Critical Path Method Analysis: Practice Questions: Q1. Activity Immediate Predecessor Duration

This document provides three examples of activity networks with questions about analyzing the critical path for each using the critical path method. The questions ask to: 1) Develop activity-on-node (ADM) and precedence diagramming method (PDM) networks. 2) Calculate early start, early finish, late start, late finish for each activity. 3) Identify the critical path on the network diagram. 4) Summarize critical path calculations including total and free slacks in a table.

Uploaded by

aa61353
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
389 views2 pages

Critical Path Method Analysis: Practice Questions: Q1. Activity Immediate Predecessor Duration

This document provides three examples of activity networks with questions about analyzing the critical path for each using the critical path method. The questions ask to: 1) Develop activity-on-node (ADM) and precedence diagramming method (PDM) networks. 2) Calculate early start, early finish, late start, late finish for each activity. 3) Identify the critical path on the network diagram. 4) Summarize critical path calculations including total and free slacks in a table.

Uploaded by

aa61353
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 2

Critical Path Method Analysis: Practice Questions

Q1.
Activity Immediate Predecessor Duration
A None 3
B None 4
C None 3
D C 2
E B 1
F A 5
G B 2
H B 3
I C 11
J D,E 3
K F,G 1
L K 4
M J,H 4

1) Develop the ADM and PDM networks for the above-mentioned project?

2) Calculate the early start, early finish, late start, and the late finish of each activity?

3) Show the critical path in the network diagram?

4) Also compute the total slacks and free slacks, and summarize the critical path
calculations in a tabular form?

Q2.
Activity Immediate Duration
Predecessor
A None 1
B A 2
C A 1
D A 2
E C,D 3
F E 4
G D 4
H G 2
I H 3
J F,I 4
K F,I 1
L J,K 2
M L 2
N L 2
O D 2
P B,M,N,O 1
Q P 2
R Q 1
S Q 1
T S 2
U R,T 2

1) Develop the ADM and PDM networks for the above-mentioned project?

2) Calculate the early start, early finish, late start, and the late finish of each activity?

3) Show the critical path in the network diagram?

4) Also compute the total slacks and free slacks, and summarize the critical path
calculations in a tabular form?

Q3.

Immediate
Activity Duration (days)
Predecessor
A --- 3
B --- 4
C --- 3
D C 2
E B 1
F A 5
G B 2
H E, G 3

1) Develop the ADM and PDM networks for the above-mentioned project?

2) Calculate the early start, early finish, late start, and the late finish of each activity?

3) Show the critical path in the network diagram?

4) Also compute the total slacks and free slacks, and summarize the critical path
calculations in a tabular form?