge all the functions, powers and duties
of his appointer as a Member. For the purpose of the proceedings at such meetings, the provisions
of this Constitution shall apply as if the alternate appointed were a Member. An alternate shall have
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 61
CHAPTER 4 Governance
4.3.13.2 Voting
The ENTGCRC will seek to achieve a unanimous consensus agreement among all voting Members.
If the Committee is unable to reach unanimous consensus on an item, a simple majority voting
method will be used. If there is a tie after voting, the Chairperson will be allowed to cast a tie-
breaking vote. Otherwise, the Chairperson shall not cast a vote.
4.3.14 Removal
Any person or persons entitled to appoint a Member, including the Chairperson, may at any time
replace that Member or the Chairperson, as the case may be, from office and appoint another
person in his place. A person or persons will only have the right to remove from the Committee the
person that it or they have appointed, and will have no right to remove from office the Chairperson
or any other Member, as the case may be, appointed by another person. In the event of
disagreement amongst persons entitled to appoint a Member, the relevant provisions of 4.3.7
“Appointment by the Regulatory Authority” shall apply with any necessary changes. Whenever any
individual Member or the Chairperson changes, the person or group of persons entitled to appoint
that Member or the Chairperson, shall notify the Secretary in writing within seven (7) days of the
change taking effect.
4.4.1 Appointment/Removal
The Regulatory Authority may, at any time replace the Chairperson. Upon retirement or
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 62
CHAPTER 4 Governance
replacement by the Regulatory Authority of the first and each successive Chairperson, the
Regulatory Authority shall appoint a person to act as Chairperson.
4.5.2 Duties
The Secretary’s duties shall be to attend to the day-to-day operation of the ENTGCRC and, in
particular, to:
(a) Attend to the requisition of meetings and to serve all requisite notices;
(b) Maintain a register of names and addresses of Members and their alternates as appointed
from time to time; and
(c) Keep minutes of all meetings.
4.5.3 Registers
The Secretary shall make available the registers of names and addresses and minutes for inspection
by the Regulatory Authority, Members, and Member Transmission and Transmission Licensees.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 63
CHAPTER 4 Governance
4.6 MEETINGS
4.6.1 Date and Venue
The ENTGCRC shall hold meetings quarterly at regular scheduled times as the Committee may
decide.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 64
CHAPTER 4 Governance
4.6.5 Agenda
Only matters identified in the agenda shall be resolved upon at a meeting. However, this shall not
prevent matters raised under the heading “Any Other Business” from being discussed, and if the
Chairperson thinks fit, be resolved.
4.6.8 Minutes
4.6.8.1 Circulation
The Secretary shall circulate copies of the minutes of each meeting of the ENTGCRC to each Member
as soon as practicable and in any event within ten (10) business days after the meeting has been
held.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 65
CHAPTER 4 Governance
4.6.8.3 Amendments
If the Secretary receives any comments on the minutes, he shall then include those aspects of the
minutes upon which there is disagreement into the agenda for the next following meeting of the
ENTGCRC as the first item for resolution.
4.6.10.3 Resolutions
Resolutions of sub-committees and working groups shall not have binding effect unless approved by
resolution of the ENTGCRC.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 66
CHAPTER 4 Governance
4.8.2 Representation
In the exercise of its powers and the performance of its duties and responsibilities as a
Member, a Member shall represent the interests of the institution or entity by whom he
was appointed, provided that such obligation of representation shall at all times be
subordinate to the obligations of the Member as a Member of the ENTGCRC.
The Regulatory Authority shall, as required, prepare and issue amended versions of the ENTGC
containing such revisions, as have been approved by the Regulatory Authority. All revisions to the
ENTGC shall be recorded in the ENTGCRR, which shall indicate the date, Chapter amended and the
reason for the change. An up to date ENTGC including all approved revisions shall be published on
the Regulatory Authority website along with the ENTGC Revision Register. The revised version of the
ENTGC shall take effect from the date on which it is published on the Regulatory Authority website,
or such other later date as specified by the Regulatory Authority.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 67
CHAPTER 4 Governance
requesting participant may not request such information in relation to a particular section of the
ENTGC within six (6) months of a previous request made under this Section in relation to the relevant
Section.
4.11 CONTRACTING
The ENTGC shall comprise one of the standard documents that form part of the contract between
TNSP and each of their customers. TNSP shall contract with customers for any services specified in
the ENTGC.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 68
CHAPTER 4 Governance
A User who no longer holds a license from the Regulatory Authority shall be removed from the
register of licensees.
4.13 NOTICES
4.13.1 Service of Notices under the ENTGC
A notice is properly given under the ENTGC to a person if:
(a) It is personally served; or
(b) A letter containing the notice is prepaid and posted to the person at an address (if any)
supplied by the person to the sender for service of notices or, where the person is a User, an
address shown for that person in the register of Users to whom licenses have been issued
under Proclamation 810/2013 maintained by the Regulatory Authority or, where the
addressee is the Regulatory Authority, the registered office of the Regulatory Authority or
(c) It is sent to the person by facsimile or electronic mail to a number or reference which
corresponds with the address referred to in Section 4.14.1(b) in this chapter or which is
supplied by the person to the Regulatory Authority for service of notices; or
(d) It is published in a newspaper with wide circulation in the area where the person is resident
or in a daily newspaper circulated generally
(e) It is communicated verbally to the person and that communication is recorded or thereafter
confirmed in writing; or
(f) The person receives the notice
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 69
CHAPTER 4 Governance
(h) In all other cases, on the day when the notice is recorded as having been first received at
the electronic mail destination, if a business day or if that time is after 16h00 Hr
(addressee’s time), or the day is not a business day, at 9h00 Hr on the following business
day; or
(i) Where published in a newspaper in accordance with Section 4.13.1(d), on the next day after
the date of publication of the notice
(j) In any other case, when the person actually receives the notice
4.14 ENFORCEMENT
4.14.1 Investigations
(a) A User shall, if requested by the Regulatory Authority, supply it with information relating to
any matter concerning the ENTGC in such form, covering such matters and within such
reasonable time as the Regulatory Authority may request
(b) If a User fails to comply with a request by the Regulatory Authority for information as
described in Section 4.15.1(a) in this chapter, the Regulatory Authority may appoint a
person to investigate the matter and to prepare a report or such other documentation as
the Regulatory Authority may require. A User shall assist the person to undertake the
investigation and to prepare the report or other documentation. In addition, a User shall, at
the request of the person appointed, direct third parties to make available such information
as the person may reasonably require
(c) The cost of the investigation and of preparing the report or other documentation prepared
by the person appointed shall be met by the User directed to supply the information under
Section 4.15.1(a) in this chapter unless the Regulatory Authority otherwise determines
(d) Any report or other documentation referred to in this Section 4.14.1 in this chapter may be
used in any proceeding involving the Regulatory Authority under the Act or for the purpose
of commencing any such proceeding
(e) The Regulatory Authority shall develop and implement guidelines in accordance with the
ENTGC consultation procedures governing the exercise of the powers conferred on it by this
Section 4.14.1.
(f) The guidelines referred to in Section 4.14.1(e) in this chapter shall set out the circumstances
that a User will be required to bear the cost of providing the information sought by the
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 70
CHAPTER 4 Governance
Regulatory Authority under this Section 4.14.1, including where no breach of the ENTGC by
the relevant User has occurred
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 71
CHAPTER 4 Governance
4.14.5 Sanctions
The nature of sanctions that may be imposed under the ENTGC and the circumstances, in which a
User or the Regulatory Authority may implement any sanction that has been imposed, shall be set
out in regulations approved or issued by the Regulatory Authority.
4.14.8 Publications
(a) The Regulatory Authority shall publish a report at least once every six (6) months setting
out a summary for the period covered by the report of:
1. Matters which have been referred to it
2. All its findings during that period; and
3. Any sanctions it applied under the Proclamation 810/2013
(b) In considering the circulation of a report under Section 4.14.8(a), the Regulatory Authority
shall have regard to ENTGC objectives
(c) In addition to the regular publication described in Section 4.14.8(a), the Regulatory
Authority may publish a report on any one or more matters that have been referred to it, its
findings in relation to those matters and any sanctions imposed in relation to those matters.
A decision by the Regulatory Authority to publish a report under this Section 4.14.8(c) is a
reviewable decision
(d) No User, or former User is entitled to make any claim against the Regulatory Authority for
any loss or damage incurred by the User or former User from the publication of any
information pursuant to Section 4.14.8(a) Or (c) if the publication was done in good faith. No
action or other proceeding will be maintainable by the person or User referred to in the
publication against the Regulatory Authority or any person publishing or circulating the
publication on behalf of the Regulatory Authority and this Section operates as leave for any
such publication except where the publication was not done in good faith
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 72
CHAPTER 4 Governance
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 73
CHAPTER 4 Governance
2. Procedures and standards applicable to the Regulatory Authority and Users relating
to information and data received by or from Users in relation to matters relevant to
the ENTGC
(b) Prior to establishing requirements or standards and procedures referred to in Section 4.15.2(a),
the Regulatory Authority shall consult with such Users as the Regulatory Authority
considers appropriate. In formulating requirements or procedures and standards, the
Regulatory Authority shall take into consideration the monitoring objectives set out in Section
4.15.1. The reporting requirements, standards, and procedures established by the Regulatory
Authority are reviewable decisions
(c) Subject to Section 4.15.2(d), the Regulatory Authority shall notify to all Users particulars of
the requirements, procedures, and standards that it establishes under this Section 4.15.2
(d) If the Regulatory Authority establishes additional or more onerous requirements or
procedures and standards, which do not apply to all Users, and the Regulatory Authority
considers that notification of those matters to all Users would contravene the confidentiality
provisions in Section 3.15, the Regulatory Authority shall notify only those Users to whom
the requirements or procedures and standards apply
(e) Each User shall comply with all requirements, procedures and standards established by the
Regulatory Authority under this Section 4.15.2 to the extent that they are applicable to him
within the time period specified for the requirement, procedure or standard or, if no such
time period is specified, within a reasonable time. Each User shall bear his own costs
associated with complying with these requirements, procedures, and standards
(f) In complying with his obligations or pursuing his rights under the ENTGC, a User shall not
recklessly or knowingly provide, or permit any other person to provide on behalf of that
User, misleading or deceptive data, or information to any other User or to the Regulatory
Authority
(g) Any User may ask the Regulatory Authority to impose additional requirements, procedures,
or standards under this Section 4.15.2 on another User in order to monitor or assess
compliance with the ENTGC by that User. When such a request is made, the Regulatory
Authority may but is not required to impose the additional requirements, procedures, or
standards. A decision by the Regulatory Authority to impose additional requirement
procedures or standards is a reviewable decision. If the Regulatory Authority decides to
impose additional requirements, procedures, or standards, the Regulatory Authority may
determine the allocation of costs of any additional compliance monitoring undertaken
between the relevant Users. Users shall pay such costs as allocated. In the absence of such
allocation, the User subject to the additional requirements, procedures, or standards will
bear his own costs of compliance
(h) The Regulatory Authority shall develop and implement guidelines in accordance with the
ENTGC consultation procedures governing the exercise of the powers conferred on it by
Section 4.15.2(g) which guidelines shall set out the matters to which the Regulatory
Authority shall have regard prior to deciding the allocation of costs of any additional
requirements, procedures or standards imposed pursuant to Section 4.15.2(g) between the
relevant Users
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 74
CHAPTER 4 Governance
4.15.4 Reporting
(a) Not later than the last day in each calendar year, the Regulatory Authority shall prepare and
give an annual report for the previous fiscal year to all Users and interested parties. The
annual report shall include:
1. The Regulatory Authority ’s assessment of the extent to which the operation of the
ENTGC during that period met the ENTGC objectives and of the strategic
development of the ENTGC to meet industry objectives
2. The Regulatory Authority ’s audited accounts for the period covered by the report
3. A report on the matters set out in the Operations Chapter concerning the System
Operator’s use of powers of direction in relation to power system security granted
to him under the Operations Chapter
4. A summary of, and reasons for, any changes to the ENTGC
5. A summary of identified material breaches of the ENTGC and the actions taken in
response, including particulars of any sanctions imposed
6. A summary of any Dispute involving the Regulatory Authority and their resolutions
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 75
CHAPTER 4 Governance
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 76
5 PLANNING
The PC specifies the requirements for the interchange of information between EAPP Sub-Committee
on Planning and individual TSOs. This information is required to enable EAPP Sub-Committee on
Planning and TSOs to take due account of developments, new connection sites or the modification
of existing connection sites in a National System or new, or the modification of, connections with
External Systems, including changes in factors such as demand, generation, new technology,
reliability and environmental requirements that may also have an impact on the planning and
operation of the EAPP Interconnected Transmission System.
All parts of the EAPP Interconnected Transmission System shall be designed so that the demand for
electricity can be met reliably at the lowest cost. This means that the EAPP Interconnected
Transmission System shall be planned, built, and operated so that sufficient transmission capacity
will be available to utilise the generation capacity and to meet the needs of customers in an
economic way.
The long-term economic design of the EAPP Interconnected Transmission System aims at a balance
between investments and the cost of maintenance, operation, and supply interruptions, taking into
account environmental and other limitations. Flexible solutions, which take into, account future
uncertainties, such as generation limitations, new generation technologies, uncertain load
development and technical development, should be selected.
5.1.2 Objectives
The objectives of the PC are to provide for:
(a) Coordination by the EAPP Sub-Committee on Planning of any proposed development or
reinforcement of a National System or construction of new or modification of
interconnections with External Systems to ensure that the reliability and security of the
EAPP Interconnected Transmission System is not compromised
(b) Cooperation between the TSOs in the planning and procurement of new generation capacity
at lowest overall cost, taking into account environmental considerations, and
(c) Submission of sufficient information to enable a TSO to optimise the planning and
development of its National System including the use of available transmission capacity on
the EAPP Interconnected Transmission System
5.1.3 Scope
The PC applies to the EAPP Sub-committee on Planning and to the TSOs. The TSOs are responsible
for the collection of information from all Users connected to their National System and for providing
any relevant information required by the PC to the EAPP Sub-committee on Planning.
Those TSOs with connections to External Systems shall ensure that the supply of data required under
the PC should be contemplated in the Interconnection Agreement with the External System seeking
a new or modified interconnection.
The principles should also be applied in the planning of National Systems to ensure that the
reliability criteria can be met. The principles, however, do not apply to local supply reliability and
other local considerations, which are the subject of National Grid Codes or equivalent documents.
The reliability level for the EAPP Interconnected Transmission System is defined by a set of minimum
criteria in the PC together with the performance characteristics and requirements set out in the
Connection Chapter, which must both be met when designing developments, expansions, and
reinforcements of both EAPP Interconnected Transmission System and National Systems. The criteria
are based on a balance between the probability of contingencies and their consequences.
Reliable transmission capacity can be achieved by specifying standards for primary, protection, and
auxiliary equipment as well as by reserve capacity and other operational resources as set out in the
Operations Chapters.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 78
CHAPTER 5 Planning
The security and reliability of the EAPP Interconnected Transmission System shall not be
compromised by the loss of any single power system element such as Generating Unit, transmission
circuit, and section of busbar, transformer or reactive compensation equipment.
These criteria are not applicable to areas connected by radial lines to a National System where loss
of load and any local generation may be acceptable.
The N-1 criterion may be assured in a National System with the support of another interconnected
National System, subject to the prior agreement of the respective TSOs.
The planning criteria for dynamic security are defined such that the EAPP Interconnected
Transmission System shall remain stable following a single Contingency. The EAPP Interconnected
Transmission System is able to remain stable in some cases following a fault without the outage of
any transmission element by a successful auto-reclosing. If the attempt of auto-reclosing fails, the
fault shall be cleared by tripping the faulted element.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 79
CHAPTER 5 Planning
(a) The projection of the seasonal maximum and minimum demand for electricity in each
National System and the corresponding energy requirements for each year across the study
period. These forecasts will correspond to certain reference dates to be defined by the EAPP
Sub-committee on Planning
(b) The amount and nature of generation capacity currently available to meet the demand and
any anticipated restrictions in the production of energy
(c) The amount of generation capacity it expects will be required to ensure that Operating
Margins are achieved
(d) Details of plans for building additional Generating Units including upgrades of existing
generation capacity
(e) The amount and nature of demand to be met by other EAPP Member Countries using
transmission capacity available on the EAPP Interconnected Transmission System, and
(f) The power transfers anticipated with External Systems
The difference between available generating capacity and demand at the reference dates is called
the Remaining Capacity and is calculated under normal climatic conditions. This Remaining Capacity
represents the reserves available, which can be used to cover demand above forecast or Generating
Unit Outages greater than expected. The Remaining Capacity can be positive with export potential
or negative where the lack of capacity signals a need for imports.
The EAPP Sub-committee on Planning shall produce a Power Balance Statement for the EAPP
Interconnected Transmission System based on the individual TSOs’ Power Balance Statements.
Based on the transmission adequacy assessment carried out by each TSO, the EAPP Subcommittee
on Planning will produce a Transmission System Capability Statement for the EAPP Interconnected
Transmission System. This Transmission System Capability Statement is focused on the cross-border
connections and those TSO’s National Systems, which have a direct effect on the cross-border exchanges.
In producing the Transmission System Capability Statement, the EAPP Sub-committee on Planning
shall consider various scenarios for interchanges, demands and generation. Sensitivity analysis shall
be carried out taking into account such parameters as hydrological conditions and fuel price variations.
The EAPP Sub-committee on Planning may also consider the use of Remedial Action Schemes (RAS),
in which automatic control equipment disconnects or otherwise controls generation, demand, or
network elements other than for faults. Such RAS are used to enhance transmission capacity at the
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 80
CHAPTER 5 Planning
expense of reliability and may only be used following specific agreement between the EAPP Steering
Committee and the affected TSO.
The EAPP Sub-committee on Planning will determine the form and content of the Transmission
System Capability Statement to be issued each year and shall publish it on the EAPP Website.
These system studies will be carried out by both the EAPP Sub-committee on Planning and the TSOs
and shall be performed using a common set of principles and a common database. To achieve this,
the EAPP Sub-committee on Planning shall establish a set of common objectives for the development
and submission of system data for EAPP power system modelling. The data shall include sufficient
detail to ensure that system contingencies, steady state, transient and dynamic analyses can be
simulated. The data required for system studies is set out in the Data Exchange Chapter.
5.1.8 Responsibilities
EAPP Sub-committee on Planning in conjunction with the TSOs shall identify the scope and specify
the data required for reliability analyses and the procedures for data reporting. These requirements
and procedures should be periodically reviewed, documented, and published for the EAPP
Interconnected Transmission System at least every five (5) years.
Each TSO shall provide accurate and appropriate equipment characteristics and power system data
for modelling and simulation purposes as required by the EAPP Sub-committee on Planning.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 81
CHAPTER 5 Planning
5.2.1 Introduction
Section 5.2 specifies the criteria and procedures to be applied by Ethiopia’s Planning and
Development organization(s) in the planning and development of the ENTS. It furthermore provides
for accountability for ENTS planning and development and sets the required standards and targets.
It also specifies the reciprocal obligations and interactions between Users.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 82
CHAPTER 5 Planning
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 83
CHAPTER 5 Planning
2. Regular interfacing and joint planning with Users regarding the ENTS development
(d) Dispute s arising from the above process shall be decided in terms of the Dispute resolution
mechanism in Chapter 4 (Governance)
(e) The ENTSO shall provide a five (5)-year statement of opportunities to render ancillary
services for the mitigation of network constraints
1. The first Transmission Asset Management/Service Plan shall be submitted after six
month of completion of construction work in case of newly constructed
transmission line or after six months of issuance of license in case of already
established transmission lines
5.2.5 Technical Limits and Targets for Long Term Planning Purposes
(a) The planning limits, targets and criteria form the basis for evaluation of options for the long-
term development of the ENTS
(b) The limits and targets against which proposed options are checked by the ENTSO shall
include technical and statutory limits that must be observed and other targets that indicate
that the system is reaching a point where power transfer problems may occur. If planning
limits are not attained, alternative options shall be evaluated
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 84
CHAPTER 5 Planning
(c) Table 5-3 has target voltages for planning purposes at transmission voltages
Statutory voltage on bus supplying customer for any period longer Un plus or minus 5%
than 10 consecutive minutes (unless otherwise agreed in Supply
Agreement)
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 85
CHAPTER 5 Planning
Maximum voltage change owing to load varying N times per hour: (4.5 log10n)% of Un
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 86
CHAPTER 5 Planning
Transformers
Standard transformer ratings shall be determined by the ENTSO and updated from time to
time using International Electro-technical Commission (IEC) specifications. The permissible
overload of a specific transformer depends on load cycle, ambient temperature and other
factors. If target loads are exceeded, the specific situation shall be assessed, as it may be
possible to defer adding extra transformers.
Series Capacitors
The ENTSO shall assure that the maximum steady state current should not exceed the rated
current of the series capacitor. The internationally accepted standard’s cyclic overload
capabilities are for operational use only, to allow time to reduce loading to within the rated
current without damaging the series capacitor.
Circuit Breakers
The TNSP shall specify and install circuit breakers as directed by the ENTSO that meet
system fault levels and other conditions considered important for the safe and secure
operation of the ENTS. Ratings are to be according to international circuit breaker standards
such as those of the IEC.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 87
CHAPTER 5 Planning
(d) A system cannot be made one hundred percent (100%) reliable, as planned and forced
outages of components will occur and multiple outages are always possible, despite having
a very low probability of occurrence. However, reliability is ensured to the extent possible
employing the following process:
1. The Generation and Transmission entities shall provide the ENTSO their proposed
outage programmes (Identifying each generating unit/line/ICT, the preferred date
for each outage and its duration and where there is flexibility, the earliest start date
and latest finishing date) in writing for the next fiscal year
2. TSO shall conducts system studies with these inputs and available resources to
ensure adequate balance between generation and load requirement in an optimal
manner while maintaining system security standards. Outcome of this analysis is a
draft outage plan for the next fiscal year, which may have been rescheduled, if
deemed necessary, based on the studies
3. The outage plan shall be finalized by ENTSO in consultation with the concerned
Generation/Transmission entities. The detailed generation and transmission outage
programmes shall be based on the latest annual outage plan (with all up-to-date
adjustment). Each Utility shall obtain the final approval from ENTSO, just prior to
availing an outage
4. The above annual outage plan shall be reviewed by ENTSO on quarterly basis in
coordination with all parties concerned, and adjustments made wherever found
necessary
5. In case of a system emergency (e.g., loss of generation, breakdown of transmission
line affecting the system, grid disturbances, system isolation), the ENTSO may
conduct studies again before clearance of the planned outage
6. The ENTSO is authorized to defer the planned outage in case of any of the followings
based on an analysing on its criticality: (i) grid disturbances; (ii) System isolation; (iii)
Partial Black out; (iv) Any other event in the system that may have an adverse
impact on the system security by the proposed outage
(e) The ENTSO shall ,in planning the ENTS, minimise as far as practicable the risk of common
cause failure of two (2) or more items of Plant (e.g. loss of two (2) or more lines in a
common servitude or on a double circuit or multicircuit structure), and insofar as such risk is
unavoidable, shall take reasonable measures to mitigate such risk
(f) Additional equipment shall be provided if it can be justified to be included in the rate base in
terms of the Least Economic Cost and/or Cost Reduction Investment or the cost is
recoverable from a customer or group of customers in accordance with the descriptions
under Strategic Investments in this chapter
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 88
CHAPTER 5 Planning
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 89
CHAPTER 5 Planning
(d) The cost of ensuring transient stability shall be carried by the Generation Licensee if the
optimum solution, as determined by the ENTSO, results in unit or Generating Plant
equipment being installed. In other cases, the TNSP shall bear the costs and recover these as
per the approved Tariff methodology
(e) Busbar layouts shall allow for selection to alternative busbars. In addition, feeders must
have the ability to go onto bypass
(f) The busbar layout shall ensure that not more than 100 MW of generation is lost as a result
of a single Contingency
(g) To enable the ENTSO to successfully integrate new Generating Plant, detailed information is
required for each Generating Plant, as described in the Information Exchange Chapter 20.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 90
CHAPTER 5 Planning
1. Interruptions
2. Load shedding
3. Network constraints
4. Voltage dip, surge, flicker, and harmonic distortion
(d) The least-cost investment criterion equation to be satisfied can be expressed as follows: “Value
of improved Quality of Service (QOS ) to customers > cost to the TNSP to provide improved
QOS”
(e) From this equation, it is evident that if the value of the improved QOS to the customer is
less than the cost to the TNSP, then the TNSP should not invest in the proposed project(s).
The investment decision shall then be delayed such that optimised economic benefit can be
derived
(f) This implies that for the criteria to be satisfied: “COUE annual value (B/kWh) x annual
reduction in Expected Unserved Energy (EUE) to consumers (kWh) > annual cost to the TNSP to
reduce EUE”
(g) The reduction in EUE shall be calculated on a probabilistic basis based on a methodology
approved by Regulatory Authority
(h) The Cost of Unserved Energy (COUE) is a function of the types of loads, the proportion of
the total load contributed by each different type of load, the duration and frequency of the
interruptions, the time of the day they occur, whether notice is given of the impending
interruption, the indirect damage caused, the start-up costs incurred by the customers, the
availability of customer backup generation and many other factors
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 91
CHAPTER 5 Planning
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 92
CHAPTER 5 Planning
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 93
CHAPTER 6 Connections
6 CONNECTIONS
This chapter contains requirements specific to both the EAPP IC and the ENTGC. If in any instance
there is a difference in requirements, the more stringent requirement shall hold.
Respective National legislation and codes may lay down local requirements. These local
requirements should observe the minimum standards in this CC to avoid adverse effects on the
EAPP Interconnected Transmission System, which may affect power interconnection security and
quality of supply to other Parties or increase fault levels beyond the capabilities of existing
Connection Points.
The provisions of the CC shall apply to all connections to the EAPP Interconnected Transmission System:
(a) Existing at the date when this Chapter comes into effect, or
(b) As established or modified thereafter
6.1.2 Objective
The CC is designed to ensure:
(a) That a new or modified connection shall not impose adverse effects upon the EAPP
Interconnected Transmission System nor will it be subject itself to unacceptable effects by its
connection to the EAPP Interconnected Transmission System
(b) That the basic rules for connection treat all TSOs and Users in a nondiscriminatory manner, and
(c) Ongoing compliance with the technical and operational requirements of the Interconnection
Code to facilitate operational management of the EAPP Interconnected Transmission System
6.1.3 Scope
The CC applies to TSOs and to all Users connected or seeking connection to the EAPP Interconnected
Transmission System.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 94
CHAPTER 6 Connections
6.1.4.1 Frequency
Frequency is the one parameter common to all members of a synchronous electric power system,
and an accepted indicator of that system’s ability to balance resources and demand as well as to
manage disturbances.
Under normal operation, the frequency of the EAPP Interconnected Transmission System shall be
nominally 50 Hz (±1%) and shall be controlled between 49.5 Hz and 50.5 Hz unless exceptional
circumstances prevail. Following a system disturbance such as a load variation, the frequency band
is extended to 49.0–51.0 Hz (±2%). If a major Generating Unit is tripped, a major transmission
element fails or large loads are suddenly disconnected, the maximum frequency band becomes
48.75–51.25 Hz (±2.5%). If several of the contingencies mentioned previously occur simultaneously,
the operating condition is labeled as extreme and the frequency can be below 47.5 Hz or above 51.5
Hz (-5%/+3%) for up to 20 seconds, and then extreme measures should be taken to restore the
system. These figures are summarized in Table 6-1 and graphically represented in Figure 6-1.
Extreme System operation or fault conditions (f<47.50 Hz or f>51.50 Hz) for up to 20 seconds
Normal (49.5 –
50.5) Hz
6.1.4.2 Voltage
Requirements for voltage characteristics are defined below:
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 95
CHAPTER 6 Connections
The voltages on the EAPP Interconnected Transmission System shall normally be maintained within
the limits set out below:
1. Operating voltage range of 0.95 to 1.05 per unit in steady state normal conditions for
nominal voltages used in the EAPP Interconnected Transmission System namely 500 kV, 400
kV, 230 KV, 220 kV, 132 kV, 110 kV and 66 kV,
2. Operating voltage range of 0.90 to 1.10 per unit after any single Contingency, and
3. Operating voltage range of 0.85 to 1.20 per unit after any multiple Contingency or severe
system stress as indicated in Table 6-2 below.
Table 6-2: Steady State Voltage Limits
Operating Conditions Voltage Limits
Normal 0.95 - 1.05
Contingency (N-1) 0.90 – 1.10
Multiple Contingency 0.85 – 1.20
The TSOs shall ensure that during periods of minimum demand, Users comply with a unity or lagging
power factor, and a power factor of 0.95 lagging or higher during periods of peak and shoulder
hours.
Transient Voltage
Transient over-voltages can occur on the EAPP Interconnected Transmission System as a result of
lightning surges or the switching of long transmission lines or cables. The insulation level of all Plant
and Apparatus at the Connection Point must be coordinated to take account of these transient over-
voltages. The insulation levels for equipment shown in Table 6-3 below are based on IEC 60071-1:
Table 6-3: Permissible Transient Voltages
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 96
CHAPTER 6 Connections
Tanzania
Egypt, Kenya,
220 kV 245 kV 950 N/A 395
Sudan, Tanzania
230 kV Ethiopia 245 kV 1050 N/A N/A
400 kV Ethiopia 420 kV 1050 – 1425 850 / 950 / 1050 N/A
500 kV Egypt 550 kV 1175 – 1550 950 / 1050 / 1175 N/A
The lowest operating voltages at each voltage level depend on the local conditions. The lowest
values are reached during operational disturbances and are usually not lower than 0.9 per unit.
Voltage Dips
A voltage reduction with duration of 10 ms to 1 minute and a voltage drop of more than 10 % of the
existing value is known as a voltage dip. There are no standard requirements for the severity or
extent of voltage dips since they are highly dependent on the system configuration. The duration of
a voltage dip is highly dependent on the type of fault concerned and on which relay protection
methods are used locally.
Most voltage dips are caused by earth faults. Whether or not such voltage dips are transferred to
lower voltages depends on which earthing methods are used and on the transformer connections.
The voltage dips may often become deeper and may spread to other parts of the system if faults occur
in more than one phase, but this is relatively rare.
Voltage Flicker
Voltage Flicker is an increase or decrease in voltage over a short period of time, normally associated
with a fluctuating load. The characteristics of the particular Voltage Flicker problem depend on the
characteristics of the load change.
Voltage Flicker may arise during the start-up of an Induction Generator, motor, energisation of a
transformer or other equipment as the large starting or inrush current may cause the voltage to
drop considerably.
TSOs and Users are required to minimise the occurrence of Voltage Flicker on the EAPP
Interconnected Transmission System as measured at the Connection Point. The Voltage Flicker limits
are contained in the following IEC standards:
(a) IEC/TR3 61000-3-7 (1996) “Assessment of emission limits for fluctuating loads in MV and HV
power systems”
(b) IEC 868/Engineering Recommendation P28 (page 17) “Limits on voltage flicker short term
and long term severity values”
(c) In general, the total Voltage Flicker at a Connection Point shall not exceed:
1. ± one (1) percent (%) of the steady state voltage level, when these occur
repetitively; or
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 97
CHAPTER 6 Connections
2. ± three (3) percent (%) of the steady state voltage level, when these occur
infrequently
6.1.4.3 Harmonics
Harmonics can cause telecommunication interference and thermal heating in transformers; they can
disable solid-state equipment and create resonant over-voltages. In order to protect such
equipment harmonics must be managed and mitigated. Harmonics are normally produced by Plant
and Apparatus generating waveforms that distort the fundamental 50 Hz wave.
The following Table 6-4, based on IEEE 519-92, shows the permitted harmonic distortion levels on
the EAPP Interconnected Transmission System. The acceptable distortion levels are the same as the
ones described in Table 4-1 Standards for Voltage Harmonics in the EEA QoS Code.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 98
CHAPTER 6 Connections
ensure that they do not cause any sub-synchronous resonance, undamped oscillations, rapid voltage
variations, harmonic voltages and interference with telecommunications.
The conditions specified in this Chapter of the CC apply to HVDC interconnections connecting to or
within the EAPP Interconnected Transmission System. Each HVDC Interconnection shall have the
following minimum capabilities:
(a) Operate continuously at its declared MW Output at frequencies in the range 49.5 Hz to 50.5 Hz
(b) Operate and remain connected to the EAPP Interconnected Transmission System at
frequencies within the range 48.75 Hz to 51.25 Hz
(c) Remain connected to the EAPP Interconnected Transmission System at frequencies within
the range 47.0 Hz to 47.5 Hz for a duration of 20 seconds on each occasion that the
frequency is below 47.5 Hz
(d) Remain synchronised to the EAPP Interconnected Transmission System during a rate of
change of frequency of values up to and including 1 Hz per second
(e) Remain connected to the EAPP Interconnected Transmission System at declared MW Output
at voltages within the ranges specified in Section 6.1.4 (Connection). Transmission System
Performance Characteristics (Voltage) for step changes in voltage of up to 10%
(f) Remain connected during and following voltage dips at the HV terminals of the HVDC
Interconnection Transformer of 95% of nominal voltage for a duration of 0.2 seconds and
voltage dips of 50% of nominal voltage for a duration of 0.6 seconds. Following fault
clearance the HVDC Interconnection should return to pre-fault conditions subject to normal
frequency control and Automatic Voltage Regulator responses
(g) Operate within all normal operating characteristics at a minimum short circuit level at the
Connection Point of 1000 MVA
(h) Remain connected to the EAPP Interconnected Transmission System during a negative phase
sequence load unbalance in accordance with IEC 60034-1
(i) In an emergency be capable of reversing the power flow on the HVDC Interconnection at a
rate which shall be no less than the HVDC Interconnection registered capacity within five (5)
seconds, up to ten (10) times during the life of the Plant and no more than two (2) times in
any given twelve (12) months
6.1.7.1 General
Protection system design shall be based on simplicity, safety to persons, mitigation, and limitation of
equipment damage and control of the spread of any disturbance. The speedy operation of
protection systems to clear faults in the EAPP Interconnected Transmission System is a pre-requisite
to avoid instability and cascade tripping.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 99
CHAPTER 6 Connections
The protection systems to be applied to the User’s Plant and Apparatus at the Connection Point shall
be designed, coordinated, and tested to achieve the desired level of speed, sensitivity, and selectivity in
fault clearing and to minimize the impact of faults on the EAPP Interconnected Transmission System.
Nothing shall prevent a TSO or User utilising faster fault clearance times. Total fault clearance time
shall be from fault inception until arc extinction, which therefore includes relay operation, circuit
breaker operation and telecommunications signaling times.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 100
CHAPTER 6 Connections
The Turbine Controller shall be sufficiently damped for both isolated and interconnected operation
modes. Under all operating conditions, the damping coefficient of the Turbine Speed Control shall
be above 3% for gas turbines and 5% for steam turbines.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 101
CHAPTER 6 Connections
Under all system operating conditions, the Generating Unit speed shall not exceed 103%
corresponding to 51.5 Hz for more than 20 seconds in the EAPP Interconnected Transmission System
(refer to Frequency Sensitive Relays in this chapter in this context).
The Turbine Speed Controller and any other superimposed control loop such as load control or gas
turbine temperature limiting control shall contribute to the Primary Response to maintain the unit
within the Generating Unit capability limits.
The Primary Response characteristics shall be maintained under all operational conditions.
Additionally, in the event that a Generating Unit becomes isolated from the system but is still supplying
demand the Generating Unit must be able to provide Primary Response to maintain the frequency.
The AVR shall have no negative impact on Generating Unit oscillation damping. If required by the
TSO, in consultation with EAPP Sub-Committees on Planning and Operation, a Power System
Stabiliser (PSS) shall be provided. Control principle, parameter setting and switch on/off logic shall
be coordinated with the TSO and EAPP Sub-Committees on Planning and Operation and specified by
the TSO in the Connection Agreement.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 102
CHAPTER 6 Connections
Black Start facilities shall be routinely tested by the Generation Licensee to ensure satisfactory
operation. The TSO shall have the right to require the Generation Licensee to demonstrate the Black
Start Capability.
Each TSO shall make the necessary arrangements to disconnect its National System from the EAPP
Interconnected Transmission System under the circumstances stated below.
In the case of Generating Units, these Ancillary Services include Primary and Secondary Response,
voltage and load flow control and Black Start Capability. TSOs may enter into Ancillary Services
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 103
CHAPTER 6 Connections
Agreements with Generation Licensee s for the provision of these capabilities. The Ancillary Services
Agreements may also contain commercial arrangements in relation to the provision of these
capabilities or of more enhanced capabilities. Tertiary Reserve of a Generating Unit (fast start hydro,
gas turbine, and steam turbine on hot standby) is an Ancillary Service that is being delivered when a
Generating Unit is able to start up and synchronise or change its loading within the timescales
specified by the TSO.
For transmission facilities the Ancillary Services provision is related to voltage control equipment
such as shunt capacitors, flow control devices such as Phase Shifting Transformers and to special
control systems such as RAS. The provision of such Ancillary Services would be subject to an
agreement between the transmission provider and the TSO.
Each TSO shall take appropriate measures to protect the telecommunications network against risks
related to the disruption of operation, data corruption or disclosure of confidential information.
Alternate and physically independent telecommunication channels shall be provided for emergency
use to back up the circuits used for critical data and voice communications.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 104
CHAPTER 6 Connections
6.1.11.8 Standards
The following Standards shall be used for telecommunications services:
(a) The Wide Area Network (WAN) shall be based on TCP/IP protocol
(b) Communication between Control Centres shall be harmonised and based on ICCP protocol
or as agreed between TSOs and EAPP CC
(c) Tele-control real-time information shall be based on IEC 870-6 TASE.2 protocol
(d) Non real-time services such as file transfer for exchange of transmission schedules, network
model, planning data or statistics shall be based on the FTP protocol; and
The recording system shall be capable of playing back directly up to one-month telephone conversations.
Archival storage shall be done on CDs or DVDs or any appropriate medium. Archives shall be stored
for at least one (1) year.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 105
CHAPTER 6 Connections
Additionally, the TSO shall be required to monitor Governor selection mode, and AVR selection
mode for all power generation plants (with total plant capacity above 30 MW) connected to the
national grid as indicated in Table 6-5 below. Table 6-5 also sets out the minimum telemetered data
required by the EAPP CC.
Telemetered Status
Type of Connection Telemetering Required
Indicators
Generating Unit connected MW, Mvar, kV, pf Generating Unit main circuit
directly to Interconnected breakers
Transmission System MWh, Mvarh
Generating Unit > 30 MW not MW, Mvar, kV, pf Generating Unit main circuit
directly connected to breakers
Interconnected Transmission
System
The EAPP Coordination Centre shall define any further system parameters it requires to monitor.
TSOs and Users shall ensure that Plant and Apparatus, including protection systems, are tested and
maintained and remain rated for the duty required. TSOs shall ensure that a copy of the Annual
Transmission System Capability Statement including the update of system fault levels is made available.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 106
CHAPTER 6 Connections
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 107
CHAPTER 6 Connections
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 108
CHAPTER 6 Connections
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 109
CHAPTER 6 Connections
Generating Plants built after the implementation of the ENTGC shall be equipped with power system
stabilisers as defined in IEC 60034, IEEE421 or any other standard agreed to by the ENTSO. The
requirements for other excitation control facilities and AVR refurbishment shall be determined in
conjunction with the ENTSO.
6.2.6.2 Limiter
(a) The excitation control system shall be equipped with a load angle limiter and flux limiter
except for installed AVR equipment up to and including analogue electronic technology.
(b) The excitation system shall have a minimum excitation ceiling limit of 1,6 pu rotor current,
where 1 p.u. is the rotor current required to operate the unit at rated load and at rated
power factor as defined in IEC 60034, IEEE421 or any other standard agreed to by the
ENTSO.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 110
CHAPTER 6 Connections
EAPP Section 6.1.4.1 describes frequency ranges and controllability issues. Chapter 15 Balancing
and Frequency Control under Section 15.2 provides the requirements for maintaining normal system
conditions.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 111
CHAPTER 6 Connections
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 112
CHAPTER 6 Connections
4. The start-up facilities for a new unit not being designed to minimise start up time
delays for the unit following loss of external auxiliary AC supplies for 30 minutes or
less
(f) A requirement to withstand the following ARC cycle for multi-phase faults (phase-to-phase
or 3-phase) on the transmission lines connected to the power station:
3ph fault - 3ph trip - 3 seconds 3ph ARC dead time - 3ph ARC - 3ph fault - 3ph trip - lock out
Routine and prototype response tests shall be carried out to demonstrate capabilities.
6.2.13 On-load Tap Changing for Generating Plant Step-up Transformers (GCR12)
All Generating Plant step-up transformers shall have on-load tap changing with remote control
capability. The range and mode of control shall be agreed between the organization(s) responsible for
the planning, development, and operation of the ENTS and the Generation Licensee.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 113
CHAPTER 6 Connections
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 114
CHAPTER 6 Connections
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 115
CHAPTER 6 Connections
Generator unit transformers, associated busbar ducts, and switchgears shall be equipped with well-
maintained protection functions to rapidly disconnect appropriate plant sections should a fault
occur within the relevant protection zones that may affect the ENTS.
Backup impedance requirement ensures the availability of an impedance facility with a reach
greater than the impedance of the generator transformer. It operates for phase faults in the unit, in
the HV yard or in the adjacent transmission lines, with a suitable delay for cases when the
corresponding main protection fails to operate. This requirement is considered for units 20 MVA or
higher.
Generating Plants shall have reactive power capability for providing voltage support depending on
the system requirement at Connection Point.
Table 6-6: Summary of the Requirements Applicable to Specific Classes of Units Other than Hydro
Units other than Hydro and Renewables (MVA rating)
Grid Code Requirement
<20 20 to 100 100 to 200 200 to 300 300 - 800 >800
Depends on
GCR1 Plant availability - Yes Yes Yes Yes
Sys Reqts
Depends on
GCR2 Plant reliability - Yes Yes Yes Yes
Sys Reqts
GCR3 Protection
- Backup Impedance Yes Yes Yes Yes Yes Yes
- Depends on
- Loss of Field Yes Yes Yes Yes
Sys Reqts
Depends on Depends on
- Pole Slipping - Yes Yes Yes
Sys Reqts Sys Reqts
Depends on Depends on
- Trip to House Load - - Yes Yes
Sys Reqts Sys Reqts
- Generator Transformer HV
Yes Yes Yes Yes Yes Yes
backup earth fault
- HV Breaker Fail Yes Yes Yes Yes Yes Yes
- HV Breaker Pole
Yes Yes Yes Yes Yes Yes
Disagreement
- Unit Switch-onto-standstill Depends on
- Yes Yes Yes Yes
Protection Sys Reqts
- Main Protection only Yes Yes Depends on - - -
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 116
CHAPTER 6 Connections
Table 6-7: Summary of the Requirements Applicable to Specific Classes of Hydro Units
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 117
CHAPTER 6 Connections
- HV Breaker Pole
Yes Yes Yes Yes Yes Yes
Disagreement
- Unit Switch-onto-standstill Depends on
- Yes Yes Yes Yes
Protection Sys Reqts
- Main Protection only Yes Yes - - -
- Main Protection Depends on
(monitored) or main and - - Sys Reqts - -
backup Depends on
Sys Reqts Depends
- Main and Backup
- - - on Sys Yes
Protection (both monitored)
Reqts
GCR4 Ability To Island - - - - - -
Excitation system
GCR5 Yes Yes Yes Yes Yes Yes
requirements
Depends on Depends on
- Power System Stabilizer - - Yes Yes
Sys Reqts Sys Reqts
Depends on
- Limiters - - Yes Yes Yes Yes
Sys Reqts
Depends on Depends on
GCR6 Reactive Capabilities Yes Yes Yes Yes
Sys Reqts Sys Reqts
If the total station output is greater than the
Depends on If more than 1
GCR7 Multiple Unit tripping - single largest contingency as defined for
Sys Reqts unit at station
instantaneous reserve
Depends on
GCR8 Governing Yes Yes Yes Yes Yes
Sys Reqts
If the total station output is greater than the single
Restart after Station Depends on If more than
GCR9 - largest contingency as defined for instantaneous
1 unit at station
Blackout Sys Reqts reserve
GCR10 Black Starting - If agreed If agreed If agreed GCR10 Black Starting
If more than If the total station output is greater than the single
External Supply Disturbance Depends on If more than
GCR11 5 unit at largest contingency as defined for instantaneous
1 unit at station
Withstand Capacity Sys Reqts station reserve
On load tap
On load tap Changer for Changer for
Depends on
GCR12 generating Unit Yes Yes Yes GCR12 generating
Sys Reqts
step up transformers Unit step up
transformers
Depends on Depends on
GRC13 Emergency unit capabilities Yes Yes Yes Yes
Sys Reqts Sys Reqts
Facility for Independent Depends on
GCR14 - - Yes Yes Yes
Generating Plant Action Sys Reqts
Sys Reqts = System Requirements
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 118
CHAPTER 6 Connections
Transmission Percentage of actual circuit [Sum of all circuit hours Greater than 90%
System hours available in relation available/{(Number of circuits)x for the
Availability to total possible circuit (Number of hours in transmission
period)}]X100% system
hours available; Circuit
outages that result from
both planned and
unplanned unavailability
are taken into account;
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 119
7 RENEWABLE POWER PLANT
This chapter contains requirements specific to both the EAPP IC and the ENTGC. If in any instance there
is a difference in requirements, the more stringent requirement shall hold.
7.1.2 Technical Requirements for Wind and Solar Power Generating Plants
The requirements for Generating Plants set out in section 6.1.8 in Chapter 6 (Connections) refer to
synchronous units. Wind Turbine Generating Plants and Solar Power Generating Plants do not have
the same characteristics as Synchronous Generators and alternative provisions are required. This
section sets out the specific requirements for controllable Wind Turbine Generating Plants and Solar
Power Generating Plants.
(a) During a voltage dip, the controllable Wind Turbine /Solar Power Generating Plant shall provide
Active Power in proportion to retained voltage and maximise reactive current to the EAPP
Interconnected Transmission System without exceeding its declared limits. The maximisation of
reactive current shall continue for at least 600 ms or until the voltage recovers to within the normal
operational range of the EAPP Interconnected Transmission System whichever is the sooner
(b) The controllable Wind Turbine / Solar Power Generating Plant shall provide at least 90% of its
maximum available Active Power as quickly as possible and in any event within one (1) second of the
voltage recovering to the normal operating range
(a) Operate continuously at normal rated output at frequencies in the range 49.5 Hz to 50.5 Hz
(b) Remain connected to the EAPP Interconnected Transmission System at frequencies within the
range 49.0 Hz to 51.0 Hz for a duration of 60 minutes
(c) Remain connected to the EAPP Interconnected Transmission System at frequencies within the
range 47.0 Hz to 47.5 Hz for a duration of 20 seconds each time that the frequency is below 47.5 Hz,
and
(d) Remain connected to the EAPP Interconnected Transmission System during rate of change of
frequency of values up to and including 0.5 Hz per second
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 121
CHAPTER 7 Renewable Power Plant
per minute ramp rate averaged over one (1) minute. The second ramp rate setting shall apply to the
MW per minute ramp rate averaged over ten (10) minutes. These ramp rate settings shall be
applicable for all ranges of operation including start up, normal operation and shut down.
It is recognised that falling wind speed or frequency response may cause either of the maximum
ramp rate settings to be exceeded.
It shall be possible to vary each of these two maximum ramp rate settings independently over a
range between one (1) and thirty (30) MW per minute. The Wind Turbine Generating Plant control
system shall have the capability to set the ramp rate in MW per minute averaged over both one (1)
and ten (10) minutes.
The Wind Turbine /Solar Power Generating Plant operator and the TSO shall agree a procedure for
setting and changing the ramp rate control.
7.2.1 Objective
The primary objective of this section is to specify minimum grid connection technical and design
requirements for variable RPP connected to or seeking connection to the ENTS.
7.2.2 Scope
The requirements in this section apply to all variable RPPs with a design capacity of 10 MVA or larger
connected or seeking connection to the ENTS, the ENTSO, and prospective TNSPs.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 122
CHAPTER 7 Renewable Power Plant
(Flow Battery Systems For Stationary Applications – Part 2-2: Safety requirements), IEC 61850
(Communications networks and management systems), and IEC 60529 (Buildings, enclosures and
protection from the elements).
A Generation Licensee shall have an agreement with the ENTSO regarding the controllability of a
Generating Unit. Below are some key technical requirements of a controllable variable RPP:
The EAPP IC requirements specified under Section 7.1.2 shall apply to all RPPs within ENTS.
Four main characteristics typically provide the requirements for RPPs in the event of a voltage
disturbance:
(a) Conditions for which the RPP Generating Plant must remain connected
(b) Active Power provision during fault
(c) Voltage support requirements during the disturbance
(d) Restoration of Active Power after the fault has been cleared
An RPP shall remain connected to the ENTS for voltage disturbances on any or all phases, where
the system phase voltage measured at the HV terminals of the connection transformer remains
above a specified level for a specified length of time
The remain connected requirements during fault take the form of a voltage vs. time profile which
dictates the level of voltage drop or increase that RPPs must be capable of withstanding along with
the time for which the voltage drop or increase should be endured. Figure 7-2 shows the
combinations of voltages and time that the RPP shall be able to endure.
As shown in Figure 7-2, area A shows that the RPP shall be able to operate continuously between 0.9
p.u. and 1.1 p.u, after any single Contingency. In Area A, the RPP shall stay connected to the network
and uphold normal production.
Area B is the area between the Lower Bound and the bottom of the continuous operating range, at
0.9 p.u. In Area B, the RPP shall stay connected to the network. The RPP shall be able to withstand
voltage drops to zero (0), measured at the Connection Point, for a minimum period of 0.15 seconds
without disconnecting. Less severe voltage drops increase the length of time that must be endured.
Just below 0.85 p.u., the voltage drop shall be endured for nearly two (2) seconds. At 0.85 p.u. the
voltage drop shall be endured a minimum of three (3) seconds.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 123
CHAPTER 7 Renewable Power Plant
Area C is the area outside the Lower Bound and below the continuous operating range, at 0.9 p.u. In
Area C, disconnecting the RPP is allowed.
Area D is the area between the Upper Bound and the top of the continuous operating range, at 1.1
p.u. In Area D the RPP shall stay connected to the network. Figure 7-2 shows that the Generating
Plant shall be able to withstand voltage increases to 1.2 p.u. for at least two (2) seconds.
Area E is the area above the Upper Bound and above the continuous operating range, at 1.1 p.u. In
Area E, disconnecting the RPP is allowed.
p 0.6
(
U
u Upper Bound
)
)
0.4
a
t 0.2
0
0 1 2 3 4 5
Seconds
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 124
CHAPTER 7 Renewable Power Plant
For a frequency band of 48.00–51.50 Hz (-4% to + 3%) a RPP shall be capable of operating for at least
30 minutes.
For a frequency band of 47.50–51.50 Hz (-5% to +3%) a RPP shall be capable of operating for at least
3 minutes.
Under extreme system operation or fault conditions, a Generating Plant shall be capable of
operating at frequencies above 51.50 Hz, for at least 20 seconds.
For frequencies below 47.00 Hz, a Generating Plant shall be capable of operating for at least 200 ms.
RPPs shall remain connected to the ENTS during rate of change of frequency of values up to and
including 1.0 Hz per second.
For frequencies above 52.00 Hz, a Generating Plant must disconnect as indicated in Table 7-1.
Table 7-1: Frequency Limits in the Ethiopia National Transmission System (ENTS)
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 125
CHAPTER 7 Renewable Power Plant
The RPP control system shall be capable of operating the RPP at a reduced level if the Active Power
output has been restricted by the ENTSO. The RPP control system shall be capable of receiving an
on-line Active Power Control Set-point sent by the ENTSO and shall commence implementation of
the set-point within 10 seconds of receipt of the signal from the ENTSO. The rate of change of
output to achieve the Active Power Control Set-point should be no less than the maximum ramp rate
settings of the RPP control system, as advised by the ENTSO.
Although it is usually economically beneficial for RPPs to operate at their instantaneous available
capacity, RPPs shall operate below their instantaneous available capacity, as and when instructed by
the ENTSO accordingly.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 126
CHAPTER 7 Renewable Power Plant
The RPP control system shall be capable of controlling the ramp rate of its Active Power output with
a maximum MW per minute ramp rate set by the ENTSO. There shall be two maximum ramp rate
settings. The first ramp rate setting shall apply to the MW ramp rate averaged over one (1) minute.
The second ramp rate setting shall apply to the MW per minute ramp rate averaged over ten (10)
minutes. These ramp rate settings shall be applicable for all ranges of operation including start up,
normal operation and shut down. It is recognised that falling wind speed, rapidly changing cloud
conditions, or frequency response may cause either of the maximum ramp rate settings to be
exceeded.
Power output of Solar Power Generating Plant has to be reduced in steps of 10% per minute, under
any operating condition and from any working point to a maximum power value (target value) which
could correspond also to one hundred percent (100%) power reduction, without disconnection of
the Plant from the network.
It shall be possible to vary each of these two maximum ramp rate settings independently over a
range between one (1) and thirty (30) MW per minute. The RPP control system shall have the
capability to set the ramp rate in MW per minute averaged over both one (1) and ten (10) minutes.
The RPP operator and the ENTSO shall agree a procedure for setting and changing the ramp rate
control
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 127
CHAPTER 7 Renewable Power Plant
The Wind Turbine Generating Plant shall stay connected to the ENTS at average wind speeds below
a predefined cut-out wind speed. The cut-out wind speed shall as a minimum be twenty five (25)
m/s, based on the wind speed measured as an average value over a ten (10)-minute period. To
prevent instability in the ENTS, the wind power plant shall be equipped with an automatic
downward regulation function making it possible to avoid a temporary interruption of the Active
Power production at wind speeds close to the cut-out wind speed.
It shall be possible to continuously downward regulate the Active Power supplied by the RPP to an
arbitrary value in the interval from one hundred percent (100%) to at least forty percent (40%) of
the rated power. When downward regulation is performed, the shutting-down of individual Wind
Turbine Generating Plant units is allowed so that the load characteristic is followed as well as
possible.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 128
CHAPTER 7 Renewable Power Plant
0
Wind Speed, m/sec Cutout Wind Speed
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 129
8 OPERATIONS CODE NO. 1 – OPERATIONAL PLANNING
This chapter contains requirements specific to both the EAPP IC and the ENTGC. If in any instance there
is a difference in requirements, the more stringent requirement shall hold.
In accordance with the terms of the Planning Chapter 5 (Section 5.1 EAPP IC Requirements), the
TSOs and the EAPP Sub-Committee on Planning are required to produce a Power Balance Statement
and a Transmission System Capability Statement on an annual basis for the succeeding ten (10)
years. The Transmission System Capability Statement forms the basis for individual Users of National
Systems to determine the potential for power transfers within the EAPP Interconnected
Transmission System.
OC 1 sets out a refinement of the planning process to take account of the following:
(a) Outage requirements for generation and transmission facilities whether for construction,
maintenance or operational tests or System Tests
(b) Changes in the characteristics of generation or transmission facilities
(c) Changes in demand estimates
(d) Changes in Generating Unit availability caused by breakdown, fuel shortage or hydrological
conditions
(e) Current and forecast weather conditions
(f) Anticipated commercial energy flows across the EAPP Interconnected Transmission System,
and
(g) Other information supplied by TSOs or Users
The outcome of the Operational Planning process will be a definition of the Power Balance and
Transmission System Capability over various timescales.
TSOs are responsible for liaison with the Users connected to their National Systems in respect of the
Operational Planning process.
8.1.2 Objective
OC 1 specifies:
(a) The requirements for the exchange of information across the TSO-EAPP interfaces
throughout the Operational Planning process, from Outage requirements identified up to
three (3) years ahead for complex schemes and EAPP Interconnected Transmission and
National Systems reinforcement to handover of the Operational Plan into the Control Phase
(b) The Operational Planning procedure including information required and a typical timetable
for the coordination of Planned Outage requirements for Generating Units and transmission
facilities including protection and associated communication channels that may have an
effect on the operation of the EAPP Interconnected Transmission System, and
(c) The coordination of Outages to minimise as far as possible the number and effect of
constraints on the EAPP Interconnected Transmission System
8.1.3 Scope
OC1 applies to TSOs and to EAPP CC. It should be noted that certain information and data may be
required from individual Users and also from External Systems. It is the responsibility of individual
TSOs to ensure such information and data is updated and made available.
By 10h00 Hrs each Friday, TSOs shall provide the EAPP CC with hourly demand forecasts for the
following eight (8) weeks on each node of the EAPP Interconnected Transmission System. The
demand forecasts shall include Active and Reactive Power requirements for each sub-station that is
part of the EAPP Interconnected Transmission System.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 131
CHAPTER 8 Operations Code No. 1 – Operational Planning
The EAPP demand forecast shall normally be based on the aggregate of individual TSO forecasts.
Nevertheless, the EAPP CC may carry out its own forecast using its own criteria if it has doubts on
the validity of the individual TSO forecasts. If in the event there are significant differences between
the aggregated TSO forecasts and the EAPP forecast, the EAPP CC shall prepare a report on the
reasons for any discrepancies for presentation to the EAPP Sub-Committee on Operations to
determine the matter.
TSOs shall provide the EAPP CC with estimates of the load, which could be disconnected if required.
Details shall be given of the load shedding blocks and procedures required to implement load
shedding in accordance with Chapter 12 (Demand Control, also known as OC 5 or DCC). Details shall
also be provided of the Automatic Load Shedding Scheme installed in the TSO’s National System.
By the end of October in each calendar year, the TSOs will provide the EAPP CC with:
(a) Draft Provisional Generating Unit Outage Programme for Years 2 and 3 for its centrally
despatched Generating Units
(b) Final Generating Unit Outage Programme for Year 1 for its centrally dispatched Generating
Units
Between October and December of each calendar year, EAPP CC will consider the implications of the
draft Provisional Generating Unit Outage Programmes submitted on the Operating Margin and the
security of operation of the EAPP Interconnected Transmission System and request modifications if
necessary. The Final Generating Unit Outage Programmes for Years 1, 2 and 3 shall be published on
the EAPP Website at the end of December each year.
The planning of transmission system Outages in Years 0 and 1 ahead will, in addition, take into
account Outages required because of maintenance and or operational or System Tests.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 132
CHAPTER 8 Operations Code No. 1 – Operational Planning
This may occur where the User concerned has provided generation or transmission facilities as a
consequence of a bilateral agreement. The TSO shall notify the EAPP CC of the existence and extent
of such agreements for operational planning purposes.
In carrying out Operational Planning, the capacity rights shall be taken into account in the placement
of generation or transmission Outages. However, the security of the EAPP Interconnected
Transmission System shall be the overriding consideration.
The method of calculation of the Net Transmission Capability is set out in Section 14.1.3 (Chapter 14
or ISC 1).
The EAPP CC and each TSO shall seek to resolve any Outage placement conflicts through
collaboration with each other, any relevant Users and External Systems.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 133
CHAPTER 8 Operations Code No. 1 – Operational Planning
By the end of October in each year, each TSO shall prepare a draft Maintenance Plan covering the
period up to three (3) years ahead for discussion with EAPP CC and other TSOs. TSOs shall notify
each User of those aspects of the draft Maintenance Plan that may operationally affect such User
including, in particular, proposed start dates and end dates of relevant EAPP Interconnected
Transmission System Outages. The TSO shall indicate to a Generation Licensee where a need may
exist to impose restrictions on the operation of Generating Plant Units to allow the security of the
EAPP Interconnected Transmission System to be maintained.
The development of the draft Maintenance Plan is an iterative process requiring frequent EAPP CC
and TSO liaison. Each TSO shall review the draft Maintenance Plan on an ongoing basis and provide
EAPP CC with Outage change requests, as they become known to that TSO, taking account of known
or advised User Outages.
By the end of December in each year, the draft Maintenance Plan will be confirmed and will become
the Annual Maintenance Plan for the immediate year ahead (Year 1).
In the Programming Phase, operational planning is carried out on a rolling eight (8) week cycle. Each
Friday TSOs shall update the Annual Maintenance Plan for the following eight (8) week period
beginning at 00h01 Hrs on the following Monday.
The Outage Plan for the eight (8) week period ahead will determine the transmission constraints,
which impact on the Transmission System Capability. Agreed final Outages, as published in the
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 134
CHAPTER 8 Operations Code No. 1 – Operational Planning
Annual Maintenance Plan, are only to be amended if a changed requirement is brought about by an
unplanned event on the EAPP Interconnected Transmission System.
Users shall give as much notice as reasonably practicable of any Outages affecting the EAPP
Interconnected Transmission System. Any short notice Outage on the EAPP Interconnected
Transmission System, which could not be planned, with ten (10) days’ notice is considered an
Unplanned Outage. A Planned Outage is an Outage for which at least ten (10) days’ notice has been
given.
Any variation in the planned return to service date or Outage start and completion times shall be
brought to the notice of any other TSO involved and the EAPP CC immediately it is foreseen. The
matter will be discussed between the respective TSOs and the EAPP CC in order to agree a new
return to service date and or Outage start and finish times.
Where a TSO or the EAPP CC is obliged to cancel a Planned Outage in order to safeguard the
operation of the EAPP Interconnected Transmission System, the Outage will be replanned to
minimise any adverse impact on either the User or TSO concerned.
The Operational Plan shall contain details of any additional security studies, temporary protection
settings and changes to operational arrangements to facilitate an Outage and agreements for
operational actions including emergency return to service time, demand and Generating Plant Unit
intertrip requirements and demand transfers. Any resource requirement for local switching shall be
confirmed between relevant TSOs.
The Operational Plan will contain details of all Outages of Generating Units and transmission
facilities, details of anticipated transfers, transmission constraints, Contingency plans and any other
relevant information.
8.1.11 Records
TSOs and EAPP CC shall keep records of:
(a) The availability of Generating Units and transmission facilities
(b) The duration and reasons for unavailability, whether planned or unplanned
(c) The changes requested for planned Outages in the Operational Planning process, and
(d) The cost of any constraint imposed by unavailability
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 135
CHAPTER 8 Operations Code No. 1 – Operational Planning
These records shall be made available to the EAPP Steering Committee and to the Independent
Regulatory Board upon request.
Operations planning for the ENTS shall include the following procedures wherever applicable.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 136
CHAPTER 8 Operations Code No. 1 – Operational Planning
(d) The EAPP operational agreements shall apply in the case of operational liaison with all
international power systems connected to the ENTS
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 137
CHAPTER 8 Operations Code No. 1 – Operational Planning
The equipment shall only be considered suitable for return to service when all safety
documents have been cleared and isolation points normalized.
(d) In the event of an accident during work on the ENTSO grid or at points of connection, the
following steps shall be taken:
2. Notify designated authorised person for decision on whether work should continue
or not
4. Designated authorized person produces a preliminary report and notify the ENTSO
management, the ENTGCRC as soon as possible, but no later than seven (7) days
7. The ENTSO circulates report internally and to key people in the Users systems
(e) Authorized switching personnel for TNSP(s) shall have to be recertified every year through
simulating training/testing provided by the ENTSO
8.2.5 Communication
The Generation, Transmission and Distribution entities shall provide and maintain adequate and
reliable communication facilities internally and with the ENTSO to ensure exchange of
data/information necessary to maintain reliability and security of the grid. Wherever possible,
redundancy and alternate path shall be maintained for communication along important routes.
The ENTSO shall be responsible for providing Users with operational information including planned
and forced outages as agreed upon. Any changes or modifications to the existing transmission
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 138
CHAPTER 8 Operations Code No. 1 – Operational Planning
network and/or information regarding network condition that is likely to impact the short and long-
term operation of the Users shall be communicated in a timely manner. Planned Outage shall be
deferred if it will cause any of the following:
(a) Grid disturbances
(b) System isolation
(c) Partial blackout on the ENTS
(d) Any other event that may have an adverse impact on the system
Generation Licensees shall provide the ENTSO:
(a) A 52-weeks-ahead outage plan per Generating Plant, showing Planned Outage return dates,
and other known generation constraints, updated weekly by 15:00 every Monday (or first
working day of the week)
(b) An annual maintenance / outage plan per Generating Plant, looking five (5) years ahead,
showing the same information as above and issued by July 8 (updated by September for
hydroelectric Generating Plants) each year
(c) A monthly variance report, explaining the differences between the above two reports
The ENTSO shall coordinate network Outages affecting unit output with related unit Outages to
the maximum possible extent.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 139
CHAPTER 8 Operations Code No. 1 – Operational Planning
Procedure for scheduling energy from hydroelectric units shall be done as follows:
(a) After the end of rainy season around September, an annual declaration of energy shall
be provided on a monthly basis, given the status of reservoirs and available energy
taking projected evaporation and inflows into account
(b) Available energy shall be updated on a monthly basis
(c) Available energy shall be updated for the short rainy season in March and April
(d) Daily schedules for each dam shall be updated each month. Daily schedules shall also be
updated as required in response to critical system conditions, including generator
availability
(e) During the dry season between October and February, schedules shall be adjusted as
needed to accommodate downstream water requirements from sugar plantations
(f) Generator operations shall be managed to meet the monthly energy targets
A daily generation dispatch shall be done as per the schedules described in Section 20.4.4.1 (b) and
(c) following the procedure shown below:
A dispatch form is created by the ENTSO with the date/time of the dispatch and is archived.
Expected half-hourly country demand is estimated using historical demands for the particular day.
Available Generating Plants are scheduled in half hour increments to meet forecast demand based
hydro energy targets, Spinning Reserve and other Ancillary Service system security and merit order
requirements. The generation schedules is evaluated to determine if country demand, spinning
reserve and other Ancillary Service system security needs, main hydro target and merit order
requirements have been met.
If the requirements have not been met, the system shall be re-dispatched until requirements have
been met. The ENTSO shall log the dispatch form, and customised copies of the dispatch forms shall
be sent to relevant recipients.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 140
CHAPTER 8 Operations Code No. 1 – Operational Planning
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 141
CHAPTER 8 Operations Code No. 1 – Operational Planning
deviate from normal operating limits or are expected to exceed emergency limits following a
Contingency, and if reliability of the bulk power supply is threatened, the ENTSO shall take
immediate steps to relieve the conditions. These steps include notifying other systems
(international/regional), adjusting Generation, changing Scheduling between control areas, initiating
load relief measures, and taking such other action as may be required. Please refer to Chapter 10
Emergency Operations) for more details.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 142
9 OPERATIONS CODE NO. 2 – OPERATIONAL SECURITY
This chapter contains requirements specific to both the EAPP IC and the ENTS. If in any instance there is
a difference in requirements, the more stringent requirement shall hold.
System security and reliability are primary goals of the operation of the EAPP Interconnected
Transmission System. Each TSO is responsible for the operation of its National System but the
interrelationship between that system and the EAPP Interconnected Transmission System requires
coordination by the EAPP CC at regional level.
Pending full interconnection between all countries of EAPP, the EAPP Interconnected Transmission
System shall be operated in a number of Control Areas. A Control Area comprises various National
Systems or parts of National Systems capable of regulating its Generating Units in order to meet its
constantly changing demand and to maintain its interchange schedule with other systems or Control
Areas and contributing its frequency bias obligation to the interconnection. Each Control Area shall
have one of the TSOs designated as Control Area Operator. The designation of the Control Area
Operator shall be agreed with the TSOs concerned and with the EAPP CC.
The Control Area Operator shall ensure that within its Control Area sufficient reserves of generation
are available to allow for continuous generation and load balancing, frequency control and the
maintenance of EAPP operational security standards as described in OC2. Any failure to meet these
minimum requirements can lead to reduced security or to disturbances or events causing
undesirable effects on the EAPP Interconnected Transmission System.
OC 2 specifies the technical requirements and standards for the operational security of the EAPP
Interconnected Transmission System as they relate to the following issues:
(a) N-1 Contingency criterion
(b) Interchange scheduling
(c) Operating reserves for control of system frequency and interchange with other Control
Areas or External Systems
(d) Voltage control
(e) Fault level control
(f) Protection coordination, and
9.1.2 Objective
The objectives of OC 2 are:
(a) To provide a framework of principles and requirements for achieving and maintaining the
security and reliability of the EAPP Interconnected Transmission System during operation of
the system under normal and emergency conditions, and
(b) To ensure that the EAPP Interconnected Transmission System is operated within the
technical parameters set out in Chapters 5 and 6 (Planning, and Connection)
This criterion shall be applied by all TSOs in combination with appropriate choice of generation,
transmission facilities, and sufficient active and reactive reserves. TSOs shall identify by means of
operational planning potentially insecure situations in order to take appropriate measures in advance.
Control Area Operators are responsible for the application of the N-1 Criterion throughout their
Control Area.
9.1.3.1 Contingency
The loss of any element of the EAPP Interconnected Transmission System shall not cause:
(a) A frequency deviation outside operating limits
(b) A voltage deviation leading to voltage instability
(c) Thermal overloading of equipment
(d) Islanding of any part of the EAPP Interconnected Transmission System
(e) Angular instability in the EAPP Interconnected Transmission System, and
(f) Cascading Outages
It is acceptable in some cases for TSOs to allow for loss of load on condition that its magnitude is
compatible with secure operation and is predictable and locally limited. The following normal
Contingencies shall be considered:
(a) A single transmission line
(b) A single Generating Unit or combination of Generating Units
(c) A single transformer
(d) a voltage compensation installation
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 144
CHAPTER 9 Operations Code No. 2 – Operational Security
TSOs shall also take account of multiple Contingencies when such Contingencies may occur with
sufficiently high probability to threaten the security of operation. Examples of such multiple
Contingencies are:
(a) A double circuit line, which refers to two circuits on the same towers over a considerable
distance
(b) A single busbar, during periods when the TSO assesses there is a significantly higher risk of
Outage
(c) A common mode failure with the loss of more than one Generating Unit
The Contingency monitoring process includes the loss of single or multiple elements of generation or
transmission equipment at any time. This monitoring shall also take account of temporary weather
conditions or temporary limitation of transmission facilities.
9.1.3.2 Responsibilities
It is the responsibility of each TSO to monitor the N-1 Criterion on its own National System, to carry
out computer simulations for Contingency analysis and to notify the EAPP CC, TSOs of Neighbouring
Systems and External Systems of potential problems in the application of the criterion. TSOs
concerned shall jointly verify the compliance with the N-1 criterion taking into consideration cross-
border power transfers.
After a Contingency, each TSO shall return its power system to N-1 compliant condition as soon as
possible and in case of a delay, it shall immediately notify the EAPP CC and all other TSOs affected.
The entire EAPP Interconnected Transmission System shall be operated in such a way that sufficient
transmission capacity is available for the delivery of reserve power for Primary Response for the
National Systems or Control Areas which may be affected by the most severe single Contingency.
Requirements for interchange scheduling on the EAPP Interconnected Transmission System are set
out in the Interchange Scheduling and Balancing Chapters 14 through 16.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 145
CHAPTER 9 Operations Code No. 2 – Operational Security
The requirements for operating reserve on the EAPP Interconnected Transmission System are set out
in Chapter 15 (Balancing and Frequency Control).
Each TSO shall operate reactive resources within its National System to maintain system and
interconnection voltages within limits. Each TSO shall maintain reactive resources to support its
voltage under N-1 Contingency conditions and shall disperse and locate the reactive resources so
that they can be applied promptly and effectively when Contingencies occur. The TSO shall direct
corrective action, including load shedding, necessary to prevent voltage collapse when reactive
resources are insufficient.
Reactive Power flows on the EAPP Interconnected Transmission System shall be maintained at a
minimum level in order to limit voltage drop and to allocate the total Transmission System Capability
mainly to Active Power. In the event that sufficient reactive resources are not available within a
TSO’s National System, bilateral agreements may be made with Neighbouring Systems to transfer
Reactive Power through cross-border connections.
9.1.6.2 Responsibilities
Each TSO individually and jointly with other TSOs and the EAPP CC shall ensure that formal policies
and procedures are developed, maintained, and implemented for monitoring and controlling
voltage levels and Mvar flows within their National Systems and with Neighbouring Systems.
Without limitation, the procedures shall include the following methods of voltage control:
(a) Adjusting Generating Unit Reactive Power output
(b) Transformer tap changing, cable switching, reactor and capacitor switching, and other
control methods
(c) Tap changing on Generating Unit transformers
(d) Scheduling must-run generation, and
(e) Switching out of transmission lines
TSOs shall ensure that data on all generation and transmission Reactive Power resources, including
the status of voltage regulators, tap changers and Power System Stabilisers, is available to
neighbouring TSOs and the EAPP CC.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 146
CHAPTER 9 Operations Code No. 2 – Operational Security
TSOs shall ensure that the setting and function of the protection equipment is checked regularly. If
there are significant changes in operating conditions, the settings of protection devices shall be
adjusted to suit the new conditions.
9.1.7.1 Standards
Each TSO shall operate its National System such that, at any node of the EAPP Interconnected
Transmission System, short-circuit currents do not exceed the breaking capacity of the switchgear
installed at that node, so that failure to clear a fault does not lead to cascading Outages. The TSO
shall use an appropriate protection strategy as set out in Chapter 6 (Connection) to ensure
selectivity and to provide backup protection in case of failure of the main protection system to
isolate a fault.
Each TSO shall calculate where appropriate the short-circuit currents at each node of its National
System taking into account the contributions of Neighbouring Systems to the short circuit current.
TSOs of Neighbouring Systems shall exchange the data required for short circuit calculations.
In order to limit fault levels in operational timescales, TSOs have a number of options including the
switching out of lines and the operation of busbars in separate sections. However, TSOs shall take
into account the operational security standards when considering such measures.
Each TSO and the EAPP CC shall ensure that its Control Centre personnel are familiar with the
purpose and limitations of the protection system schemes applied in the EAPP Interconnected
Transmission System. Power system protection procedures shall be made available to all
appropriate system personnel and shall provide for instructions and training where applicable.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 147
CHAPTER 9 Operations Code No. 2 – Operational Security
9.1.9 Requirements
Since protection systems in one National System can affect operations in Neighbouring Systems, all
protection systems in the EAPP Interconnected Transmission System shall be co-ordinated between
Users and the relevant TSOs. Protection systems on transmission interconnections with External
Systems shall also be coordinated to prevent operational problems, which may impact on the EAPP
Interconnected Transmission System.
Each TSO shall supervise the status of its protection system and notify all relevant neighbouring
TSOs of every change in status.
Each protection device shall be recalibrated at least once a year. A review of the protection settings
shall also be carried out whenever there is an expansion or change to the transmission or generation
facilities. Any incorrect operation of a protection device shall be reported in accordance with the
guidelines in Chapter 11 (Incident Reporting or OC 4), investigated immediately and corrective
action implemented as soon as possible.
Neighbouring TSOs shall be notified in advance of changes in generating sources, transmission, load
or operating conditions, which may require adjustments to their protection systems.
RAS installed on the EAPP Interconnected Transmission System shall be subject to agreement
between the relevant TSOs and the EAPP CC unless the automatic actions following operation of RAS
are confined to the area of a single TSO. RAS shall be subject to procedures detailing the operation
and the conditions for switching into service of the scheme. The effects of the automatic actions
arising from the operation of the RAS shall be subject to the specific agreement of all TSOs and Users
involved.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 148
CHAPTER 9 Operations Code No. 2 – Operational Security
TSO Control Centres shall monitor the status of all RAS and notify all relevant TSOs and the EAPP CC
of any change of status.
Each TSO shall agree with neighbouring TSOs and the EAPP CC the real- time data to be exchanged
on-line and its format.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 149
CHAPTER 9 Operations Code No. 2 – Operational Security
If there are no objections, the Generating Plant operator shall carry out required operation as
instructed as expeditiously as possible. The Generating Plant operator shall inform the ENTSO of
completion of carrying out required operation.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 150
CHAPTER 9 Operations Code No. 2 – Operational Security
In case of any objections, the Generating Plant operator shall notify the ENTSO, and the ENTSO shall
investigate the refusal to carry out the operation.
Both the ENTSO and the Generating Plant operator shall log the following information upon sending
or receiving an operational message/instruction/report on radio/telephone/ cell phone/carrier
Generating Plant AVRs and VAR limiter relays (where fitted) should be in service continuously.
Whenever a Generating Plant is operating without its AVR or VAR limiter, the ENTSO must be
immediately informed.
The times at which a Generating t Plant shall be synchronised and switched off the interconnected
system and the output (MW and Mvars) of such plant shall be directed by ENTSO.
The ENTSO shall instruct the Generating Plant when to turn on and off and the Generating Plant
shall comply. When the Generating Plant is on, it shall follow the ENTSO’s instructions regarding
output (MW and Mvars).
Generating Plants shall not be taken out of service or rendered unavailable without reference to the
ENTSO except in cases of emergency when the ENTSO shall be informed as soon as possible of the
action taken.
The ENTSO shall as soon as possible be notified of any factors, which may affect the output,
efficiency or inflexibility of operation of any Generating Plant.
Free Governor Action must be allowed within the prescribed limits whenever practicable to assist
frequency control.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 151
CHAPTER 9 Operations Code No. 2 – Operational Security
(c) The TNSP shall switch in system neutral earthing as fast as possible, and inform the ENTSO
of completion of switching in neutral earthing
(d) If restoration is not possible, the ENTSO shall quickly co-ordinate activities with the TNSP to
make that part of the system without neutral earthing dead and log the time
(e) The ENTSO shall log down exact time of switching in system neutral earthing
The TNSP shall inform the ENTSO of the intention to carry out work on the protective apparatus. The
TNSP shall also provide details of work to be carried out.
The ENTSO shall assess the request and determine if work can proceed or not according to the
following conditions:
If none of the three conditions is prevalent, the ENTSO shall approve the request and inform TNSP to
proceed with work. The TNSP shall carry out the work accordance with a procedure for such kind of
work.
If any of the above conditions exists, the ENTSO shall reject the request for work and inform the
TNSP of the rejection.
When a line fault causes breakers controlling the line to trip, the TNSP shall coordinate with the
ENTSO as per operational guidelines listed below:
(a) The ENTSO shall notice the unexpected trip from the SCADA and check to confirm whether
the line has auto-reclosed or locked out. If line has auto-reclosed, the TNSP shall note the
relays operated and distance of fault from the distance fault recorder and pass them to the
ENTSO. The ENTSO shall log the relays operated and the distance of fault along with other
information such as location of fault, identified by station, if possible; exact time of event;
name of person working on the event; and exact time the fault was cleared. The incident
shall be logged and relevant personnel shall be informed
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 152
CHAPTER 9 Operations Code No. 2 – Operational Security
(b) If the line has locked out, the ENTSO shall evaluate impact of the trip on the system by
observing system response to the trip. In case of serious impact – the ENTSO shall take
relevant appropriate action to stabilise the system
(c) If the impact is not serious, the ENTSO shall make every effort to find the root cause of this
issue as per the established procedure of the ENTS and document it. The ENTSO shall check
to confirm with the TNSP if any work is being carried out on the line. If so, the ENTSO shall
determine if the fault is caused by the TNSP. If fault is caused by the TNSP, The ENTSO shall
instruct the TNSP to eliminate the cause of fault, and the TNSP shall notify the ENTSO of the
completion of eliminating the fault
(d) If no work is being carried out on the line, The ENTSO shall check to confirm if line is from a
manned substation or not. If the line is from a manned substation, The ENTSO shall issue
instructions for reading and resetting relays and distance of fault from the distance fault
recorder. If the line is from an un-manned substation, The ENTSO shall direct the TNSP to
the relevant substation. The TNSP shall note down relays operated, reset them, and also
record the distance of the fault from the fault recorder
(e) The ENTSO shall check to confirm whether breaker-operating commands are available or
not, and if so, issue instructions for closing of line breakers. The ENTSO shall close breakers
controlling the line by sending a closing command using SCADA
(f) If breaker-operating commands are not available, The ENTSO shall issue instructions to the
TNSP for a reclosure. The TNSP shall try a reclosure on the line and notify the ENTSO of
completion of carrying out a reclosure. If the line holds, the ENTSO shall check to confirm
whether the line trips again or not, and if any Customers are interrupted because of the trip.
If Customers are interrupted and there is alternative source of supply, the ENTSO shall
transfer or co-ordinate activities to transfer Customers to alternative source of power
(g) If no Customers are interrupted or if they are interrupted and there is no alternative source
of power, the ENTSO shall check to confirm whether there is a switch along the transmission
line or not. If there is an isolator along the line, the ENTSO shall direct the TNSP to the
isolator. The TNSP shall confirm arrival at the isolator, and the ENTSO shall issue
instructions to open the isolator on the line. Instruction shall be issued keeping in mind
Electrical safety rules. The ENTSO shall try a reclosure on the two line- sections one after
the other. If there is no trip, The ENTSO shall issue instruction to close the isolator properly
and normalise the line
(h) If there is no isolator along the line, the ENTSO shall issue instructions to isolate the faulty
section. Isolation of the fault shall be done by the TNSP, who shall open isolators controlling
the affected section and securing them in open position as instructed by the ENTSO. The
ENTSO shall notify the TNSP about the faulty part of the system. The ENTSO shall log the
incident.
(i) The TNSP shall patrol the line to determine the fault. The ENTSO shall wait for a report
from the TNSP
(j) Upon finding the fault, the TNSP shall report to the ENTSO details of isolations required for
repairs to be carried out, and the ENTSO shall issue instructions to isolate the location of the
fault. The TNSP shall inform the ENTSO of completion of carrying out isolations
(k) The TNSP shall carry out repair of fault using appropriate tools and shall notify the ENTSO of
completion of carrying out repairs. The ENTSO shall issue instructions to normalise the line
and the system
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 153
CHAPTER 9 Operations Code No. 2 – Operational Security
(l) The TNSP shall normalise line and system as instructed by The ENTSO, and confirm of
completion of normalising the system. The ENTSO shall normalise and log the incident
(a) The ENTSO shall establish whether it is a total or partial SCADA failure
(b) For a partial failure, the ENTSO shall assess the effects the failure has on generation,
transmission and sub-transmission systems
(c) In case of a total failure, the ENTSO shall inform the TNSPs and the RCCs of the failure, and
instruct the RCCs to begin diagnosis, repair and restoration work. Upon the completion of
the work, the RCCs will inform the ENTSO. The ENTSO shall issue instructions to normalise
the sub system and report -back to the ENTSO
(d) The ENTSO shall instruct the TNSPs and the RCCs to monitor system parameters i.e. system
Frequency and Voltage and report any significant variations/changes
(e) The ENTSO shall instruct all Generating Plants and TNSPs to report any trip of a machine or
line
(f) In case of a major disturbance on the ENTS affecting SCADA equipment:
1. An incident shall be reported to the ENTSO by the TNSP or RCCs as soon as possible
with the following information: nature of incident; equipment affected; location of
equipment; Customers affected; and actions to be carried out. The ENTSO shall
evaluate whether incident has severe impact on the system
2. If there is a severe impact, the ENTSO shall take the necessary appropriate action to
ensure the integrity of the system, and determine if assistance is required or not
3. If assistance is required, the ENTSO shall call relevant staff, inform them about the
incident, and instruct them to call from desired locations
4. The ENTSO shall check to find out if there are any casualties because of the incident.
In case of any casualty, the ENTSO shall call and inform the safety officer of the
affected installation; location of the equipment; cause of the incident; and damage
incurred
5. Depending on the impact caused, the ENTSO shall make sure whether the incident is
newsworthy. If it is newsworthy, the ENTSO shall inform relevant communications
officers of the following: nature of incident; affected installation; and affected
Customers
The ENTSO shall direct work for the identification of fault and repair. Upon the completion of the work,
the ENTSO shall normalise the system and log the incident.
9.2.1.11 Access Security
The ENTSO shall have a detailed plan and procedures governing security and access to the system
Users’ SCADA, computer, and communications equipment. The procedures shall allow for adequate
access to the equipment and information by the ENTSO or its nominated representative for
purposes of maintenance, repair, testing, taking of readings/measurements, and periodic checking
as deemed necessary. Participants shall ensure reasonable security against unauthorised access, use,
and loss of information and a backup storage strategy for the systems that contain the information.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 154
CHAPTER 9 Operations Code No. 2 – Operational Security
While preparing the net injection schedule for hydro generation, the ENTSO shall consider the
operating zone/technical constraints, to the extent possible.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 155
10 OPERATIONS CHAPTER NO. 3 – EMERGENCY OPERATIONS
This chapter contains requirements specific to both the EAPP IC and the ENTS. If in any instance there is
a difference in requirements, the more stringent requirement shall hold.
Although the EAPP Interconnected Transmission System may be designed and operated in line with
the security standards set out in the PC and OCs, unexpected circumstances may arise where faults
and disturbances outside the defined Contingencies may occur. Such circumstances require timely
and decisive action to prevent further propagation of the disturbance. Disturbances can result from
a number of causes but most typically may be due to the simultaneous loss of a number of
Generating Units or transmission failures resulting from severe weather conditions or mal-operation
of protection systems.
This is particularly the case where power systems today tend to be operated closer to the security
limits due to environmental constraints and market pressures. The overriding principle is that the
effects of faults and disturbances should be confined to as small a part of the EAPP Interconnected
Transmission System as possible.
10.1.2 Objective
The objectives of OC 3 are to ensure that TSOs and the EAPP CC:
(a) Are able to identify insecure operating conditions on the EAPP Interconnected Transmission
System
(b) Have procedures and plans in place to manage emergency conditions
(c) Have comprehensive contingency plans in place for the restoration of supplies in the
shortest possible time using the most effective means
(b) Lack of operating reserves (caused, for example, by Outages of Generating Units, by
hydrological conditions or by restricted transmission capacities)
(c) Human error when carrying out switching operations on the EAPP Interconnected
Transmission System
(d) Frequency excursions outside normal operating limits
(e) Significant Reactive Power constraints leading to critical high or low voltage conditions
(f) High Reactive Power flows giving rise to potential protection mal-operations
(g) Indications of instability such as voltage drop, undamped power swings or increase of phase
angles
(h) Lack of reliable real-time data, and
(i) Adverse climatic conditions
In the event of identifying a risk of insecure operation, a TSO or the EAPP CC may issue an ALERT or
an EMERGENCY warning in real-time. These warnings shall be issued to all Users within a TSO’s
National System and to the EAPP CC and any Neighbouring System, which may be affected by the
risk. Any warning issued by a TSO may be applied to the whole or part of its National System and by
agreement with neighbouring TSOs to the whole of or part of their National Systems. The EAPP CC
may also issue warnings when in its view there is a serious risk to the whole EAPP Interconnected
Transmission System.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 157
CHAPTER 10 Operations Chapter No. 3 – Emergency Operations
TSOs shall act to alleviate emergencies and to implement emergency procedures in cooperation
with neighbouring TSOs and the EAPP CC.
The Control Centre SCADA system shall also provide facilities for post-mortem review to enable a
detailed analysis of events and disturbances to be carried out.
Each TSO shall make available real-time data of relevant parts of its National System to neighbouring
TSOs and the EAPP CC. Details of the data to be exchanged in real time shall be agreed between the
parties.
TSOs shall ensure the provision of a direct telephone line to neighbouring TSOs and the EAPP CC.
The EAPP CC shall make arrangements to carry out a similar series of studies for the whole EAPP
Interconnected Transmission System.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 158
CHAPTER 10 Operations Chapter No. 3 – Emergency Operations
TSOs and the EAPP CC shall agree the list of Contingencies to be considered in carrying out the
studies. The data required for the security analysis studies is contained in Section 19.8 of Chapter 19
(Data Exchange).
Each TSO and the EAPP CC shall develop, maintain and implement robust and comprehensive
procedures for emergency situations and have a strategy and plans in place for the safe and prompt
restoration of electricity supply. TSOs shall also ensure that their personnel and any of their Users
involved in implementing the emergency procedures are fully aware of and trained and tested in
their responsibilities.
TSOs shall provide copies of their emergency plans and procedures to neighbouring TSOs, EAPP CC
and to relevant Users within their National Systems. These plans and procedures shall be
coordinated with other TSOs, the EAPP CC and External Systems.
The emergency plans and procedures agreed between TSOs, EAPP CC and relevant Users shall
include, but not be limited, to the following:
(a) The procedures for the dissemination of the system state warnings set out in Section 10.1.4
in Chapter 10 (Emergency Operations – System Warnings) to neighbouring TSOs, EAPP CC
and relevant Users and the actions to be taken on receipt of a warning
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 159
CHAPTER 10 Operations Chapter No. 3 – Emergency Operations
(b) The requirement to establish and maintain reliable communications between all interested
parties and the communications protocols to be used
(c) A list of personnel appropriately authorised to take action in emergencies together with
their contact details
(d) Any requirement under national legislation to inform government and other public authorities
of the existence of an emergency condition on the EAPP Interconnected Transmission System
and the possible effects of the situation on population and infrastructure
(e) The requirement to ensure rapid information exchange between TSOs about system
conditions particularly close to their common borders. This information should include the
topology of the system and its weak points and the potential risks of tripping
(f) The possible need to arrange new interchange agreements to provide for emergency
capacity or energy transfers if existing agreements cannot be used
(g) A contingency plan to continue safe and reliable operations in the event of total loss of a
TSO’s Control Centre or communications facilities
(h) The need to ensure that sufficient resources of trained, tested and authorized personnel are
available in control rooms and for operation under all conditions
(i) The need to modify cross-border transfers to alleviate overloading
(j) The application of load shedding in some parts of the EAPP Interconnected Transmission
System in order to limit the risk of cascade tripping
(k) The regular training of all personnel in operation under emergency conditions
TSOs shall make every effort to remain connected to the EAPP Interconnected Transmission System
under emergency conditions. If a TSO however considers that its National System is endangered if it
remains connected, it may implement any remedial action necessary to protect its own National System.
The EAPP Sub-Committee on Operations is responsible for the review of the emergency procedures
annually to ensure that the emergency plans and procedures comply with Chapter 10 (Emergency
Operations or OC 3).
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 160
CHAPTER 10 Operations Chapter No. 3 – Emergency Operations
Interconnected Transmission System as an integrated whole in the shortest possible time using the
most effective means following a Total Shutdown or Partial Shutdown.
The complexities and indeterminate nature of recovery from a Total Shutdown or Partial Shutdown
require that any Black Start Procedure is sufficiently flexible in order to accommodate the full range
of Generating Unit and EAPP Interconnected Transmission System characteristics and operational
possibilities. This precludes the setting out of concise chronological sequences. The overall strategy
may include the overlapping phases of establishment of isolated groups of Generating Units
together with complementary local demand. These groups are termed Power Islands. The step-by-
step integration of these Power Islands into larger sub-systems will eventually result in the re-
establishment of the EAPP Interconnected Transmission System.
10.1.7.1 Responsibilities
TSOs are responsible for the preparation of the strategy and plan for system restoration and Black
Start as part of the procedures set out in Section 10.1.6 (Emergency Operations – Emergency
Procedures).
When a Total Shutdown or Partial Shutdown exists on its National System, the TSOs shall notify the
TSOs of Neighbouring Systems and the EAPP CC and shall agree the initial steps in the restoration
process.
Each TSO is primarily responsible for re-starting its respective National System after a Total or
Partial Shutdown that disconnects its system from the EAPP Interconnected Transmission System.
Each TSO shall be responsible for ensuring Generating Units with Black Start Capability as specified
in CC 8.6 (Black Start Units) are available within its National System. TSOs shall contract for Black
Start capability in accordance with Chapter 16 (Ancillary Services ISBC3).
Appropriate tests and simulations shall be carried out on an annual basis to ensure that:
(a) Black Start Units are capable of starting up without any external power supply;
(b) the National System can be energised and loaded from the Black Start Unit(s), and
(c) the National System can be re-synchronised with the EAPP Interconnected Transmission System.
Black Start Tests may involve synchronisation of generation to the EAPP Interconnected
Transmission System or connection of demand remote from the Black Start Unit.
10.1.7.2 Procedure
In the event that the systems of neighbouring TSOs remain de-energised after a Total Shutdown of
the EAPP Interconnected Transmission System, TSOs shall determine, by means of tests or
simulations, the amount of system and load that could be energised from their National System.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 161
CHAPTER 10 Operations Chapter No. 3 – Emergency Operations
Whenever possible the TSOs affected by a Total Shutdown shall coordinate the restoration process.
If they consider it necessary to re-configure the EAPP Interconnected Transmission System or
disconnect some cross-border connections, they shall request the EAPP CC to coordinate the
operation with all other TSOs that may be affected by the action.
Each TSO shall recover its National System and obtain the balance between generation and demand
in coordination with its Users, handling the synchronization operations of their systems until
complete integration with the EAPP Interconnected Transmission System is achieved. The EAPP CC
shall be responsible for the overall supervision of the restoration process of the EAPP Interconnected
Transmission System.
During the initial stages of restoration normal operational security standards may not be appropriate
or possible and the EAPP Interconnected Transmission System or a National System may be operated
outside normal voltage and frequency limits provided that it does not result in damage to Plant and
or Apparatus, or a safety hazard to persons.
The designated TSO of a Power Island shall ensure that the Power Island is managed in a secure and
safe manner. Where possible a Power Island should be operated in accordance with the following
frequency and voltage criteria:
(a) the frequency in the Island shall be nominally 50 Hz and shall be controlled within the limits
49.5 – 50.5 Hz
(b) the voltage on the Transmission System in the Island shall normally remain within -/+ 10% of
nominal. Voltages of +20% and –15% should not prevail for more than 15 minutes
Close coordination between TSOs and Users is required to achieve and maintain these frequency
and voltage levels.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 162
CHAPTER 10 Operations Chapter No. 3 – Emergency Operations
(a) The ENTSO shall develop and maintain Contingency plans to manage system contingencies
and emergencies that are relevant to the performance of the Interconnected Power System
(IPS). Such Contingency plans shall be developed in consultation with all Users shall be
consistent with internationally acceptable utility practices, and shall include but not be
limited to:
1. Under-frequency load shedding
2. Meeting Ethiopia’s disaster management requirements, if any, including the
necessary minimum load requirements
3. Forced outages at all points of interface, and
4. Supply restoration
(b) Emergency plans shall allow for quick and orderly recovery from a partial or complete
system collapse, with least cost solution and minimum impact on customers
(c) Emergency plans shall comply with EAPP agreements and guidelines
(d) The ENTSO shall periodically verify Contingency and/or emergency plans by actual tests to
the greatest practical extent possible. In the event of such tests causing undue risk or undue
cost to a User, the ENTSO shall take such risks or costs into consideration when deciding
whether to conduct the tests. Any tests shall be carried out at a time that is least disruptive
to the Users and embedded end-use customers. The costs of these tests shall be borne by
the respective asset owners. The ENTSO shall ensure the co-ordination of the tests in
consultation with all affected Users
(e) The ENTSO shall specify minimum emergency requirements for distribution control centres,
Generating Plant local control centres and substations to ensure continuous operation of
their control, recording, annunciator and communication facilities
(f) It shall be ensured that other Users comply with the ENTSO’s reasonable requirements for
Contingency and emergency plans
(g) The ENTSO shall set the requirements for automatic and manual load shedding. Users shall
make available loads and schemes to comply with these requirements. When the SCADA
system displays a sudden loss of generation accompanied by a drastic drop in system
frequency without the operation of under frequency scheme, the ENTSO shall monitor the
system for a voltage collapse. If a voltage collapse is imminent, controlled load-shedding is
initiated according to Ethiopia Power System Control procedure
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 163
CHAPTER 10 Operations Chapter No. 3 – Emergency Operations
(h) If a sudden loss of a large generation plant occurs on the system followed by an operation of
under frequency scheme, the ENTSO shall initiate action as detailed in the Ethiopia Power
System Control procedure
(i) The ENTSO shall be responsible for determining all operational limits on the ENTS, updating
these periodically and making these available to the Users
(j) The ENTSO shall conduct load flow studies regularly as indicated in section 10.1.5
(Responsibilities of the ENTSOs - Security Analysis) to determine the effect that various
component failures would have on the reliability of the system. At the request of the ENTSO,
Distribution Licensees shall perform related load flow studies on their part of the network
and make the results available to the ENTSO
(k) Studies shall be made on a coordinated basis to:
1. Determine the facilities on each system, which may affect the operation of the
coordinated area
2. Determine operating limitations for normal operation when all transmission
components are in service; and
3. Determine operating limitations of transmission facilities under abnormal or
emergency conditions. In determining ratings of transmission facilities, consideration
shall be given to thermal and stability limits, short and long time loading limits, and
voltage limits
(l) Periodic studies shall be made to determine the Emergency Transfer Capability of
transmission lines interconnecting control areas. Studies shall be made annually or at such
other time that changes are made to the power system, which may affect the Emergency
Transfer Capability
(m) Studies shall be made to develop operating voltage or reactive schedules for both normal
and outage conditions
(n) Adequate coordination with the Neighbouring Systems to use uniform line identifications
and ratings when referring to transmission facilities of a transmission system network shall
foster consistency when referring to facilities and reduce the likelihood of
misunderstandings
(o) The scheduling of Outages of transmission facilities which may affect Neighbouring Systems
shall be co-ordinated with the appropriate authorities
(p) Any Emergency Outage, which may have a bearing on the reliability of the transmission
system shall be communicated to all systems which may be affected
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 164
11 OPERATIONS CHAPTER NO. 4 – INCIDENT REPORTING
This chapter contains requirements specific to both the EAPP IC and the ENTS. If in any instance there is
a difference in requirements, the more stringent requirement shall hold
OC 4 also describes the procedure for the joint investigation of significant incidents and for the
technical audit of TSO’s procedures and Plant and or Apparatus connected to, or forming part of,
the EAPP Interconnected Transmission System.
11.1.2 Objective
The objectives of OC 4 are:
(a) To specify the roles and responsibilities of TSOs and EAPP CC with regard to significant
incident reporting
(b) To provide for the joint investigation by TSOs, EAPP Steering Committee and the
Independent Regulatory Board of any significant incident that has had, or could have had, a
widespread impact on any part of the EAPP Interconnected Transmission System, and
(c) To make provision for the technical audit of a TSO’s procedures and Plant and / or
Apparatus connected to, or forming part of, the EAPP Interconnected Transmission System
The EAPP Steering Committee and the Independent Regulatory Board may require the provision of a
report on a significant incident, which in their view has compromised the secure operation of the
EAPP Interconnected Transmission System.
Without limiting the requirements of OC 4, TSOs shall report any of the following incidents that have
or could have adversely affected the security of the EAPP Interconnected Transmission System or the
safety of persons or system equipment:
(a) Manual or automatic tripping under emergency conditions of system circuits and Plant
associated with the EAPP Interconnected Transmission System
The Report shall provide a detailed description of the incidents that occurred as well as the actions
taken for the re-establishment of normal conditions on the EAPP Interconnected Transmission System.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 166
CHAPTER 11 Operations Chapter No. 4 – Incident Reporting
Transmission System. The purpose of the Interim Report is to alert the EAPP CC and other TSOs of
the possible need to take immediate action.
When a TSO requires more than thirty (30) business days to submit a Final Report, it may request
additional time and agree a new timescale to carry out the relevant investigations.
The Final Report is subject to the approval of the EAPP Steering Committee and of the Independent
Regulatory Board. If either body fails to approve the Final Report, the incident shall be subject to a
Joint Investigation in accordance with Section 11.1.4 in this chapter.
The EAPP Sub-Committees on Planning and Operations shall track and review the status of all
recommendations from Final Reports at least twice a year to ensure they have been implemented in
due time. If any recommendation has not been implemented within two (2) years, or if the tracking
and review process indicates at any time that the recommendation(s) are not being pursued with
due diligence, the matter shall be bought formally to the attention of the EAPP Steering Committee
and the Independent Regulatory Board for further action.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 167
CHAPTER 11 Operations Chapter No. 4 – Incident Reporting
where approval of the Final Report by the EAPP Steering Committee and or the Independent
Regulatory Board has been withheld.
The composition of the Joint Investigation Committee shall be appropriate for the incident to be
investigated and agreed by all parties involved. If an agreement cannot be reached on the composition
of the Committee, the EAPP Steering Committee and the Independent Regulatory Board shall decide.
The terms of reference and all matters relating to the Joint Investigation shall be agreed by the
parties in good faith and in a timely manner. The investigation shall begin within fifteen (15)
business days from the request for a Joint Investigation.
These technical audits shall be carried out by experts nominated by the EAPP Sub-Committees on
Planning and Operations or Independent Regulatory Board as the case may be. TSOs shall allow
access for the inspection of their facilities, provide the required information, and accept and comply
with the recommendations of the technical audit.
………………………………………………………………………………………………………
………………………………………………………………………………………………………
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 168
CHAPTER 11 Operations Chapter No. 4 – Incident Reporting
….…………………..……………………………………………………………………………….
….…………………..……………………………………………………………………………….
..…………………….……………………………………………………………………………….
………………………………………………………………………………………………………
………………………………………………………………………………………………............
………………………………………………………………………………………………............
………………………………………………………………………………………………............
………………………………………………………………………………………………............
………………………………………………………………………………………………............
………………………………………………………………………………………………............
OTHER RELEVANT INFORMATION (Weather conditions, change in output of Generating Units etc.)
………………………………………………………………………………………………………
………………………………………………………………………………………………………
………………………………………………………………………………………………………
………………………………………………………………………………………………………
………………………………………………………………………………………………………
………………………………………………………………………………………………………
………………………………………………………………………………………………………
………………………………………………………………………………………………………
………………………………………………………………………………………………………
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 169
CHAPTER 11 Operations Chapter No. 4 – Incident Reporting
...…………………………………………………………………………………………………….
…………………… ………………………………………………………………………………..
An incident is reported to the ENTSO by operators or regional controller when a major disturbance
occurs on the national grid resulting in casualties, loss of supplies or damage to equipment. An
incident shall be reported with the information on the nature of incident, its location,
people/customers/installations affected, and corrective actions taken as soon as possible. Procedure
for handling incident reporting shall be followed as per Ethiopia Power System Control procedure.
Following are some guidelines regarding incident reporting, investigation, and analysis:
(a) Generation Licensees shall report loss of output and tripping of units and change of status of
AGC and governor to the ENTSO within two (2) minutes of the event occurring
(b) In the event of a multiple unit tripping, the relevant Generation Licensee shall submit a
written report to the ENTSO within seven (7) to fifteen (15) days identifying the root causes
of the incident and the corrective actions taken.
(c) The ENTSO shall be responsible for developing and maintaining an adequate system of fault
statistics
(d) Incidents shall be reported to the Regulatory Authority as defined in the license conditions
(e) A User may issue an incident report to the ENTSO on becoming aware of an occurrence. The
ENTSO shall provide a reason for the incident, what has been done to address it, and, if
appropriate, indicate what action it shall take to avoid such an incident(s) in the future
(f) The ENTSO may also issue an incident report to a User, where the User does not comply
with necessary requirements. The User shall provide the ENTSO with reasons for the
incident and, where appropriate, indicate the measures that will be taken to address the
problem
(g) Incidents involving sabotage or suspected sabotage, as well as threats of sabotage on the
power system shall be reported to the ENTSO
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 170
CHAPTER 11 Operations Chapter No. 4 – Incident Reporting
(h) Any incident that materially affected the quality of the service to a Participant/User shall be
formally investigated. These include interruptions of supply, disconnections, under or over
voltage incidents, quality of supply contraventions, etc. A preliminary incident report shall
be available after three (3) working days and a final report within three months. The ENTSO
shall initiate such an investigation, arrange for the writing of the report and involve all
affected Participants/Users. All these Participants/Users shall make all relevant required
information available to the ENTSO. The confidentiality status of information involved shall
be maintained
High-risk incidents include the ones causing: (a) significant disruption of supply to customers; (b)
substantial damage to equipment and switchgears; (c) fires in establishments; and (d) adverse
environmental consequences (e.g. bushfires, environmental pollution, etc.). Information necessary
for incident reporting are summarized as:
(a) Sequence of events necessary for root cause analysis (includes loading and generation
situation before/during/after the disturbance, and historical performance of the failed
equipment)
(b) Details regarding the fault containing chronological description of the incident’s occurrence,
operations during the incident and the cause of the incident
(c) Any known facts such as: Protection malfunctions; Malfunction of Electrical Plant
equipment; Malfunction of telecommunications and SCADA; Transport problems;
Manpower problems
(d) Any of the following actions taken after occurrence of the incident: Emergency actions
taken; Strategies taken to operate the system under fault condition; Operating procedures
used during the disturbance; instructions issued, timings for execution; Restoration actions
initiated
(e) Any conclusions/recommendations that include: Weaknesses found in the disturbance
handling, equipment mal-operations performance; System response to the disturbance; Any
mal-operations; Evaluation of all aspects of operation; Any modifications of disturbance
handling procedures and why
(f) Any remedial actions taken to restore supplies and equipment
(g) Distribution of completed reports to the Operational Heads
Despite the urgency of the situation, careful, prompt, and complete logging of all operations and
operational messages shall be ensured by all Users to facilitate subsequent investigation into the
incident and the efficiency of the restoration process.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 171
12 OPERATIONS CHAPTER NO. 5 – DEMAND CONTROL
This chapter contains requirements specific to both the EAPP IC and the ENTS. If in any instance there is
a difference in requirements, the more stringent requirement shall hold
TSOs shall, after taking all other remedial actions, disconnect customer demand rather than risk an
uncontrolled failure of Plant and or Apparatus or cascading Outages of the EAPP Interconnected
Transmission System.
12.1.2 Objective
The objective of OC 5 is to require TSOs to have procedures in place to enable a reduction in
demand on the EAPP Interconnected Transmission System in order to avoid a breakdown or
overloading of the system or in the event of generation shortage.
The type of demand control utilised by the TSO in any particular circumstances will depend upon the
amount of time between the TSO becoming aware of the need for implementing demand control
and the time at which it needs to be implemented. In the event of a sudden and unexpected loss of
generation on the EAPP Interconnected Transmission System, the requisite demand control will
normally be achieved by means of Automatic Load Shedding but, occasionally, emergency manual
disconnection may additionally be required. In all cases when demand control is necessary, the TSO
shall use demand disconnection as the last option.
Any such notification issued shall be provided as soon as reasonably possible after the TSO or the EAPP CC
has grounds to believe that there is a risk of demand reduction. The notice shall include an estimate of:
(a) the required level of demand control in MW;
(b) the expected start time and duration of demand control.
Under the terms of Emergency Operations or OC 3 (Chapter 10), TSOs and or EAPP CC are
responsible for the issue of ALERT and EMERGENCY warnings. The existence of a risk of demand
reduction shall normally be included within one of these warnings.
Each TSO shall establish plans for Automatic Load Shedding for underfrequency and undervoltage
conditions. The overall Automatic Load Shedding Scheme for the EAPP Interconnected Transmission
System shall be coordinated by the EAPP CC in order to prevent excessive transfers across the EAPP
Interconnected Transmission System and possible instability.
A TSO shall implement load shedding in steps established to minimize the risk of further
uncontrolled separation, loss of generation, or system shutdown.
TSOs shall coordinate Automatic Load Shedding in their National Systems with underfrequency
isolation of Generating Units, tripping of shunt capacitors, and other automatic actions that will
occur under abnormal frequency, voltage, or power flow conditions.
12.1.5.1 Procedure
The following procedures are to be followed by a TSO in the implementation of the Automatic Load
Shedding Scheme on its National System:
(a) Each TSO shall make available up to 60% of its annual peak demand for the Automatic Load
Shedding Scheme
(b) Schemes shall be based on system dynamic performance where the greatest probable
imbalance between demand and generation is simulated
(c) Schemes should be analysed to ensure that no unacceptable over-frequency, over- voltage
or transmission overload will occur
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 173
CHAPTER 12 Operations Chapter No. 5 – Demand Control
(d) The demand on the EAPP Interconnected Transmission System subject to an Automatic Load
Shedding Scheme will be split by the TSO into discrete blocks. The number, location, size and
the associated low frequency or low voltage settings of these blocks will be as determined
by the TSO in consultation with the EAPP CC and shall not unduly discriminate against or
unduly prefer any one group of Users. The TSO and EAPP CC shall also take into account
constraints on the EAPP Interconnected Transmission System when determining the size and
location of demand reduction by Automatic Load Shedding
(e) If the EAPP Interconnected Transmission System is still in a critical condition following
frequency or voltage recovery after the activation of the Automatic Load Shedding Scheme,
a TSO may implement manual disconnection of additional demand to permit restoration of
the previously disconnected demand;
(f) Demand disconnected by the Automatic Load Shedding Scheme shall only be restored on
the instruction of the TSO with the agreement of the EAPP CC unless there are particular
local circumstances
(g) The settings of under-frequency and under-voltage relays shall be coordinated with the
emergency plans and procedures required by OC 3
(h) TSOs and EAPP CC shall review annually the settings of under-frequency and under-voltage
relays and the levels of demand to be disconnected
Each TSO shall be responsible for maintaining rota disconnection plans for use where a shortage of
generation is anticipated over a prolonged period. The rota disconnection plans shall provide for the
disconnection and reconnection of defined blocks of demand on instruction from the TSO. In this
way the TSO can instruct the necessary level of disconnection (and reconnection) required by the
circumstances at the time. The rota disconnection plans of each TSO shall be coordinated by the
EAPP CC to ensure that where the generation shortage is common to a number of countries of EAPP
the resulting demand control is applied equitably.
Emergency manual disconnection is utilised by the TSO when a loss of generation or a mismatch of
generation output and demand is such that there is an operational requirement to disconnect
demand at short notice or in real time to maintain a margin between generation output and
demand and in certain circumstances to deal with operating problems such as unacceptable voltage
levels and thermal overloads. TSOs shall maintain emergency manual disconnection plans and
procedures, coordinated with EAPP CC, to implement manual load shedding in a timeframe
adequate for responding to an emergency.
TSOs shall ensure that, as far as practicable, demand reductions are deployed equitably. In the case of
protracted generation shortage or transmission system overloading, large imbalances of generation
and demand may cause excessive power transfers across the EAPP Interconnected Transmission
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 174
CHAPTER 12 Operations Chapter No. 5 – Demand Control
System. If such transfers threaten the stability of the EAPP Interconnected Transmission System or
could damage generating and transmission facilities, the pattern of demand reduction shall be
adjusted to secure the EAPP Interconnected Transmission System, notwithstanding the inequalities of
disconnection that may arise from such adjustments.
The objective of demand control is to achieve reduction in demand in the transmission grid in order
to: (a) manage system security during low operating reserve; and (b) prevent system overload or
voltage collapse.
Demand control shall, in general, apply to Generation Licensee, TNSPs, Distribution Licensees, and
End-use Users.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 175
CHAPTER 12 Operations Chapter No. 5 – Demand Control
frequency conditions, Generating Plants shall assist through the following: (a) Make every effort to
assist the system frequency to rise to 50 Hz, by increasing generation whenever possible; (b) Not
disconnecting manually from the transmission system unless there is definite evidence that a
complete failure of generation would otherwise result. The ENTSO shall enforce demand control in
such a manner that does not unduly discriminate against, or unduly prefer anyone.
If the ENTSO anticipates any generation shortfall based on the difference between projected
maximum demand and available generation capacity, the ENTSO shall work with all relevant
personnel following the operational guidelines below:
(a) The ENTSO shall inform RCCs of their required load rationing targets
(b) The RCCs shall coordinate with the ENTSO to determine the End-use Users and feeders to be
affected
(c) The RCCs shall inform the End-use Users of their required load reduction magnitudes and
the time period
(d) The RCCs shall be at the relevant End-use Users’ premises before start of reduction period to
ensure and confirm compliance by such Users
(e) The RCCs shall inform the ENTSO of End-use Users’ compliance with load reductions
(f) The ENTSO shall evaluate system status and determine if this load reduction is adequate. If
reduction is inadequate, the ENTSO shall instruct RCCs to carry out additional load shedding
(g) The RCCs shall carry out load shedding as instructed by the ENTSO. The RCCs shall instruct
operators to carry out load shedding in places where there are no SCADA commands
(h) The RCCs shall notify the ENTSO of completion of carrying out load shedding
(i) The ENTSO shall evaluate system status. If load shedding is still inadequate, The ENTSO shall
instruct RCCs to carry out further load shedding
(j) If load shedding is adequate, the ENTSO shall wait for the recovery of the system while monitoring
system status parameters (voltage and frequency) on the SCADA
(k) The ENTSO shall determine if system has recovered from generation shortfall
(l) If system has not recovered from generation shortfall, the ENTSO shall wait for the recovery of the
system while monitoring system status parameters (voltage and frequency) on the SCADA
(m) If system has recovered from the generation shortfall, the ENTSO shall instruct the RCCs to restore
Customer load through remote control. The RCCs shall instruct operators to restore Customers
where there is no remote control. The RCCs shall also inform End-use Users who had reduced
load to resume normal operation. Restoration of such Users shall be done systematically as
directed by the ENTSO
(n) When the system returns to normal operation, the RCCs shall notify the ENTSO of the completion of load
shedding, and the ENTSO compiles Load shedding detail report
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 176
13 OPERATIONS CHAPTER NO. 6 – SYSTEM TESTS
This chapter contains requirements specific to both the EAPP IC and the ENTS. If in any instance there is
a difference in requirements, the more stringent requirement shall hold.
System Tests are those tests, which involve either a simulated or a controlled application of
irregular, unusual or extreme conditions on the EAPP Interconnected Transmission System. In
addition, they include commissioning and or acceptance tests on Plant and Apparatus to be carried
out by a User and which may have a significant impact upon the EAPP Interconnected Transmission
System.
System Tests or operational tests may involve single items of Plant and or Apparatus through to
whole sections of the EAPP Interconnected Transmission System and may be proposed by EAPP Sub-
Committees on Planning or Operations or a TSO.
To minimise disruption to the operation of the EAPP Interconnected Transmission System and or to
other TSO’s National Systems, it is necessary that these tests be subjected to central coordination by
the EAPP CC in cooperation with the relevant TSO.
OC 6 also describes the data exchange and communication requirements between EAPP and the
TSOs to facilitate planning, implementation and reporting of System Tests or operational tests.
13.1.2 Objective
The objectives of OC 6 are to specify procedures for central co-ordination and control of a System
Test or operational test required by a TSO or the EAPP Sub-Committees on Planning or Operations,
where such test will or may:
(a) Affect the secure operation of the EAPP Interconnected Transmission System
(b) Have a significant effect on the operation of the EAPP Interconnected Transmission System
or a National System
(c) Affect the economic operation of the EAPP Interconnected Transmission System, or
(d) Affect the quality or continuity of supply of electricity from the EAPP Interconnected
Transmission System
13.1.3 Procedure
13.1.3.1 General
Tests shall be planned to ensure all Plant and Apparatus remain within the applicable capability
limits specified by the relevant TSO and carried out such that there is minimal impact on the EAPP
Interconnected Transmission System or TSOs’ National Systems. System Tests required by TSOs or
EAPP CC shall include, but not be limited to the following:
(a) Tests involving the controlled application of frequency and or voltage variations aimed at
gathering information on the behaviour of the EAPP Interconnected Transmission System
(b) Black Start and system restoration tests
(c) Testing of procedures and plans for system ALERT and EMERGENCY conditions
(d) Testing or monitoring of power quality under various system conditions and generation
configurations
TSOs shall be responsible for obtaining the agreement of the relevant User(s) before tests proceed.
All Outage requests for Tests shall be progressed in accordance with the guidelines in Chapter 8
(Operational Planning).
The category of Tests shall be agreed by the EAPP Sub-Committees on Planning and Operations and
relevant TSOs.
Major Tests are those considered sufficiently complex by either Party to require a detailed Test
programme to be submitted in accordance with Test Proposal as described below.
OC 6 is not intended to deal with Tests categorised as minor or routine. Such tests do not require a
detailed Test programme to be submitted.
Any System Tests on the EAPP Interconnected Transmission System, which may affect an External
System, or tests on an External System, which may affect the EAPP Interconnected Transmission
System, shall be carried out in accordance with the appropriate bilateral agreements.
The Test Proposer shall provide a Test Proposal to EAPP Sub-Committees on Planning or Operations
who shall be responsible for circulation to relevant TSOs.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 178
CHAPTER 13 Operations Chapter No. 6 – System Tests
Individual TSOs shall ensure that any of their Users who may be involved in or affected by the Test
shall be provided with a copy of the Test Proposal and any updates thereof. Where practicable, the
Test Proposal shall be submitted at least three (3) months prior to the proposed date of the Test.
The Test Proposer shall ensure that sufficient detail is included in the Test Proposal to allow the
affected parties to assess the impact of the Test on the EAPP Interconnected Transmission System,
TSOs’ National Systems and Users’ Systems.
The Test Proposer shall be responsible for change control of the Test Proposal and shall issue a
revised Test Proposal to EAPP Sub-Committees on Planning or Operations. EAPP Sub-Committees on
Planning or Operations is responsible for liaising with any other affected TSOs who in turn shall
notify any Users affected by the change.
EAPP Sub-Committees on Planning or Operations and the affected TSOs shall assess the implications
and agree the category of the Test within a reasonable time. TSOs shall liaise with each affected
User, seek their agreement to the Test Proposal, collate, and coordinate their responses to the EAPP
Sub-Committees on Planning or Operations.
Following receipt of the Test Proposal and evaluation of the Test’s likely impact, including
discussions of test requirements with the Test Proposer and other affected parties, the EAPP Sub-
Committees on Planning or Operations taking into account the criteria set out in this chapter will
decide if approval for the Test is granted.
If the Test Proposal is not acceptable to the EAPP Sub-Committees on Planning or Operations, an
affected TSO or User, EAPP Sub-Committees on Planning or Operations shall refuse the Test Proposal
and shall immediately notify the Test Proposer. The Test Proposer may choose to revise and re-submit
the Test Proposal in accordance with this procedure or raise a Dispute under the terms of section 3.11
of Chapter 3 (Dispute Resolution).
Any Test Proposal made by the EAPP Sub-Committees on Planning or Operations shall be subject to
the prior approval of the EAPP Steering Committee and Independent Regulatory Board and shall
otherwise be subject to the procedure set out above.
The Test Proposer shall provide, within a reasonable time, a draft Test programme to a level of detail
including, but not limited to, the content shown under Sample Report in Section A of this chapter.
The Test Proposer shall be responsible for change control of the draft Test programme and shall
issue within a reasonable time, a revised Test programme where appropriate to EAPP CC. EAPP CC is
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 179
CHAPTER 13 Operations Chapter No. 6 – System Tests
responsible for liaising with any other affected TSOs who in turn shall notify any Users affected by
the change.
EAPP CC shall provide to each affected TSO a copy of the draft Test Programme and all updates thereof.
TSOs shall liaise with each affected User and seek their agreement to the Test Programme and
collate and co-ordinate their responses to the EAPP CC.
EAPP CC and affected TSOs shall assess the implications of the Test programme on the safety,
security, and reliability of the EAPP Interconnected Transmission System, individual TSO National
Systems and User Systems.
When all issues raised have been addressed to the reasonable satisfaction of all parties and the draft
Test programme agreed by all parties, the agreed Test programme shall be issued by EAPP CC to
relevant TSOs at least fifteen (15) business days prior to the commencement date of the Test unless
otherwise agreed.
In the event that that there is a Dispute regarding the acceptability or otherwise of a Test
programme or associated Outage, the Test shall not take place until the Dispute has been resolved.
When Tests have commenced, any change in System, site or Test conditions that could affect or
invalidate the Test or have an Operational Effect shall be communicated to other parties as soon as
reasonably practicable. The Tests shall be suspended until all parties involved have assessed the
implications of the change in system, site, or Test conditions.
In the event of a failure of communications between EAPP CC and relevant TSOs or the Test location
during the Test, then the Test shall be suspended until satisfactory communications are restored
and agreement is reached to continue with the Test programme.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 180
CHAPTER 13 Operations Chapter No. 6 – System Tests
Where testing of an operational intertripping scheme is not the stated purpose of testing then no
Tests shall take place involving a circuit associated with an operational intertripping scheme unless
the operational intertripping scheme is not required in service. The scheme must be deselected
from service by a means agreed with all affected Parties.
The Final Report shall include a description of the Plant and or Apparatus tested and a description of
the System Test carried out together with the results, conclusions and recommendations as they
relate to the EAPP and TSOs.
In addition to the safety of the system as described under Section 13.1.3 (Detailed Test Programme)
in this chapter, it is necessary to ensure that the safety of personnel or members of the public are
not threatened while conducting system tests.
It is important to ensure that the test programme specifies switching sequence and proposed
timings, list of staff involved in the test, and site safety responsible persons. If a Generating Plant
fails the system test, the Generation Licensee shall:
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 181
CHAPTER 13 Operations Chapter No. 6 – System Tests
(e) Demonstrate to the reasonable satisfaction of the ENTSO that the relevant Generating
Plant passes the test and is compliant
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 182
CHAPTER 13 Operations Chapter No. 6 – System Tests
(a) Excitation Response Test -With the Generating Plant in the open circuit mode, carry out the
large signal performance testing as described in IEEE 421.2 of 1990; Determine time
response, Ceiling voltage, voltage response. With the Generating Plant connected to the
network and loaded, carry out the small signal performance tests according to IEEE
421.2.1990. Also, carry out power system stabiliser tests and determine damping with and
without Power System stabiliser. Document all responses
(b) Reactive Power Capability Test - Reactive output for a Generating Plant shall be fully
variable between its rated limits under AVR, manual or other control. The duration of the
test shall be for a period of up to 60 minutes, during which period the system voltage at the
grid entry point for the relevant Generating Plant shall be maintained by the Generating
Plant at the voltage specified by adjustment of Reactive Power on the remaining Generating
Plant units, if necessary, for a period of 60 minutes. The Generating Plant shall demonstrate
maintaining its reactive capability within plus or minus five percent (±5%) of its rated
capability
(c) Governor Response Tests - Prove that the unit is capable of the minimum requirements
required for governing frequency deviations
(d) Black Start Test - Black Start Units shall perform appropriate tests and simulations on an
annual basis to ensure that the Black Start facility is available. Such tests shall be witnessed
and approved by the ENTSO. A Black Start Station shall demonstrate that it can be
synchronised to the system within thirty (30) minutes of the commencement of the Black
Start procedure.
Other tests include:
(a) Contingency/ Emergency plan Verification - Tests shall be periodically carried out to the
greatest practical extent, as agreed by the parties, without causing undue risk or undue cost.
(b) Under - frequency load shedding (UFLS) Test - Test shall be done by isolating all actual
tripping circuits, injecting a frequency to simulate a frequency collapse and checking all
related functionality.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 183
14 ISCB CHAPTER NO. 1 - INTERCHANGE SCHEDULING
This chapter contains requirements specific to both the EAPP IC and the ENTS. If in any instance there is
a difference in requirements, the more stringent requirement shall hold.
14.1.1 Introduction
One of the objectives of the EAPP is to facilitate trading in electricity among the EAPP Member
Countries. In its initial stages, such trading will consist of bilateral cross-border transactions between
Neighbouring Systems. Once further infrastructure is developed, more complex arrangements
including multilateral transactions with or without transit through Neighbouring Systems will
become possible and a Regional Power Pool Market will be established. Accordingly, the provisions
of the ISBCs will be modified to reflect any EAPP/EAC new electricity market rules.
To operate the EAPP Interconnected Transmission System and to facilitate bilateral trade between EAPP
Member Countries it is necessary to schedule in advance the Active Power and Active Energy to be
transferred between TSO National Systems and to be imported from or exported to External Systems.
The term Interchange Scheduling in the context of balancing power specifically refers to the
intended delivery of Active Power and Active Energy from one Control Area to another Control Area
within the EAPP Interconnected Transmission System or to be imported from or exported to External
Systems.
This chapter deals with the following aspects of the scheduling process:
(a) Determination of the Net Transmission Capability (NTC) between Neighbouring Control
Areas and or External Systems over the Operational Planning timescales
(b) Publication of NTC values to enable TSOs and Users to evaluate possible Active Power and
Active Energy interchanges;
(c) Allocation of NTC to TSOs and or External Systems in accordance with predetermined rules
and the issue of Interchange Schedules
14.1.2 Objectives
The objectives are:
(a) to enable EAPP CC and TSOs to establish and publish the NTC on the interconnections
between Control Areas and or External Systems corresponding to the Operational Planning
Phase, Programming Phase and Control Phase respectively as set out in Chapter 8
(Operational Planning, or, OC 1), and
(b) to require TSOs to allocate the NTC to Users in accordance with certain rule
The NTC of the interconnection between Control Areas or with External Systems is firstly allocated to
those Users with pre-emptive rights over the capability based on their bilateral agreements. After
allocating NTC to Users who hold pre-emptive rights, TSOs may allocate the remaining capability of a
particular interconnection in accordance with commercial agreements, which are not the subject of this
chapter.
As part of the Operational Planning process under OC 1, TSOs are required to make an assessment
over various timescales of the NTC available on the interconnections between Control Areas and
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 185
CHAPTER 14 ISCB Chapter No. 1 - Interchange Scheduling
External Systems. This assessment is based on the commissioning of new facilities and on the
Outages required for planned maintenance of generating and transmission facilities. TSOs are
required to publish details of the NTC on the EAPP Website.
Where a constraint in the NTC is identified when carrying out Interchange Scheduling in any of the
Operational Planning timescales, the TSOs concerned shall seek to reallocate the Interchange
Schedule to Users in the following priority order:
(a) Lowest priority will be energy exchanged as compensation for Inadvertent Deviations
(b) Energy transfers scheduled on a commercial basis by TSOs over and above the pre-emptive
rights
(c) Energy transfers scheduled as a consequence of pre-emptive rights, and
(d) Any agreements between TSOs for the provision of operating reserve
By the end of October each year, TSOs shall agree on the allocation of transmission capability and
shall publish an Annual Interchange Schedule. This Interchange Schedule is indicative only and is
used to advise Users of potential availability of power trading opportunities over and above those
pre-emptive rights held by the TSO on behalf of a User connected to its National System.
EAPP CC shall develop the Weekly Interchange Schedule to achieve the operating reserve
requirements as set out in the Balancing and Frequency Control Chapter, and shall finalise the NTC
based on the data received from TSOs.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 186
CHAPTER 14 ISCB Chapter No. 1 - Interchange Scheduling
In accordance with OC 1.10 at 15h00 Hrs each day, TSOs shall finalise the Operational Plan for use
on the following day commencing at 00h01 Hrs. The Operational Plan shall be issued and published
by the EAPP CC. In the case of the Operational Plan issued on a Friday, the Plan will cover the three
(3) days commencing at 00h01 Hrs on the Saturday. Apart from the information set out in Chapter 8
(Operational Planning, or, OC 1), the Operational Plan will contain the following:
(a) the NTC between each Control Area, Neighbouring Systems and External Systems and its
allocation between Users
(b) the transfer in MW between each Control Area, Neighbouring Systems and External Systems
on an hourly basis
(c) the Operating Reserve levels to be maintained within the TSO’s National System on an hourly basis
(d) the Operating Reserves contracted with other TSOs on an hourly basis and for which NTC
has been reserved
Any additional information that may be reasonably considered to be of relevance to the daily
Schedule for that TSO shall be included. This may include:
(a) Weather
(b) Voltage control issues
(c) System stability issues
(d) System Tests in accordance with OC 6 to be carried out in another part of the EAPP
Interconnected Transmission System which may compromise security of supply
In real-time, neither the total of the schedules of individual Users, nor the actual power transfer between
Control Areas, Neighbouring Systems and External Systems may exceed the NTC for that interconnection.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 187
CHAPTER 14 ISCB Chapter No. 1 - Interchange Scheduling
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 188
CHAPTER 14 ISCB Chapter No. 1 - Interchange Scheduling
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 189
15 ISBC CHAPTER NO. 2 - BALANCING AND FREQUENCY
CONTROL
This chapter contains requirements specific to both the EAPP IC and the ENTS. If in any instance there is
a difference in requirements, the more stringent requirement shall hold.
Balancing and Frequency Control Code (also known as ISBC2 in EAPP) sets out the procedure that
the TSOs will use to direct frequency control. The frequency of the EAPP Interconnected
Transmission System will be controlled by:
(a) Automatic response from synchronised Generating Units;
(b) The dispatch of Generating Units including Automatic Generation Control (AGC);
(c) Response from interconnections with External Systems, and
(d) Demand control.
Frequency control is an Ancillary Service and TSOs shall contract for its provision in accordance with
the Chapter 16 (Ancillary Services or ISBC 3).
15.1.2 Objective
The objectives of ISBC 2 are to establish:
(a) Procedures to ensure adequate operating reserves are maintained by each TSO when
connected to the EAPP Interconnected Transmission System;
(b) Procedures for the minimisation of Area Control Error (ACE), and
(c) Procedures for the calculation and settlement of Inadvertent Deviations from scheduled
interchanges.
Interconnected Transmission System. TSOs shall maintain at all times adequate operating reserves to
control the frequency of the EAPP Interconnected Transmission System within the limits set out in
Section 6.1.4 (Connection), and to avoid sudden, unexpected loss of load following transmission or
generation Contingencies. Operating reserves are also required to maintain agreed interchange
schedules following changes in demand or generation.
The control of the frequency of EAPP Interconnected Transmission System is a multi-stage process.
For every stage of control, adequate reserves are needed. The Operating reserves have three
components, which are realisable in the following distinct timescales.
Demand side also participates in Primary Response through the self-regulating effect of frequency-
sensitive loads such as Induction Motors or the action of under frequency relays that disconnect
some demand at given frequency thresholds.
Secondary Response is the automatic response to a frequency change which is fully available by
thirty (30) seconds from the time of frequency change to take over from Primary Response, and
which is sustainable for a period of at least thirty (30) minutes. Secondary Response is provided by
Generating Units already synchronised to the EAPP Interconnected Transmission System and is
normally controlled by the TSO by AGC where available.
Secondary Response replaces Primary Response within minutes. Once replaced, Primary Response is
again available to cover any further incidents that cause frequency deviation from the EAPP
Interconnected Transmission System target frequency.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 191
CHAPTER 15 ISBC Chapter No. 2 - Balancing and Frequency Control
Where Tertiary Reserve is held on Generating Units not synchronised to the EAPP Interconnected
Transmission System, the Units shall be capable of being synchronized within a specified time
generally between fifteen (15) minutes and one (1) hour. Non synchronized Tertiary Reserve could
consist of, for example, fast start hydro, gas turbine, and steam turbine Generating Plants on hot-
standby.
Tertiary Reserve capability (i.e., hydro and gas turbines) in the EAPP Interconnected Transmission
System is considered an Ancillary Service that is delivered when a Generating Unit is able to start up
and synchronise or change its loading within the timescales specified by the TSO.
TSOs shall monitor operating reserves continuously, particularly after a loss of generation or demand
and shall re-establish the required amount of reserve as soon as practicable, in order to protect
against a further Contingency and to avoid endangering the EAPP Interconnected Transmission System.
In calculating the amount of Primary Response required the demand-frequency response within the
Control Area or National System shall be taken into account. For initial calculations, the demand-
frequency response can be assumed to be one percent (1 %)/Hz i.e. a load decrease of one percent
(1%) following a frequency drop of one (1) Hz.
The Contribution Coefficient is the ratio of the energy generated within one year in the relevant
Control Area to the total energy generated in the EAPP Interconnected Transmission System.
The contribution coefficients shall be determined by the EAPP Sub-Committee on Operations and
published annually on January 1 for each Control Area. The contribution coefficients are binding for
the corresponding Control Area for the following calendar year.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 192
CHAPTER 15 ISBC Chapter No. 2 - Balancing and Frequency Control
Each Control Area must contribute to the Primary Response as required. The respective shares are
defined by multiplying the required Primary Response for the EAPP Interconnected Transmission
System by the contribution coefficient of the Control Area.
The actual Primary Responses shall be monitored in real-time by TSOs and the EAPP CC.
The insensitivity range of primary controllers shall not exceed ±ten (10) mHz. Where dead bands
exist in specific controllers, these must be reduced as much as possible.
Each TSO shall provide adequate Secondary Response by AGC to regulate interchange and frequency
and shall operate its AGC in tie-line bias mode, unless such operation is adverse to the reliability of
the EAPP Interconnected Transmission System.
Secondary Response shall only be used to correct an overall system deviation and shall not be used
to minimize unintentional electricity exchanges or to correct other imbalances.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 193
CHAPTER 15 ISBC Chapter No. 2 - Balancing and Frequency Control
frequency deviations to restore the frequency and consequently free the system wide activated
Primary Response.
TSOs shall, therefore, immediately activate Tertiary Reserve in case of large imbalances between
generation and demand and or for the restoration of sufficient Secondary Response.
The amount of Tertiary Reserve required at the day ahead and in subsequent timescales shall be
determined by each TSO on the basis of historical trends in the reduction in availability of
Generating Units and increases in forecast demand up to real-time operation.
As a minimum, each TSO shall arrange at least enough Tertiary Reserve to cover the loss of the
largest Generating Unit on its National System.
Inadvertent Deviations in the EAPP Interconnected Transmission System shall be balanced by the import
or export of an equal number of MWh at the same hours on the same day of the following week.
The measurement and accounting for Inadvertent Deviations shall be carried out using metering
equipment installed in accordance with the metering codes as described in Chapters 17 (Ethiopia
Metering) and 18 (Interconnection Metering).
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 194
CHAPTER 15 ISBC Chapter No. 2 - Balancing and Frequency Control
The standard compensation period comprises seven (7) days (one week), from Thursday 00:01 Hrs
to Wednesday 24h00 Hrs. In case of holidays or for other reasons, exceptions to this rule may apply.
In any case, a compensation period shall last at least four (4) days and shall commence three (3)
business days after the end of the corresponding recording period.
The settings and other parameters of each HVDC Interconnection shall be determined by the
relevant TSOs and the EAPP Sub-Committee on Operations.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 195
CHAPTER 15 ISBC Chapter No. 2 - Balancing and Frequency Control
Warnings
When a shortfall in supply is expected to occur, Emergency generation warning
issue warnings in sequence until sufficient capacity Interruptible load shedding warning
is obtained to cover the shortfall
Generation deficit foreseen with load shedding Warning to RCCs
expected
Gradual frequency decline – refer to merit order in control room for order of use
CONDITION FOR USAGE RESOURCES IN DEFAULT ORDER OF
USAGE
If frequency falls below 50 Hz and an abnormal a. Run all available units at Maximum
condition exists, the ENTSO shall apply resources Continuous Rating
in the order most suitable to ensure system security b. Dispatch emergency capacity according to the
depending on the conditions existing at the time ENTSO equipment order, voltage profiles,
and equipment loading
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 196
CHAPTER 15 ISBC Chapter No. 2 - Balancing and Frequency Control
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 197
16 ISBC CHAPTER NO. 3 - ANCILLARY SERVICES
This chapter contains requirements specific to both the EAPP IC and the ENTS. If in any instance there is
a difference in requirements, the more stringent requirement shall hold.
16.1.1 Introduction
The Ancillary Services Chapter (ASC) deals with the provision of Ancillary Services used to describe
those services that must be exchanged among generation resources, load customers, and TNSPs to
operate the EAPP Interconnected Transmission System in a reliable fashion and allow separation of
generation, transmission, and distribution functions.
The ASC defines those services that are necessary to support the transmission of capacity and
energy from resources to loads while maintaining reliable operation of the EAPP Interconnected
Transmission System in accordance with Prudent Utility Practice. These Ancillary Services are
required to ensure that TSOs meet the obligations and responsibilities under the Interconnection
Code for a safe secure and reliable operation of the EAPP Interconnected Transmission System.
The ASC does not cover the commercial arrangements between TSOs and Ancillary Service providers
for the provision of Ancillary Services. Such arrangements are the subject of bilateral agreements.
16.1.2 Objective
The objective of this section is to define the Ancillary Services to be provided by TSOs to support the
transmission of energy across the EAPP Interconnected Transmission System and to maintain reliable
operation.
In general, frequency control action can be provided at any location within the EAPP Interconnected
Transmission System. However, when transmission facilities are operating at or near their limits,
sufficient control action is needed on each side of the limiting facility to prevent overloading of the facility.
TSOs are required to provide the following frequency control Ancillary Services:
(a) Primary Response of Generating Units in accordance with Section 6.1.8 of Chapter 6
(Connections, Technical Requirements for Generating Units) and Section 15.1.3 of Chapter
15 (Balancing and Frequency Control – Primary Reserve).This Ancillary Service is being
delivered if the Generating Unit is responding to changes in frequency within ten (10)
seconds and is able to sustain the response for a further twenty (20) seconds;
(b) Secondary Response of Generating Units in accordance with Chapter 9 (Operational Security
or OC2), and Section 15.1.3 of Chapter 15 (Balancing and Frequency Control – Operating
Reserve). This Ancillary Service is provided by AGC and is being delivered if the Generating
Unit’s output is correctly responding to signals sent from the TSO’s AGC equipment in
response to changes in frequency;
(c) Tertiary Reserve in accordance with Chapter 9 (Operational Security or OC 2) and Section
15.1.3 of Chapter 15 (Balancing and Frequency Control – Operating Reserve). This Ancillary
Service is being delivered when a Generating Unit is able to start up and synchronise or
change its loading within the timescales specified by the TSO;
(d) Demand control in accordance with the provisions of Chapter 12 (Demand Control or OC 5).
This service is being delivered if: 1. Demand can be automatically disconnected in response
to an under frequency condition (Automatic Load Shedding); or 2. Demand can be
disconnected on request from the TSO (Emergency Manual Load Shedding). Emergency
Manual Load Shedding Ancillary Service can be provided by industrial load, commercial load,
residential load or hydro generating units operating as pumps.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 199
CHAPTER 16 ISBC Chapter No. 3 - Ancillary Services
Sufficient control range should be available at all times to control frequency within the limits
specified in the CC under various circumstances including unexpected load and generation changes.
In accordance with the voltage standards set out in the CC, TSOs shall control system voltages within
specific ranges. One method of controlling voltages on the EAPP Interconnected Transmission
System is through the dispatch of voltage control Ancillary Services. Under these Ancillary Services,
Generating Units absorb or generate Reactive Power from or onto the EAPP Interconnected
Transmission System and control the local voltage accordingly. Voltage control requirements are
location dependent because of technical limitations inherent in transporting Reactive Power.
Stability control services are required to prevent instability following a Contingency, which is more
severe than defined for the purposes of determining NTC. Stability control can be achieved by
Generating Units which can rapidly respond to a control signal to increase or decrease generation.
This network Ancillary Service is being delivered if the EAPP Interconnected Transmission System
remains stable after any Contingency (N-1) and oscillations are damped out. Remedial Action
Schemes (RAS) are considered a network control Ancillary Service. Power flows on the EAPP
Interconnected Transmission System shall be maintained within the NTC limits, as imposed by
thermal ratings, stability, and voltage. In the event of a Contingency (N-1), equipment loadings
should not exceed short-term ratings, but may exceed long-term ratings provided the loadings can
be reduced to within the long-term ratings in an appropriate time period by either manual or
automatic means. It is proposed to obtain network loading Ancillary Services by superimposing
signals on the AGC and by emergency manual load shedding.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 200
CHAPTER 16 ISBC Chapter No. 3 - Ancillary Services
TSOs may also contract for Ancillary Services with other TSOs. All such contracts shall be notified to
EAPP CC.
The ENTSO shall be responsible for the provision of all short-term reliability services for the IPS.
These include restoration, the balancing of supply and demand, as well as the provision of quality
voltages and the management of the real-time technical risk.
The ENTSO shall certify providers of ancillary services and keep a register of all certified providers.
The ENTSO shall determine reliability targets for the purposes of acquiring ancillary services in
consultation with relevant Users.
The ENTSO shall be responsible for procuring the required ancillary services as appropriate, in
accordance with the license and market rule. The ENTSO shall state opportunities for the provision
of ancillary services as identified.
The various ancillary services that can be used by the ENTSO are described below:
(a) Reserves as defined in section 2.1 of this Chapter
(b) Black start and unit islanding
(c) Reactive power supply and voltage control from units
The ENTSO shall ensure Spinning Reserve is available as needed to arrest the frequency at
acceptable limits following a Contingency, such as a unit trip or a sudden surge in load.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 201
CHAPTER 16 ISBC Chapter No. 3 - Ancillary Services
This reserve is used for second-by-second balancing of supply and demand. The reserve is also used
to restore Spinning Reserve within ten (10) minutes of the disturbance.
The amount of reserve required is to be calculated by the ENTSO and shall be based on EAPP
minimum requirements, supplemental and emergency reserve availability, and other reserve
considerations.
All Generating Plants capable of unit islanding are required to contract the service provision to the
ENTSO. The ENTSO shall certify units capable of islanding.
To ensure optimal operation of the IPS, the ENTSO may deploy system islanding schemes on the
network, e.g. an out-of-step tripping scheme.
The ENTSO shall determine the minimum requirements for each black start supplier and ensure that
the contracted suppliers are capable of providing the service.
The ENTSO shall control the amount of reactive power. This may be done directly through the
energy management system or by telephone.
When a unit is generating or pumping, reactive power supply is mandatory in the full operating
range as specified.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 202
17 ETHIOPIA METERING
To avoid confusion regarding the two chapters that deal with metering, they have different names.
The metering code, which is part of the EAPP IC, is described in Chapter 18 as the EAPP IC Metering
Chapter (IMC), and the metering code, which is specific to the ENTGC, is described in Chapter 17 as
Ethiopia Metering Chapter (EMC).
The IMC deals with metering of each point of interchange of energy between Control Areas and is
not concerned with Metering of Connection Points between Users and National Systems.
The EMC deals primarily with metering entirely within Ethiopia, to which the IMC does not apply.
The EMC also includes each metering point connecting Ethiopia’s networks to a Neighbouring
Country. The IMC applies to those inter-country connections.
17.1.1 Introduction
The Ethiopia Metering Chapter (EMC) specifies the minimum technical, design and operational
criteria to be complied with for the metering of each Connection Point of a User to the ENTS.
(a) This Chapter ensures a metering standard for all current and future Users. It specifies
metering requirements to be adhered to, and clarifies levels of responsibility.
(b) The ENTS shall follow nationally adopted metering standards currently in place that includes
IEC 62052, IEC 62053, IEC 62054, IEC 62056, IEC 62059, and/or any equivalent IEEE/local
standards as appropriate.
17.1.2 Scope
The Ethiopia Metering Chapter addresses the following:
(a) Application
(b) Principles and responsibility
(c) Installations and testing
(d) Database, data validation, verification and inconsistencies
(e) Data access and confidentiality
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 204
CHAPTER 17 Ethiopia Metering
(b) For the metering between transmission and distribution lines, the TNSP will place the
primary meters on the outgoing lines on all HV substations. The DNSP will own and put
check meters on the outgoing distribution lines. Each entity/owner of the respective meter
shall be responsible for their meters and perform the role of the Transmission Metering
Administrator (TMA)
(c) The TNSP shall be responsible for ensuring that all points identified as metering points in
accordance with Sections 17.1.3 and 17.1.4 in this chapter have metering installations
(d) The TMA shall be responsible for managing and collecting metering information
(e) Users connected to or wanting to connect to the ENTS shall provide the TMA with all
information deemed necessary to enable performance of its metering duties
(f) In case of a material difference in location between the metering point and Connection
Point, an adjustment for losses between these two points shall be calculated and agreed
upon by the TMA and the customer
(g) The TMA shall ensure that an adequate level of security is applied to the metering system
with appropriate seals that will only be broken in the presence of the TMA unless agreed
otherwise
(h) In the event of a metering installation between the TNSP and a User, the TNSP will provide
the meter and shall be responsible for managing and collecting metering information as a
TMA of the meter
(i) In the event of a metering installation being positioned between two TNSPs, the following
shall apply:
1. Both TNSPs shall be responsible for installing and maintaining the metering
installation in accordance with the requirements of this Chapter
2. All costs related to this metering installation shall be borne by both TNSPs
3. The TNSPs shall ensure that the TMA is given remote/electronic access to the
metering installation. Should access to the metering installation compromise the
Security of the installation, then metering data shall be supplied to the TMA on a
daily basis in an appropriate format
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 205
CHAPTER 17 Ethiopia Metering
In the event of the electronic access to the meters not being possible, an emergency bypass or other
scheme having no metering system, or Metering data not being available, the following options may
be resorted to by the TMA:
1. Manual meter data downloading
2. Estimation or substitution subject to mutual agreement between the affected parties;
3. Profiling
4. Reading of the meter at scheduled intervals
In the event of an estimation having to be made, the following shall apply:
1. A monthly report shall be produced for all estimations made
2. No estimation shall be made on three (3) or more consecutive time slots, and if such
estimation had to be made, the TMA shall ensure that the meter readings are
downloaded for the billing cycle
3. Any logs on data estimation shall be kept for the entire period of data retention. As per
IEC 62056, five (5) years' data retention shall be made available
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 206
CHAPTER 17 Ethiopia Metering
Not more than ten (10) slots may be estimated per meter point per Month. If such estimation had to
be made, the TMA shall ensure that the meter readings are downloaded for the billing cycle.
Meters needing three or more consecutive estimations or a total of ten (10) or more estimations in
a month shall be tracked for problems needing attention.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 207
CHAPTER 17 Ethiopia Metering
17.1.12 Confidentiality
Metering data and passwords are confidential information and shall be treated as such at all times.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 208
18 INTERCONNECTION METERING
18.1.1 Introduction
The Interconnection Metering Chapter (IMC) specifies the minimum technical, design, and
operational criteria to be complied with for the metering of each point of interchange of energy
between Control Areas. The metering at the Interchange Point is required for real-time operation of
AGC systems and for the accounting of Inadvertent Deviations in accordance with the Balancing and
Frequency Control Chapter. The IMC also specifies the associated Data Collection and the related
metering procedures required for the operation of the EAPP Interconnected Transmission System.
These metering systems are subject to National Grid Codes or Regulations and or Power Purchase
Agreements.
18.1.2 Objectives
For the metering of the interconnections between Control Areas of the EAPP Interconnected
Transmission System and between Control Areas and External Systems, the IMC specifies the
conditions governing the following:
(a) technical, design and operational criteria
(b) accuracy and calibration
(c) approval, certification and testing, and
(d) meter reading and data management
TSOs are responsible for the maintenance and operation of the Metering Equipment at each IP and
shall be responsible for the initial design, installation, testing and commissioning of the Metering
and Check Metering Equipment.
Main and Check Metering Equipment procured, installed, operated and maintained for the purpose
of the IMC shall meet the standards of accuracy and calibration in relation to meters and Metering
Equipment as set out in this IMC.
TSOs and the EAPP CC shall establish metering related policies, procedures and standards in support
of the IMC including, but not limited to registration, testing and calibration, sealing, loss
adjustments, data security, inspection, testing and audit of Metering Equipment and measurement
error correction.
CT and VT windings and cables connecting such windings to Main Meters shall be dedicated for such
purposes and such cables and connections shall be securely sealed.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 210
CHAPTER 18 Interconnection Metering
CT and VT windings and cables connecting such windings to Check Meters may be used for other
purposes provided the overall accuracy requirements are met and evidence of the value of the
additional burden is available for inspection by or on behalf of the EAPP Independent Regulatory
Board.
The Main Meter, Check Meter and additional burdens shall have separately fused VT supplies.
All existing CT s and VTs shall conform to IEC 60044 or IEC 61869 or equivalent as appropriate.
Combined unit measurement transformer (VT & CT) shall comply with IEC Standard 60044 or IEC
61869 or equivalent as appropriate.
All meters shall include a non-volatile meter register for each measured quantity. The meter
register(s) shall not rollover more than once within the normal meter reading cycle.
Meters shall be calibrated by an independent calibrating agency approved by the EAPP Independent
Regulatory Board for this purpose. The agency shall provide a calibration certificate with expiry date
of the calibration.
Where combined instrument transformers to IEC60044-3 are used, they shall meet the accuracy
requirements of Chapters IMC 18.1.9.as stated for the CTs and VTs below.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 211
CHAPTER 18 Interconnection Metering
The voltage drop in each phase of the VT connections will be such as to maintain the same accuracy
and class and shall not exceed 0.2 Volts. The VT shall be connected through appropriate isolation and
test facilities to the meter with a total burden that shall not affect the accuracy of measurement.
The CT's rated secondary current shall be either 1 or 5 Amperes. The neutral conductor shall be
effectively grounded at a single point and shall be connected to the meter and other series technical
equipment via separate “bridge type” isolation and test facilities with a total burden that shall not
affect the accuracy of measurement.
18.1.8.3 Meters
Meters shall be of the three-element type independent for each phase, rated as appropriate and
shall comply with IEC Standard 62052-11: Electricity Metering Equipment (AC)-General
requirements, tests, and testing conditions for static watt-hour meter and other types of meters,
and shall be of the accuracy class of 0.2 or better.
The meters shall measure and locally display at least the MW, MWh, Mvar, Mvarh, and cumulative
demand, with additional features such as time-of-use, maintenance records and power quality
monitoring. Meters shall be digital unless agreed otherwise by EAPP CC. A cumulative register of the
parameters measured shall be available on the internal storage facilities of the digital meters for a
minimum of thirty (30) calendar days with one (1) hour values. Bi-directional Meters shall have two
such registers available.
The loss of auxiliary supply to the Metering Equipment shall not erase these registers. The meter
registers shall be readable by both the TSO’s SCADA and by the DCS of EAPP CC. Where data storage
is not provided internally, it shall be provided externally to the Metering Equipment by way of a data
logger, which summates the pulse outputs of the meters. The internal registers of these devices
shall provide a register per measured quantity that can be interrogated by the TSO’s SCADA system
and by the DCS of EAPP CC.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 212
CHAPTER 18 Interconnection Metering
VTs and CTs shall be tested according to the relevant IEC standards prior to installation at the DMP.
The TSO shall provide manufacturer’s test certificates to EAPP CC to show compliance with the
accuracy standards in this IMC.
Where, following a test, the accuracy of the Metering Equipment is shown not to comply with the
requirements of this IMC, the TSO shall take such measures as are required to restore the accuracy
of the Metering Equipment to the required standard.
The cost of routine testing shall be met by the TSO as owner of the Metering Equipment.
The cost of calibration testing shall be met by the Party requesting the test unless the test shows the
accuracy of the Metering Equipment does not comply with the requirements of the IMC, in which
case the cost of the tests shall be met by the TSO.
TSOs shall ensure that all Metering Equipment at DMPs is physically inspected and read by it or on
its behalf not less than once in every three (3) months. The purpose of this reading is to reconcile
cumulative register readings on site with readings collected remotely. Physical checks shall be
carried out at the same time to identify such things as missing seals or damage or any other issues
for concern.
Where a Metering Equipment is found to be faulty or to be non-compliant with the IMC, EAPP CC
and the other relevant TSO shall be informed of the failure or non-compliance promptly. Such
notification shall include the plans by the TSO concerned to restore the Metering Equipment to
compliance with the IMC.
The EAPP CC shall in cooperation with the TSOs involved assess the duration of the period where the
Metering Equipment has been faulty. For that period, recorded data from the Check Meter shall be used.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 213
CHAPTER 18 Interconnection Metering
18.1.11 Security
Each TSO as owner of the Metering Equipment at the DMPs shall ensure that the equipment itself is
sealed and that any links and secondary circuits are sealed where practically possible. The seals shall
only be broken in the presence of representatives of the EAPP Independent Regulatory Board and
the TSO unless agreed otherwise by the parties involved.
18.1.12 Disputes
Disputes concerning this IMC will be dealt with in accordance with the procedures set out in Section
3.11 of Chapter 3 (Dispute Resolution).
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 214
19 DATA EXCHANGE
19.1 INTRODUCTION
The Data Exchange Chapter (DEC) defines the system data to be exchanged between TSOs and EAPP
Sub-Committees on Planning and Operations for the purpose of the modelling and analysis of
steady-state and dynamic conditions for the EAPP Interconnected Transmission System.
The DEC sets out the information flows required between TSOs and EAPP Sub-Committees on
Planning and Operations to produce EAPP system models for the various processes that require
system studies to be undertaken.
These processes include those associated with System Planning as set out in Chapter 5 (Planning or
PC), including the preparation of the Transmission System Capability Statement, and with
Operational Planning as set out in Chapter 8 (OC 1).
19.2 OBJECTIVE
The objectives of the DEC are:
a) To detail how EAPP system models are produced and agreed
b) To address the methods of information management across the interface between EAPP
Sub-Committees on Planning and Operations and TSOs to ensure consistency of the EAPP
system model, and
c) To provide a basis for cooperation between EAPP Sub-Committees on Planning and
Operations and TSOs in the field of power system analysis. The power system analysis
studies are required in order to resolve balance and capacity problems and for secure
exploitation of the advantages of the EAPP Interconnected Transmission System
The Model will characterise Generating Unit responses to system disturbances such as voltage and
frequency deviations, and oscillations and control signals for power and voltage scheduling. The
dynamic model will be part of the Power System Model used in the system studies to determine
operating transfer limits and system reinforcements.
The system data to be provided by TSOs to the EAPP Sub Committee on Planning is set out in Section
19.8 of this chapter.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 216
CHAPTER 19 Data Exchange
d) Interchange with External Systems modelled as demand or generation as the case may be.
Equivalents of the External Systems shall be used if studies other than load flow are being
carried out
e) Ratings of transmission facilities based on appropriate ambient temperature and seasonal
conditions
f) Timing of new facilities and outage schedules for existing facilities; and
g) A list of Contingencies to be considered during programme execution agreed between TSOs
and EAPP Sub Committees on Planning and Operations
TSOs are responsible for the production of models of their own National Systems and they may
determine the software to be used. If the software is different from that in use by EAPP then
appropriate data format conversion shall be carried out. The data shall be the latest version
available unless a specific version of the data is requested and in all cases, the data must be
complete.
EAPP Sub-Committee on Planning shall perform data verification to ensure correct TSO model
conversion, that the system configuration is maintained, and that the parameters for all lines,
transformers, and reactors are properly converted. The EAPP Sub-Committee on Planning shall
maintain a database of all problems encountered during data conversion and the solutions found.
19.6 EQUIVALENTS
An equivalent is a simplified version of the complete EAPP Interconnected Transmission System
model. Equivalents can be supplied to and used by third-parties for their studies. The aim is that the
characteristics of the equivalent at the Connection Points should be the same as those of the
complete model in terms of load distribution, impedances, and dynamic response.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 217
CHAPTER 19 Data Exchange
Notes
a) Design data shall be provided for new or refurbished excitation systems (for Synchronous
Generating Units and synchronous condensers) at least three (3) months prior to the installation
date
b) Unit-specific dynamics data shall be reported for Generating Units and synchronous
condensers (including, as appropriate to the model, items such as inertia constant, damping
coefficient, saturation parameters, and direct and quadrature axes reactances and time
constants), excitation systems, voltage regulators, turbine-governor systems, power system
stabilizers, and other associated generation equipment
c) Estimated or typical manufacturer’s dynamics data, based on units of similar design and
characteristics, may be submitted when unit-specific dynamics data cannot be obtained
d) The Interconnection-wide requirements shall specify unit size thresholds for permitting:
i. The use of non-detailed vs. detailed models
ii. The netting of small generating units with bus load, and
iii. The combining of multiple Generating Units at one Generating Plant
e) Device specific dynamics data shall be reported for dynamic devices, including, among
others, static VAR controllers, high voltage direct current systems, flexible AC transmission
systems, and static compensators
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 218
20 INFORMATION EXCHANGE
20.1 INTRODUCTION
The Information Exchange Chapter defines the reciprocal obligations of parties with regard to the
provision of information for the implementation of the ENTGC. The information requirements, as
defined for the Generation, Transmission, and Distribution entities, the ENTSO, the Regulatory
Authority and Users, are necessary to ensure non-discriminatory access to the ENTS and the safe,
reliable provision of transmission services.
The information requirements are divided into planning information, operational information and
post-dispatch information.
Information criteria specified in the Information Exchange Chapter are supplementary to the other
Chapters within the ENTGC. In the event of inconsistencies between other Chapters and the
Information Exchange Chapter with respect to information exchange, the requirements of the
Information Exchange Chapter shall prevail.
Requirements in this chapter apply to communications between the ENTSO and Users.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 220
CHAPTER 20 Information Exchange
Item Description
Commissioning Projected or target commissioning test date
Operating Target operational or on-line date
Reliability of connection Number of connecting circuits, e.g. one or two feeders, or firm/nonfarm
requested supply required as per Chapter 6 (Connections)
Location map Upgrades: name of existing point of supply to be upgraded and supply
voltage
New connections: provide a 1:50 000 or other agreed scale location map,
with the location of the facility clearly marked. In addition, co-ordinates
of the Connection Point to be specified
Site plan Provide a plan of the site (1:200 or 1:500) of the proposed facility, with
the proposed point of supply, and where applicable, the transmission line
route from the facility boundary to the point of supply, clearly marked
Electrical single line Provide an electrical single-line diagram of the User intake substation
diagram
(j) The TNSP and/or ENTSO may estimate any system planning information not provided by a
User as specified in items (b) and (c) above. The ENTSO shall take all reasonable steps to
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 221
CHAPTER 20 Information Exchange
reach agreement with the User on estimated data items. The ENTSO shall indicate to the
User any data item that has been estimated. The obligation to ensure the correctness of
data remains with the User
(k) Generation Licensees shall submit weekly to the ENTSO all maintenance planning
information requested with regard to each unit at each Generating Plant as well as
transmission switching
(l) The TNSP shall provide the Generation Licensees with a monthly rolling maintenance
schedule for all planned work in HV yards for a period of one year in advance. Log books
on all vessels under pressure for receivers installed in HV yards shall be made available on
request from the Generation Licensees
(m) Notification of all forced outages of both generation and transmission resources, shall be
made immediately, not exceeding in any case beyond thirty (30) minutes after they are
identified
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 222
CHAPTER 20 Information Exchange
(d) The asset owner shall, before the equipment is returned to service, communicate to ENTSO
changes made to commissioned equipment during an outage. ENTSO shall keep
commissioning records of operational data for the operational life of the Generating Plant
connected to the ENTS
(e) Users shall also provide notification on:
1. Planned and actual operational start-up dates for any permanently added, removed
or significantly altered transmission segments
2. Planned and actual start-up testing and operational start-up dates for any
permanently added, removed or significantly altered generation units
(a) Users and TNSPs shall agree on the formats to be used for the measurements and indications to
be supplied to the ENTSO. Where required signals become unavailable or do not comply with
applicable standards for reasons within the control of the provider of the information, such User
shall report and restore or correct the signals and/or indications as soon as reasonable
(b) The ENTSO shall notify the Users, where the ENTSO, acting reasonably and in consultation
with the Users, determines that additional measurements and/or indications in relation to a
User’s Generating Plant and equipment are needed to meet ENTS requirement. The costs
related to the User’s modifications for the additional measurements and/or indications shall
be for the account of the providing Use.
(c) On receipt of such notification from the ENTSO, the User shall promptly ensure that such
measurements and/or indications are made available at the unit’s communications gateway
equipment
(d) The data formats to be used and the fields of information to be supplied to the ENTSO by
the various Users shall be agreed among the parties
(e) The TNSP shall provide periodic feedback to Users regarding the transmission power flows,
bus voltages, and status of equipment and systems installed in the substations where they
are connected to the ENTS. The feedback shall include results from tests, condition
monitoring, inspections, audits, failure trends and calibration. The frequency of the
feedback shall be determined in the operating agreement, but will not exceed one year
(f) Generating Plant status reports provided by the TNSP shall also include Contingency plans
where applicable
(g) The ENTSO needs to inform Users where in the network out-of-step relays are installed, and
how the relays are expected to operate. Furthermore, the characteristics of such an islanded
network shall be provided, based on the most probable local network configuration at such a
time
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 223
CHAPTER 20 Information Exchange
(h) The cost of the installation of the DTE will be paid for by the User
(i) The User shall decide on the location of the DTE
(j) The User will be responsible for the maintenance of communications links between the
Generating Plant gateway and the DTE
(k) The TSO shall be responsible for the maintenance, upkeep, and communications charges
of the DTE
(l) Users shall exchange SCADA data that shall include:
1. Breaker statuses
2. Analog measurements (flows and voltages)
3. Generation MW and Mvar
4. Load MW and Mvar
5. Balancing area net interchange, operating reserve, and instantaneous demand
(m) Parties shall provide detailed EMS model data to the ENTSO once a year in a mutually agreed-
upon electronic format with updates as new data becomes available as current and up-to-date
representation of the EMS models become important for reliability coordination and market
operations
(n) Users shall comply with all governing confidentiality agreements relating to information
exchange
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 224
CHAPTER 20 Information Exchange
(h) At the discretion of the ENTSO, the Dispatchable Resource will submit a daily energy
schedule, which the ENTSO will use to determine the hourly power and Ancillary Service
schedule of the User, subject to the unit and/or hydrological constraints
(i) Variable Renewable Power Plants shall provide forecasts as specified in Section 7.2.11
(j) See Sections 8.2.7 (Operational Planning) and 14.2.1 (Interchange Scheduling) for more
details on units and interchange scheduling
20.4.4.2 File Transfers
The applicable User and the ENTSO shall agree on the format of the file used for data transfer. The
data shall be made available in a secure but accessible, electronically protected directory. All file
transfer data shall be fetched by the ENTSO. File transfer descriptions are detailed in Table 20-2
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 225
CHAPTER 20 Information Exchange
20.4.6.1 Telecontrol
(a) The User’s Plant shall support data acquisition to and from the Plant gateway. The ENTSO
shall be able to monitor the state of the ENTS via telemetry from the gateway connected to
the User’s Plant
(b) The signals and indications required by the ENTSO shall be agreed between the ENTSO and
the User, together with such other information as the ENTSO may from time to time
reasonably require by notice to the User
(c) Users shall interface via the standard digital interfaces, as specified by the ENTSO. Interface
cabinets shall be installed in the User’s Plant and equipment room if required. The provision
and maintenance of the wiring and signalling from the User’s Plant and equipment to the
interface cable shall be the responsibility of the User
(d) Users shall comply with such telecontrol requirements as may be applicable to the primary
control centre and, as reasonably required, to the emergency control centre of the ENTSO.
Any changes to telecontrol requirements impacting on User equipment shall be designed in
consultation with Users and shall be informed by a reasonable business motivation
20.4.6.2 Telephone/facsimile
(a) Each User shall be responsible for the provision and maintenance of no fewer than one
telephone and one facsimile unit on separate lines that shall be reserved for operational
purposes only, and shall be continuously attended to and answered without undue delay.
Scanned information sent via email may be accepted in place of facsimile at the discretion of
the ENTSO
(b) The ENTSO shall use a voice recorder for historical recording of all operational voice
communication with Users. These records shall be available for at least three (3) months.
The ENTSO shall make the voice records of an identified incident in Dispute available within
a reasonable time period after such a request from a User and/or the Regulatory Authority
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 226
CHAPTER 20 Information Exchange
Authority. A party may, at its sole discretion, designate more than one person to perform
these duties
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 227
CHAPTER 20 Information Exchange
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 228
CHAPTER 20 Information Exchange
AGC pulses The total pulses sent to a unit by the Ongoing, file created Hourly
AGC system to move the set-point up or at end of hour
down
System near real- Historical near real-time system data Communication To be agreed
time data files on readings as required for post- failure
dispatch
Unit near real-time Historical near real-time unit data files on Communication To be agreed
data readings as required for post-dispatch failure
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 229
CHAPTER 20 Information Exchange
5. Start-up time
6. Successful start-up ratio
(b) Generation Licensee shall report significant events, such as catastrophic failures, to the
Regulatory Authority within one (1) week of occurrence of such event.
(c) Generating Plants shall report Generating Plant Data and Service Performance Indicators as
described in Table 20-4 below.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 230
CHAPTER 20 Information Exchange
B Personnel
Indicator
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 231
CHAPTER 20 Information Exchange
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 232
CHAPTER 20 Information Exchange
(e) The Regulatory Authority shall determine criteria for the contracting of acceptable levels of
performance.
(f) If Distribution Licensees or end-use Users are aware that their network performance could be
unacceptable as described above, they shall take reasonable steps at their own cost to
overcome the shortcomings (e.g. by improving their line maintenance practices, improving
protection and breaker operating times, if necessary replacing the said equipment, installing
additional network breakers, changing operating procedures, installing fault-limiting devices if
the number of faults cannot be reduced, etc.). These changes to their networks should be
effected in consultation with the ENTSO regarding both the technical scope and the time
frame
(g) Where quality of service (QOS) standards are not met, the parties shall co-operate and agree
in accordance with Regulatory Authority power quality directives in determining the root
causes and plans of action
(h) Distribution Licensees shall report periodic testing of under-frequency and under-voltage
load shedding relays in the following format:
Distribution Licensee:
Date:
Substation:
Fed from transmission substation (directly or indirectly):
Activating Frequency/Voltage Timer Setting
Required As tested Required As tested
Stage 1
Stage 2
Stage 3
Stage 4
Feeders Selected (required) Feeders Selected (as tested)
Stage 1
Stage 2
Stage 3
Stage 4
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 233
CHAPTER 20 Information Exchange
Monthly Annual
A Technical
Indicators
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 234
CHAPTER 20 Information Exchange
Monthly Annual
B Personnel
Indicator
(b) A transmission provider shall provide Users with all performance indicators at each point of
supply.
20.5.3.4 System Operational Performance Information
(a) The following ENTS operational information shall be published by the ENTSO to all Users:
Daily:
1. The hourly actual demands of the previous day (MW)
2. The reserve amounts over the morning and evening peaks of the previous day (MW)
Monthly:
1. MW generated, Imports, exports, available for distribution/sale and
transmission losses.
2. Generating Plant availability
3. Regulating reserve Hours deficit over total hours
4. Number of frequency excursions > 50.05 or <49.5
5. For each abnormal network, condition the action taken by the System Operator
to restore normal operations.
6. Network constraints (details to be defined by Regulatory Authority)
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 235
CHAPTER 20 Information Exchange
Annually:
1. Annual peak (MW), date and hour
2. Annual minimum (MW), date and hour
The TNSP shall make available all information collected via recorders installed at substations, to the
ENTSO for analyses. The ENTSO shall make this information available to affected Users on request.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 236
21 CYBER SECURITY
Cyber Security is the protection required to ensure confidentiality, integrity, and availability of the
electronic communication system. With the two-way flow of electricity and information, the
management and protection of the electrical communication system that includes information
technology and telecommunication infrastructure, has become critical to the electric utility industry.
21.1 INTRODUCTION
With the increase in dependence on modern communication technology, power systems are
vulnerable to cyber-attacks and hackers. In Ethiopia, the growth in the field of information,
communication, and technology (ICT) makes it imperative to develop a sound Cyber Security
strategy that will ensure confidentiality, integrity, and availability of public and private sector
information across Ethiopia’s ICT infrastructure.
The ICT policy outlines the legislative instruments needed to govern cyber-related activities, such as
data protection laws, cybercrime laws, and intellectual property laws. Ethiopia adheres to the
cybercrime, personal data protection and electronic commerce law and policy set forth by the cyber
convention adopted by the African Union (AU), which incorporates many of the provisions in the
Council of European Convention on Cybercrime. Roadmap development for establishing Ethiopian
Computer Emergency Response Team (Computer Security Incident Response Team or CSIRT) is in
place as per African Union Convention.
Ethiopia’s Information Network Security Agency (INSA) responsible for drafting Ethiopia’s Cyber
Security Law established in 2012 the Cyber Emergency Readiness and Response Team (also known
as ETHIO-CERT). The Cyber Security Law drafted in 2014 contains internet law that addresses
“unlawful interference”, “unlawful interception”, and “illegal access” to a telecommunication
network.
Following the guidelines and best practices as described by the US DOE, National Institute of
Standard and Technology (NIST – under US Department of Commerce), National Rural Electric
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 237
CHAPTER 21 Cyber Security
Cooperative Association (NRECA, from US), convention of African Union, Ethiopia’s Cyber Security
draft provisions, and some observations of Cyber Security best practices in India and Europe, this
document provides guidance for developing Cyber Security controls that would help meet the ICT
policy and potential security challenges for Ethiopia’s power grid modernization.
This chapter addresses: (a) development of information security management controls and
procedures; (b) development of Cyber Security systems with identity; (c) access management
systems; and (d) developing skill set for defense against threats.
21.2 OBJECTIVES
Based on Ethiopia’s ICT policy as well as cyber security & personal data protection initiatives set
forth as per the African Union (AU) convention, the key objectives are identified as:
(a) Protect ion of Critical Information Infrastructure
(b) Building Skill Sets for Resource Development and Enhancing Cyber Security Awareness
among Government/Private/Public Sector
(c) Development of a Comprehensive Governance Framework for Leveraging Resources,
and Conflict Resolution,
(d) Facilitating Ethiopia’s Cyber Security and ICT Implementation Strategy and Goals
21.3 SCOPE
The Cyber Security code of Ethiopia shall adhere to the cybercrime, personal data protection and
electronic commerce law and policy set forth by the cyber convention adopted by the African Union
(AU), which incorporates many of the provisions in the Council of European Convention on
Cybercrime. The scope includes the following issues categorically:
(a) People and policy
(b) Operational issues
(c) Insecure software development life cycle (SDLC) risks
(d) Physical security
(e) Third-party relationship
(f) Network security
(g) Platform security
(h) Application security
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 238
CHAPTER 21 Cyber Security
and secure operations. Policies and procedures shall be well- documented to ensure there is no
deficiency that can lead to any security risks for the organization.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 239
CHAPTER 21 Cyber Security
Workshops shall be arranged periodically to provide training in such areas as Cyber Security for
Critical Infrastructure, Threats and Attacks, Code of Conduct relating to computer
resources/network/communication, Cyber Security Framework and Communications, Network and
Information Security, Building Cyber Attack Resilience, Cyber Security Audit and Assessment, Data
Protection and Privacy, and Cyber Security Assessment Project. Such workshops shall be aimed at
providing exposure to the local utilities (Generation including IPP, Transmission, and Distribution),
local Academia and R&D organizations as well as industry experts from overseas sharing with the
best practices knowledge and experience.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 240
CHAPTER 21 Cyber Security
be granted the lowest levels of access to cyber assets and other privileges needed to do his or her
job efficiently. A list of all personnel with authorized cyber access or authorized unescorted physical
access to critical cyber assets shall be maintained. This list that contains each person’s specific
electronic and physical access rights to such assets shall be reviewed quarterly and updated within
seven (7) days of any change in a list member’s access rights.
It is often possible to provide additional security measures that are not fully dependent on
operational mistakes. However, before implementing additional security measures a formal risk
assessment needs to be performed to balance the cost of the additional measures with the cost of
the risk incurred due to operational weaknesses. A Cyber Security program must be
comprehensive—it is only as strong as its weakest link. Failure to develop appropriate controls in
any category provides openings for attackers. This guide includes sections that describe common
risks and mitigations in each category.
Although a risk management strategy strives for risk prevention where practical, it also must
balance the costs and benefits of security controls.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 241
CHAPTER 21 Cyber Security
All cyber assets, where technically feasible, shall include automated tools or organizational process
controls to monitor Cyber Security-related system events. All automated mechanisms or processes shall
be documented. The monitoring function shall log each detected Cyber Security incident and issue an
alert. All such events shall be reviewed and logged. Logs shall be maintained for at least 90 days.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 242
CHAPTER 21 Cyber Security
Cyber vulnerability assessment of the access points to each ESP shall be done at least once a year to
examine ways in which the security perimeter can be breached and existing security controls
bypassed to compromise confidentiality, integrity, or availability of critical cyber assets.
A designated network team shall execute the configuration actions. Typical actions such as: (a)
adding vulnerable hardware; (b) introducing tampered device to the system; (c) failure to document
changes made to the network configuration; (d) not having a sign-off approval in the configuration
management process; and (e) changing network configuration that reduces security profile shall be
in the realm of responsibilities of the network team.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 243
CHAPTER 21 Cyber Security
A disaster recovery plan applies to a major disruption to service that deny access to the primary
facility infrastructure for an extended period of time. It includes the preparation (e.g., off-site
storage of system backups), emergency facilities, and procedures for restoring critical cyber assets
and infrastructure at an alternate site after an emergency.
A business continuity plan focuses on sustaining an organization’s mission and business functions
during and after a disruption. A business continuity plan shall be written for mission/business
functions within a single business unit or it may address the entire organization’s processes.
Continuity and recovery plans also define interim measures that increase the speed with which
organizations resume service after disruptions. These plans must be tailored to each system.
Creating specific measures requires a detailed understanding of specific scenarios.
Some of the key items that need to be addressed in the Contingency plan are:
(a) Server backup and recovery
(b) Data backup and recovery
(c) Network backup and recovery; and
(d) Employee backup
Information gathered from incident handling shall be used at the beginning of the SDLC to help define
better security requirements in products and provide a better understanding of the threat
environment within which these products must operate. Knowledge gained from containing and
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 244
CHAPTER 21 Cyber Security
mitigating computer security risks and threats shall also help identify auditing and recovery
requirements for systems and software. Such requirements include: (i) building alerts when files and
components that should not be changing are modified, (ii) establishing policy and configuration setting
capabilities to identify and control specific software and hardware components that should not be
changed during normal operations, and (iii) providing functionality for logging unauthorized changes or
malicious attacks in a manner that would preserve evidence in a forensically sound manner.
Collection and sharing of information shall be smooth and successful if there is a well-defined and
structured relationship between the software system developers and incident management staff.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 245
CHAPTER 21 Cyber Security
Routinely review network logs for anomalous / malicious behavior via automated and manual
techniques.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 246
CHAPTER 21 Cyber Security
number of login attempts, inactive session logout, screen lock by application, and denial of repeated
or recycled use of the same password.
In the case of preexisting contracts and relationships, it is crucial first to perform a full audit of these
previous contracts to determine whether Cyber Security gaps exist, and then to determine how best
to fill any gaps through contract renegotiation with the vendor. Vendors shall provide details on
their patch management and update process.
All settings used on network hardware shall be set to their secure settings. Settings provided by
each piece of hardware must be fully understood. Do not assume that default settings are secure.
User devices shall be prohibited from cross-connecting (i.e., acting as a router) between any two
networks. Unneeded network services shall be disabled.
21.3.4.2 Firewall
Firewalls play an important role in establishing the first line of defense against cyber threats.
Combined with anti-spyware, anti-virus and anti-spam software, strong passwords and safe online
practices, a firewall adds a layer of protection that helps enhance Cyber Security. Firewalls protect
the computer and information from: (a) hackers breaking into the system; (b) viruses and worms
that spread across the Internet; and (c) outgoing traffic from the host computer created by a virus
infection.
Firewalls and virtual local area networks (VLANs) technologies can be used to properly segment the
network and to increase its compartmentalization (e.g., machines with access to business services
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 247
CHAPTER 21 Cyber Security
like e-mail should not be on the same network segment as SCADA machines). Firewall rules shall be
routinely reviewed and tested to confirm expected behavior.
Firewalls shall be configured in accordance with the organization’s standards and policies, and deny
any of the following traffic types:
(a) Firewalls and other boundary security mechanisms that filter or act as a proxy for traffic
from one network segment to another of a different security level
(b) Invalid source or destination address (e.g., broadcast addresses, RFC 1918 address
spaces on interfaces connected to public networks, addresses not assigned by IANA on
interfaces connected to public networks)
(c) Those destined for the firewall itself, unless the firewall provides a specific service (e.g.,
application proxy, VPN)
(d) Source routing information
(e) Directed broadcasts that are not for the subnet of the originator (these can be used to
create broadcast storms in denial-of-service attacks against third parties)
(f) Destined for internal addresses or services that have not been approved for access from
external sources
Requests for allowing additional services through a firewall or other boundary protection
mechanisms must be approved by the information security manager.
Ensure channel security of critical communication links with technologies like Transport Layer
Security (TLS). Where possible, implement Public Key Infrastructure (PKI) to support two-way mutual
certificate-based authentication between nodes on the network.
Ensure that only standard, approved, and properly reviewed communication protocols are used on
the network
Ensure availability, integrity, and confidentiality of data traversing the networks through use of
digital fingerprints and signed hashes. If channel-level encryption is not possible, apply data-level
encryption to protect the data traversing the network links. Time stamps to protect against replay
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 248
CHAPTER 21 Cyber Security
attacks must be ensured. No actions shall be taken based on the data coming from network nodes
that may have been compromised.
Ensure that proper certificate and key management practices are in place. Remember that
cryptography does not help if the encryption key is easy to compromise. Ensure that keys are
changed periodically and that they can be changed right away in the event of a compromise.
21.3.4.6 Network Routing Control /Use of Secure Routing Protocols or Static Routes
When exchanging routing information with external parties, secure routing protocols or static routes
shall be used. If possible, network address translation shall be employed to prevent accidental
leakage of internal routing information. Rules include:
(a) Users and devices shall not be allowed to specify the routing of network traffic.
Development, test, and production environments shall be separated
(b) Sufficient redundancy shall be ensured to exist in the network links so that rerouting
traffic is possible if some links are compromised
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 249
CHAPTER 21 Cyber Security
may be exploited by adversaries to compromise the system. The software development process
therefore must to be security aware.
The security requirement for AMI begins with establishing fidelity of the meter data. Since smart
meters in the field are readily available, with few if any physical security controls, an attacker
gaining physical access to the smart meter may “patch” their firmware, thereby compromising the
smart meter. From this point on, any data supplied by the smart meter to the SCADA can no longer
be trusted. If the attacker can repeat the same tactic on a broader scale, it may be possible for the
hacker to generate incorrect actions for the SCADA system based on meter readings from
compromised meters. Detection of a compromised meter through remote attestation and other
state-of-the art techniques is therefore of utmost importance.
It is important to note that an attacker need not gain physical access to many meters. Since meters are
networked together, gaining access to one smart meter, downloading its firmware, reverse
engineering the firmware to look for software vulnerabilities (e.g., buffer overflow), and then creating
a root kit that can exploit that vulnerability to modify the functionality of the smart meter is all an
attacker needs to do. A worm can then be used to propagate that root kit from one smart meter to
another via a network that connects them. An attacker may then have a botnet of compromised smart
meters that he or she can activate at any time to achieve the attack goal (e.g., cause a blackout).
The following actions shall be taken in order to help mitigate this vulnerability:
(a) Verify with the software/hardware vendors (with embedded software) with proof of
evidence (e.g., third-party assessment) that their software is secure and free of security
weaknesses
(b) Perform remote attestation of smart meters to ensure that the firmware has not been
modified
(c) Make use of communication protocol security extensions (e.g., MultiSpeak® security
extensions) to ascertain the integrity, including the origin integrity, of smart meter data.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 250
CHAPTER 21 Cyber Security
(d) Establish and maintain secure configuration management processes (e.g., when servicing
field devices or updating their firmware)
(e) Ensure that all software (developed internally or procured from a third party) is developed
using security-aware SDLC
(f) Apply a qualified third-party security penetration test to all hardware and software
components prior to live deployment
(g) Ensure that the software running on the smart meter is free of software weaknesses,
especially if they are remotely exploitable. Otherwise, an attacker may be able take control
of a user’s smart meter to begin manipulating the climate in the user’s home. When done on
a large scale, this may result in blackouts
(h) Implement physical security controls and detection mechanisms when tampering occurs.
(i) Ensure that a reliable source of network time is maintained
(j) Disable the remote disconnect feature that allows electricity to be remotely shut down
using a smart meter
To safeguard end user privacy, smart meter information shall be decoupled from end-user
information. Meter identification shall be done through a generic number instead of a specific
household address, GPS location, etc.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 251
CHAPTER 21 Cyber Security
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 252
CHAPTER 21 Cyber Security
(q) Perform technical audits of SCADA devices, networks, and any other connected
networks to identify security concerns
(r) Perform monitoring and logging, and ensure that people can be held accountable for
their actions
(s) Avoid taking critical control decisions without human confirmation
(t) Avoid taking critical control decisions based on too few data points
(u) Avoid taking critical control decisions based on data points from compromised field
devices or based on data that has been tampered with
(v) Ensure proper network segmentation in the SCADA environment
(w) Ensure sufficient fault tolerance and redundancy in the SCADA environment
(x) Use individual (rather than shared) user login accounts with strong passwords
(y) Ensure that all hardware authentication settings have been changed from their default values
Additionally, if utilities and third parties bundle internet access as a potential marketing hook, the
device will also be subject to potential malware when a customer surfs the internet. It is therefore
imperative to have a mechanism for frequent security patches. The following actions shall be taken
to ensure security of IHD:
(a) Ensure that the software running on IHDs is free of software weaknesses
(b) Ensure the integrity of data shown on the user’s IHD.
(c) Ensure the integrity of data sent from the user’s IHD to the control center.
(d) Ensure the anonymity and privacy of data (where appropriate) pertaining to electricity
usage patterns such that it cannot be tied back to the consumer.
(e) Perform remote attestation of IHDs to alert the control center when unauthorized
firmware updates occur.
(f) Request third-party security penetration testing of IHDs
Tables 21-1 through 21-5 below provides at-a-glance summaries of risks, impacts, and
mitigations for People and Policy Risks, Operational Risks, Thirds Party Risks, Network Risks, and
Platform Risks.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 253
CHAPTER 21 Cyber Security
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 254
CHAPTER 21 Cyber Security
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 255
CHAPTER 21 Cyber Security
Monitoring for unusual System may be vulnerable to Ensure dedicated senior management to
activities not performed fraudulent activities rigorously enforce policies and procedures
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 256
22 SYSTEM OPERATOR TRAINING
THIS Chapter contains requirements specific to both the EAPP IC and the ENTGC. If in any instance there
is a difference in requirements, the more stringent requirement shall hold.
22.1.2 Objective
The objectives of the System Operator Training Chapter are to establish mandatory continuing
training and authorisation to improve and maintain System Operator capability and performance in
their job tasks.
22.1.3 Responsibility
TSOs shall establish and authorise the System Operator positions that will have the responsibility in
their Control Centres for the safe and reliable operation of the EAPP Interconnected Transmission
System and National System. The TSO shall also be responsible for the ongoing training of their
System Operators in accordance with the SOTC. In a TSO’s Control Centre and in the EAPP CC at least
one System Operator, authorised in accordance with the SOTC, shall be on duty at all times and shall
be responsible for the operation of the EAPP Interconnected Transmission System and for complying
with the EAPP/EAC Interconnection Code.
22.1.4 Scope
Reliable operation of the EAPP Interconnected Transmission System requires highly trained and
tested System Operators who are able to evaluate information on the status of their National
System and EAPP Interconnected Transmission System. They must evaluate possible risks to system
reliability, and make near-instant decisions about actions necessary to protect the system in a safe
and reliable manner under all conditions. When recruiting System Operators, each TSO shall ensure
that they have basic qualifications and shall provide them with a continuous and coordinated
training and authorisation. System Operators should be selected on the basis of their level of
intellectual and reasoning ability and their capacity for working under stressful conditions. They
should have good engineering, mathematical and problem-solving skills and communicate clearly
both in writing and verbally. System Operators shall also have sufficient language skills to enable
them to communicate with other EAPP Control Centres under operational conditions in both the
English and French languages. System Operators must be able to deal with their peers in other
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 257
CHAPTER 22 System Operator Training
Control Centres and also with regulators, Generation Licensees, and End-use Users. System
Operators should be capable of supervising and training other operating personnel in their own
National System.
The Continuous Course is targeted at System Operators to enable them to maintain their proficiency
and professional development throughout their career. The Continuous Course is required to be
completed before expiry of the previous authorisation and will require the accumulation of a
number of credits to be defined by the EAPP Steering Committee.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 258
CHAPTER 22 System Operator Training
The training programme will introduce the basics of interconnected system operation and control
practices including security analysis, stability studies, optimal power flow and system management.
The deregulation processes adopted in EAPP Member Countries will be covered. Different
restructuring models and technical problems in operation and control including congestion
management, Ancillary Services, automatic generation control, demand forecasting, power systems
security and state estimation will be discussed.
The detailed course material shall be reviewed periodically to account for changing requirements
and developments in Prudent Utility Practice. The EAPP Steering Committee shall establish a
Committee of experts to review the training needs to ensure that the content of both courses is
relevant and covers all aspects.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 259
CHAPTER 22 System Operator Training
(d) Balancing (primary and secondary response and tertiary reserve), Automatic Generation
Control
(e) EAPP Interconnection Code and National Grid Codes
(f) Other technical or operational policies of the TSO
(g) Emergency scenarios including manual and automatic remedial actions and system
restoration philosophies
(h) Electricity Market operations
(i) Communication and reporting of system incidents
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 260
CHAPTER 22 System Operator Training
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 261
CHAPTER 22 System Operator Training
The Regulatory Authority shall certify the training practices established by each Licensee.
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 262
APPENDIX REVISION LOG
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 263
CHAPTER 0 Appendix Revision Lo
Error! No text of specified style in document.Ethiopia National Transmission Grid Code – DRAFT 264