Control Excel

The document presents a chart showing the activities, predecessors, duration, start and finish dates, slack, and criticality for a project with 7 activities labeled A through G. Activity A starts at time 0 and finishes at time 2, with 0 slack and being on the critical path. The critical path through the project is A-B-D-G, which has a total duration of 12 time units.

Uploaded by

LY Solier
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
12 views

Control Excel

The document presents a chart showing the activities, predecessors, duration, start and finish dates, slack, and criticality for a project with 7 activities labeled A through G. Activity A starts at time 0 and finishes at time 2, with 0 slack and being on the critical path. The critical path through the project is A-B-D-G, which has a total duration of 12 time units.

Uploaded by

LY Solier
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 2

DATOS INICIACION CULMINACION

ACT. ACT.PRECE DURACION DESCRIP ES EF


A 2 0 2
B A 8 2 10
C A 2 2 4
D C-E 3 5 8
E A 3 2 5
F E 1 5 6
G D-B-F 2 10 12

0 2 4 6 8 10 12 14
NICIACION CULMINACION
LS LF HOLGURA CRITICIDAD
0 2 0 AC
2 10 0 AC
5 7 3 ANC
7 10 2 ANC
4 7 2 ANC
9 10 4 ANC
10 12 0 AC

Chart Title
G

0 2 4 6 8 10 12 14