Load Flow
Load Flow
Operation
Dr S.R.Samantaray
School of Electrical Science
IIT Bhubaneswar
Course Content:
•Unit commitment
• Mid-Sem: 30 Marks
• End-Sem: 50 Marks
• TA: 20 Marks
Sample Power System
Indian Power-Grid Scenario
Evolution of National Grid
•Grid management on regional basis started in 1960s.
•Initially, State grids were inter-connected to form regional grid and India was demarcated
into 5 regions namely Northern, Eastern, Western, North Eastern and Southern region.
•In October 1991 North Eastern and Eastern grids were connected.
•August 2006, North and East grids were interconnected and thereby 4 regional grids
Northern, Eastern, Western and North Eastern grids are synchronously connected
forming central grid operating at one frequency.
•On 31st December 2013, Southern Region was connected to Central Grid in Synchronous
mode with the commissioning of 765kV Raichur-Solapur Transmission line thereby
achieving 'ONE NATION'-'ONE GRID'-'ONE FREQUENCY'.
Indian Power-Grid Scenario
Indian Power-Grid Scenario
•The utility electricity sector in India had an installed capacity of 358.97 GW as
of June 2019.
•India became the world's third largest producer and third largest consumer of
electricity in the world.
Region %
Western Region 32.6%
Northern Region 27.49%
Southern Region 28.14%
Eastern Region 9.8%
North-Eastern 1.1%
Region
Indian Power-Grid Scenario
Indian Power Grid SCADA structure:
NLDC
RLDC RLDC
2. Problem formulation
Two-bus case
Matrix- Y-BUS
General equations
Bus classification
Variable types and limits
6. Adjustment of bounds
7. DC load flow
• Given the load demand and supply, to find out all bus voltages
and complex power flowing in the network.
Stage-1 Stage-2
Finding complex voltages at Computing remaining
the busses (where conventional parameters of interest
linear circuit analysis fails) including active and reactive
powers, line losses etc)
Applications:
1. On-line analyses
State estimation
Security
Economic analyses
2. Off-line analyses
Operation analyses
Planning analyses
Network expansion planning
Power exchange planning
Security analyses
-Faults
-Stability
Problem Formulation:
Matrix Representation
Now by replacing:
• ‘4n’ variables
2. PV buses
• Power balance
• Variable types
Variable types and limits
• Variable limits
Gauss-Seidel Method:
• Non-linear system:
✔ Iteration
✔ Stopping rule
• Example
Gauss-Seidel for Power Flow Solution
1. Known Quantities:
3. Initialize voltages
Gauss-Seidel solution technique
4. PQ buses
Gauss-Seidel solution technique
5. PV buses
At iteration (r+1):
Limits:
Gauss-Seidel solution technique
6. Stop criterion
7. If no convergence, go to step 4
Vector form:
Per iteration:
PV buses: iteration (r+1) : Bus-2
where
where
Stopping criterion:
If convergence:
Line losses:
Final results
(11 iterations needed to attain the solution)
Errors for |V| & |Q|:
Final solution
The Newton-Raphson solution technique
• One variable:
• Example:
Faster !!
General Formulation:
Matrix form:
The Newton-Raphson solution technique
Load flow case:
Using Taylor Expansion:
Matrix notation:
Jacobian matrix:
Jacobian dimension:
For
Steps involved in N-R Technique
1. Build
2. Specify
3. Initialize
4. Compute
5.
6. Compute
sub-matrices
7. Solve
8. Update
9. Go to step 4..
Example:
Assumptions:
1. Three (3) buses:
Bus1: Slack
Bus 2: PV
Bus 3: PQ
Now
Initialization:
Residuals:
Checking:
Jacobian:
First iteration:
Residuals:
No convergence.
Residuals:
Tolerance OK
Jacobian iteration 3:
Final power values:
Decoupled Newton-Raphson Technique
Assume:
We have
Now
Tolerance 0.1
MVA
• Admittance matrix
• Initialization:
Flow Diagram:
• Compute
• Calculate P and Q:
No convergence
• First iteration:
• Residuals:
• Residuals:
where
Solution:
Example:
Now:
Final result:
Comparison of load flow methods:
1. Gauss-Seidel (G-S)
• Simple technique
• Iteration time increases linearly with the number of buses.
Lower iteration time than NR. Seven times faster in large
systems
• Linear rate of convergence. Many iterations required for
getting close to the solution
• Number of iteration increases with the number of buses
2. Newton-Raphson (N-R)
• Widely used
• Iteration-time increases linearly with the number of buses
• Quadratic rate of convergence. A few iterations for getting close to the
solution
• Number of iterations independent of the number of buses of the system
• The Jacobian is a very sparse matrix
• Method non-sensitive to slack bus choice and the presence of series
capacitors
• Sensitive to initial solution
Comparison of load flow methods:
3. AC decoupled
• has to be computed and factorized only once
• It requires more iterations than Newton Raphson method
• Iteration time is 5 times lower than Newton Raphson´s iteration
time
• Useful for analyzing topology changes because can be easily
modified
• Used in planning and contingency analyses
Regulating Transformer:
• Transformers which provide small adjustment in voltage magnitude and phase are
important components on power systems.
• Most of the transformers provide windings to adjust the ratio of the transformer at
deenergized condition. However, when the taps are changed when the transformer
is energized is known as a load-tap-changing transformer.
• The tap changing is automatic and achieved by motors triggered by the relays set on
the voltage at the prescribed level.
• Regulating Transformers are used to control both active and reactive power flows
in the transmission systems.
Y-BUS matrix:
Load-Flow study:
Load-Flow study:
Load-Flow study:
Load-Flow study:
Example:
Load-Flow study:
Load-Flow study:
Load-Flow study:
Load-Flow study:
Load-Flow study:
Load-Flow study:
Load-Flow study:
Load-Flow study:
Load-Flow study:
Load-Flow study:
Load-Flow study:
Thank You