Sarangani District Engineering Office: Bidding Documents FOR

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 132

Note: This is the Cover Sheet for the Contract-Specific Bidding Documents.

DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS

PROCURING ENTITY: SARANGANI DISTRICT ENGINEERING OFFICE

BIDDING DOCUMENTS

FOR

PROCUREMENT ID/CONTRACT ID: 19ME0143

CONTRACT NAME: CONSTRUCTION OF MULTI-PURPOSE


BUILDING PUBLIC MARKET AT MAITUM;

LOCATION: MAITUM, SARANGANI PROVINCE

DATE OF OPENING OF BIDS: NOVEMBER 12, 2019

START DATE FOR ISSUANCE


OF BIDDING DOCUMENTS: OCTOBER 24 – NOVEMBER 12, 2019

19ME0143
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
SARANGANI
DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE XII
Alabel, Sarangani Province

BIDDER’S CHECKLIST OF REQUIREMENTS FOR ITS BID, INCLUDING


TECHNICAL AND FINANCIAL COMPONENTS OF THE BID

The Technical Component shall contain the following:

 PhilGEPS Certificate of Registration and Membership


 a. If not yet enrolled in the CWR
o PCAB License and Registration
o Statement of All Ongoing Government and Private Contracts
o SLCC
o NFCC Computation and Statement of Total Assets and Total Liabilities
o JVA, if applicable
b. If already enrolled in the CWR but wishes to update Eligibility0 Documents

o Documents to be updated: ________________________________________

 Bid Security (Form DPWH-INFR-09, 10, or 11, as applicable)


 Project Requirements:
o Duly initialed Organizational Chart for the Contract (Form DPWH-INFR-12)
o Duly initialed Contractor’s List of Key Personnel for the Contract (Form DPWH-INFR-13)
o Duly initialed List of Contractor’s Major Equipment (Form DPWH-INFR-14)
o Sworn statement under RA9184-IRR Sec. 25.2b)iv) (Form DPWH-INFR-15)
 Signatory is proprietor/duly authorized representative of bidder.
 Full power and authority to perform acts or represent bidder.
 Not “blacklisted” or barred from bidding.
 Each document is authentic copy of original, complete, and correct.
 Authorizing Head of Procuring Entity to verify all documents submitted.
 Not related to HOPE, BAC, TWG, Secretariat, PMO/IU, within 3rd civil degree.
 Complies with existing labor laws and standards.
 Aware of and undertaken responsibilities as a bidder.
 Did not give any commission, amount, fee, or consideration.

The Financial Component shall contain the following:

 Duly signed Bid Form


 Duly signed Bid Prices in the Bill of Quantities (Forms DPWH-INFR-16 and 17)
 Duly initialed Detailed Estimates
 Duly initialed Cash Flow by Quarter (Form DPWH-INFR-18)

19ME0143
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
SARANGANI
DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE XII
Alabel, Sarangani Province

TABLE OF CONTENTS

ANNEX II-1.1A : Section I. Invitation to Bid (IB) ……………………………………. 6


ANNEX II-1.1B : Section II. Eligibility Requirements (ER) ……………………….. 10
ANNEX II-1.1C : Section III. Eligibility Data Sheet (EDS) ……………………….. 18
ANNEX II-1.1D: Section IV. Instructions to Bidders (ITB) ………………………… 20
ANNEX II-1.1E : Section V. Bid Data Sheet (BDS) ……………………………….… 58
ANNEX II-1.1F : Section VI. General Conditions of Contract (GCC) ……..... 63
ANNEX II-1.1G: Section VII. Special Conditions of Contract (SCC) ………..... 100
ANNEX II-1.1H: Section VIII. Specifications ……………………………………….….. 104

ANNEX II-1.1I: Section IX. Drawings ……………………………………………….……. 105

ANNEX II-1.1J: Section X. Bill of Quantities (BOQ) …………………………………. 106

ANNEX II-1.1K: Section XI. Bidding Forms (BFs) …………………………….……… 107

ANNEX II-1.1L: Section XII. Foreign-Assisted Projects (FAPs) …………….…… 109

19ME0143
ANNEX II–1.1A
Section I. Invitation to Bid
Notes on the Invitation to Bid

The Invitation to Bid (IB) (Form DPWH-INFR-04) provides information that enables
interested Bidders to decide whether to participate in the procurement of the particular contract
at hand. The Procuring Entity shall undertake the following:

a. Advertise the IB at least once in one (1) newspaper of general nationwide circulation
which has been regularly published for at least two (2) years before the date of the
advertisement, provided that this requirement for advertisement shall not apply to
contracts with an ABC of PhP 5 million or below each, subject to Section 21.2.1(c) of the
IRR if RA 9184; Two (2) years after the effectivity of the Revised RA 9184-IRR on 28
October 2016, advertisement in a newspaper of general nationwide circulation shall no
longer be required. However, a Procuring Entity that cannot post its opportunities in the
PhilGEPS for justifiable reasons shall continue to publish its advertisements in a
newspaper of general circulation.

b. Post the IB the following websites, continuously for seven (7) calendar days starting on
the date of advertisement of the IB:

(1) Website of the DPWH www.dpwh.gov.ph.

(2) Website of the Philippine Government Electronic Procurement System (PhilGEPS)


www.philgeps.gov.ph.

(3) Website prescribed by the concerned foreign government/foreign or international


financing institution or IFI (e.g., United Nations Development Business (UNDB),
dgMarket.

Together with the IB, post the other parts of the BDs for the contract on the three
websites mentioned over the same periods.

c. Post the IB at any conspicuous place reserved for this purpose in the premises of the
Procuring Entity, as certified by the head of the Bids and Awards Committee (BAC)
Secretariat of the Procuring Entity for seven (7) calendar days starting on the date of
advertisement of the IB.

The IB shall include the following:

a. Procurement/Contract ID, name and location, brief description of the type, size, major
items and other important or relevant features of the works.

b. Approved Budget for the Contract (ABC).

c. Source of funding.

d. Contract duration.

19ME0143
e. Statement that the bidding is conducted in accordance with RA 9184 and its
Implementing Rules and Regulations (IRR).

f. General statements of the criteria to be used for the eligibility check, examination and
evaluation of bids, post-qualification, and award.

g. Date of availability of the Bidding Documents, which shall be from the time the
Invitation to Bid is first advertised/posted until the deadline for the submission and
receipt of bids.

h. Place where the Bidding Documents may be acquired or the website where it may be
downloaded.

i. Deadline for the submission and receipt of bids from the last day of posting of the
Invitation to Bid.

j. Date, time, deadline, and place for the Pre-Bid Conference, receipt of bids, and opening
of bids.

h. Payment of Fee for the BDs.

k. Reservation for the Procuring Entity to accept/reject any/all bids or annul the bidding
process without any liability to the bidders.

l. Name, address, telephone number, fax number, email and website addresses of the
concerned Procuring Entity and its designated contact person.

m. Statement as to whether or not Electronic Bidding, under GPPB Resolution No. 13-2013,
will be adopted in this procurement.

n. Other necessary information as determined by the Procuring Entity.

The IB should be incorporated into the contract-specific Bidding Documents (BDs). The
information contained in the IB must be consistent with all other parts of the BDs, including
the Instructions to Bidders (ITB) and the Bid Data Sheet (BDS).

19ME0143
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
SARANGANI
DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE XII
Alabel, Sarangani Province

INVITATION TO BID

for

The DPWH-Sarangani District Engineering Office, Alabel Sarangani Province, through its
Bids and Awards Committee (BAC), invites contractors to submit bids for the Contracts:

1. Contract ID No.: 19ME0143


Contract Name: Construction of Multi-Purpose Building Public
Market at Maitum;
Location: Maitum, Sarangani Province
Brief Description: Construction of Multi-Purpose Building
Approved Budget for the Contract (ABC): Php 19,800,000.00
Source of Funds: FY 2019 DPWH Local Infrastructure Program
Contract Duration: 180 calendar days
Bidding Doc. Fees Php 25,000.00

The BAC is conducting the public bidding for this Contract in accordance with RA 9184 and its
Implementing Rules and Regulations (IRR).

To be eligible to bid for this Contract, a contractor must meet the following major requirements:
(a) Filipino Citizen of 75% Filipino-owned partnership/corporation with PCAB license for Size Range
___, (b) completion of a similar contract costing at least 50% of the ABC, and (c) Net Financial
Contracting Capacity (NFCC) at least equal to the ABC.

The DPWH will use non-discretionary “pass/fail” criteria in the eligibility check, preliminary
examination of bids, evaluation of bids, post-qualification, and award.

The schedule of key procurement activities for this Contract is shown below:
Activity Time Place
1. Issuance/Downloading of Date: October 24 – *Hard copies at BAC
Bidding Documents November 12, 2019 Secretariat, DPWH Sarangani
Time: 8:00 a.m. to District Engineering Office
5:00 p.m. Brgy., Kawas, Alabel,
Sarangani Province
*Downloadable from (a)
DPWH website
www.dpwh.gov.ph, (b)
PhilGEPs website
www.philgeps.gov.ph,
and (c) website of concerned
foreign financing institution.

19ME0143
2. Pre-bid Conference Time: 10:00 a.m. DPWH Sarangani District
Date: October 31, 2019 Engineering Office Brgy.,
Kawas, Alabel, Sarangani
Province

3. Receipt by the BAC of Bids Deadline: DPWH Sarangani District


Time: not later than 10:00 Engineering Office Brgy.,
o’clock in the morning Kawas, Alabel, Sarangani
Province
Date: November 12, 2019
4. Opening of Bids Time: immediately after the DPWH Sarangani District
deadline for submission Engineering Office Brgy.,
of Bids Kawas, Alabel, Sarangani
Date: November 12, 2019 Province

Bidders shall pay the BAC a non-refundable fee for the Bidding Documents in the amount upon
securing hard copies of the Documents. Bidders that downloaded the Documents from the
DPWH/PhilGEPS website shall pay the fee upon submission of their bids.

“If at the time of the post-qualification procedure, the BAC verifies that any of the deficiencies is
due to the contractor's fault or negligence pursuant to 34.3(b)(ii)(c) of the 2016 Revised
Implementing Rules and Regulations of Republic Act No. 9184 (2016 RlRR of RA 9184), the
Procuring Entity shall disqualify the contractor from the award without any right to reimburse fees
and incidental cost paid for the procurement of infrastructure contract subject of the Bid".

Bids must be delivered by the Authorized Managing Office (AMO) or by his/her Authorized Liaison
Officer indicated in the contractor’s information to the address below on or before November 12,
2019 not later than 10:00 o’clock in the morning at DPWH Sarangani District Engineering Office.
All bids must be accompanied by a bid security in any of the acceptable forms and in the amount
stated in ITB Clause 18. Bids will be opened in the presence of the bidders' representatives who
choose to attend at the address below. Late bids shall not be accepted.

The DPWH-Sarangani District Engineering Office, Alabel Sarangani Province, reserves the right to
accept or reject any bid and to annul the bidding process any time before the Contract award,
without incurring any liability to the affected bidders, in accordance with the provisions of Section
41 of RA 9184 and its IRR.

Any requests for additional information concerning this bidding shall be directed to the following:

HERMON JEROME L. PAEZ


BAC Chairperson
DPWH Sarangani District Engineering Office
Brgy., Kawas, Alabel, Sarangani Province
Email Address: _______________________

EDWARD D. CARILLO
BAC Secretariat Head
DPWH Sarangani District Engineering Office
Brgy., Kawas, Alabel, Sarangani Province
Email Address:[email protected]

19ME0143
Approved by:

ADRIANO N. NOGODULA III


BAC Vice Chairperson

Dates of Publication: October 24 – 30, 2019

*For PCAB Small A and Small B Contractors, delete (b) of this paragraph, and rename (c) as (b).
R12.14-Proc-agp/EDC

Form DPWH-INFR-04

19ME0143
ANNEX II-1.1B
Section II. Eligibility Requirements

Notes on the Eligibility Requirements (ER)

This Section provides the information necessary for prospective bidders to prepare responsive
applications for eligibility to bid for the Contract in accordance with the requirements of the
Procuring Entity.

The provisions contained in this Section shall be used unchanged. Additional information or
requirements specific to each contract to be procured shall be specified in the Eligibility Data
Sheet (EDS).

19ME0143
STANDARD FORMAT

ELIGIBILITY REQUIREMENTS
1. Unless otherwise indicated in the Instructions to Bidders (ITB), the prospective bidder
must meet the following Eligibility Requirements (ER) for purposes of determining by the
DPWH the eligibility of the bidder for the contract to be procured:

a. Submission of Class “A” and Class “B” Documents

To participate in the bidding for an infrastructure contract in the DPWH, a contractor/


bidder must submit to the BAC of the Procuring Entity the following Class “A” and Class
“B” Documents, as part of the Technical Component of its bid for the contract. . The
submission of these Documents is required only of contractors that are not yet enrolled in
the DPWH Civil Works Registry (CWR) or those that wish to update their Class “A”/Class
“B” documents submitted earlier for the CWR. In any case, prior enrolment or registration
of a contractor with the CWR is not a prerequisite to the submission of bids for a specific
contract.

Class “A” Documents (IRR Section 23.1a):

(1) Legal Documents

(a) Registration certificate from the Securities and Exchange Commission (SEC) in the
case of a Partnership or Corporation, or from the Department of Trade and
Industry (DTI) in the case of a Single Proprietorship, or from the Cooperatives
Development Authority in the case of a cooperative.

(b) Mayor’s/Business Permit issued by the city or municipality where the principal
place of business of the prospective bidder is located.

(c) Tax Clearance per Executive Order (EO) No. 398, series of 2005, as finally
reviewed and approved by the Bureau of Internal Revenue (BIR).

(2) Technical Documents

(a) Valid Philippine Contractors’ Accreditation Board (PCAB) license and registration for
the type and cost of contract to be procured. In the case of a joint venture, the
license and registration must be those of the joint venture, not of any of its
members.

(b) Record of the prospective bidder’s completed contracts, both government and
private, including the following information for each contract:

i. Contract ID, name and location.


ii. Contract start and actual completion dates.
iii. Owner’s name and address.
iv. Nature of work and size/dimensions.

19ME0143
v. Contractor’s role (whether sole contractor, sub-contractor, or partner in a joint
venture), specific components or aspects of the work done by it, and its
participation percentage.
vi. Total as-built cost at completion.

Bidder’s single largest completed contract similar to the contract to be procured.


(During the Eligibility Check of bids submitted for the contract to be procured, the
CWR program will automatically identify the Bidder’s SLCC similar to the contract
to be bid from the Bidder’s record of completed contracts in the CWR.)

(c) Record of the prospective bidder’s on-going contracts, including awarded but not
yet started, both in government and the private sector, indicating the following
information for each contract.

i. Contract ID, name and location.


ii. Contract start and completion date.
iii. Owner’s name and address.
iv. Nature of work and size/dimension.
v. Contractor’s role, specific components or aspects of the work done by it, and
participation percentage.
vi. Percentage work accomplished.
vii. Percentage time elapsed.

(3) Financial Documents

(a) The prospective bidder’s Audited Financial Statement (AFS), stamped “received’’ by
the BIR or its duly accredited and authorized institution, for the immediately
preceding calendar year, showing, among other things, the prospective bidder’s
total and current assets and liabilities.

(b) The prospective bidder’s computation for its Net Financial Contracting Capacity
(NFCC).

To facilitate determination of eligibility, the BAC of a Procuring Entity shall use the
contents of the PhilGEPS electronic registry of contractors (IRR Section 23.3).

All bidders shall maintain in the PhilGEPS a current and updated file of the following Class
“A” Eligibility Documents (IRR Section 8.5.2 in relation to Sec. 23.1(a)):

(a) Registration Certificate from SEC/DTI/CDA,

(b) Mayor’s/Business Permit,

(c) Tax Clearance,

(d) PCAB License and Registration.

(e) Audited Financial Statements

19ME0143
With a bidder’s submission to the PhilGEPS of these five Class “A” Documents, the bidder
shall secure a PhilGEPS Certificate of Registration and Membership.

For every specific contract to be procured, the bidder shall submit to the BAC, as part of
its bid, its PhilGEPS Certificate of Registration and Membership. This PhilGEPS Certificate
will already cover the abovementioned five Class “A” Eligibility Documents. Unless the
bidder is previously enrolled in the DPWH Civil Works Registry (CWR), the bidder shall
submit to the BAC, as part of its bid for the contract, all other Class “A” and Class “B”
Eligibility Documents which are not covered by the PhilGEPS Certificate. The bidder,
however, shall still submit to the BAC, as part of its bid, a copy of its current PCAB License
and Registration (even if this is already covered by the PhilGEPS Certificate) since it is
needed to provide detailed data to be used in the computerized Eligibility Check,
considering that the DPWH is not yet interconnected with the PhilGEPS and, hence, cannot
directly access the PCAB License from the PhilGEPS.

Class “B” Document (IRR Section 23.1b)

Valid joint venture agreement (JVA), in case the joint venture is already in existence. In
the absence of a JVA, duly notarized statements from all the potential joint venture (JV)
partners shall be included in the bid, to the effect that they will enter into and abide by
the provisions of the JVA in the instance that the bid is successful. Failure to enter into a
JV shall be a ground for the forfeiture of the Bid Security. Each partner of the JV shall
submit the PhilGEPS Certificate of Registration in accordance with Section 8.5.2 of the IRR
of RA 9184. The submission of technical and financial eligibility documents by any of the
JV partners constitutes compliance. The partner responsible to submit the NFCC shall
likewise submit the statement of all of its ongoing contracts and Audited Financial
Statements.

b. Legal Requirements for Eligibility

The prospective bidder must be either of the following:

(1) A Filipino citizen/sole proprietorship.

(2) A partnership duly organized under the laws of the Philippines and of which at least
seventy-five percent (75%) of the interest belongs to citizens of the Philippines.

(3) A corporation duly organized under the laws of the Philippines and of which at least
seventy five (75%) of the outstanding capital stock belongs to citizens of the
Philippines.

(4) A cooperative duly registered with Cooperative Development Authority.

(5) Persons/entities forming themselves into a joint venture (JV), i.e., a group of two (2)
or more persons/entities that intend to be jointly and severally responsible or liable for
a particular contract, provided that, in accordance with the President’s Letter of
Instructions No. 630, Filipino ownership or interest in the JV concerned shall be at
least seventy-five (75%); provided, further, that JVs in which Filipino ownership or
interest is less than seventy-five percent (75%) may be eligible where the structures
to be built require the application of techniques and/or technologies which are not
adequately possessed by a person/entity meeting the seventy-five percent (75%)
Filipino ownership requirement; and provided, finally, that in the latter case, Filipino

19ME0143
ownership or interest shall not be less than twenty-five percent (25%). For this
purpose, Filipino ownership or interest shall be based on the contributions of each of
the members of the JV as specified in their joint venture agreement (JVA).

c. Technical Requirements for Eligibility

(1) PCAB License

For this particular contract to be bid, the prospective bidder must possess a valid
license issued by the PCAB in accordance with the provisions of RA 4566, for the
specific category indicated in the Eligibility Data Sheet (EDS), out of the following
PCAB categories:

Table 1. PCAB License Categories


Size Range License Single Largest Project/ Allowable Range of
Category Required Track Record Contract Cost (ARCC)
Large B AAA Above PhP150M No limit
Large A AA Above PhP100M up to PhP150M Up to PhP300M
Medium B A Above PhP50M up to PhP100M Up to PhP200M
Medium A B Above PhP10M up to PhP100M Up to PhP100M
Small B C&D Above P500,000 up to PhP10M Up to PhP15M
Small A Trade Up to PhP500,000 Up to PhP500,000

For this particular contract to be procured, the Approved Budget for the Contract
(ABC) is indicated in the EDS. The required PCAB license for this project, based on
Table 1 above, is also specified in the EDS.

(2) Work Experience in Similar Contracts

The prospective bidder must possess the experience of having a Single Largest
Completed Contract (SLCC) “similar” to the contract to be procured, and whose value,
adjusted to current prices using the consumer price indices of the Philippine Statistics
Authority (PSA), is at least fifty percent (50%) of the ABC to be bid. Small A and Small
B contractors without similar experience on the contract to be bid, however, may be
allowed to bid if the cost of such contract is not more than the Allowable Range of
Contract Cost (ARCC) corresponding to their PCAB license as shown in Table 1 above
(IRR Section 23.4.2.4).

As stated in Appendix 2.2 (Guidelines for Major and Similar Categories of Works), a
“Major Category of Works” is the main classification of works in the contract to be bid,
according to type of infrastructure and kind of work performed - e.g. road
construction, bridge rehabilitation, etc. On the other hand, a “Similar Category of
Works” is a kind of works whose classification is considered to be comparable to the
Major Category of Works in the contract to be bid and, therefore, shall be considered
for purposes of evaluation of the bidder’s eligibility for the contract to be bid. A
“Qualifier” is an additional specific requirement on Major or Similar Categories of Work,
to be required from the bidders at the bidding stage, to show that they have the
necessary expertise and experience to execute the contract, such as an extraordinarily
large embankment volume, or soft ground treatment, or long tunnel using tunnel
boring machine, or bridge retrofitting using special jacking technology, or very long
sheet piling, multi-level basement, etc.

19ME0143
For the specific project or contract to be bid under these BDs and based on the
Guidelines and Matrix of Categories in Appendix 2.2, the Major Categories of Works
and Similar Categories of Work, as well as any Qualifier, that shall be considered in
determining a bidder’s eligibility for the contract to be bid are indicated in the EDS.

Select either the following item (a) or item (b), whichever is applicable, and delete the
other:

(a) For a contract involving a single category of works (i.e., type of infrastructure and kind
of work) - e.g., road construction, or bridge retrofitting, or flood control rehabilitation -
the following criteria shall be adopted:

i. The Major Category of Works is the single category itself.

ii. To be eligible to bid for the contract, a contractor must have done a Single Largest
Completed Contract (SLCC) for a Major/Similar Category of Works whose total cost
is at least 50% of the Approved Budget of the Contract (ABC) to be bid.

(b) For a contract to be bid involving multiple categories of works – e.g., road construction
plus bridge retrofitting plus flood control rehabilitation – the following criteria shall be
adopted:

i. Each category of works whose cost is at least 30% of the ABC shall be
considered a Major Category of Works. All other categories of works shall be
considered Minor Categories of Works.

ii. To be eligible to bid for the contract, a contractor must comply with the
following work experience requirements:

ii-a As the basic requirement, the contractor must have undertaken a SLCC
similar to the contract to be bid. To be so considered similar, the SLCC
must meet the following requirements:

 The SLCC must contain the same Major Categories of Works as the
contract to be bid, and each Major Category of Works in the SLCC
must cost at least 30% of the total cost of the SLCC.

 The total cost of the SLCC must be at least 50% of the total ABC to
be bid.

ii-b As an additional requirement, for each Minor Category of Works in the


contract to be bid, the contractor must have undertaken an SLCC –
which could be different from the SLCC required in item B2b(1) above –
containing a Category of Works whose cost is at least 50% of the ABC to
be bid for that Minor Category of Works.

In the case of contracts which include special equipment to be supplied and installed
by the supplier/manufacturer, the cost of such equipment shall be excluded from the
ABC to be used in computing the required work experience as stated in the preceding
paragraph.

19ME0143
As an exception to the foregoing, however, as mentioned above, Small A and B
contractors may be allowed to bid if the cost of the contract is not more than the ARCC
corresponding to their PCAB license as shown in Table 1 above, even if they have no
experience similar to the contract to be bid.

(3) Owner’s Certificate of Final Acceptance or Constructor’s Performance


Evaluation System (CPES) Rating

To support its SLCC, the bidder must submit the corresponding Owner’s Certificate of
Final Acceptance issued by the project owner other than the contractor, or at least a
satisfactory CPES Rating. In case of contracts with the private sector, an equivalent
document shall be submitted.

 Financial Requirements for Eligibility

The prospective bidder must have a Net Financial Contracting Capacity (NFCC) at least
equal to the ABC to be procured.

The NFCC shall be calculated as follows:

NFCC = [(Current assets minus current liabilities) (15)] minus the value of all
outstanding or uncompleted portions of the projects under ongoing contracts,
including awarded contracts yet to be started, which portions coincide with the contact
to be bid.

The values of the bidder’s current assets and current liabilities shall be based on the latest
Audited Financial Statements (AFS) submitted to the BIR.

For purposes of computing the foreign bidders' NFCC, the value of the current assets and
current liabilities shall be based on their Audited Financial Statements prepared in
accordance with international financial reporting standards.

The Procuring Entity shall apply the abovementioned Eligibility Requirements (ER) not only to
the main contractor/bidder but also to any sub-contractors for the portions of the main
contract works that are proposed to be sub-contracted to them, except for pakyaw contracts
as defined in Appendix 11 of RA 9184-IRR.

The main contractor/bidder, however, must meet all of the abovementioned Eligibility
Requirements by itself, with or without any sub-contractor. Hence, if any nominated sub-
contractor is declared ineligible, the main contractor, on its own, must still meet the
prescribed Eligibility Requirements.

Notwithstanding the eligibility of a bidder, the Procuring Entity concerned reserves the right to
review the qualifications of the bidder at any stage of the procurement process if the
Procuring Entity has reasonable grounds to believe that a misrepresentation has been made
by that bidder, or that there has been a change in the bidder’s capability to undertake the
project from the time it submitted its eligibility requirements. Should such review uncover
any misrepresentation made in the eligibility requirements, statements or documents, or any
changes in the situation of the bidder which will affect the capability of the bidder to
undertake the project so that it fails the eligibility criteria, the Procuring Entity shall consider
the said bidder as ineligible and shall disqualify it from obtaining an award or contract, in
accordance with Rules XXI, XXII, and XXIII of the IRR of RA 9184 (IRR Section 23.6).

19ME0143
The eligibility requirements or statements, the bids, and all other documents to be submitted
to the BAC must be in English. If the eligibility requirements or statements, the bids, and all
other documents submitted to the BAC are in foreign language other than English, it must be
accompanied by a translation of the documents in English. The documents shall be translated
by the relevant foreign government agency, the foreign government agency authorized to
translate documents, or a registered translator in the foreign bidder’s country; and shall be
authenticated by the appropriate Philippine foreign service establishment/post or the
equivalent office having jurisdiction over the foreign bidder’s affairs in the Philippines. The
English translation shall govern, for purposes of interpretation of the bid.

2. If, as specified in the EDS, Electronic Bidding is adopted for this procurement pursuant to
GPPB Resolution No. 23-2013, dated 30 July 2013, the following procedure shall be observed
with regard to the registry with the PhilGEPS:

a. To facilitate determination of eligibility and subject to the Government Official Merchants


Registry (OMR) guidelines, a Procuring Entity may use the registry system of the PhilGEPS
that allows submission and/or recording/entry of eligibility requirements simultaneously
with registration.

b. Only a Certified Member with the appropriate classification can avail of the PhilGEPS
advance eligibility submission by uploading their electronic documents to the PhilGEPS
document library, which can be accessed for current or future procurements.

c. Submission of eligibility requirements to the PhilGEPS document library is not tantamount


to a finding of eligibility.

19ME0143
ANNEX II-1.1C
Section III. Eligibility Data Sheet (EDS)

Notes on the EDS

This Section is intended to assist the Procuring Entity in providing the specific information and
requirements in relation to corresponding clauses in the Eligibility Requirements(ER) for each
specific procurement.

The Procuring Entity should indicate in this Section the information pertaining to the contract
at hand that specifies and complements provisions of the ER.

19ME0143
Eligibility Data Sheet
Eligibility
Requirements
1c(1) The ABC for this contract is: 19,800,000.00

1c(1) The required PCAB license for this contract is as follows:


a. Size Range: Medium A
b. License Category: B
c. Largest Single Project: Above PhP10M up to PhP100M
d. Allowable Range of Contract Cost: Up to PhP100M

1c(2) (1) The following are the “Major Categories of Works” involved in the
contract to be bid:

a. BICWOPLC – Buildings: Construction-without Piles-Low Rise-Concrete


(Frame) (1 to 5 Storeys)

(2) The following are the “Similar Categories of Works” that shall be
considered in the evaluation of the work experience required for the
contract to be bid:

a. BICWPHCCP – Buildings: Construction-with Piles-High Rise-Concrete


(Frame)-Cast-in-Place Piles

b. BICWPLCCP – Buildings: Construction-with Piles-Low Rise-Concrete


(Frame)-Cast-in-Place Piles

c. BICWPHCDP – Buildings: Construction-with Piles-High Rise-Concrete


(Frame)-Driven Piles

d. BICWPLCDP – Buildings: Construction-with Piles-Low Rise-Concrete


(Frame)-Driven Piles

e. BICWOPHC – Buildings: Construction-without Piles-High Rise-Concrete


(Frame)

f. BIH – Buildings: Industrial Plant – High Rise

g. BIL – Buildings: Industrial Plant – Low Rise

h. BIM – Buildings: Industrial Plant – Medium Rise

(3) The following “Qualifiers” shall be applied to this contract:


a. _________________________
b. _________________________

2. No further instruction.

19ME0143
ANNEX II-1.1D
Section IV. Instructions to Bidders

Notes on the Instructions to Bidders (ITB)


This Section of the Bidding Documents (BDs) provides the information necessary for
Bidders to prepare responsive Bids in accordance with the requirements of the
Procuring Entity. It also provides information on the Bid submission, opening, and
evaluation, post-qualification, and award of contract.

The provisions of this Section are to be used unchanged. Annex II-1.1E: Bid Data
Sheet (BDS) consists of provisions that supplement, amend, or specify in detail
information or requirements included in this Section, and that are specific to each
particular contract to be procured.

Matters governing the performance of the Contractor, payments under the Contract, or
matters affecting the risks, rights, and obligations of the parties under the Contract are
not normally included in this Section, but rather under Annex II-1.1F: General
Conditions of Contract (GCC), and/or Annex II-1.1G: Special Conditions of
Contract (SCC).

19ME0143
STANDARD FORMAT

INSTRUCTIONS TO BIDDERS (ITB)


TABLE OF CONTENTS
A. GENERAL ………………………………………………………………. 23
1. Scope of Bid …………………………………………………………………… 23
2. Budget and Source of Funds ………………………………………….… 23
3. Corrupt, Fraudulent, Collusive, Coercive, and Obstructive Practices … 23
4. Conflict of Interest ………………………………………………………….. 25
5. Eligible Bidders ……………………………………………………………….. 26
6. Bidder’s Responsibilities …………………………………………………… 26
7. Origin of Goods and Services ………………………………………….... 28
8. Sub-contracts …………………………………………………………………. 28
9. Pre-Bid Conference ……………………………………………………….… 29
B. CONTENTS OF BIDDING DOCUMENTS ………………………….. 30
10. Content of Bidding Documents ………………………………………….. 30
11. Clarification/Amendment of Bidding Documents through Bid Bulletins … 31
C. PREPARATION OF BIDS …………………………………………….. 31
12. Cost of Bidding …………………………………………………………….. 31
13. Language of Bid ………………………………………………………..…. 31
14. Documents Comprising the Bid ……………………………….…….. 32
15. Bid Prices …………………………………………………………..…..…… 35
16. Currencies of Bid and Payment ……………………………..….…… 35
17. Bid Validity ………………………………………………………………….. 36
18. Bid Security …………………………………………………..……….……. 36
19. Alternative Bids by Bidders ………………………………………….… 39
20. Format and Signing of Bid ……………………………………….….… 39
21. Sealing and Marking of Bids ………………………..………………... 40
D. SUBMISSION AND OPENING OF BIDS ……………………………. 40
22. Place and Deadline for Receipt of Bids ……………………………… 40
23. Late Bids …………………………………………………………………….…. 40
24. Modification and Withdrawal of Bids ………………………………… 41

19ME0143
25. Receipt of Bids under Electronic Bidding ………………………………... 41
26. Opening and Preliminary Examination of Technical Components of Bids .. 42
27. Eligibility Check …………………………………………………………..………. 44
28. Preliminary Examination of Financial Components of Bids ……….. 45
29. Opening and Preliminary Examination under Electronic Biding …… 46
E. EVALUATION AND COMPARISON OF BIDS …………………….. 47
30. Process to be Confidential ……………………………………………………... 47
31. Clarification of Bid ……………………………………………………………..…. 47
32. Detailed Evaluation and Comparison of Bids ……………………………. 47
33. Procedure for Detailed Evaluation of Bids under Electronic Bidding… 49
34. Post-Qualification of the Lowest Calculated Bid ……………................. 50
35. Post-Qualification under Electronic Bidding …………………………….. 51
36. Right of the Procuring Entity to Reject Bids …………………………….. 51
F. AWARD OF CONTRACT ……………………………………………... 53
37. Award Criterion …………………………………………………………………….. 53
38. Notice of Award ……………………………………………………………………. 53
39. Performance Security ……………………………………………………………. 55
40. Documents Comprising the Contract ……………………………………… 55
41. Signing and Approval of the Contract ……………………………………. 57
42. Notice to Proceed ……………………………………………………........ …… 57
43. Protest Mechanism……………………………………………………............. 57

19ME0143
INSTRUCTIONS TO BIDDERS (ITB)

A. General

1. Scope of Bid

1.1 The Procuring Entity, as defined in the BDS, invites Bids for the construction of
the Works under the proposed Contract, as described in the BDS. The name
and ID of the Contract are stated in the BDS.

1.2 The winning Bidder will be expected to complete the Works by the intended
completion date specified in the SCC Clause 1.17.

Budget and Source of Funds

The Procuring Entity has an Approved Budget for the Contract (ABC) or has applied for
or received funds from the Funding Source named in the BDS, and in the amount
indicated in the BDS. It intends to apply part of the funds received for the Project, as
defined in the BDS, to cover eligible payments under the Contract for the Works.

Corrupt, Fraudulent, Collusive, Coercive, and Obstructive Practices

3.1 The Procuring Entity requires that the Bidders and Contractors, as well as
officials and personnel of the Procuring Entity, observe the highest standard of
ethics during the procurement and execution of such contracts. In pursuance of
this policy, the DPWH:

a. defines, for purposes of this provision, the terms set forth below as
follows:

(1) "Corrupt practice" means behavior on the part of officials in the


public or private sectors by which they improperly and unlawfully
enrich themselves and others, or induce others to do so, by
misusing the positions in which they are placed, and includes the
offering, giving, receiving, or soliciting of anything of value to
influence the action of any such official in the procurement
process or in contract execution; entering, on behalf of the
Government, into any contract or transaction manifestly and
grossly disadvantageous to the same, whether or not the public
officer profited or will profit thereby, and similar acts as provided
in Republic Act 3019.

(2) "Fraudulent practice" means a misrepresentation of facts in order


to influence a procurement process or the execution of a contract
to the detriment of the Procuring Entity, and includes collusive
practices among Bidders – before or after Bid submission -
designed to establish Bid prices at artificial, non-competitive
levels and to deprive the Procuring Entity of the benefits of free
and open competition;

19ME0143
(3) “Collusive practice” means a scheme or arrangement between
two or more Bidders, with or without the knowledge of the
Procuring Entity, designed to establish Bid prices at artificial, non-
competitive levels.

(4) “Coercive practice” means harming or threatening to harm,


directly or indirectly, persons, or their property to influence their
participation in a procurement process, or affect the execution of
a contract.

(5) “Obstructive practice” is:

(a) deliberately destroying, falsifying, altering or concealing


of evidence material to an administrative proceedings or
investigation or making false statements to investigators
in order to materially impede an administrative
proceedings or investigation of the Procuring Entity or any
foreign government/foreign or international financing
institution into allegations of a corrupt, fraudulent,
coercive or collusive practice; and/or threatening,
harassing or intimidating any party to prevent it from
disclosing its knowledge of matters relevant to the
administrative proceedings or investigation or from
pursuing such proceedings or investigation; or

(b) acts intended to materially impede the exercise of the


inspection and audit rights of the Procuring Entity or any
foreign government/foreign or international financing
institution herein.

b. will reject a proposal for award if it determines that the Bidder


recommended for award has engaged in corrupt, fraudulent, collusive or
coercive practices in competing for the Contract; and

c. will declare a firm ineligible, either indefinitely or for a stated period of


time, to be awarded a Contract if it at any time determines that the firm
has engaged in corrupt, fraudulent, collusive or coercive practices in
competing or, or in executing, a Contract.

3.2 Furthermore, the Procuring Entity will also seek to impose the maximum
penalties for civil and criminal liability available under the applicable law on
individuals and organizations deemed to be involved in corrupt, fraudulent,
collusive or coercive practices.

3.3 The Funding Source and the Procuring Entity reserve the right to inspect and
audit records and accounts of a contractor in the bidding for and performance
of a particular contract, through DPWH official or independent auditors as
provided in GCC Clause 35.

19ME0143
Conflict of Interest

4.1 All Bidders found to have a conflict of interest shall be disqualified to participate
in the procurement at hand, without prejudice to the imposition of appropriate
administrative, civil, and criminal sanctions. A Bidder may be considered to have
a conflict of interest with another Bidder in any of the events described in items
a through d of this ITB Clause 4.1 and a general conflict of interest in any of
the circumstances set out in items e through h of ITB Clause 4.1:

a. A Bidder has controlling shareholders in common with another Bidder.

b. A Bidder receives or has received any direct or indirect subsidy from any
other Bidder.

c. A Bidder has the same legal representative as that of another Bidder for
purposes of this Bid.

d. A Bidder has a relationship, directly or through third parties, that puts it


in a position to have access to information about or influence on the Bid
of another Bidder or influence the decisions of the Procuring Entity
regarding this bidding process. This will include a firm or an organization
who lends, or temporarily seconds, its personnel to firms or
organizations which are engaged in consulting services for the
preparation related to procurement for or implementation of the project
if the personnel would be involved in any capacity on the same project.

e. A Bidder submitted more than one Bid in this bidding process. However,
this does not limit the participation of sub-contractors in more than one
Bid.

f. A Bidder participated as a consultant in the preparation of the design or


technical specifications of the works, goods and related services that are
the subject of the Bid.

g. A Bidder lent, or temporary seconded, its personnel to firms or


organizations which are engaged in consulting services for the
preparation related to the procurement for or implementation of the
project, if the personnel would be involved in any capacity on the same
project.

4.2 In accordance with Section 47 of the IRR of RA 9184, the Bidder must include in
its Bid a sworn affidavit (part of Form DPWH-INFR-15, as provided in Clause
10.1 of this ITB) that it is not related to the Head of the Procuring Entity
(HoPE), members of the BAC, the Technical Working Group (TWG), and the BAC
Secretariat, the head of the IU, and the project consultants, by consanguinity or
affinity up to the third civil degree. Failure to comply with the aforementioned
provision shall be a ground for the automatic disqualification of the bid in
consonance with Section 30 of this IRR. For this reason, relation to the
aforementioned persons within the third civil degree of consanguinity or affinity
shall automatically disqualify the bidder from participating in the procurement of
contracts of the Procuring Entity, notwithstanding the act of such persons

19ME0143
inhibiting themselves from the procurement process. On the part of the bidder,
this provision shall apply to the following persons:

a. If the Bidder is an individual or a sole proprietorship, to the Bidder


himself.

b. If the Bidder is a partnership, to all its officers and members.

c. If the Bidder is a corporation, to all its officers, directors, and controlling


stockholders.

d. If the bidder is a cooperative, to all its officers, directors, and controlling


shareholders or members.

e. If the Bidder is a joint venture (JV), to each member of the JV for the
applicable items a, b, and c of this Clause.

Eligible Bidders

5.1 Unless otherwise indicated in the BDS, bidders must meet the Eligibility
Requirements in ANNEXII-1.1B of the SBDs.

5.2 The Procuring Entity may also invite foreign bidders when provided for under any
Treaty or International or Executive Agreement as specified in the BDS.

Bidder’s Responsibilities

6.1 The Bidder is responsible for the following:

a. Having taken steps to carefully examine all of the Bidding Documents.

b. Having acknowledged all conditions, local or otherwise, affecting the


implementation of the contract.

c. Having made an estimate of the facilities available and needed for the
contract to be bid, if any.

d. Having complied with its responsibility to inquire or secure


Supplemental/Bid Bulletin/s as provided under ITB Clause 11.3.

e. Ensuring that it is not “blacklisted” or barred from bidding by the


Government of the Philippines (GOP) or any of its agencies, offices,
corporations, or LGUs, including foreign government/foreign or
international financing institution whose blacklisting rules have been
recognized by the Government Procurement Policy Board (GPPB).

f. Ensuring that each of the documents submitted in satisfaction of the


bidding requirements is an authentic copy of the original, complete, and
all statements and information provided therein are true and correct

g. Authorizing the HoPE or its duly authorized representative/s to verify all


the documents submitted.

19ME0143
h. Ensuring that the signatory is the duly authorized representative of the
Bidder, and granted full power and authority to do, execute and perform
any and all acts necessary and/or to represent the Bidder in the bidding,
with the duly notarized Secretary’s Certificate attesting to such fact, if
the Bidder is a corporation, partnership, cooperative, or joint venture.

i. Complying with the disclosure provision under Section 47 of the Act in


relation to other provisions of Republic Act 3019.

j. Complying with existing labor laws and standards, if applicable.

k. Ensuring that it did not give or pay, directly or indirectly, any


commission, amount, fee, or any form of consideration, pecuniary or
otherwise, to any person or official, personnel or representative of the
government in relation to any procurement project or activity.

Failure to observe any of the above responsibilities shall be at the risk of the
Bidder concerned.

6.2 The Bidder or its duly authorized representative shall submit a sworn statement,
covering items e to k of ITB Clause 6.1 above, in the form prescribed in
DPWH-INFR-15 in ANNEX II-1.1K hereof.

6.3 The Bidder, by the act of submitting its bid, shall be deemed to have inspected
the site, determined the general characteristics of the contract works and the
conditions for this Project and examine all instructions, forms, terms, and
project requirements in the Bidding Documents.

6.4 It shall be the sole responsibility of the prospective bidder to determine and to
satisfy itself by such means as it considers necessary or desirable as to all
matters pertaining to this Project, including: (a) the location and the nature of
the contract, project, or work; (b) climatic conditions; (c) transportation
facilities; (c) nature and condition of the terrain, geological conditions at the site
communication facilities, requirements, location and availability of construction
aggregates and other materials, labor, water, electric power and access roads;
and (d) other factors that may affect the cost, duration and execution or
implementation of the contract, project, or work.

6.5 The Procuring Entity shall not assume any responsibility regarding erroneous
interpretations or conclusions by the prospective or eligible bidder out of the
data furnished by the procuring entity.

6.6 Before submitting their bids, the Bidders are deemed to have become familiar
with all existing laws, decrees, ordinances, acts and regulations of the
Philippines which may affect the contract in any way.

6.7 The Bidder shall bear all costs associated with the preparation and submission
of his bid, and the Procuring Entity will in no case be responsible or liable for
those costs, regardless of the conduct or outcome of the bidding process.

19ME0143
6.8 Bidders should note that the Procuring Entity will only accept bids only from
those that have paid the applicable fee for the Bidding Documents at the office
indicated in the Invitation to Bid.

Origin of Goods and Services

There is no restriction on the origin of Goods, or Contracting of Works or Services other


than those prohibited by a decision of the United Nations Security Council taken under
Chapter VII of the Charter of the United Nations.

Sub-Contracts

8.1 Unless otherwise specified in the BDS, sub-contracting of the Works shall be
subject to the provisions of DPWH Department Order (DO) No. 38, series of
2015, as stated in Clauses 8.2 to 8.7.

8.2 All sub-contracts shall be subject to prior approval of the concerned Heads of
the DPWH Procuring Entity within the limits of their delegated authority to
approve the original contracts.

8.3 The contractor may sub-contract portions of the works to such an extent as
may be approved by the Procuring Entity and stated in the BDS, provided that
the main contractor shall directly undertake, using its own resources, not less
than fifty percent (50%) of the contract works in terms of cost.

8.4 Each sub-contractor must comply with the eligibility criteria as specified in the
Eligibility Requirements (ER) for the portion of the contract works to be
sub-contracted to that sub-contractor- e.g., applicable license from the
Philippine Constructors Accreditation Board, satisfactory completion of works
similar to the portion of the contract to be subcontracted and costing at least
fifty percent (50%) of the cost of such portion, and sufficient Net Financial
Contracting Capacityto cover the cost of the work to be sub-contracted, as well
as minimum equipment and manpower for the sub-contracted work set by the
Procuring Entity. These requirements shall not apply to labor pakyaw contracts
provided in the IRR Appendix 11.

8.5 The bidder/main contractor may identify the sub-contractors to whom portions
of the contract works will be sub-contracted at any stage of the bidding process
or during contract implementation, provided that any sub-contracting requires
prior approval of the Procuring Entity. If the bidder opts to disclose the name of
the sub-contractors during the bid submission, the bidder shall include the
required eligibility documents for the sub-contractors as part of the technical
component of its bid. Sub-contractors identified during the bidding may be
changed during the implementation of the contract, subject to compliance with
the eligibility requirements and approval of the Procuring Entity.

8.6 Sub-contracting of any portion of the contract shall not relieve the main
contractor from any liability or obligation that may arise from the contract. The
main contractor shall be responsible for the acts, defaults, and negligence of
any subcontractor, its agents or workmen.

19ME0143
8.7 For any assignment and sub-contracting of the contract or any part thereof
made without prior written approval by the concerned HoPE, the DPWH shall
impose on the erring contractor, after the termination of the contract, the
penalty of suspension for one (1) year for the first offense, and suspension of
two (2) years for the second offense from participating in the public bidding
process, pursuant to the provision of Appendix 3, Section 4.2 of the IRR of RA
9184, without prejudice to the imposition of additional administrative sanctions
as the internal rules of the agency may provide and/or further criminal
prosecution as provided by applicable laws.

9. Pre-Bid Conference

9.1 If so specified in the BDS, a Pre-Bid Conference shall be held at the venue and
on the date indicated therein, to clarify and address the Bidders’ questions on
the technical and financial components of this Project. The Pre-Bid Conference
shall be held at least twelve (12) calendar days before the deadline for the
submission and receipt of Bids, but not earlier than seven (7) calendar days
from the posting of the IB/BDs in the DPWH and PhilGEPS websites. However,
attendance of the Bidders shall not be mandatory. If the Procuring Entity
determines that, by reason of the method, nature, or complexity of the contract
to be bid, or when international participation will be more advantageous to the
GOP, a longer period for the preparation of bids is necessary, the Pre-Bid
Conference shall be held at least thirty (30) calendar days before the deadline
for the submission and receipt of bids, as specified in the BDS.

9.2 Bidders are encouraged to attend the Pre-Bid Conference to ensure that they
fully understand the Procuring Entity’s requirements. Non-attendance of the
Bidder will in no way prejudice its bid; however, the Bidder is expected to know
the changes and/or amendments to the Bidding Documents as recorded in the
minutes of the Pre-Bid Conference and the Supplemental/Bid Bulletin. The
minutes of the Pre-Bid Conference shall be recorded and prepared not later
than five (5) calendar days after the Pre-Bid Conference. The minutes shall be
made available to prospective bidders not later than five (5) days upon written
request.

9.3 Any statement made at the Pre-Bid Conference shall not modify the terms of
the bidding documents unless such statement is specifically identified in writing
as an amendment thereto and issued as a Supplemental/Bid Bulletin at least
seven (7) calendar days before he deadline for the submission and receipt of
bids.

9.4 If, as indicated in the BDS, Electronic Bidding is adopted for this procurement
pursuant to GPPB Resolution No. 23-2013, dated 30 July 2013, the Procuring
Entity shall observe following procedure with regard to the PBC:

a. For contracts to be bid where the conduct of PBC is required under Section
22 of RA 9184-IRR (Section 5.5.3 of this Manual Volume II), the same
procedure governing the manual method will also apply.

19ME0143
b. A Procuring Entity with videoconferencing capabilities may conduct its PBC
conferences electronically, provided that its Registered Merchants shall also
have similar capabilities and facilities.
c. During the conduct of the PBC, Registered Merchants may send requests for
clarification through the PhilGEPS online facility, which shall be read during
the meeting and shall form part of the minutes, unless the Procuring Entity
has previously decided that only those who have purchased the Bidding
Documents shall be allowed to participate in the PBC and raise or submit
written queries or clarifications.

d. The minutes of the PBC shall be recorded as an electronic document made


electronically available to all participating Registered Merchants through the
PhilGEPS Electronic Bulletin Board not later than three (3) calendar days
after the PBC.

e. Requests for clarification(s) on any part of the BDs or for an interpretation


must be in writing and submitted to the BAC of the Procuring Entity, either
electronically through the PhilGEPS or otherwise, at least ten (10) calendar
days before the deadline set for the submission and receipt of bids.

f. Only Bid Bulletins/Supplements approved by the Bid Notice Approver shall


be posted in the PhilGEPS at least seven (7) calendar days before the
deadline for the submission and receipt of bids. The PhilGEPS shall
automatically notify through e-mail all Registered Merchants who have
downloaded the bidding documents and paid the BDs Fee.

B. Contents of Bidding Documents

10. Content of Bidding Documents

The set of Bidding Documents (BDs) for the specific contract at hand consists of the
documents listed below and bulletins issued in accordance with ITB Clause 11

Reference in the SBDs

Section I. Invitation to Bid (IB) ANNEX II-1.1A


Section II. Eligibility Requirements (ER) ANNEX II-1.1B
Section III. Eligibility Data Sheet (EDS) ANNEX II-1.1C
Section IV. Instructions to Bidders (ITB) ANNEX II-1.1D
Section V. Bid Data Sheet (BDS) ANNEX II-1.1E
Section VI. General Conditions of Contract (GCC) ANNEX II-1.1F
Section VII. Special Conditions of Contract (SCC) ANNEX II-1.1G
Section VIII. Specifications ANNEX II-1.1H
Section IX. Drawings ANNEX II-1.1I
Section X. Bill of Quantities (BOQ) ANNEX II-1.1J
Section XI. Bidding Forms (BFs) ANNEX II-1.1K
Section XII. Foreign-Assisted Projects (FAPs) – if applicable ANNEX II-1.1L

10.1 Bidders should note that the Procuring Entity shall only accept Bids from Bidders
that have purchased the BDs from the office indicated in the IB, or have

19ME0143
downloaded the BDs from the DPWH website subject to the payment of the fee
for the BDs upon submission of their bids.

11. Clarification/Amendment of Bidding Documents through Bid Bulletins

11.1 Prospective Bidders may request clarification(s) or an interpretation of any part


of the BDs. Such a request must be in writing and submitted to the Procuring
Entity at the address indicated in the BDS at least ten (10) calendar days
before the deadline set for the submission and receipt of Bids. The BAC of the
Procuring Entity shall respond to the said request by issuing a Bid Bulletin, to be
made available to all those who have properly secured BDs, at least seven (7)
calendar days before the deadline for the submission and receipt of bids .

11.2 The BAC, upon its initiative, may also issue Supplemental/Bid Bulletins to amend
or clarify any provision of the BDs, to be made available to all those who have
properly secured BDs, not later than seven (7) calendar days before the
deadline for the submission and receipt of Bids. .

11.3 Any Supplemental/Bid Bulletin issued by the BAC shall be posted on the
websites of the DPWH and the PhilGEPS, an at anhy conspicuous place in the
premises of the Procuring Entity. It shall be the responsibility of all Bidders who
secured the Bidding Documents to inquire and secure Supplemental/Bid
Bulletins that may be issued by the BAC. However, bidders who have submitted
bids before the issuance of the Supplemental/Bid Bulletin must be informed and
allowed to modify or withdraw their bids in accordance with ITB Clause 24.

C. Preparation of Bids

12. Cost of Bidding

The Bidder shall bear all costs associated with the preparation and submission of its
Bid, and the Procuring Entity shall in no case be responsible or liable for those costs.

13. Language of Bid

The Bid, as well as all correspondence and documents relating to the Bid exchanged by
the Bidder and the Procuring Entity, shall be written in English. Supporting documents
and printed literature furnished by the Bidder may be in another language provided
they are accompanied by an accurate translation of the relevant passages in English, in
which case, for purposes of interpretation of the Bid, the English translation shall
govern.

14. Documents Comprising the Bid

14.1 Unless otherwise indicated in the BDS, the Bidder shall submit its Bid in
accordance with the provisions of ITB Clauses 14.2 to 14.4.

14.2 The Bidder shall present its Bid which shall consist of the Technical Component
and the Financial Component.

19ME0143
a. Technical Component – This shall include all of the following documents:

(1) PhilGEPS Certificate of Registration and Membership in


accordance with Section 8.5.2 of the IRR.

(2) (a) If the bidder is not previously enrolled in the CWR: the
bidder’s Class “A” and Class “B” Documents, excluding four
Class “A” documents covered by the PhilGEPS Certificate of
Registration – viz., SEC/DTI/CDA Registration,
Mayor’s/Business Permit, Tax Clearance, and Audited
Financial Statement. These Documents should include,
among others, the following information required in IRR
Section 25.2b:

i. Unless otherwise provided in the BDS, valid PCAB


License or special PCAB License in case of joint
ventures, and registration for the type and cost of the
contract to be bid.

ii. Statement of all On-going Government and Private


Contracts, including contracts awarded but not yet
started, if any, whether similar or not similar in nature
and complexity to the contract to be bid.

iii. Statement identifying the Bidder’s SLCC similar to the


contract to be bid.

iv. NFCC Computation and Statement of Total Assets and


Total Liabilities.

v. JVA, if applicable.

(b) If the bidder is previously enrolled in the CWR but would like
to update any of its Class “A” and Class “B” Documents in the
CWR: the pertinent Documents to be updated.

(3) Bid Security in/with the required form, amount, and validity
period as provided in ITB Clause 18 (Use Form DPWH-INFR-
10 or 11 or 12).

(4) Project Requirements which shall include the following:

(a) Organizational chart for the contract to be bid (Use Form


DPWH-INFR-13).

(b) List of contractor’s personnel (e.g., Project Manager,


Project Engineers, Materials Engineers, and Foremen), to
be assigned to the contract to be bid, with their complete
qualification and experience data (Use Form DPWH-
INFR-14). These personnel must meet the required
minimum years of experience set in the BDS.

19ME0143
(c) List of contractor’s major construction and laboratory
equipment units, which are owned, leased, and/or under
purchase agreements, supported by proof of ownership
and certification of availability of equipment from the
equipment lessor/vendor for the duration of the project),
as the case may be (Use Form DPWH-INFR-15. These
equipment units must meet the minimum major
equipment requirements for the contract set in the BDS.

(d) Omnibus sworn statement by the prospective


bidder or its duly authorized representative in the form
prescribed by the GPPB as to the following (Use Form
DPWH-INFR-16):

i. It is not “blacklisted” or barred from bidding by the


Government of the Philippines or any of its agencies,
offices, corporations, or LGUs, including foreign
government/ foreign or international financing
institution whose blacklisting rules have been
recognized by the GPPB.

ii. Each of the documents submitted in satisfaction of the


bidding requirements is an authentic copy of the
original, complete, and all statements and information
provided therein are true and correct.

iii. It is authorizing the Head of the Procuring


Entity or his duly authorized representative(s) to
verify all the documents submitted.

iv. The signatory is the duly authorized representative of


the prospective bidder, and granted full power and
authority to do, execute and perform any and all acts
necessary and/or to represent the prospective bidder
in the bidding, with the duly notarized Secretary’s
Certificate attesting to such fact, if the prospective
bidder is a corporation, or duly notarized Special
Power of Attorney in case of sole proprietorship,
partnership or joint venture.

v. It complies with the disclosure provision under Section


47 of RA 9184 and its IRR in relation to other
provisions of R.A. 3019.

vi. It complies with the responsibilities of a prospective or


eligible bidder provided in the BDs, including ITB 6.

vii. It complies with existing labor laws and standards.

19ME0143
viii. It did not give or pay, directly or indirectly, any
commission, amount, fee, or any form of
consideration, pecuniary or otherwise, to any person
or official, personnel or representative of the
government in relation to any procurement project or
activity.

b. Financial Component – This shall include all of the following documents:

(1) Bid Form, using Form DPWH-INFR-09.

(2) Bill of Quantities (BOQ) indicating the bid prices, using Forms
DPWH-INFR-17 and Form DPWH-INFR-18. The bid prices
may be in terms of (a) bid unit prices for different work items
under the BOQ, or (b) fixed total lump-sum price for the entire
contract, based on the type and complexity of the project.

(3) Detailed estimates, including a summary sheet indicating the unit


prices of construction materials, labor rates and equipment
rentals used in coming up with the Bid.

(4) Cash flow by quarter (Use Form DPWH-INFR-19).

14.3 a. Unless indicated in the BDS, all Total Bid Prices that exceed the
Approved Budget for the Contract (ABC) indicated in BDS 1.3 shall be
rejected.

a. Unless otherwise indicated in the BDS, for foreign-funded procurement,


a ceiling may be applied to the Total Bid Prices provided the following
conditions are met:

(i) The BDs are obtainable free of charge on a freely accessible


website. If payment of the BDs is required by the Procuring
Entity, payment could be made upon the submission of bids.

(ii) The Procuring Entity has procedures in place to ensure that the
ABC is based on recent estimates made by the responsible unit of
the Procuring Entity and that the estimates are based on
adequate detailed engineering and reflect the quality, supervision
and risk and inflationary factors, as well as prevailing market
prices, associated with the types of works to be procured.

(iii) The Procuring Entity has trained cost estimators on estimating


prices and analyzing bid variances. It must also have trained
quantity surveyors.

(iv) The Procuring Entity has established a system to monitor and


report bid prices relative to the ABC and the Procuring Entity’s
estimate.

19ME0143
(v) The Procuring Entity has established a monitoring and evaluation
system for contract implementation to provide a feedback on
actual total costs of works.

14.4 The bidder may use, as reference, the checklist of requirements for its Technical
and Financial Proposals, as shown in Form DPWH-INFR-20.

15. Bid Prices

15.1 The Contract shall be for the whole Works, as described in ITB Clause 1.1, based
on the priced BOQ (Use Form DPWH-INFR-17) submitted by the Bidder.

15.2 The Bidder shall fill in its unit and total Bid prices for all items of the Works
described in the BOQ. Bids not addressing or providing all of the required
items in the BOQ, shall be considered non-responsive and, thus, automatically
disqualified. In this regard, where a required item is provided, but no price is
indicated, the same shall be considered as non-responsive, but specifying a "0"
(zero) or a dash (“-”) for the said item would mean that it is being offered for
free to the Government.

15.3 All duties, taxes, and other levies payable by the Contractor under the Contract,
or for any other cause, prior to the deadline for submission of Bids, shall be
included in the Bid prices submitted by the Bidder.

15.4 For the given scope of work in the Contract as awarded, all Bid prices shall be
considered as fixed prices, and therefore not subject to price escalation during
contract implementation, except under extraordinary circumstances as specified
in GCC Clause 47. Price escalation may be allowed in extraordinary
circumstances as may be determined by the National Economic and
Development Authority in accordance with the Civil Code of the Philippines, and
upon the recommendation of the Procuring Entity. Furthermore, in cases where
the cost of the awarded contract is affected by any applicable new laws,
ordinances, regulations, or other acts of the GOP, promulgated after the date of
bid opening, a contract price adjustment shall be made or appropriate relief
shall be applied on a no loss-no gain basis.

16. Currencies of Bid and Payment

16.1 All Bid prices shall be quoted in Philippine Peso sunless otherwise provided in
the BDS. However, for purposes of bid evaluation, bids denominated in foreign
currencies shall be converted to Philippine currency based on the exchange rate
prevailing on the day of the Bid opening.

16.2 If so allowed in accordance with ITB Clause16.1, the Procuring Entity for purposes
of bid evaluation and comparing the bid prices will convert the amounts in various
currencies in which the bid price is expressed to Philippine Pesos at the exchange
rate as published in the BSP reference rate bulletin on the day of the bid opening.

16.3 Unless otherwise specified in the BDS, payment of the contract price shall be
made in Philippine Pesos.

19ME0143
17. Bid Validity

17.1 Bids shall remain valid for the period specified in the BDS, which shall not
exceed one hundred twenty (120) days from the date of the opening of Bids.

17.2 In exceptional circumstances, the Procuring Entity may request that the Bidders
extend the period of validity of their Bids for a specified additional period. The
request and the Bidders’ responses shall be made in writing. A Bidder may
refuse the request without forfeiting the Bid Security. A Bidder agreeing to the
request will not be required or permitted to otherwise modify the Bid, but will
be required to extend the validity of the Bid Security for the period of the
extension, and in compliance with ITB Clause 14 in all respects.

18. Bid Security

18.1 The Bidder shall submit to the Procuring Entity, as part of its Bid, a Bid Securing
Declaration (using Form DPWH-INFR-12) or any form of Bid Security in an
amount stated in the BDS, which shall not be less than a percentage of the ABC
in accordance with the following schedule:

Table 18.1. Forms and Amounts of Bid Security


Form Minimum Amount
(1) Cash or cashier’s/manager’s check issued by a Two percent (2%)
Universal or Commercial Bank of ABC
(2) Bank draft/guarantee or irrevocable letter of credit Two percent (2%)
issued by a Universal or Commercial Bank (Use Form of ABC
DPWH-INFR-10 or 11)
(3) Surety bond callable on demand issued by a surety or Five percent (5%)
insurance company duly certified by the Insurance of ABC
Commission as authorized to issue such security

18.2 A Bid Securing Declaration is an undertaking which states, among others, that
the bidder shall enter into contract with the Procuring Entity and furnish the
required Performance Security within ten (10) calendar days, or less, as
indicated in the BDs, from receipt of the Notice of Award, and commits to pay
the corresponding amount as fine and be suspended for a period of time from
being qualified to participate in any government activity in the event it violates
any of the conditions stated therein as required in the guidelines issued by the
Government Procurement Policy Board (GPPB).

18.3 The Bid Security should be valid for the period specified in the BDS.

18.4 Any Bid not accompanied by a Bid Securing Declaration or an acceptable Bid
Security shall be rejected by the Procuring Entity as non-responsive.

18.5 No Bid Securities shall be returned to Bidders after the opening of Bids and
before contract signing, except to those that failed or post-disqualified in
accordance with the IRR, upon submission of a written waiver of their right to
file a motion for reconsideration and/or protest, or lapse of the reglementary
period without having filed a motion for reconsideration or protest. To comply
with any of the requirements to be submitted in the Technical Proposal and

19ME0143
Financial Proposal of the Bid, as provided in the IRR of R.A. 9184. Without
prejudice to the forfeiture of Bid Securities, Bid Securities shall be returned only
after the Bidder with the Lowest Calculated Responsive Bid has signed the
Contract and furnished the Performance Security, but in no case later than the
expiration of the Bid Security validity period indicated in ITB Clause 18.3.

18.6 The Bid Security may be forfeited:

a. if the Bidder withdraws its Bid after Bid opening during the period of Bid
validity; or

b. if the Bidder does not accept the correction by the Bids and Awards
Committee of arithmetical and computational errors in its Bid prices,
pursuant to ITB Clause 28; or

c. in the case of the winning Bidder, if the Bidder fails, within ten (10) days
from its receipt of the Notice of Award, to:

(1) submit to the Procuring Entity the following documents:

(a) Notice of Award with the bidder’s signed “conforme;”

(b) Authority of Signing Official/Board Resolution/Secretary’s


Certificate;

(c) For a joint venture (JV), Contractor’s PCAB Special JV


License and JV Agreement;

(d) Performance Security (Use Form DPWH-INFR-43 or


DPWH-INFR-44, as applicable);

(e) Construction Methods (Use Form DPWH-INFR-45);

(f) Construction Schedule in the form of PERT/CPM Diagram


or Precedence diagram and Bar Chart with S-Curve (Use
Form DPWH-INFR-46);

(g) Professional Regulatory Commission (PRC) License No.


and Tax Identification Number (TIN) of Each Key
Personnel

(h) Manpower Schedule (Use Form DPWH-INFR-47);

(i) Equipment Utilization Schedule (Use Form DPWH-INFR-


48);

(j) Construction Safety and Health Program (Use Form


DPWH-INFR-49);

(k) Contractor’s All Risk Insurance (CARI);

19ME0143
(l) Latest Income Tax and Business Returns duly stamped
and received by BIR and duly validated with the tax
payments made. Tax Clearance from the BIR to prove full
and timely payment of taxes;

(m) Integrity Pledge in accordance with Department Order No.


86, series of 2013;

(n) For a local contractor, Certification under oath stating that


the Contractor is free and clean of all tax liabilities;

(o) For a foreign bidder, valid PCAB License and Registration


for the type and cost of the contract to be bid, when the
Treaty or International or Executive Agreement expressly
allows submission of the PCAB License and Registration
for the type and cost of the contract to be bid as a pre-
condition to the NOA; or

(2) has a finding against the veracity of the required documents


submitted in accordance with ITB Clause 34-b; or
(3) sign the Contract Agreement; or

d. if the Bidder submits eligibility requirements that contain false


information or falsified documents, or conceals such information, in
order to influence the outcome of the eligibility screening or any other
stage of the bidding; or

e. if the Bidder submits Bids that contain false information or falsified


documents, or conceals such information in the Bids, in order to
influence the outcome of the bidding; or

f. if the Bidder allows the use of its name by another contractor, or uses
the name of another contractor, for purposes of public bidding; or

g. if the Bidder refuses to clarify or validate in writing its Bid during post-
qualification within a period of seven (7) calendar days from receipt of
the request for clarification; or

h. if the Bidder makes any documented unsolicited attempt to unduly


influence the outcome of the bidding in its favor; or

i. if the Bidder commits any other act that tends to defeat the purpose of
the competitive bidding, such as habitually withdrawing from bidding or
submitting letters of non-participation for at least three (3) times within
twelve (12) months, except for valid reasons.

19. Alternative Bids by Bidders

19.1 Bidders shall submit offers that comply with the requirements of the Bidding
Documents, including the basic technical design as indicated in the drawings
and specifications. Unless there is a value engineering clause in the BDS,

19ME0143
alternative bids shall not be accepted. For this purpose, alternative bid is an
offer made by a Bidder in addition or as a substitute to its original bid which
may be included as part of its original bid or submitted separately therewith for
purposes of bidding. A bid with options is considered an alternative bid
regardless of whether said bid proposal is contained in a single envelope or
submitted in two (2) or more separate bid envelopes.

19.2 Each Bidder shall submit only one Bid, either individually or as a partner in a JV.
A Bidder who submits or participates in more than one bid (other than as a
subcontractor if a subcontractor is permitted to participate in more than one
bid) will cause all the proposals with the Bidder’s participation to be disqualified.
This shall be without prejudice to any applicable criminal, civil and
administrative penalties that may be imposed upon the persons and entities
concerned.

20. Format and Signing of Bid

20.1 Bidders shall submit their bids through their duly authorized representative
using the appropriate forms provided in Section XI of the SBDs (ANNEX IIA-
11) on or before the deadline specified in the ITB Clause 22 in two (2)
separate sealed bid envelopes, and which shall be submitted simultaneously.
The first shall contain the technical component of the bid as provided in ITB
Clause 14.2a, and the second shall contain the financial component of the bid
as provided in ITB Clause 14.2a.

20.2 Forms as mentioned in ITB Clause 20.1 must be completed without any
alterations to their format, and no substitute form shall be accepted. All blank
spaces shall be filled in with the information requested.

20.3 The Bidder shall submit one original of the Technical Proposal and one original
of the Financial Proposal as described in ITB Clause 20.1 and clearly mark each
as “ORIGINAL - TECHNICAL PROPOSAL” and “ORIGINAL – FINANCIAL
PROPOSAL”. In addition, the Bidder shall submit copies of the Technical
Proposal and the Financial Proposal, and clearly mark them “COPY NO… -
TECHNICAL PROPOSAL” and “COPY NO…. – FINANCIAL PROPOSAL”. In the
event of any discrepancy between the original and the copies, the original shall
prevail.

20.4 The original copy of the Bid as indicated in the BDS shall be typed or written in
indelible ink and shall be signed by the Bidder or a person or persons duly
authorized to bind the Bidder to the contract. Each page of the Bid Form and
the accomplished Bill of Quantities shall be signed by the Bidder or its duly
authorized representative. Failure to do so shall be a ground for the rejection of
the Bid.

20.5 Any interlineations, erasures, alterations or overwriting shall be valid only if they
are signed or initialed by the person signing the Bid.

20.6 Commissions or gratuities are not allowed.

19ME0143
21. Sealing and Marking of Bids

21.1 The Bidder shall enclose the original of the Technical Proposal in one sealed
envelope marked as “ORIGINAL - TECHNICAL PROPOSAL”; whereas, the
original of the Financial Proposal shall be enclosed in another sealed envelope
marked as “ORIGINAL - FINANCIAL PROPOSAL”. Both envelopes shall then be
placed in another single envelope marked as “ORIGINAL BID.”

21.2 Each copy of the Technical Proposal and Financial Proposal, shall be similarly
sealed duly marked as “COPY NO… - TECHNICAL PROPOSAL” and “COPY NO…
– FINANCIAL PROPOSAL” respectively and the outer envelope as “COPY NO”.

21.3 These envelopes containing the original and the copies shall then be enclosed in
one single envelope that shall:

a. indicate the name of the Contract to be bid;

b. bear the name and address of the Bidder;

c. be addressed to the Procuring Entity in accordance with ITB Clause 7;

d. bear the specific identification of this bidding process indicated in the


BDS; and

e. bear a warning “DO NOT OPEN BEFORE…” the time and date for the
opening of Bids , in accordance with ITB Clause 21.

21.4 If all envelopes are not sealed and marked as required, the Procuring Entity will
assume no responsibility for the misplacement or premature opening of the Bid.
If a Bid is not sealed and marked as required, the bidder or its authorized
representative shall acknowledge the condition of such Bid as submitted;
otherwise the Bid shall be disqualified.

D. Submission and Opening of Bids

22. Place and Deadline for Receipt of Bids

Bids must be received by the BAC of the Procuring Entity at the address and on or
before the deadline indicated in the BDS.

23. Late Bids

Any Bid submitted after the deadline for the receipt of Bids prescribed by the Procuring
Entity, pursuant to ITB Clause 18, shall be declared “Late” and shall not be accepted
by the Procuring Entity. The BAC shall record in the minutes of the bid submission and
opening, the bidder’s name, its representative and the time the late bid was submitted.

24. Modification and Withdrawal of Bids

24.1 The Bidder may modify its Bid after it has been submitted provided that the
modification is received by the Procuring Entity prior to the deadline prescribed
for the receipt of Bids by the BAC. The Bidder shall not be allowed to retrieve its
original Bid, but shall be allowed to submit another Bid equally sealed, properly

19ME0143
identified, in accordance with ITB Clause 21, linked to its original bid marked as
“TECHNICAL MODIFICATION” or “FINANCIAL MODIFICATION” and stamped
“received” by the BAC. Bid modifications received after the applicable deadline
shall not be considered and shall be returned to the Bidder unopened.

24.2 A Bidder may, through a Letter of Withdrawal, withdraw its Bid after it has been
submitted, for valid and justifiable reasons, provided that the Letter of
Withdrawal is received by the Procuring Entity not later than the deadline
prescribed for the receipt of Bids. The letter of withdrawal must be executed by
the authorized representative of the Bidder identified in the Omnibus Sworn
Statement, a copy of which should be attached to the letter.

24.3 Bids requested to be withdrawn in accordance with ITB Clause 20.2 shall be
returned unopened to the Bidders. A Bidder that withdraws its Bid shall not be
permitted to submit another Bid, directly or indirectly, for the same contract.

24.4 No Bid may be modified after the deadline for the receipt of Bids. No Bid may
be withdrawn in the interval between the deadline for the receipt of Bids and
the expiration of the period of Bid validity specified by the Bidder in accordance
with ITB Clause 13.1. Withdrawal of a Bid during this interval may result in the
forfeiture of the Bidder’s Bid Security, pursuant to the ITB Clause 14.5, and the
imposition of administrative, civil and criminal sanctions as prescribed by R.A.
9184 and its IRR.

25. Receipt of Bids under Electronic Bidding

If, as indicated in the BDS, Electronic Bidding is adopted for this procurement pursuant
to GPPB Resolution No. 23-2013, dated 30 July 2013, the following procedure shall be
observed with regard to the submission and receipt of bids:

a. On-line Bidders may submit their eligibility requirements to the Procuring Entity
through the e-bidding facility of PhilGEPS.

b. Joint Ventures

(1) In case of joint venture, each partner of the joint venture must: (i) be
registered in the PhilGEPS, (ii) secure Certified Membership Status, and
(iii) electronically send its respective eligibility documents.

(2) The joint venture partners must identify and designate the Primary and
Secondary Partner(s).

(3) Before the PhilGEPS will accept submissions of Technical and Financial
Proposals from the Primary Partner, there must be a confirmation from
the Secondary Partner(s) as to existence of, or agreement to enter into,
a joint venture.

(4) Upon Confirmation, the Primary Partner shall be required by the


PhilGEPS to upload the Joint Venture Agreement or a duly notarized
statement.

19ME0143
c. With regard to the requirement for a Bid Security as part of the Technical
Proposal under Section 5.6.2a(2) above, the following guidelines shall be
observed:

i. On-line bidders may submit the Bid Security in cash through the
PhilGEPS electronic payment facility.

ii. In case of other forms of Bid Security, the on-line bidder shall prepare
and submit a scanned copy of the Bid Security together with the
electronic bid. However, the original Bid Security must be submitted to
the BAC concerned before the end of business hours on the day of bid
submission, a failure of which shall automatically render the bid
submission as non-compliant.

iii. If the on-line bidder sends the original Bid security through registered
mail or private courier, the indicated date of receipt by the postal service
or private courier shall be considered as the date of submission to the
BAC concerned, without prejudice to any verifications during post-
qualification.

d. On-line Bidders, or the Primary Partner in the case of Joint Ventures, shall
electronically submit their bids through the Bidder’s On-line Nominee, at any
time before the closing date and time specified in the BDs.

e. The actual time of bid submission of an On-line Bidder shall be the time
indicated on the PhilGEPS Server when the bidder clicks the “Submit” button
which shall be automatically recorded by the PhilGEPS. Upon receipt of a bid,
the PhilGEPS shall automatically generate a bid receipt page that can be printed
by the on-line bidder. This contains the recorded “submission time” which shall
be considered as the Official Submission Time of the bidder.

f. An On-line Bidder may modify its bid at any time before the closing date and
time for the submission and receipt of bids.

g. An On-line Bidder may withdraw its bid before the deadline for the submission
and receipt of bids.

h. The PhilGEPS shall bar all incoming bids after the closing date and time.

26. Opening and Preliminary Examination of Technical Components of Bids

26.1 The BAC shall open the Bid envelopes in the presence of Bidders’
representatives who choose to attend, at the time, on the date, and at the place
specified in the BDS. Bidders’ representatives who are present shall sign a
register evidencing their attendance. In case the Bids cannot be opened as
scheduled due to justifiable reaons, the BAC shall take custody of the Bids
submitted and reschedule the opening of Bids on the next working day or at the
soonest possible time through the issuance of a bid bulletin to be posted in the
DPWH and PhilGEPS websites.

19ME0143
26.2 The BAC shall read out and record letters of withdrawal, and return the
unopened envelopes containing the corresponding withdrawn Bid to the Bidders
concerned.

26.3 Outer envelopes marked “TECHNICAL MODIFICATION” or “FINANCIAL


MODIFICATION” shall be identified but not opened. The BAC shall announce the
presence and type of modification from the information contained on the outer
envelope.

26.4 The BAC shall then conduct the Preliminary Examination of the Bids. The
purpose of this examination is solely to determine the “presence-or-absence” of
each of the required documents comprising the bid, as stated in Clause 14
above, using a simple non-discretionary “pass (if present) – or - fail (if absent)”
criterion, with the aid of checklists.

26.5 The BAC shall first open and undertake the Preliminary Examination of the
envelopes containing the Technical Components of the Bids, one at a time, and
reading out and recording the following:

a. Name of the Bidder.

b. Whether there is a technical modification or substitution.

c. Presence, amount and validity of the Bid Security.

d. Presence or absence of each document comprising the Technical


Proposal vis-à-vis a checklist of the required documents.

26.6 The BAC of the Procuring Entity shall determine each Bidder’s compliance with
the documents required to be submitted for the Technical Component of the
Bid, as prescribed in ITB Clause 14. For this purpose, the BAC shall check the
submitted documents in the Technical Component envelope against a checklist
(Form DPWH-INFR-31) of the required documents to ascertain if the latter
are all present in the Technical Component envelope. If the required document
is present, the Technical Component shall be rated as “passed” for that
particular requirement. On the other hand, if the required document is absent,
i.e., missing, incomplete or patently insufficient, the Technical Component shall
be rated as “failed” for that particular requirement. In case one or more of the
required documents in the Technical Component of a particular Bid is absent -
i.e., missing, incomplete, or patently insufficient - the BAC shall rate the
Technical Component as “failed” and immediately return to the Bidder
concerned its second envelope (Financial Component) unopened. If all of the
required documents in the Technical Component envelope are present, the
Technical Component is rated as “passed.”

27. Eligibility Check

27.1 Unless otherwise indicated in the BDS, after the Preliminary Examination of the
Technical Components of the Bids, the BAC of the Procuring Entity, assisted by
its BAC Secretariat, shall conduct the Eligibility Check of each bidder that passed
the documentary requirements for the Technical Component of the Bids - i.e.,
the BAC shall determine if the bidder is eligible to bid for the contract being

19ME0143
procured. This shall be done electronically by computer using the data and
program in the DPWH Civil Works Registry (CWR). The submission of the
Original Receipt (OR) for payment of the BDs for the contract issued by any
DPWH field office is sufficient for the BAC of the Procuring Entity to undertake
the electronic eligibility evaluation of contractors.

27.2 The BAC Secretariat of the Procuring Entity shall enter into the CWR the
Contract Profile (CP) for the contract being procured. The CP will give the basic
contract data, including the ABC, works similar to those of the contract to be
bid, and contract duration.

27.3 In case a bidder is already enrolled in the CWR and submits the Original Receipt
(OR) for payment of the BDs for the contract issued by any DPWH field office,
together with its bid, the BAC Secretariat shall enter into the CWR the PCAB
License Number and/or name of the bidder.

27.4 In case a bidder is not previously enrolled in the CWR and submits its Eligibility
Requirements – i.e., Class “A” and Class “B” Documents - as part of its bid,
together with Original Receipt (OR) for payment of the BDs for the contract
issued by any DPWH field office, the BAC Secretariat shall immediately encode
and enter into the CWR the appropriate data and information – e.g., SLCC,
NFCC, etc. - from the submitted Documents.

27.5 In both cases, the CWR program will then electronically process and match the
prospective bidder’s capability or eligibility data in the CWR – e.g., value of
Single Largest Completed Contract (SLCC) similar to the contract being procured
and actual NFCC - against the eligibility requirements for the contract derived
from the CP – e.g., SLCC similar to the subject contract and costing at least
50% of ABC, and NFCC at least equal to ABC. The computer program will thus
automatically determine whether or not the prospective bidder meets the
following eligibility requirements:

a. The cost of the bidder’s SLCC is at least 50% of the ABC of the project to be
procured.

b. The bidder’s NFCC is at least equal to ABC of the project to be procured.

The program will also generate the results of the Eligibility Check, including the
Notices of Ineligibility. The reasons for ineligibility will also be automatically
shown in the Notices of Ineligibility.

27.6 During the bids opening session, the BAC will issue the Notices of Ineligibility to
the bidders concerned. If any of the bidders immediately agrees to their
ineligibility as indicated in the Notices, the BAC shall promptly not consider its
bid and thus return its Financial Component envelope to the bidder unopened.
If, on the other hand, any of the bidders indicate its intent to seek a
reconsideration of its declared ineligibility, the BAC shall set aside its sealed
Financial Component envelope which shall be signed on its cover by the bidder
and other competing bidders and members of the BAC. If, after evaluating the
bidder’s request for reconsideration, the BAC finds the bidder to be eligible for

19ME0143
the contract at hand, the BAC shall set the date and time for the opening of its
Financial Component envelope.

27.7 In either case - i.e., the ineligible bidder accepting its ineligibility or expressing it
intent to seek a reconsideration of its ineligibility - the either case - i.e., the
ineligible bidder accepting its ineligibility or expressing it intent to seek a
reconsideration of its ineligibility - the BAC shall then proceed with the opening
and preliminary examination of the Financial Component of the bids of the
bidders that are declared eligible.

28. Preliminary Examination of Financial Components of Bids

28.1 On the same day, the BAC shall then open the Financial Component of the Bid
(second envelope) of each bidder whose Technical Component of the Bid was
rated as “passed” (i.e., with complete documentary requirements) and was
declared to be eligible for the contract. The BAC shall check the submitted
documents in the Financial Component against a checklist of required
documents (Form DPWH-INFR-31) to ascertain if the latter are all present in
the Financial Component envelope. If the required document is present, the
Financial Component shall be rated as “passed” for that particular requirement.
In case one or more of the required documents in the Financial Component of a
particular Bid is absent - i.e., missing, incomplete or patently insufficient -
and/or if the submitted total bid price exceeds the ABC, the BAC shall rate the
Financial Component and, thus, the entire bid, as “failed.” If all of the required
documents in the Financial Component are present, the entire bid is rated as
“passed.” Bids that are so rated as “passed” shall immediately be considered
for detailed evaluation.

28.2 The BAC shall prepare the minutes of the proceedings of the Bid opening that
shall include, as a minimum: (a) the Abstract of Bids as Read including the
name of each Bidder, its Bid prices, Bid Security, and findings of the Preliminary
Examination of Bids; and (b) the attendance sheet.

28.3 The BAC members shall sign the Abstract of Bids as Read and the BAC
Observers may witness the same. The Abstract of Bids as Read and the
minutes of the Bid opening shall be available to the public upon written request
and payment of a specified fee to cover the cost of materials.

29. Opening and Preliminary Examination under Electronic Bidding

If, as indicated in the BDS, Electronic Bidding is adopted for this procurement
pursuant to GPPB Resolution No. 23-2013, dated 30 July 2013, the following
procedure shall be observed with regard to the opening and preliminary examination:

a. Upon receipt of manually-filed bids, the Bid Opener, before the Bid Opening, but
immediately after the deadline for submission of bids, shall record and input
into the PhilGEPS E-bidding module the date and time each of the bid was
manually received, including the name of the bidder’s authorized representative.

b. The BAC shall open the bids immediately after the deadline for submission and
receipt of bids, and on the bid opening date.

19ME0143
c. Before the decryption of electronic bids, the Bid Opener must first login to the
PhilGEPS and only then can BAC members input their respective USER IDs and
PASSWORDS, provided however, that PhilGEPS decryption will not take place
unless all the members present and logging in constitute quorum.

d. The Bid Opener shall publicly open the first bid envelopes of bidders who
submitted bids manually to determine each bidder’s compliance with the
documents required to be submitted for eligibility, that is, legal, technical and
financial eligibility documents; and for the technical requirements. For this
purpose, the BAC shall check the submitted documents of each bidder against a
checklist of required documents to ascertain if they are all present, using a non-
discretionary “pass/fail” criterion. If a bidder submits the required document, it
shall be rated “passed” for that particular requirement. In this regard, bids that
fail to include any requirement or are incomplete or patently insufficient shall be
considered as “failed”. Otherwise, the BAC shall rate the bidder “passed” in
relation to the eligibility and technical documents in the first envelope.

e. After all the manually submitted first envelopes of bidders were opened, and the
results and findings were encoded in the PhilGEPS Preliminary Examination
Report facility, the Bid Opener shall thereafter proceed to decrypt the electronic
First Bid Envelopes submitted by the On-line Bidders to determine each bidder’s
compliance with the required eligibility and technical documents following the
steps and procedures outlined in Section 5.6.9d above. Thereafter, the Bid
Opener shall input the findings and results into the PhilGEPS’ Preliminary
Examination Report facility.

f. Immediately after determining compliance with the requirements in the first


envelope, the Bid Opener shall forthwith open the manually submitted second
bid envelope of each eligible bidder whose first bid envelope was rated
“passed.” The second envelope of each complying bidder shall be opened within
the same day.

g. After all the manually submitted second envelopes of bidders were opened, and
the results and findings were encoded in the PhilGEPS Preliminary Examination
Report facility, the Bid Opener shall thereafter proceed to decrypt the electronic
Second Bid Envelopes of each On-line Bidders whose electronic first bid
envelope was rated “passed” to determine each bidder’s compliance with the
required financial documents following the steps and procedures outlined in
Section 5.6.9f above.

h. In case one or more of the requirements in the second envelope of a particular


bid is missing, incomplete or patently insufficient, and/or if the submitted total
bid price exceeds the ABC, the BAC shall rate the bid concerned as “failed”. The
Bid Opener shall then input the findings and results into the PhilGEPS’
Preliminary Examination Report facility.

i. Only bids that are determined to contain all the bid requirements for both
components shall be rated “passed” and shall immediately be considered for
evaluation and comparison.

19ME0143
j. The PhilGEPS shall automatically send an electronic mail to all bidders who
failed in the preliminary examination of the first and/or second envelope.

E. Evaluation and Comparison of Bids

30. Process to be Confidential

Members of the BAC, its staff and personnel, Secretariat and TWG, as well as
observers, are prohibited from making or accepting any kind of communication with
any bidder regarding the evaluation of any of the bids until the issuance of the Notice
of Award.

31. Clarification of Bids

To assist in the evaluation, comparison and post-qualification of the bids, the Procuring
Entity may ask in writing any Bidder for a clarification of its bid. All responses to
requests for clarification shall be in writing. Any clarification submitted by a Bidder in
respect to its bid and that is not in response to a request by the Procuring Entity shall
not be considered.

32. Detailed Evaluation and Comparison of Bids

a. The Procuring Entity shall evaluate and compare, in detail, only the Bids that are
rated as “complying” (“passed”) for both Technical and Financial Proposals
pursuant to ITB Clause 26.

b. In evaluating the Bids to get the Lowest Calculated Bid, the Procuring Entity
shall undertake the following:

c. The detailed evaluation of the Financial Proposals of the Bids, to establish the
correct calculated prices of the Bids.

d. The ranking of the total bid prices as so calculated from the lowest to highest.
The
Bid with the lowest price in the ranking shall be identified as the Lowest
Calculated Bid.

e. To determine the Lowest Calculated Bid, the BAC shall use non-discretionary
“pass/fail” criteria, as stated in the IB, which shall include a consideration of the
following:

(1) Completeness of the bid. Unless the ITB specifically allows partial bids,
bids not addressing or providing all of the required items in the BDs,
including the BOQ, shall be considered as non-responsive and, thus,
automatically disqualified. In this regard, where a required item is
provided, but no price is indicated, the same shall be considered as non-
responsive, but specifying a “0” (zero) or a dash (“-”) for the said item
would mean that it is being offered for free to the Government, except
those required by law or regulations to be provided for (IRR Section
32.2.1a); and

19ME0143
(2) Arithmetical corrections. The BAC shall consider computational errors,
omissions and discounts if allowed in the BDs to enable proper
comparison of all eligible bids. Any adjustment shall be calculated in
monetary terms to determine the calculated prices.

In case a bid offers a discount on the total bid price, the percentage of
the discount to the total bid price shall be applied to all pay items for
purposes of evaluating the value of work accomplished during the
implementation stage.

(3) Evaluation on equal footing. The BAC shall evaluate all bids on an equal
footing to ensure fair and competitive bid comparison. For this purpose, all
bidders shall be required to include the cost of all taxes, such as, but not
limited to, value added tax (VAT), income tax, local taxes, and other fiscal
levies and duties which shall be itemized in the Bid Form and reflected in
the detailed estimates. Such bids, including said taxes, shall be the basis
for bid evaluation and comparison.

iv. Rule on discrepancies. In case of discrepancies between: (a) bid prices in


figures and in words, the latter shall prevail; (b) total price per item and
unit price for the item as extended or multiplied by the quantity of that
item, the latter shall prevail; (c) stated total price and the actual sum of
prices of component items, the latter shall prevail; (d) unit cost in the
detailed estimate and unit cost in the BOQ, the latter shall prevail. The
corrected per item cost for all items shall be the basis for the corrected
grand total cost.

v. Total calculated bid prices. The total calculated bid prices are obtained
after making the detailed evaluation and corrections according to the
abovementioned criteria.

f. The Procuring Entity’s evaluation of bids shall only be based on the bid price
quoted in the Financial Bid Form.

g. In case of discrepancies between:

(1) bid prices in figures and in words, or

(2) total bid prices per pay item and unit prices applied to the quantities per
pay item, or

(3) stated total Bid price and the actual sum of prices of component items,
or

(4) unit prices in the detailed estimate and unit bid prices in the Bill of
Quantities,

the latter in each of the above cases shall prevail, and the total Bid amount shall
be corrected accordingly.

19ME0143
h. Based on the detailed evaluation of the bids, those that comply with the
abovementioned requirements shall be ranked in the ascending order of their
total calculated bid prices, as evaluated and corrected for computational errors,
discounts and other modifications, in accordance with the provisions of this ITB
Clause. This will identify the Lowest Calculated Bid. Total calculated bid prices,
as evaluated and corrected for computational errors, discounts and other
modifications, which exceed the ABC shall not be considered, unless otherwise
indicated in BDS 14.3a.

i. The provision in this Clause 32-i is not to be considered in the evaluation of the
bids to determine the technically complying bid or the lowest calculated bid, but
shall be applied by the Procuring Entity during the implementation of the contract,
particularly in making contract payments:

(1) During the evaluation of the bids, the BAC shall take note of any
unbalanced bids on early works and other items for unit-priced contracts.

(2) Unbalanced bids are defined as those where the total bid price for a major
pay item is more than fifty percent (50%) of the corresponding cost of
that pay item in the ABC. A major pay item is defined as that whose cost
in the ABC is 20% or more of the total ABC; if there is no such pay item,
then major pay items are defined as the two pay items in the ABC with the
highest total costs.

(3) Unbalanced bids also include those with a minor pay item whose cost in
the ABC is more than five percent (5%) of the total ABC and where the
corresponding bid price for that pay item is more than one hundred
percent (100%) of the ABC for that item.

(4) For unbalanced bids, during the implementation of the contract works, the
payment for these major and minor pay items shall be made initially at the
unit prices in the ABC, and the remainder - i.e., contract unit price minus
ABC unit price for the major pay item - shall be paid when the work under
the major pay item is completed.

33. Procedure for Detailed Evaluation of Bids under Electronic Bidding

In case Electronic Bidding is adopted pursuant to GPPB Resolution No. 23-2013, dated
30 July 2013, the Procuring Entity shall apply the manual procedure for the detailed
evaluation of bids prescribed under Section 31 of the ITB. In addition, the procuring
Entity shall observe the following guidelines:

a. After conducting the detailed evaluation of all bids using non-discretionary


criterion, the Bid Opener shall input and record the results of the evaluation into
the PhilGEPS’ Evaluation Summary Report facility.

b. The PhilGEPS shall automatically rank the bidders in ascending order based on
their total calculated bid prices to identify the LCB as evaluated and corrected
for computational errors, and other bid modifications. Total calculated bid
prices, as evaluated and corrected for computational errors, and other bid
modifications, which exceed the ABC shall be disqualified. After all bids have

19ME0143
been received, opened, examined, evaluated, and ranked, the system shall
thereafter generate the Abstract of Bids in the form of PhilGEPS Evaluation
Summary Report.

c. The BAC shall manually prepare a Resolution whether approving or denying the
Abstract of Bids generated by the system. However, after the BAC Resolution
approving the Abstract of Bids is uploaded in the PhilGEPS, an electronic
message shall be automatically sent to all bidders who participated informing
them that the Abstract of Bids is available for downloading.

34. Post-Qualification of the Lowest Calculated Bid

a. The Procuring Entity shall conduct a Post-Qualification of the Bidder that is


evaluated to have the Lowest Calculated Bid (LCB) to determine definitely if it
complies with and is responsive to all requirements and conditions for eligibility
and of the Bidding for the contract specified in ITB Clauses 5 and 14.

b. Within a non-extendible period of five (5) calendar days from receipt by the
Bidder of the notice from the BAC that it submitted the LCB, the Bidder shall
submit the following post-qualification documentary requirements (IRR
Section 34.2):

(1) Latest income and business tax returns.

(2) Other appropriate licenses and permits required by law and stated in the
BDS.

Failure of the Bidder declared as LCB to submit the requirements under this
Clause on time or a finding against the veracity thereof, shall disqualify the
Bidder for award. In the event that a finding against the veracity of any of the
documents submitted is made, it shall cause the forfeiture of the bid security in
accordance with Sewction 69 of the IRR.

c. The determination shall use non-discretionary “pass/fail” criteria and be based


upon examination, verification, and validation of all statements made and
documents submitted by the Bidder in the Technical and Financial Components
of its Bid. The Procuring Entity shall use the post-qualification criteria indicated
in Form DPWH INFR-37. The post-qualification shall be completed within
twelve (12) calendar days.

d. If the BAC determines that the Bidder with the LCB passes all the criteria for
Post-Qualification, it shall declare the said bid as the Lowest Calculated
Responsive Bid, (LCRB) and recommend to the HoPE the award of contract to
the said Bidder at its submitted price or its calculated bid price, whichever is
lower.

e. If the BAC determines that the Bidder with the LCB fails the criteria for Post-
Qualification, it shall proceed to the next LCB with a fresh period to make a
similar determination of that Bidder’s capabilities. If the second Bidder,
however, fails the Post-Qualification, the procedure for Post-Qualification shall
be repeated for the Bidder with the next LCB, and so on until the LCRB is
determined for recommendation of contract award.

19ME0143
35. Post-Qualification under Electronic Bidding

If, as indicated in the BDS, Electronic Bidding is adopted for this procurement pursuant
to GPPB Resolution No. 23-2013, dated 30 July 2013, the Procuring Entity shall observe
the following procedure with regard to the post-qualification:

a. Within one (1) day after the approval of the Abstract of Bids, the bidder with
the Lowest Calculated Bid (LCB) should be notified through electronic mail that
the bidder shall undergo post-qualification and submit the post-qualification
requirements within five (5) calendar days as provided for under Section 34.2 of
RA 9184-IRR.

b. If the BAC determines that the bidder with the LCB passes all the criteria for
post-qualification, it shall declare the said bid as the Lowest Calculated
Responsive Bid (LCRB), and recommend to the HoPE the award of contract to
the said bidder at its submitted bid price or its calculated bid price, whichever is
lower or, in the case of quality-based evaluation procedure, submitted bid price
or its negotiated price, whichever is lower.

c. If, however, the BAC determines that the bidder with the LCB fails the criteria
for post-qualification, it shall immediately notify the said bidder electronically in
writing of its post-disqualification and the grounds for it.

d. Immediately after the BAC has electronically notified the first bidder of its post-
disqualification, and notwithstanding any pending request for reconsideration
thereof, the BAC shall initiate and complete the same post-qualification process
on the bidder with the second LCB. If the second bidder passes the post-
qualification, and provided that the request for reconsideration of the first
bidder has been denied, the second bidder shall be post-qualified as the bidder
with the LCRB.

e. If the second bidder, however, fails the post-qualification, the procedure for
post-qualification shall be repeated for the bidder with the next LCB, and so on
until the LCRB, as the case may be, is determined for award, subject to Section
37 of the IRR.

f. The post-qualification process shall be completed in not more than twelve (12)
calendar days from the determination of the LCB. In exceptional cases, the
post-qualification period may be extended by the HoPE, but in no case shall the
aggregate period exceed forty five (45) calendar days.

g. The BAC or its Bid Opener shall record and encode the post-qualification results
of manually submitted documents in the PhilGEPS. For electronic documents
submitted online, the BAC or its Bid Opener shall decrypt the documents and
the results recorded automatically.

h. After recording the post-qualification summary and uploading the BAC resolution
declaring the bidder with the LCRB in the PhilGEPS, an electronic message shall
be automatically sent to all bidders who participated informing them that the
Notice of LCRB is available for downloading.

19ME0143
36. Right of Procuring Entity to Reject Bids

36.1 Notwithstanding the eligibility or post-qualification of a Bidder, the Procuring


Entity concerned reserves the right to review the qualifications of the Bidder at
any stage of the procurement process if the Entity has reasonable grounds to
believe that the Bidder has made a misrepresentation, or that there has been a
change in the Bidder’s capability to undertake the contract from the time it
submitted its eligibility requirements. Should such review uncover any
misrepresentation made in the eligibility and bidding requirements, statements
or documents, or any changes in the situation of the Bidder which will affect its
capability to undertake the contract so that it fails the preset eligibility or bid
evaluation criteria, the Procuring Entity shall consider the said Bidder as
ineligible and shall disqualify it from submitting a bid or from obtaining an
award for the contract.

36.2 The Procuring Entity reserves the right to reject any and all bids, declare a
failure of bidding, or not award the contract in the following situations, without
incurring any liability to the affected bidders:

a. If there is prima facie evidence of collusion among appropriate public


officers or employees of the Procuring Entity, or between the BAC and
any of the bidders, or among the bidders themselves, or between a
bidder and a third party, including any act which restricts, suppresses or
nullifies or tends to restrict, suppress or nullify competition.

b. If the BAC is found to have failed in following the prescribed bidding


procedures.

c. For any justifiable and reasonable ground where the award of the
contract will not redound to the benefit of the Government as follows:

(1) if the physical and economic conditions have significantly changed so


as to render the contract works no longer economically, financially or
technically feasible as determined by the HoPE;

(2) if the contract works are no longer necessary as determined by the


HoPE; or

(3) if the funds for the contract have been cancelled, withheld or
reduced through no fault of the Procuring Entity.

36.3 In addition, the Procuring Entity may likewise declare a failure of bidding,
without incurring any liability to the affected bidders, when:

a. no bids are received;

b. all prospective bidders are declared ineligible;

c. all bids fail to comply with all the bid requirements or fail post-
qualification; or

19ME0143
d. the bidder with the LCRB refuses, without justifiable cause to accept the
award of contract, and no award is made.

F. Award of Contract
37. Award Criterion
The Procuring Entity shall award the contract to the winning Bidder whose Bid has been
determined, after the evaluation of bids and Post-Qualification, as the LCRB, at its
submitted bid price or its calculated bid price, whichever is lower (IRR Section 34.4).

38. Notice of Award

38.1 Based on the Bid-Evaluation and Post-Qualification Report, the BAC shall declare
the LCRB and recommend, through a Resolution to the HoPE, the award of the
contract to the Bidder with the LCRB. The HoPE shall approve or disapprove the
said BAC Resolution recommending the award within fifteen (15) calendar days
from the receipt of that Resolution.

38.2 Immediately upon the approval of the BAC Resolution for award and prior to the
expiration of the Bid validity period, the Procuring Entity shall issue a written
Notice of Award (NOA) to the Bidder with the LCRB to be received by the Bidder
personally, by registered mail, or electronically, receipt of which must be
confirmed in writing within two (2) days by the Bidder with the LCRB and
submitted personally or sent by registered mail or electronically to the Procuring
Entity.

38.3 The NOA shall state the proposed contract price – i.e., whichever is lower of the
submitted bid price or calculated bid price - together with the documentary
requirements to be submitted by the Bidder to perfect the contract.

38.4 Notwithstanding the issuance of the NOA, award of contract shall be subject to
the following conditions:

a. Submission by the bidder with the LCRB of the following documents


within ten (10) from the bidder’s receipt of the NOA, as conditions for
signing the contract:

(1) Notice of Award (NOA) with the bidder’s signed “conforme” (Use
Form DPWH-INFR-41)

(2) Authority of Signing Official/Board Resolution/Secretary’s Certificate

(3) For a joint venture (JV), Contractor’s PCAB Special JV License and
JV Agreement.

(4) Performance Security in accordance with Section 3.9.2.2 of the


DPWH Procurement Manual Volume II (Use Form DPWH-INFR-
43 or DPWH-INFR-44, as applicable).

(5) Construction Methods (Use Form DPWH-INFR-45)

19ME0143
(6) Construction Schedule in the form of PERT/CPM Diagram or
Precedence Diagram and Bar Chart with S-Curve, or other
approved tools of project scheduling, and Cash Flow (Use Form
DPWH-INFR-46).

(7) PRC License No. and Tax Identification No. (TIN) of Each Key
Personnel.

(8) Manpower Schedule (Use Form DPWH-INFR-47).

(9) Equipment Utilization Schedule (Use Form DPWH-INFR-48).

(10) Construction Safety and Health Program (Use Form DPWH-


INFR-49).

(11) Contractor’s All-Risk Insurance (CARI)

(12) Latest Income Tax and Business Returns duly stamped and
received by BIR and duly validated with the tax payments made.
Tax Clearance from the BIR to prove full and timely payment of
taxes.

(13) Integrity Pledge in accordance with Department Order No.


86, series of 2013;

(14) For a local contractor, Certification under oath stating that the
Contractor is free and clean of all tax liabilities.

(15) For a foreign bidder, valid PCAB License and Registration for the
type and cost of the contract to be bid, when the Treaty or
International or Executive Agreement expressly allows submission
of the PCAB License and Registration for the type and cost of the
contract to be bid as a pre-condition to the NOA.

b. Signing of the contract as provided in ITB Clause 41.

c. Approval of the contract as provided in ITB Clause 41.

38.5 In the event of disapproval by the Head of the Procuring Entity of the BAC
Resolution to award the contract to the Bidder with the LCRB, which shall be based
only on valid, reasonable, and justifiable grounds as provided for under Section 41
of the IRR of RA 9184, the Head of the Procuring Entity shall notify the BAC and
the Bidder in writing of such decision and the grounds therefor. When applicable,
the BAC shall conduct a post-qualification of the Bidder with the next Lowest
Calculated Bid. The Bidder may file a request for reconsideration in accordance
with Section 37.1.3 of the IRR of RA 9184.

39. Performance Security

39.1 Within a maximum period of ten (10) calendar days upon receipt of the NOA
from the Procuring Entity, and in no case later than the signing of the contract

19ME0143
by the winning Bidder and the Procuring Entity, the winning Bidder shall furnish
to the Procuring Entity, the required Performance Security in an amount equal
to the percentage of the total contract price in accordance with the following
schedule and with the conditions specified in GCC Clause 7:

Table 39.1 Forms and Amounts of Performance Security


Form Minimum Amount
a. Cash or cashier’s/manager’s check issued by Ten percent (10%) of
a Universal or Commercial Bank Total Contract Price
b. Bank draft/guarantee or irrevocable letter of Ten percent (10%) of
credit issued by a Universal or Commercial Total Contract Price
Bank; provided that it shall be confirmed or
authenticated by a Universal or Commercial
Bank if issued by a foreign bank (Use Form
DPWH-INFR-42)
c. Surety bond callable upon demand issued by a Thirty percent (30%) of
surety or insurance company duly certified by Total Contract Price
the Insurance Commission as authorized to
issue such security (Use Form DPWH-INFR-
43)

39.2 Failure of the winning Bidder to comply with the requirements of ITB Clause
39.1 shall constitute sufficient grounds for cancellation of the award and
forfeiture of its Bid Security. In this event, the Procuring Entity shall have a
fresh period to initiate and complete the post-qualification of the second Lowest
Calculated Bid. The procedure shall be repeated until the Lowest Calculated
and Responsive Bid is identified and selected for recommendation of contract
award. However, if no Bidder passed post-qualification, the BAC shall declare
the bidding a failure and conduct a re-bidding with re-advertisement.

40. Documents Comprising the Contract

40.1 The Contract shall consist of the following:

a. Contract Agreement (Use Form DPWH-INFR-50)

b. Documents forming part of the Contract Agreement in the following


order of priority:

(1) Notice of Award (NOA) with the Contractor’s signed “conforme”

(2) Contractor’s Bid in the Form of Bid, including its Technical and
Financial Proposals, as calculated by the Procuring Entity and
conformed by the Contractor through the NOA, and all other
documents/statements submitted (e.g., bidder’s response to
request for clarifications on the bid), including corrections to the
bid, if any, resulting from the Procuring Entity’s bid evaluation

(3) Bidding Documents (other than b(4) to b(7) below) with Bulletins

(4) Specifications

19ME0143
(5) Drawings

(6) Special Conditions of Contract (SCC)

(7) General Conditions of Contract (GCC)

(8) Performance Security

c. Other Documents

(1) Construction Methods

(2) Construction Schedule in the form of PERT/CPM Diagram or


Precedence Diagram and Bar Chart with S-Curve, or other
approved tools of project scheduling, and Cash Flow

(3) PRC License No. and TIN of Each Key Personnel.

(4) Manpower Schedule

(5) Equipment Utilization Schedule

(6) Construction Safety and Health Program initially approved by the


HoPE

(7) Contractor’s All Risk Insurance (CARI)

(8) Integrity Pledge in accordance with Department Order No.


86, series of 2013;

40.2 The documents in ITB Clauses 40.1a and b(2) to b(7) shall be provided by the
Procuring Entity, while the documents in Clauses 40.1b(1), b(8), and c(1) to
c(7) shall be submitted by the winning bidder to the Procuring Entity within ten
(10) calendar days from the date of its receipt of the Notice of Award.

41. Signing and Approval of the Contract

41.1 Within ten (10) days from the date of receipt from the winning Bidder of the
documents mentioned in ITB Clause 40.1b(1), b(8), and c(1) to c(7), the
successful Bidder and the authorized official of the Procuring Entity shall sign
the Contract Agreement.

41.2 If further approval of the contract is required, the approving authority is given a
maximum of twenty (20) calendar days from receipt thereof to approve or
disapprove it.

41.3 Upon approval of the Contract, the Procuring Entity shall notify the other
Bidders that their bids were unsuccessful.

19ME0143
42. Notice to Proceed

42.1 Within seven (7) calendar days from the date of signing and, if required, further
approval of the contract, by the appropriate government approving authorities,
the Procuring Entity shall issue the Notice to Proceed (NTP), using Form
DPWH-INFR-51, together with a copy or copies of the approved contract, to
the successful bidder All notices, including the NTP, called for by the terms of
the contract shall be effective only at the time of receipt thereof by the
successful bidder (IRR Section 37.4).

42.2 The contract effectivity date shall be the date of contract signing. The Bidder
shall commence performance of its obligations only upon receipt of the Notice
to Proceed.

43. Protest Mechanism

Decision of the procuring entity at any stage of the procurement process may be
questioned in accordance with Sections 55 of the IRR of RA 9184.

19ME0143
ANNEX II-1.1E
Section V. Bid Data Sheet

Notes on the Bid Data Sheet


The Bid Data Sheet (BDS) complements the Instructions to Bidders (ITB) and must be
prepared for each particular contract to be procured. The BDS provides the
information specific to the Contract.

19ME0143
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
SARANGANI
DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE XII
Alabel, Sarangani Province

Contract ID No.: 19ME0143


Contract Name: Construction of Multi-Purpose Building Public Market at
Maitum;
Location: Maitum, Sarangani Province

BID DATA SHEET


ITB Clause

1.1 The PROCURING ENTITY is Department of Public Works and Highways-


Sarangani District Engineering Office.

The scope of the Works under this Contract is


Construction of Multi-Purpose Building

The Contract Name is


Construction of Multi-Purpose Building Public Market at Maitum;
Maitum, Sarangani Province

The Procurement/ Contract ID 19ME0143

2. The Approved Budget for the Contract is Nineteen Million Eight Hundred
Thousand Pesos Only (Php 19,800,000.00).

The Funding Source is the Government of the Philippines (GOP) through


FY 2019 DPWH Local Infrastructure Program

The name of the Project is :


Construction of Multi-Purpose Building Public Market at Maitum;
Maitum, Sarangani Province

0 Bidding is restricted to eligible bidders as defined in ITB Clause 5.1.

8.1 No further instruction.

8.3 No further instruction.

9.1 The Procuring Entity will hold a Pre-bid Conference for this Project on
October 31, 2019 @ 10:00 a.m. at DPWH-Conference Room @ DPWH-
Sarangani District Engineering Office.
9.4 No further instruction.

19ME0143
11.1 The Procuring Entity’s address is: Kawas, Alabel, Sarangani Province

JONATHAN G. BANTUG
District Engineer
083-554-2530

14.2a(2)(a)i No further instructions.

14.2a(4)(b) The minimum work experience requirements for the key personnel are the
following:

Minimum Years Minimum Years


of Similar Experience of Similar and
Key Personnel (Same Position) Related Experience

Project Manager 1 3
Project Engineer 1 3
Materials Engineer 1 2
Foreman 1 2
Others [Specify] - -

14.2 a(4)(c) The minimum major equipment requirements are the following:

Construction Required No. Minimum of


Equipment of Units Capacity/Unit

Backhoe 1 (0.80m3)
Dump Truck 2 (12yd3)
Plate Compactor 1 (5Hp)
Concrete Vibrator 1 (5amp)
Pumpcrete 1
Welding Machine 1 (500amp)
One Bagger Mixer 1 (4-6cu.ft./min.)

Laboratory Required No. Minimum of


Equipment of Units Capacity/Unit

Minimum Laboratory 1-set


Testing Equipment

Manpower (Personnel)
Designation Required

Civil Engineer 1
Materials Engineer 1
Safety Officer 1
First Aider 1
Electrical Engineer 1

19ME0143
14.3a No further instructions.

14.3 b No further instructions.

17.1 Bids shall be valid until one hundred twenty (120) calendar days from the date
set for bids opening.

18.1 The bid security shall be limited to a Bid Securing Declaration or one of the
following forms in accordance with the following amounts:

1. The amount of __________ [Insert 2% of ABC], if bid security is in cash,


cashier’s/manager’s check, bank draft/guarantee or irrevocable letter of
credit;

2. The amount of __________ [Insert 5% of ABC] if bid security is in Surety


Bond.
3.
18.3 The Bid Security shall be valid until one hundred twenty (120) calendar days
from the date set for bids opening.

19.1 There is no provision for a value engineering change proposal.

20.4 The Bidder shall submit one (1) original and two (2) copies (properly book
bound and/ numbered paginated consecutively) of the first (Technical) and
second (Financial) components of its bid.

21.4 d The specific identification of this bidding process is 19ME0143


Construction of Multi-Purpose Building Public Market at Maitum;
Maitum, Sarangani Province

22 The address for Receipt of bids is Kawas, Alabel, Sarangani Province.

The deadline for Receipt of bids is NOVEMBER 12, 2019 @ 10:00 A.M.

25 No further instructions.

27.1 The place of opening of bid is DPWH-Sarangani District Engineering


Office (Conference Room).

The date and time of opening of bid is immediately after the deadline
for submission of Bids.

29 No further instructions.

34 b(2) List licenses and permits relevant to the Project and the corresponding laws
requiring it.

35 No further instructions.

19ME0143
ANNEX II-1.1F
Section VI. General Conditions of Contract
Notes on the General Conditions of Contract (GCC)
The GCC provides the general terms and conditions of the contract between the
Procuring Entity and the winning bidder.

The provisions of the GCC are to be used unchanged as part of the contract-specific
BDs.

To supplement the GCC, the Special Conditions of Contract (SCC) in ANNEX II-
1.1G provide detailed information or requirements on particular provisions of the GCC
that are specific to the contract at hand.

19ME0143
STANDARD FORMAT

GENERAL CONDITIONS OF CONTRACT

TABLE OF CONTENTS

1. Definitions ……………………………………………………………………..……… 66

2. Interpretation ………………………………………………………………………… 68

3. Governing Language and Law ………………………………………………..… 70

4. Communications …………………………………………………………………….. 70

5. Procuring Entity’s Obligation to Deliver the Site, Materials, Equipment, and Plans .. 70

6. Contractor’s Obligations …………………………………………………………… 70

7. Performance Security ……………………………………………………………….. 71

8. Sub-Contracting……………………………………………………………………….. 72

9. Liquidated Damages …………………………………………………………….…… 73

10. Site Investigation Reports ………………………………………………………… 74

11. Licenses and Permits ………………………………………………………………… 74

12. Contractor’s Risk and Warranty Security ……………………………………… 74

13. Liability of the Contractor …………………………………………………………. 76

14. Procuring Entity’s Risk…………………………………..…………………………… 76

15. Insurance ……………………………………………………………………………...... 76

16. Termination for Default of Contractor …………................................. 78

17. Termination for Default of Procuring Entity …………………………………… 80

18. Termination for Convenience ………………………………………………………… 80

19. Procedure for Termination of Contracts ……….………………………………. 81

20. Force Majeure and Release from Performance ……………...................... 83

21. Payment on Termination …………..…………………………………………….…… 84

19ME0143
22. Resolution of Disputes …………………………………………………………………. 84

23. Suspension of Loan, Credit, Grant, or Appropriation …………………………. 85

24. Procuring Entity’s Representative’s Decisions ……………………………………… 85

25. Approval of Drawings and Temporary Works by Procuring Entity’s Representative ….. 85

26. Acceleration Ordered by Procuring Entity’s Representative ………………. 85

27. Extension of Intended Completion Date ………………………………………. 86

28. Contractor’s Right to Claim …………………………………………………......... 86

29. Dayworks ………………………………………………………............................. 86

30. Early Warning ……………………………………………………………..……………… 86

31. Program of Work ………………………………………………………………………… 87

32. Management Conferences ………………………………………………………….. 87

33. Bill of Quantities ………………………………………………………………..………. 88

34. Instructions, Inspections and Audits …………………………………………….. 88

35. Identification of Defects …………………………………………………………….. 88

36. Cost of Repairs …………………………………………………………………..……… 89

37. Correction of Defects ……………………………………………....................... 89

38. Uncorrected Defects …………………………………………………………….……… 89

39. Advance Payment ……………………………………………………………….……… 89

40. Monthly Statements or Progress Billings ……………………………………… 90

41. Monthly Certificates and Progress Payments ………………………..………. 90

42. Retention ………………………………………………………………………………….. 91

43. Variation Orders …………………………………………………........................ 92

44. Punch List……………………………………………………………………………..….. 94

45. Suspension of Work …………………………………………………………….……. 94

19ME0143
46. Extension of Contract Time …………………………………………………………. 96

47. Price Adjustment …………………………………………………………………….….. 97

48. Certificates of Completion and Acceptance …………………………………… 97

49. Taking Over ………………………………………………………………………………. 98

50. “As-Built” Drawings and Operating and Maintenance Manuals …………. 99

19ME0143
GENERAL CONDITIONS OF CONTRACT
1. Definitions

1.1 Arbiter is the person appointed jointly by the Procuring Entity and the
Contractor to resolve disputes in the first instance.

1.2 As-Built Drawings refer to the engineering plans for the structure as
actually constructed and completed under this Contract, considering all
variations and modifications as approved and executed.

1.3 Bill of Quantities refers to a list of the specific pay items of the Works
under this Contract, particularly their identification numbers, descriptions,
units of measurement, and quantities, together with their corresponding
unit and total bid prices.

1.4 Certificate of Completion is the document issued by the Procuring


Entity, certifying that the Works have been completed, including correction
of all Defects, as of the end of the Contract Time with approved time
extensions, in accordance with the provisions of this Contract.

1.5 Certificate of Acceptance is the document issued by the Procuring


Entity, certifying that the Works have been completed, including correction
of all Defects, as of the end of the Defects Liability Period, in accordance
with the provisions of this Contract, and that, therefore, the completed
Works are accepted by the Procuring Entity.

1.5 Contract is the legal agreement between the Procuring Entity and the
Contractor to execute, complete, and maintain the Works. It consists of the
documents listed in GCC Clause 2.2.

1.6 Contract Price is the price stated in the Notice of Award and thereafter to
be paid by the Procuring Entity to the Contractor for the execution of the
Works in accordance with this Contract.

1.7 Contract Time is the allowable period or duration within which the
Contract Works must be completed, i.e., from the Start Date to the
Intended Completion Date as specified in the SCC.

1.8 Contractor is the juridical entity whose bid has been accepted by the
Procuring Entity and to whom this Contract to execute the Work was
awarded, entered into, and approved.

1.9 Contractor’s Bid is the signed offer or proposal submitted by the


Contractor to the Procuring Entity in response to the Bidding Documents.

1.10 Days are calendar days.

1.11 Dayworks are varied work inputs subject to payment on a time basis for
the Contractor’s employees and Equipment, in addition to payments for
associated Materials and Plant.

19ME0143
1.12 Defect is any part of the Works not constructed in accordance with this
Contract.

1.13 Defects Liability Certificate is the certificate issued by Procuring Entity’s


Representative upon correction of defects by the Contractor.

1.16 Defects Liability Period is the one-year period after the issuance of the
Certificate of Completion during which the Contractor assumes the
responsibility to undertake the repair of any defect in or damage to the
Works at his own expense as a condition for the issuance of the Certificate
of Acceptance.

1.17 Drawings are graphical presentations of the Works. They include all
engineering plans, supplementary details, shop drawings, calculations, and
other information provided or approved for the execution of this Contract.

1.18 Equipment refers to all machines, tools, facilities, supplies, appliances,


and related items required for the execution and completion of the Works
provided by the Contractor and which shall not form or are not intended to
form part of the Permanent Works.

1.19 Intended Completion Date refers to the date specified in the SCC when
the Contractor is expected to have completed the Works. It shall be
reckoned from the Start Date. The Intended Completion Date may be
revised only by the Procuring Entity’s Representative by issuing an
extension of Contract Time or an acceleration order.

1.20 Materials are all supplies, including consumables, used by the Contractor
for incorporation in the Works.

1.21 Notice to Proceed is a written notice issued by the Procuring the


Procuring Entity’s Representative to the Contractor requiring the latter to
begin the Works not later than the date specified in this Notice.

1.21 Permanent Works refer to all permanent structures and all other project
features and facilities required to be constructed and completed in
accordance with this Contract which shall be delivered to the Procuring
Entity and which shall remain at the Site after the removal of all Temporary
Works.

1.22 PERT/CPM is the acronym for Program Evaluation Review


Technique/Critical Path Method and is a technique for planning, scheduling,
and controlling a project, involving a network of interrelated activities with
their start and finish times. The critical path is the longest time path
through the network of activities.

1.23 Plant refers to the machinery, apparatus, and the like intended to form an
integral part of the Permanent Works.

1.24 Procuring Entity is the party that engages the Contractor to carry out the
Works stated in the SCC.

19ME0143
1.25 Procuring Entity’s Representative refers to the HoPE or his duly
authorized representative, identified in the SCC, who shall be responsible
for supervising the execution of the Works and administering this Contract.

1.26 Site is the right-of-way or place provided by the Procuring Entity where the
Works shall be executed and any other place or places which may be
designated in the SCC, or notified to the Contractor by the Procuring
Entity’s Representative, as forming part of the Site.

1.27 Site Investigation Reports are factual and interpretative reports about
the surface and subsurface conditions at the Site, which are provided by
the Procuring Entity in the Bidding Documents.

1.28 Slippage is a delay in work execution occurring when actual


accomplishment falls below the target as measured by the difference
between the scheduled and actual accomplishment of the Works by the
Contractor as established from the work schedule. This is actually described
as a percentage of the whole Works.

1.29 Specifications mean the description of the Works to be done, qualities of


materials to be used, equipment to be installed, construction methods,
workmanship, and finished product required under this Contract.

1.30 Start Date, as specified in the SCC, is the date when the Contractor is
obliged to commence execution of the Works. It is the date of the
Contractor’s receipt of the Notice to Proceed.

1.31 Sub-Contractor is any person or organization to whom a part of the


Works has been subcontracted by the Contractor for execution, as allowed
by the Procuring Entity, but not any assignee of such person.

1.32 Temporary Works are works designed, constructed, installed, and


removed by the Contractor that are needed for the construction or
installation of the Permanent Works.

1.33 Work(s) refer to the Permanent Works and Temporary Works to be


executed by the Contractor in accordance with this Contract, including (i)
the furnishing of all labor, materials, equipment and others incidental,
necessary or convenient to the complete execution of the Works; (ii) the
passing of any tests before acceptance by the Procuring Entity’s
Representative; (iii) and the carrying out of all duties and obligations of the
Contractor imposed by this Contract as described in the SCC.

2. Interpretation

2.1 In interpreting the Conditions of Contract, singular also means plural, male
also means female or neuter, and the other way around. Headings have no
significance. Words have their normal meaning under the language of this
Contract unless specifically defined. The Procuring Entity’s Representative
will provide instructions clarifying queries about the Conditions of Contract.

2.2 If sectional completion is specified in the SCC, references in the Conditions of


Contract to the Works, the Completion Date, and the Intended Completion

19ME0143
Date apply to any Section of the Works (other than references to the
Completion Date and Intended Completion Date for the whole of the Works).

2.3 The documents forming this Contract shall be interpreted in the following
order of priority:

a. Contract Agreement

b. Documents forming part of the Contract Agreement:

(1) Notice of Award (NOA) with the Contractor’s signed


“conforme”

(2) Contractor’s Bid in the Form of Bid, including its Technical


and Financial Proposals, as calculated by the Procuring Entity
and conformed to by the Contractor through the NOA

(3) Instructions to Bidders (ITB) and Bid Data Sheet (BDS)

(4) Supplemental/Bid Bulletins for Bidding Documents

(5) Special Conditions of Contract (SCC)

(6) General Conditions of Contract (GCC)

(7) Specifications

(8) Drawings

(9) Performance Security

(10) Integrity Pledge in accordance with Department Order


No. 86, series of 2013;

(11) Other Documents

(a) Construction Methods

(b) Construction Schedule in the form of PERT/CPM Diagram


or Precedence Diagram and Bar Chart with S-Curve, or
other approved tools of project scheduling, and Cash
Flow.

(c) Manpower Schedule

(d) Equipment Utilization Schedule

(e) Construction Safety and Health Program initially


approved by the HoPE

(f) Contractor’s All Risk Insurance (CARI)

19ME0143
3. Governing Language and Law

3.1 This Contract has been executed in the English language, which shall be the
binding and controlling language for all matters relating to the meaning or
interpretation of this Contract. All correspondence and other documents
pertaining to this Contract which are exchanged by the parties shall be
written in English.

3.2 This Contract shall be interpreted in accordance with the laws of the
Republic of the Philippines.

4. Communications

Communications between parties that are referred to in these Conditions of


Contract shall be effective only when in writing. A notice shall be effective only
when it is received by the concerned party.

5. Procuring Entity’s Obligation to Deliver the Site, Materials, Equipment, and


Plans and to Obtain the Environmental Compliance Certificate (ECC)

5.1 On the date specified in the SCC, the Procuring Entity shall grant the
Contractor possession of so much of the Site as may be required to enable
it to proceed with the execution of the Works. If the Contractor suffers
delay or incurs cost from failure on the part of the Procuring Entity to give
possession in accordance with the terms of this clause, the Procuring
Entity’s Representative shall give the Contractor a Contract Time Extension
and certify such sum as fair to cover the cost incurred, which sum shall be
paid by Procuring Entity.

5.2 If possession of a portion is not given by the date stated in SCC Clause 5.1,
the Procuring Entity will be deemed to have delayed the start of the
relevant activities. The resulting adjustments in contract time to address
such delay shall be in accordance with GCC Clause 46.

5.3 The Contractor shall bear all costs and charges for special or temporary
right-of-way required by it in connection with access to the Site. The
Contractor shall also provide at its own cost any additional facilities outside
the Site required by it for purposes of the Works.

5.4 The Contractor shall allow the Procuring Entity’s Representative and any
person authorized by the Procuring Entity’s Representative access to the
Site and to any place where work in connection with this Contract is being
carried out or is intended to be carried out.

5.5 The Procuring entity shall be responsible for obtaining the appropriate
Environmental Compliance Certificate (ECC) for the Project.

6. Contractor’s Obligations

6.1 The Contractor shall carry out the Works properly and in accordance with
this Contract. The Contractor shall provide all supervision, labor, Materials,

19ME0143
Plant and Equipment, which may be required. All Materials and Plant on Site
shall be deemed to be the property of the Procuring Entity.

6.2 The Contractor shall commence execution of the Works on the Start Date
and shall carry out the Works in accordance with the approved PERT/CPM
network diagram submitted by the Contractor, as updated with the
approval of the Procuring Entity’s Representative, and shall complete the
Works by the Intended Completion Date.

6.3 The Contractor shall be responsible for the safety of all activities on the
Site.

6.4 The Contractor shall carry out all instructions of the Procuring Entity’s
Representative that comply with the applicable laws where the Site is
located.

6.5 The Contractor shall employ the key personnel, named in the Schedule of
Key Personnel in the SCC, to carry out the supervision of the Works. The
Procuring Entity will approve any proposed replacement of key personnel
only if their relevant qualifications and abilities are equal to or better than
those of the personnel listed in the Schedule.

6.6 If the Procuring Entity’s Representative asks the Contractor to remove a


member of the Contractor’s staff or work force, for justifiable cause, the
Contractor shall ensure that the person leaves the Site within seven (7)
days and has no further connection with the Work in this Contract.

6.7 During Contract implementation, the Contractor and its subcontractors shall
abide at all times by all labor laws, including child labor related enactments,
and other relevant rules.

6.8 The Contractor shall submit to the Procuring Entity for consent the name
and particulars of the person authorized to receive instructions on behalf of
the Contractor.

6.9 The Contractor shall cooperate and share the Site with other contractors,
public authorities, utilities, and the Procuring Entity during the dates given
in the schedule of other contractors particularly when they shall require
access to the Site. The Contractor shall also provide facilities and services
for them during this period. The Procuring Entity may modify the schedule
of other contractors, and shall notify the Contractor of any such
modification thereto.

6.10 Should anything of historical or other interest or of significant value be


unexpectedly discovered on the Site, it shall be the property of the
Procuring Entity. The Contractor shall notify the Procuring Entity’s
Representative of such discoveries and carry out the Procuring Entity’s
Representative’s instructions in dealing with them.

19ME0143
7. Performance Security

7.1 The Contractor shall submit its Performance Security to the Procuring Entity
not later than the date specified in the Notice of Award and shall be issued
in any of the following forms and corresponding amounts in ITB Clause 34.

7.2 The Performance Security posted in favor of the Procuring Entity shall be
forfeited in the event it is established that the Contractor is in default in any
of its obligations under the Contract.

7.3 The Performance Security shall remain valid until issuance by the Procuring
Entity of the Certificate of Final Acceptance.

7.4 The Performance Security may be released by the Procuring Entity and
returned to the Contractor after the issuance of the Certificate of Final
Acceptance, subject to the following conditions, provided that the
Performance Security is replaced by a Warranty Security against structural
defects and/or failure as provided in GCC Clause 12:

a. There are no pending claims against the Contractor or the surety


company filed by the Procuring Entity;

b. The Contractor has no pending claims for labor and materials filed
against it; and

c. Other terms specified in the SCC.

7.5 The Contractor shall post an additional Performance Security following the
amount and form specified in ITB Clause 34 to cover any cumulative
increase of more than ten percent (10%) over the original value of the
contract as a result of amendments to order or change orders, extra work
orders and supplemental agreements, as the case may be. The Contractor
shall cause the extension of the validity of the performance security to
cover approved contract time extensions.

7.6 In case of a reduction in the contract value or for partially completed Works
under the contract which are usable and accepted by the Procuring Entity
the use of which, in the judgment of the implementing agency or the
Procuring Entity, will not affect the structural integrity of the entire project,
the Procuring Entity shall allow a proportional reduction in the original
performance security, provided that any such reduction is more than ten
percent (10%) and that the aggregate of such reductions is not more than
fifty percent (50%) of the original Performance Security.

7.7 Unless otherwise indicated in the SCC, the Contractor, by entering into the
Contract with the Procuring Entity, acknowledges the right of the Procuring
Entity to institute action pursuant to Act 3688 against any sub-contractors
be they an individual, firm, partnership, corporation, or association
supplying the Contractor with labor, materials and/or equipment for the
performance of this Contract.

19ME0143
8. Sub-Contracting

8.1 Unless otherwise provided in the SCC, sub-contracting of the Works shall
be subject to the provisions of DPWH Department Order (DO) No. 38,
series of 2015 as provided below.

8.2 All sub-contracts shall be subject to prior approval of the appropriate official
of the Procuring Entity within the limits of his delegated authority.

8.3 The Contractor may sub-contract portions of the works to such an extent as
may be approved by the Procuring Entity and stated in the SCC, provided
that the Contractor shall directly undertake, using its own resources, not
less than fifty percent (50%) of the contract works in terms of cost.

8.4. Each sub-contractor must comply with the eligibility criteria as specified in
the Eligibility Requirements (ER) for the portion of the contract works
to be sub-contracted to that sub-contractor- e.g., applicable license from
the Philippine Constructors Accreditation Board, satisfactory completion of
works similar to the portion of the contract to be subcontracted and
costing at least fifty percent (50%) of the cost of such portion, and
sufficient Net Financial Contracting Capacity, as well as minimum
equipment and manpower. This requirement does not apply to labor
pakyaw contracts.

8.5 The bidder/main contractor may identify the sub-contractors to whom


portions of the contract works will be sub-contracted at any stage of the
bidding process or during contract implementation, provided that any sub-
contracting requires prior approval of the Procuring Entity. Sub-contractors
identified during the bidding may be changed during the implementation of
the contract, subject to compliance with the eligibility requirements and
the approval of the Procuring Entity.

8.6 Sub-contracting of any portion of the contract shall not relieve the main
contractor from any liability or obligation that may arise from the contract.
The main contractor shall be responsible for the acts, defaults, and
negligence of any subcontractor, its agents or workmen.

8.7 For any assignment and sub-contracting of the contract or any part thereof
without prior written approval by the concerned Head of the DPWH
Procuring Entity, the DPWH shall impose on the erring contractor, after the
termination of the contract, the penalty of suspension for one (1) year for
the first offense, and suspension of two (2) years for the second offense
from participating in the public bidding process, pursuant to the provision
of Appendix 11 Section 4.2 of the IRR of RA 9184, in accordance with
Section 69(6) of RA 9184 and without prejudice to the imposition of
additional administrative sanctions as the internal rules of the agency may
provide and/or further criminal prosecution as provided by applicable laws.

9. Liquidated Damages

9.1 The Contractor shall pay liquidated damages to the Procuring Entity for
each day that the Completion Date is later than the Intended Completion

19ME0143
Date. The applicable liquidated damages is at least one-tenth (1/10) of a
percent of the cost of the unperformed portion for every day of delay. The
total amount of liquidated damages shall not exceed ten percent (10%) of
the amount of the contract. The Procuring Entity may deduct liquidated
damages from payments due to the Contractor. Payment of liquidated
damages shall not affect the Contractor’s liabilities. Once the cumulative
amount of liquidated damages reaches ten percent (10%) of the amount of
this Contract, the Procuring Entity may rescind or terminate this Contract,
without prejudice to other courses of action and remedies open to it.

9.2 If the Intended Completion Date is extended after liquidated damages have
been paid, the Engineer of the Procuring Entity shall correct any
overpayment of liquidated damages by the Contractor by adjusting the next
payment certificate.

10. Site Investigation Reports

The Contractor, in preparing the Bid, shall rely on any Site Investigation Reports
referred to in the SCC supplemented by any information obtained by the
Contractor.

11. Licenses and Permits

The Procuring Entity shall, if requested by the Contractor, assist it in applying for
permits, licenses or approvals, which are required for the Works. These shall
include assistance to the contractor in securing necessary quarry permits,
construction permits, access to sites, among others, from the Local Government
Units concerned.

12. Contractor’s Risk and Warranty Security

12.1 The Contractor shall assume full responsibility for the Works from the time
project construction commenced up to final acceptance by the Procuring
Entity and shall be held responsible for any damage or destruction of the
Works except those occasioned by force majeure. The Contractor shall be
fully responsible for the safety, protection, security, and convenience of his
personnel, third parties, and the public at large, as well as the Works,
Equipment, installation, and the like to be affected by his construction work.

12.2 The defects liability period for infrastructure projects shall be one year from
contract completion up to final acceptance by the Procuring Entity. During
this period, the Contractor shall start the repair works, at his own expense,
of any damage to the Works on account of the use of materials of inferior
quality, and shall complete the repair works within ninety (90) days from
the time the HoPE has issued an order to undertake repair. In case of
failure or refusal to comply with this mandate, the Procuring Entity shall
undertake such repair works and shall be entitled to full reimbursement of
expenses incurred therein upon demand.

12.3 Unless otherwise indicated in the SCC, in case the Contractor fails to
comply with the preceding paragraph, the Procuring Entity shall forfeit its
performance security, subject its properties to attachment or garnishment
proceedings, and perpetually disqualify it from participating in any public

19ME0143
bidding. All payables of the GOP in his favor shall be offset to recover the
costs.

12.4 After final acceptance of the Works by the Procuring Entity, the following
shall be held responsible for “Structural Defects”, i.e., major
faults/flaws/deficiencies in one or more key structural elements of the
project which may lead to structural failure of the completed elements or
structure, or “Structural Failures,” i.e., where one or more key structural
elements in an infrastructure facility fails or collapses, thereby rendering the
facility or part thereof incapable of withstanding the design loads, and/or
endangering the safety of the users or the general public:

a. Contractor – where Structural Defects/Failures arise due to faults


attributable to improper construction, use of inferior
quality/substandard materials, and any violation of the contract
plans and specifications, the contractor shall be held liable;

b. Consultants – where Structural Defects/Failures arise due to faulty


and/or inadequate design and specifications as well as construction
supervision, then the consultant who prepared the design or
undertook construction supervision for the project shall be held
liable;

c. Procuring Entity’s Representatives/Project Manager/Construction


Managers and Supervisors –where the Structural Defects/Failures
are due to his/their willful intervention in altering the designs and
other specifications; negligence or omission in not approving or
acting on proposed changes to noted defects or deficiencies in the
design and/or specifications; and the use of substandard
construction materials in the project;

d. Third Parties- where Structural Defects/Failures are caused by work


undertaken by them such as leaking pipes, diggings or excavations,
underground cables and electrical wires, underground tunnel,
mining shaft and the like, in which case the applicable warranty to
such structure should be levied to third parties for their construction
or restoration works.

e. Users - where Structural Defects/Failures are due to abuse/misuse


by the end user of the constructed facility and/or non–compliance
by a user with the technical design limits and/or intended purpose of
the same, then the user concerned shall be held liable.

12.5 The warranty against Structural Defects/Failures, except those occasioned


on force majeure, shall cover the period specified in the SCC reckoned from
the date of issuance of the Certificate of Final Acceptance by the Procuring
Entity.

12.6 The Contractor shall be required to put up a warranty security in the form
of cash, bank guarantee, letter of credit, GSIS or surety bond callable on
demand, in accordance with the following schedule:

19ME0143
Table 12.1 Forms and Amounts of Amounts of Warranty Security
Form Minimum Amount
a. Cash or letter of credit (LC) issued by a
Universal or Commercial Bank, provided that Five Percent (5%) of
the LC shall be confirmed by a Universal or Total Contract Price
Commercial Bank, if issued by a foreign bank.
b. Bank guarantee confirmed by a Universal or Ten Percent (10%) of
Commercial Bank. Total Contract Price
c. Surety bond callable on demand issued by the
GSIS or a surety or insurance company Thirty Percent (30%)
accredited by the Insurance Commission as of Total Contract Price
authorized to issue such security.

12.7 The warranty security shall be stated in Philippine Pesos and shall remain
effective for one year from the date of issuance of the Certificate of Final
Acceptance by the Procuring Entity, and returned only after the lapse of
said one year period.

12.8 In case of structural defects/failure occurring during the applicable warranty


period provided in GCC Clause 12.5, the Procuring Entity shall undertake
the necessary restoration or reconstruction works and shall be entitled to
full reimbursement by the parties found to be liable for expenses incurred
therein upon demand, without prejudice to the filing of appropriate
administrative, civil, and/or criminal charges against the responsible
persons as well as the forfeiture of the warranty security posted in favor of
the Procuring Entity.

13. Liability of the Contractor

Subject to additional provisions, if any, set forth in the SCC, the Contractor’s
liability under this Contract shall be as provided by the laws of the Republic of the
Philippines.

14. Procuring Entity’s Risk

From the Start Date until the Certificate of Acceptance is issued, the following are
risks of the Procuring Entity:

a. The risk of personal injury, death, or loss of or damage to property


(excluding the Works, Plant, Materials, and Equipment) which are due to:

(1) any type of use or occupation of the Site authorized by the


Procuring Entity after the official acceptance of the works; or

(2) negligence, breach of statutory duty, or interference with any legal


right by the Procuring Entity or by any person employed by or
contracted to him except the Contractor.

19ME0143
b. The risk of damage to the Works, Plant, Materials, and Equipment to the
extent that it is due to a fault of the Procuring Entity or in the Procuring
Entity’s design, or due to war or radioactive contamination directly affecting
the Philippines.

15. Insurance

15.1 The Contractor shall, under his name and at his own expense, obtain and
maintain, for the duration of this Contract, the following insurance
coverage:

a. Contractor’s All Risk Insurance;

b. Transportation to the project Site of Equipment, Machinery, and


Supplies owned by the Contractor;

c. Personal injury or death of Contractor’s employees; and

d. Comprehensive insurance for third party liability to Contractor’s


direct or indirect act or omission causing damage to third persons.

15.2 The CARI shall cover the value of the completed portions of the Works. It
shall not, however, cover any damage to the Works whose value is not
more than ten percent (10%) of the Total Contract Cost, as this is to be
absorbed by the Contractor. The CARI shall, therefore, start with nil at the
beginning of Contract execution. It shall then be increased over time as the
Works progresses so that at any time it covers the value of the portions of
the Works actually completed.

15.3 The Contractor shall provide evidence to the Procuring Entity’s


Representative that the insurance required under this Contract has been
effected and shall, within a reasonable time, provide a copy of the
insurance policy to the Procuring Entity’s Representative.

15.4 The Contractor shall notify the insurer of changes in the nature, extent, or
program for the execution of the Works and ensure the adequacy of the
insurance at all times in accordance with the terms of this Contract and
shall produce to the Procuring Entity’s Representative the insurance policy
in force including the receipts for payment of the current premiums.

15.5 If the Contractor fails to obtain and keep in force the insurance which it is
required to obtain under the terms of this Contract, the Procuring Entity
may obtain and keep in force any such insurance and pay such premiums
as may be necessary for the purpose. From time to time, the Procuring
Entity may deduct the amount it shall pay for said premiums including
twenty five percent (25%) therein from any monies due, or which may
become due, to the Contractor, without prejudice to the Procuring Entity
exercising its right to impose other sanctions against the Contractor
pursuant to the provisions of this Contract.

15.6 In the event the Contractor fails to observe the above safeguards, the
Procuring Entity may, at the Contractor’s expense, take whatever measure
is deemed necessary for its protection and that of the Contractor’s

19ME0143
personnel and third parties, and/or order the interruption of dangerous
Works. In addition, the Procuring Entity may refuse to make the payments
under GCC Clause 41 until the Contractor complies with this Clause.

15.7 The Contractor shall immediately replace the insurance policy obtained as
required in this Contract, without need of the Procuring Entity’s demand,
with a new policy issued by a new insurance company acceptable to the
Procuring Entity for any of the following grounds:

a. The issuer of the insurance policy to be replaced has:

(1) become bankrupt;

(2) been placed under receivership or under a management


committee;

(3) been sued for suspension of payment; or

(4) been suspended by the Insurance Commission and its license


to engage in business or its authority to issue insurance
policies cancelled; or

b. Reasonable grounds exist that the insurer may not be able, fully and
promptly, to fulfill its obligation under the insurance policy.

16. Termination for Default of Contractor

16.1 The Procuring Entity shall terminate this Contract for default when any of
the following conditions attend its implementation:

a. Due to the Contractor’s fault and while the Works are on-going, it
has incurred a negative slippage of fifteen percent (15%) or more in
accordance with Presidential Decree 1870; or

b. Due to the Contractor’s fault and after the Contract time has
expired, it has incurred a negative slippage of ten percent (10%) or
more in the completion of the Works; or

c. The Contractor:

(1) abandons the Contract Works, refuses or fails to comply with a


valid instruction of the Procuring Entity or fails to proceed
expeditiously and without delay despite a written notice by the
Procuring Entity;

(2) after receiving a Notice from the Procuring Entity’s


Representative that failure to correct a particular Defect is a
fundamental breach of Contract, fails to correct the Defect
within a reasonable period of time determined by the Procuring
Entity’s Representative;

(3) does not actually have on the Site the minimum essential
equipment listed in the Bid necessary to prosecute the Works in

19ME0143
accordance with the approved PERT/CPM network diagram and
equipment utilization schedule as required under the Contract;

(4) does not execute the Works in accordance with this Contract or
persistently or flagrantly neglects to carry out its obligations
under this Contract;

(5) neglects or refuses to remove materials or to perform a new


work that has been rejected as defective or unsuitable; or

(6) sub-contracts any part of this Contract without approval by the


Procuring Entity.

d. The Contractor causes a fundamental breach of this Contract.


Fundamental breaches of Contract shall include, but shall not be
limited to, the following:

(1) The Contractor stops work for twenty eight (28) days when
no stoppage of work is shown on the current Program of
Work and the stoppage has not been authorized by the
Procuring Entity’s Representative.

(2) The Contractor is declared bankrupt or insolvent as


determined with finality by a court of competent jurisdiction.
In this event, termination will be without compensation to
the Contractor, provided that such termination will not
prejudice or affect any right of action or remedy which has
accrued or will accrue thereafter to the Procuring Entity
and/or the Contractor. In the case of the Contractor's
insolvency, any Contractor's Equipment which the Procuring
Entity instructs in the notice is to be used until the
completion of the Work.

(3) The Procuring Entity’s Representative gives Notice that


failure to correct a particular Defect is a fundamental breach
of Contract and the Contractor fails to correct it within a
reasonable period of time determined by the Procuring
Entity’s Representative.

(4) The Contractor does not maintain a Security, which is


required.

(5) The Contractor has delayed the completion of the Works by


the number of days for which the maximum amount of
liquidated damages can be paid, as defined in the GCC
Clause 9.

(6) In case it is determined prima facie by the Procuring Entity


that the Contractor has engaged, before or during the
implementation of the contract, in unlawful deeds and
behaviors relative to contract acquisition and
implementation, such as, but not limited to, the following:

19ME0143
(a) corrupt, fraudulent, collusive, coercive, and
obstructive practices as defined in ITB Clause 3.10,
unless otherwise specified in the SCC;

(b) drawing up or using forged documents;

(c) using adulterated materials, means or methods, or


engaging in production contrary to rules of science or
the trade; and

(d) any other act analogous to the foregoing

The Procuring Entity or the Funding Source will seek to


impose the maximum civil, administrative and/or criminal
penalties available under the applicable law on individuals
and organizations deemed to be involved with corrupt,
fraudulent, or coercive practices.

16.2 When persons from the Procuring Entity gives notice of a fundamental
breach to the Procuring Entity’s Representative in order to terminate the
existing contract for a cause other than those listed under GCC Clause
16.1-e, the Procuring Entity’s Representative shall decide whether the
breach is fundamental or not.

16.3 If this Contract is terminated, the Contractor shall stop work immediately,
make the Site safe and secure, and leave the Site as soon as reasonably
possible.

16.4 All materials on the Site, Plant, and Works, including Equipment purchased
and funded under the Contract shall be deemed to be the property of the
Procuring Entity if this Contract is terminated because of the Contractor’s
default.

17. Termination for Default of Procuring Entity

17.1 The Contractor may terminate this Contract with the Procuring Entity when
any of the following conditions attend its implementation:

a. If the works are completely stopped for a continuous period of at


least sixty (60) calendar days through no fault of the Contractor, due
to any of the following reasons:

(1) Failure of the Procuring Entity to deliver, within a reasonable


time, supplies, materials, right-of-way, or other items it is
obligated to furnish under the terms of this Contract; or

(2) The prosecution of the Work is disrupted by adverse peace


and order situation, as certified by the Armed Forces of the
Philippines Provincial Commander and approved by the
Secretary of National Defense.

19ME0143
b. The Procuring Entity causes a fundamental breach of this Contract.
Fundamental breaches of Contract shall include, but shall not be
limited to, the following:

(1) The Procuring Entity’s Representative instructs the


Contractor to delay the progress of the Works, and the
instruction is not withdrawn within twenty eight (28) days.

(2) A payment certified by the Procuring Entity’s Representative


is not paid by the Procuring Entity to the Contractor within
eighty four (84) days from the date of the Procuring Entity’s
Representative’s certificate.

17.2 When persons from the Contractor gives notice of a fundamental breach to
the Procuring Entity’s Representative in order to terminate the existing
contract for a cause other than those listed under GCC Clause 17.1-b, the
Procuring Entity’s Representative shall decide whether the breach is
fundamental or not.

18. Termination for Convenience

The Procuring Entity may terminate this Contract, in whole or in part, at any time
for its convenience. The HoPE may terminate this Contract for the convenience of
the Procuring Entity if he has determined the existence of conditions that make
Project Implementation economically, financially or technically impractical and/or
unnecessary, such as, but not limited to, fortuitous event(s) or changes in law and
National Government policies.

19. Procedure for Termination of Contracts

19.1 The following provisions shall govern the procedures for the termination of
this Contract:

a. Verification. Upon receipt of a written report of acts or causes


which may constitute grounds for termination as aforementioned, or
upon its own initiative, the Procuring Entity’s Representative shall,
within a period of seven (7) calendar days, verify the existence of
such ground(s) and cause the execution of a Verified Report, with
all relevant evidence attached.

b. Notice of Termination. Upon recommendation by the Procuring


Entity’s Representative, the HoPE shall terminate this Contract only
by a written Notice of Termination to the Contractor. The Notice
shall state:

(1) that this Contract is being terminated for any of the grounds
aforementioned, and a statement of the acts that constitute
the ground(s).

(2) the extent of termination, whether in whole or in part;

(3) an instruction to the Contractor to show cause as to why this


Contract should not be terminated; and

19ME0143
(4) special instructions of the Procuring Entity, if any.

The Notice of Termination shall be accompanied by a copy of the


Verified Report.

c. Show Cause. Within a period of seven (7) calendar days from


receipt of the Notice of Termination, the Contractor shall submit to
the HoPE a verified position paper showing cause as to why the
Contract should not be terminated. If the Contractor fails to do so,
the HoPE shall issue a written Notice of Decision confirming the
Notice of Termination of the Contract.

d. Withdrawal of Notice of Termination. The Procuring Entity may, at


anytime before receipt of the Contractor’s verified position paper,
withdraw the Notice of Termination if it is determined that certain
items or works subject of the Notice had been completed, delivered,
or performed before the Contractor’s receipt of the Notice.

e. Notice of Decision. Within a non-extendible period of ten (10)


calendar days from receipt of the verified position paper, the HoPE
shall serve the Contractor his written Notice of Decision to confirm
or withdraw the Notice of Termination. If the Notice of Decision is to
confirm the Notice of Termination, then this Contract is deemed
terminated from receipt by the Contractor of the said Notice of
Decision. The termination shall be based only on the grounds
stated in the Notice of Termination.

f. Review Committee. The HoPE may create a Contract Termination


Review Committee (CTRC) to assist him in the discharge of this
function. All decisions recommended by the CTRC shall be subject
to his approval.

19.2 Pursuant to Section 69(f) of RA 9184 and without prejudice to the


imposition of additional administrative sanctions as the internal rules of the
agency may provide and/or further criminal prosecution as provided by
applicable laws, the Procuring Entity shall impose on contractors after the
termination of the contract the penalty of suspension for one (1) year for
the first offense, suspension for two (2) years for the second offense from
participating in the public bidding process, for violations committed during
the contract implementation stage, which include but not limited to the
following:

a. Failure of the contractor, due solely to his fault or negligence, to


mobilize and start work or performance within the specified period
in the Notice to Proceed (“NTP”);

b. Failure by the contractor to fully and faithfully comply with its


contractual obligations without valid cause, or failure by the
contractor to comply with any written lawful instruction of the
Procuring Entity or its representative(s) pursuant to the
implementation of the contract. For the procurement of

19ME0143
infrastructure projects or consultancy contracts, lawful instructions
include but are not limited to the following:

i. Employment of competent technical personnel, competent


engineers and/or work supervisors;

ii. Provision of warning signs and barricades in accordance with


approved plans and specifications and contract provisions;

iii. Stockpiling in proper places of all materials and removal from


the project site of waste and excess materials, including
broken pavement and excavated debris in accordance with
approved plans and specifications and contract provisions;

iv. Deployment of committed equipment, facilities, support staff


and manpower; and

ii. Renewal of the effectivity dates of the performance security


after its expiration during the course of contract
implementation.

c. Assignment and subcontracting of the contract or any part thereof


or substitution of key personnel named in the proposal without prior
written approval by the Procuring Entity.

d. Poor performance by the contractor or unsatisfactory quality and/or


progress of work arising from his fault or negligence as reflected in
the Constructor's Performance Evaluation System (“CPES”) rating
sheet. In the absence of the CPES rating sheet, the existing
performance monitoring system of the Procuring Entity shall be
applied. Any of the following acts by the Contractor shall be
construed as poor performance:

(1) Negative slippage of 15% and above within the critical path
of the project due entirely to the fault or negligence of the
contractor; and

(2) Quality of materials and workmanship not complying with


the approved specifications arising from the contractor's fault
or negligence.

e. Willful or deliberate abandonment or non-performance of the


project or contract by the contractor resulting to substantial breach
thereof without lawful and/or just cause.

In addition to the penalty of suspension, the Performance Security posted


by the contractor shall also be forfeited.

20. Force Majeure and Release from Performance

20.1 For purposes of this Contract the terms “force majeure” and “fortuitous
event” may be used interchangeably. In this regard, a fortuitous event or

19ME0143
force majeure shall be interpreted to mean an event which the Contractor
could not have foreseen, or which though foreseen, was inevitable. It shall
not include ordinary unfavorable weather conditions, and any other cause
the effects of which could have been avoided with the exercise of
reasonable diligence by the Contractor.

20.2 If this Contract is discontinued by an outbreak of war or by any other event


entirely outside the control of either the Procuring Entity or the Contractor,
the Procuring Entity’s Representative shall certify that this Contract has
been discontinued. The Contractor shall make the Site safe and stop work
as quickly as possible after receiving this certificate and shall be paid for all
portions of the Works carried out before receiving it and for any part of the
Works carried out afterwards to which a commitment was made.

20.3 If the event continues for a period of eighty four (84) days, either party may
give the other a Notice of Termination, which shall take effect twenty eight
(28) days after the receipt of the Notice.

20.4 After termination, the Contractor shall be entitled to payment of the unpaid
balance of the value of the Works executed and of the materials and Plant
reasonably delivered to the Site, adjusted by the following:

a. Any sum to which the Contractor is entitled under GCC Clause 28.

b. The cost of his suspension and demobilization.

c. Any sum to which the Procuring Entity is entitled.

20.5 The net balance due shall be paid or repaid within a reasonable time period
from the date of the Notice of Termination.

21. Payment on Termination

21.1 If the Contract is terminated because of a fundamental breach of Contract


by the Contractor, the Procuring Entity’s Representative shall issue a
certificate for the value of the work done and materials ordered less
advance payments received up to the date of the issue of the certificate
and less the value of the work not completed. Additional liquidated
damages shall not apply. If the total amount due to the Procuring Entity
exceeds any payment due to the Contractor, the difference shall be a debt
payable to the Procuring Entity.

21.2 If the Contract is terminated for the Procuring Entity’s convenience or


because of a fundamental breach of Contract by the Procuring Entity, the
Procuring Entity’s Representative shall issue a certificate for the value of the
work done, materials ordered, the reasonable cost of removal of
Contractor’s equipment, and the Contractor’s costs of protecting and
securing the Works, less advance payments received up to the date of the
certificate.

19ME0143
21.3 The net balance due shall be paid or repaid within twenty eight (28) days
from the notice of termination.

21.4 If the Contractor has terminated the Contract under GCC Clause 17 or 18,
the Procuring Entity shall promptly return the Performance Security to the
Contractor.

22. Resolution of Disputes

22.1 If any dispute or difference of any kind whatsoever shall arise between the
parties in connection with the implementation of the contract covered by
RA 9184 and its IRR, the parties shall make every effort to resolve
amicably such dispute or difference by mutual consultation.

22.2 If the Contractor believes that a decision taken by the Procuring Entity’s
Representative was either outside the authority given to the Procuring
Entity’s Representative by this Contract or that the decision was wrongly
taken, the decision shall be referred to the Arbiter indicated in the SCC
within fourteen (14) days of the notification of the Procuring Entity’s
Representative’s decision.

22.3 Any and all disputes arising from the implementation of this Contract
covered by the RA 9184 and its IRR shall be submitted to arbitration in the
Philippines according to the provisions of RA 876, otherwise known as the
“Arbitration Law” and RA 9285, otherwise known as the “Alternative Dispute
Resolution Act of 2004. However, disputes that are within the competence
of the Construction Industry Arbitration Commission to resolve shall be
referred thereto. The process of arbitration shall be incorporated as a
provision in this Contract that will be executed pursuant to the provisions of
RA 9184 and its IRR. By mutual agreement, however, the parties may
agree in writing to resort to other alternative modes of dispute resolution.

23. Suspension of Loan, Credit, Grant, or Appropriation

In the event that the Funding Source suspends the Loan, Credit, Grant, or
Appropriation to the Procuring Entity, from which part of the payments to the
Contractor are being made:

a. The Procuring Entity is obligated to notify the Contractor of such suspension


within seven (7) days of having received the suspension notice.

b. If the Contractor has not received sums due it for work already done within
forty five (45) days from the time the Contractor’s claim for payment has
been certified by the Procuring Entity’s Representative, the Contractor may
immediately issue a suspension of work notice in accordance with GCC
Clause 44.

24. Procuring Entity’s Representative’s Decisions

24.1 Except where otherwise specifically stated, the Procuring Entity’s


Representative shall decide contractual matters between the Procuring
Entity and the Contractor in the role representing the Procuring Entity.

19ME0143
24.2 The Procuring Entity’s Representative may delegate any of his duties and
responsibilities to other people, except to the Arbiter, after notifying the
Contractor, and may cancel any delegation after notifying the Contractor.

25. Approval of Drawings and Temporary Works by Procuring Entity’s


Representative

25.1 All Drawings prepared by the Contractor for the execution of the Temporary
Works are subject to prior approval by the Procuring Entity’s Representative
before their use.

25.2 The Contractor shall be responsible for the design of Temporary Works.

25.3 The Procuring Entity’s Representative’s approval shall not alter the
Contractor’s responsibility for the design of the Temporary Works.

25.4 The Contractor shall obtain approval by third parties of the design of the
Temporary Works, when required by the Procuring Entity.

26. Acceleration Ordered by Procuring Entity’s Representative

26.1 When the Procuring Entity wants the Contractor to finish the Works before
the Intended Completion Date, the Procuring Entity’s Representative shall
obtain a priced proposal for achieving the necessary acceleration from the
Contractor. If the Procuring Entity accepts these proposals, the Intended
Completion Date will be adjusted accordingly and confirmed by both the
Procuring Entity and the Contractor.

26.2 If the Contractor’s Financial Proposals for an acceleration are accepted by


the Procuring Entity, they are incorporated in the Contract Price and treated
as a Variation.

27. Extension of Intended Completion Date

27.1 The Procuring Entity’s Representative shall extend the Intended Completion
Date if a Variation Order is issued which makes it impossible for the
Intended Completion Date to be achieved by the Contractor without taking
steps to accelerate the remaining work, which would cause the Contractor
to incur additional costs. No payment shall be made for any event which
may warrant the extension of the Intended Completion Date.

27.2 The Procuring Entity’s Representative shall decide whether and by how
much to extend the Intended Completion Date within twenty one (21) days
of the Contractor asking the Procuring Entity’s Representative for a decision
thereto after fully submitting all supporting information. If the Contractor
has failed to give an early warning of a delay or has failed to cooperate in
dealing with a delay, the delay by this failure shall not be considered in
assessing the new Intended Completion Date.

19ME0143
28. Contractor’s Right to Claim

If the Contractor incurs a cost as a result of any of the events under GCC Clause 13, the
Contractor shall be entitled to the amount of such cost. If as a result of any of the said
events, it is necessary to change the Works, this shall be dealt with as a Variation Order.

29. Dayworks

29.1 Subject to GCC Clause 44 on Variation Orders, and if applicable as


indicated in the SCC, the Dayworks rates in the Contractor’s Bid shall be
used for small additional amounts of work only when the Procuring Entity’s
Representative has given written instructions in advance for additional work
to be paid for in that way.

29.2 All work to be paid for as Dayworks shall be recorded by the Contractor on
forms approved by the Procuring Entity’s Representative. Each completed
form shall be verified and signed by the Procuring Entity’s Representative
within two days of the work being done.

29.3 The Contractor shall be paid for Dayworks subject to obtaining signed
Dayworks forms.

30. Early Warning

30.1 The Contractor shall warn the Procuring Entity’s Representative at the
earliest opportunity of specific likely future events or circumstances that
may adversely affect the quality of the Work, increase the Contract Price, or
delay the execution of the Works. The Procuring Entity’s Representative
may require the Contractor to provide an estimate of the expected effect of
the future event or circumstance on the Contract Price and Completion
Date. The estimate shall be provided by the Contractor as soon as
reasonably possible.

30.2 The Contractor shall cooperate with the Procuring Entity’s Representative in
making and considering proposals for how the effect of such an event or
circumstance can be avoided or reduced by anyone involved in the Work
and in carrying out any resulting instruction of the Procuring Entity’s
Representative.

31. Program of Work

31.1 Within the time stated in the SCC, the Contractor shall submit to the
Procuring Entity’s Representative for approval a Program of Work showing
the general methods, arrangements, order, and timing for all the activities
in the Works, including a PERT/CPM network diagram.

31.2 An update of the Program of Work shall the show the actual progress
achieved on each activity and the effect of the progress achieved on the
timing of the remaining work, including any changes to the sequence of the
activities.

19ME0143
31.3 The Contractor shall submit to the Procuring Entity’s Representative for
approval an updated Program of Work at intervals no longer than the
period stated in the SCC. If the Contractor does not submit an updated
Program of Work within this period, the Procuring Entity’s Representative
may withhold the amount stated in the SCC from the next payment
certificate and continue to withhold this amount until the next payment
after the date on which the overdue Program of Work has been submitted.

31.4 The Procuring Entity’s Representative’s approval of the Program of Work


shall not alter the Contractor’s obligations. The Contractor may revise the
Program of Work and submit it to the Procuring Entity’s Representative
again at any time. A revised Program of Work shall show the effect of any
approved Variations.

31.5 When the Program of Work is updated, the Contractor shall provide the
Procuring Entity’s Representative with an updated cash flow forecast. The
cash flow forecast shall include different currencies, as defined in the
Contract, converted as necessary using the Contract exchange rates.

31.6 All Variations shall be included in updated Program of Work produced by


the Contractor.

32. Management Conferences

32.1 Either the Procuring Entity’s Representative or the Contractor may require
the other to attend a Management Conference. The Management
Conference shall review the plans for remaining work and deal with matters
raised in accordance with the early warning procedure.

32.2 The Procuring Entity’s Representative shall prepare the minutes of


Management Conferences and provide copies of the minutes to those
attending the Conference. The responsibility of the parties for actions to be
taken shall be decided by the Procuring Entity’s Representative either at the
Management Conference or after the Management Conference and stated
in writing to all who attended the Conference.

33. Bill of Quantities

33.1 The Bill of Quantities(BOQ), shown in ANNEX II-1.1Jof these Bidding


Documents, shall contain the items of work for the construction,
installation, testing, and commissioning of the Works to be done by the
Contractor.

33.2 The BOQ is used to calculate the Contract Price. The Contractor shall be
paid for the actual quantity of each pay item, certified by the Procuring
Entity’s Representative as accomplished, at the unit price in the Bill of
Quantities for that item.

33.3 If the final quantity of any pay item accomplished differs from the original
quantity in the BOQ for that item and is not more than twenty five percent
(25%) of that original quantity, provided the aggregate changes for all work
items do not exceed ten percent (10%) of the Contract Price, the Procuring

19ME0143
Entity’s Representative shall make the necessary adjustments to allow for
the changes, subject to applicable laws, rules, and regulations.

33.4 If requested by the Procuring Entity’s Representative, the Contractor shall


provide the Procuring Entity’s Representative a detailed cost breakdown of
any unit price or rate in the BOQ.

34. Instructions, Inspections and Audits

34.1 The Procuring Entity’s personnel shall at all reasonable times during
construction of the Works be entitled to examine, inspect, measure and test
the materials and workmanship, and to check the progress of the
construction.

34.2 If the Procuring Entity’s Representative instructs the Contractor to carry out
a test not specified in the Specifications to check whether any work has a
defect and the test shows that it does, the Contractor shall pay for the test
and any samples. If there is no defect, the test shall be a Compensation
Event.

34.3 The Contractor shall permit the Funding Source named in the SCC to
inspect the accounts and records of the Contractor relating to its
performance and to have them audited by auditors approved by the
Funding Source, if so required by the Funding Source.

35. Identification of Defects

The Procuring Entity’s Representative shall check the Contractor’s work and notify
the Contractor of any Defects that are found. Such checking shall not affect the
Contractor’s responsibilities. The Procuring Entity’s Representative may instruct
the Contractor to uncover Defects and test any work that the Procuring Entity’s
Representative considers below standard and defective.

36. Cost of Repairs

Loss or damage to the Works or Materials to be incorporated in the Works between


the Start Date and the end of the Defects Liability Period shall be remedied by the
Contractor at the Contractor’s expense if the loss or damage arises from the
Contractor’s acts or omissions.

37. Correction of Defects

37.1 The Procuring Entity’s Representative shall give notice to the Contractor of
any defects before the end of the Defects Liability Period, which is one (1)
day from the Completion Date up to the date of issuance of the Certificate
of Acceptance by the Procuring Entity.

37.2 Every time notice of a Defect is given, the Contractor shall correct the
notified defect within the length of time specified in the Procuring Entity’s
Representative’s notice.

37.3 The Contractor shall correct the Defects which it notices itself before the
end of the Defects Liability Period.

19ME0143
37.4 The Procuring Entity’s Representative shall certify that all Defects have
been corrected. If the Procuring Entity’s Representative considers that
correction of a Defect is not essential, he can request the Contractor to
submit a quotation for the corresponding reduction in the Contract Price. If
the Procuring Entity’s Representative accepts the quotation, the
corresponding change shall be covered by a Variation Order.

38. Uncorrected Defects

38.1 The Procuring Entity shall give the Contractor at least fourteen (14) days
notice of its intention to use a third party to correct a Defect. If the
Contractor itself does not correct the Defect within that period, the
Procuring Entity may have the Defect corrected by the third party. The cost
of the correction will be deducted from the Contract Price.

38.2 The use of a third party to correct Defects that are uncorrected by the
Contractor shall in no way relieve the Contractor of its liabilities and
warranties under the Contract.

39. Advance Payment

39.1 The Procuring Entity shall, upon a written request of the Contractor which
shall be submitted as a Contract document, make an Advance Payment to
the Contractor in an amount not to exceed fifteen percent (15%) of the
total Contract Price, to be made in lump sum or, at most, two installments
according to a schedule specified in the SCC. The advance payment, if
requested in two installments, shall be subject to the following
prerequisites:

a. The first installment shall require the written request of the


Contractor and submission of the instrument prescribed in GCC
Clause 39.2.

b. The second installment shall require a certification of the Project


Engineer of the Procuring Entity that the Contractor has mobilized
major equipment according to the approved Equipment Utilization
Schedule.

39.2 The Advance Payment shall be made only upon the submission by the
Contractor to and acceptance by the Procuring Entity of an irrevocable
standby letter of credit of equivalent value from a commercial bank, a bank
guarantee or a surety bond callable upon demand, issued by a surety or
insurance company duly licensed by the Insurance Commission and
confirmed by the Procuring Entity.

39.3 The Advance Payment shall be repaid by the Contractor by deducting, from
periodic progress payments to be made to the Contractor, a percentage
equal to the percentage of the total Contract Price used for the Advance
Payment.

39.4 The Contractor may reduce its standby letter of credit or guarantee
instrument by the amounts refunded by the Monthly Certificates in the
advance payment.

19ME0143
40. Monthly Statements or Progress Billings

40.1 The Contractor shall submit to the Procuring Entity’s Representative, after
the end of each month, a Statement of Work Accomplished (SWA) or
Progress Billing, showing the amounts which the Contractor consider itself
to be entitled up to the end of the month, to cover:

a. the cumulative value of the Works it executed to date, based on the


items in the Bill of Quantities; and

b. adjustments made for approved Variation Orders executed.

40.2 Except as otherwise stipulated in the SCC, materials and equipment


delivered on the site but not completely put in place shall not be included
for payment.

41. Monthly Certificates and Progress Payments

41.1 The Procuring Entity’s Representative shall check the Contractor’s monthly
SWA and certify the amount to be paid to the Contractor.

41.2 The Procuring Entity’s Representative shall check the Contractor’s monthly
statement and certify the amount to be paid to the Contractor.

41.3 The value of Work executed shall:

a. be determined by the Procuring Entity’s Representative;

b. comprise the value of the quantities of the items in the Bill of


Quantities completed; and

c. include the valuations of approved variations.

41.4 The Procuring Entity’s Representative may exclude any item certified in a
previous certificate or reduce the proportion of any item previously certified
in any certificate in the light of later information.

41.5 The Procuring Entity’s Representative shall deduct the following from the
certified gross amounts to be paid, resulting in the net amount payable to
the Contractor as Progress Payment:

a. Cumulative value of the Work previously certified and paid for.

b. Portion of the advance payment to be recouped for the month under


the present certificate.

c. Retention money in accordance with GCC Clause 42.

d. Amount to cover approved third party liabilities.

e. Amount to cover uncorrected Defects in the Works.

19ME0143
f. Value of any work item presently certified but already paid for under
an earlier certification.

41.6 The Procuring Entity shall pay the Contractor the said net amounts certified
by the Procuring Entity’s Representative within twenty eight (28) days from
the date each certificate was issued. No payment of interest for delayed
payments and adjustments shall be made by the Procuring Entity.

41.7 The first progress payment may be paid by the Procuring Entity to the
Contractor provided that at least twenty percent (20%) of the work has
been accomplished as certified by the Procuring Entity’s Representative.

41.8 Items of the Works for which a price of “0” (zero) has been entered will not
be paid for by the Procuring Entity and shall be deemed covered by other
rates and prices in the Contract.

41.9 The Procuring Entity shall pay the Contractor a cumulative gross amount
not exceeding ninety percent (90%) of the total Contract price, since the
remainder shall serve as the ten percent (10%) retention money, as
provided in GCC Clause 42.

42. Retention

42.1 The Procuring Entity shall retain from each progress payment ten percent
(10%) of such payment, referred to as the “retention money.” Such
retention money shall be based on the total amount due to the Contractor
prior to any deduction and shall be retained from every Progress Payment
until fifty percent (50%) of the value of the Works, as determined by the
Procuring Entity, is completed. If, after fifty percent (50%) completion, the
Works are satisfactorily done and on schedule, no additional retention shall
be made; otherwise, the ten percent (10%) retention shall again be
imposed using the rate specified therefor.

42.2 The total retention money shall be due for release upon final acceptance of
the Works. The Contractor may, however, request the substitution of the
retention money for each progress billing with an irrevocable standby letter
of credit from a commercial bank, bank guarantee and/or surety bond
callable on demand, of amounts equivalent to the retention money
substituted for and in a form acceptable to the Procuring Entity. The
Procuring Entity shall allow such substitution provided that the Contract is
on schedule and is satisfactorily undertaken. The said irrevocable standby
letter of credit, bank guarantee and/or surety bond, to be posted in favor of
the Procuring Entity, shall be valid for a duration to be determined by the
Procuring Entity and shall answer for the purpose for which the retention is
intended, i.e., to cover uncorrected discovered Defects and third party
liabilities.

42.3 On completion of the whole Works, the Contractor may substitute retention
money with an “on demand” Bank guarantee in a form acceptable to the
Procuring Entity.

19ME0143
43. Variation Orders

43.1 Variation Orders (VOs) shall be subject to the provisions of Annex E of RA


9184-IRR and DPWH DO 28, series of 2015. may be issued by the
Procuring Entity to cover any increase or decrease in quantities, including
the introduction of new work items not included in the original Contract or
reclassification of work items due to change of plans, design or alignment
to suit actual field conditions, resulting in disparity between the
preconstruction plans used for purposes of bidding and the “as staked
plans” or construction drawings prepared after a joint survey by the
Contractor and the Procuring Entity after award of the Contract. The
cumulative amount of the positive or additive VOs, however, shall not
exceed ten percent (10%) of the original Contract cost. The addition or
deletion of works shall be within the general scope of the Contract as bid
and awarded. The scope of the Works shall not be reduced so as to
accommodate a positive VO. .

43.2 A deductive VO may be allowed only if it would not significantly impair the
functionality of the original design, i.e., it must not reduce the size of the
facility by more than ten percent (10%) of the original scope (e.g.,
shortening of road length) or must not make the facility unsafe (e.g.,
removal of guard rails) or structurally unstable (e.g., removal of a column)
or unusable (e.g., removal of a bridge abutment).

43.3 A VO in the form of a Change Order may be issued by the Procuring Entity
to cover any increase or decrease in quantities of original Work items in the
Contract.

43.4 A VO in the form an Extra Work Order may be issued by the Procuring
Entity to cover the introduction of new work necessary for the completion,
improvement or protection of the project which were not included as items
of work in the original Contract, such as where there are subsurface or
latent physical conditions at the Site differing materially from those
indicated in the Contract, or where there are duly unknown physical
conditions at the Site of an unusual nature differing materially from those
ordinarily encountered and generally recognized as inherent in the Works or
character provided for in the Contract.

43.5 Any cumulative positive VO beyond ten percent (10%) shall be the subject
of another contract to be bid out if the works are separable from the
original Contract.

43.6 In claiming for any VO, the Contractor shall, within seven (7) calendar days
after such work has been commenced or after the circumstances leading to
such condition(s) leading to the extra cost, and within twenty-eight (28)
calendar days deliver a written communication giving full and detailed
particulars of any extra cost in order that it may be investigated at that
time. Failure to provide either of such notices in the time stipulated shall
constitute a waiver by the contractor for any claim. The Contractor shall not
“accumulate” claims for VOs before submitting them to the Procuring Entity
for investigation and processing.

19ME0143
43.7 The preparation and submission of VOs shall be as follows:

a. If the Procuring Entity’s Representative/Project Engineer finds that a


Variation Order is necessary, he shall prepare the proposed Order,
accompanied with the Notice submitted by the Contractor, the plans
therefor, his computations on the quantities of the additional,
reduced or modified works involved per item indicating the specific
stations where such works are needed, the date of his inspections
and investigations thereon, and the log book thereof, and a detailed
estimate of the unit cost of such items of work, together with his
justifications for the Variation Order, and shall submit the same to
the HoPE for approval.

b. The HoPE or his duly authorized representative, upon receipt of the


proposed Change Order or Extra Work Order, shall immediately
instruct the appropriate technical staff or office of the Procuring
Entity to conduct an on-the-spot investigation to verify the need for
the Work to be prosecuted and to review the proposed Change
Order or Extra Work Order.

c. The technical staff or appropriate office of the Procuring Entity shall


submit a report of their findings and recommendations, together
with the supporting documents, to the HOPE or his duly authorized
representative for consideration.

d. The HoPE or his duly authorized representative, acting upon the


recommendation of the technical staff or appropriate office of the
Procuring Entity, shall approve the Change Order or Extra Work
Order, after being satisfied that the same is justified, necessary, and
in order.

e. The timeframe for the processing of VO from the preparation up to


the approval by the HoPE concerned shall not exceed thirty (30)
calendar days.

43.8 Work under VOs shall be valued and paid as follows:

a. At the unit prices for the same items in this Contract.

b. In the absence of unit prices for the same items rates in this
Contract, at prices or rates obtained from those of similar or related
items in this Contract.

c. Failing the above, at appropriate new unit prices or rates equal to or


lower than current market rates and to be agreed upon by both
parties and approved by the HoPE.

44. Punch List

Once the Contract reaches an accomplishment of ninety five percent (95%) of the
total Contract Works, the Procuring Entity may create an inspectorate team to
make a preliminary inspection and submit a punch list to the Contractor in
preparation for the total completion of the Works. The punch list shall contain,

19ME0143
among other things, the remaining unfinished portions of the Works, deficiencies in
the Works for necessary corrections, and the specific time to fully complete the
whole Works considering the approved remaining Contract time. This, however,
shall not preclude any claim of the Procuring Entity for liquidated damages.

45. Suspension of Work

45.1 In accordance with DPWH DO 100, series of 2015, the Procuring Entity,
through its Project Engineer/Engineer’s Representative, shall have the
authority to issue a Work Suspension Order to the Contractor suspend the
work wholly or partly by written order for such period as may be deemed
necessary, on any of the following grounds:

a. Force majeure or any fortuitous event that has taken place, which
inflicts extensive damage and/or makes it difficult to proceed with
the work, such as a devastating earthquake or flood.

b. Failure on the part of the Contractor to correct bad conditions which


are unsafe for workers or for the general public.

c. Failure of the contractor to carry out valid orders given by the


Procuring Entity or to perform any provisions of the contract.

d. Adjustments of plans to suit field conditions as found necessary


during construction.

e. Major right-of-way (ROW) problems which prohibit the contractor


from performing work in accordance with the approved construction
schedule.

f. Peace and order conditions which makes it extremely dangerous, if


not impossible to work, as certified in writing by the Philippine
National Police (PNP) Station Commander which has responsibility
over the affected area, and confirmed by the Department of Interior
and Local Government (DILG) Regional Director.
g. Major variations initiated by the Government in the scope of the
contract during its implementation to suit changes in physical and
economic conditions.

The Contractor shall immediately comply with such order to suspend the
Works wholly or partly.

45.2 The Contractor or its duly authorized representative shall have the right to
suspend work operation on any or all projects/activities along the critical
path of activities after fifteen (15) calendar days from date of receipt of
written notice from the Contractor to the district engineer/regional
director/consultant or equivalent official, as the case may be, on any of the
following grounds:

a. There exist right-of-way problems which prevent the Contractor


from performing work in accordance with the approved construction
schedule.

19ME0143
b. Requisite construction plans which must be owner-furnished are not
issued to the contractor precluding any work called for by such
plans.

c. Peace and order conditions make it extremely dangerous, if not


possible, to work. However, this condition must be certified in
writing by the Philippine National Police (PNP) station which has
responsibility over the affected area and confirmed by the
Department of Interior and Local Government (DILG) Regional
Director.

d. There is failure on the part of the Procuring Entity to deliver


government-furnished materials and equipment as stipulated in the
contract.

e. Delay in the payment of Contractor’s claim for progress billing


beyond forty-five (45) calendar days from the time the Contractor’s
claim has been certified to by the Procuring Entity’s authorized
representative and the documents are complete unless there are
justifiable reasons thereof which shall be communicated in writing to
the Contractor.

45.3 The contractor shall immediately demobilize its equipment and manpower
upon its receipt of the Work Suspension Order and to remobilize the same
upon the lifting by the Procuring Entity the Work Suspension Order through
a Work Resumption Order.

45.4 The issuance of a Work Suspension Order shall not be an automatic


contract time extension. A corresponding time extension, complete with the
documentary requirements in accordance with DO No. 52, series of
2012,has to be approved by the authorized DPWH official in lieu of
suspension, subject to evaluation to consider pre-determined unworkable
days, bond extension, quit claim for damages, and their effect on the
approved PERT/CPM schedule in order to reflect the official revised contract
time and expiry date as a result of such suspension. If the suspension is
due to any fault of the contractor, no contract time extension shall be
granted.

46. Extension of Contract Time

46.1 Extension of the Contract Time shall be subject to the provisions of DPWH
DO 100, series of 2015 and the provisions of this GCC Clause 46.

46.2 Should the amount of additional work under an approved Variation Order or
other special circumstances of any kind whatsoever occur such as to fairly
entitle the Contractor to an extension of Contract Time, the Procuring Entity
shall determine the amount of such extension; provided that the Procuring
Entity is not bound to take into account any claim for an extension of time
unless the Contractor has, prior to the expiration of the Contract time and
within thirty (30) calendar days after such work has been commenced or
after the circumstances leading to such claim have arisen, delivered to the
Procuring Entity notices in order that it could have investigated them at that
time. Failure to provide such notice shall constitute a waiver by the

19ME0143
Contractor of any claim. Upon receipt of full and detailed particulars, the
Procuring Entity shall examine the facts and extent of the delay and shall
extend the Contract time to complete the contract work when, in the
Procuring Entity’s opinion, the findings of facts justify an extension.

46.3 No extension of contract time shall be granted the Contractor due to (a)
ordinary unfavorable weather conditions and (b) inexcusable failure or
negligence of Contractor to provide the required equipment, supplies or
materials.

46.4 Extension of contract time may be granted only when the affected activities
fall within the critical path of the PERT/CPM network.

46.5 No extension of contract time shall be granted when the reason given to
support the request for extension was already considered in the
determination of the original contract time during the conduct of detailed
engineering and in the preparation of the contract documents as agreed
upon by the parties before contract perfection.

46.6 Extension of contract time may be granted for any of the following grounds:

a. Rainy/unworkable days considered unfavorable for the prosecution of


the works at the site, based on the actual conditions obtained at the
site, in excess of the number of rainy/unworkable days pre-determined
by the Procuring Entity in relation to the original contract time during
the conduct of detailed engineering and in the preparation of the
contract documents as agreed upon by the parties before contract
perfection. In these cases, the time extension shall be processed for
approval only after the total number of pre-determined
rainy/unworkable days as indicated in the contract has been fully
utilized as duly certified by the Procuring Entity’s Representative.

b. Equivalent period of delay due to major calamities such as exceptionally


destructive typhoons, floods and earthquakes, and epidemics, and for
causes such as non-delivery on time of materials, working drawings, or
written information to be furnished by the Procuring Entity, non-
acquisition of permit to enter private properties within the right-of-way
resulting in complete paralyzation of construction activities, and other
meritorious causes as determined by the Procuring Entity’s
Representative and approved by the HoPE.

c. Shortage of construction materials, general labor strikes, and peace and


order problems that disrupt construction operations through no fault of
the Contractor, provided that they are publicly felt and certified by
appropriate government agencies such as Department of Trade and
Industry (DTI), Department of Labor and Employment (DOLE),
Department of Interior and Local Government (DILG), and Department
of National Defense (DND), among others.

46.7 The written consent of bondsmen must be attached to any request of the
Contractor for extension of Contract Time and submitted to the Procuring
Entity for consideration, and the validity of the Performance Security shall
be correspondingly extended.

19ME0143
47. Price Adjustment

Except for extraordinary circumstances as determined by the National Economic


and Development Authority (NEDA) and approved by the GPPB, no price
adjustment shall be allowed unless otherwise indicated in the SCC. Nevertheless,
in cases where the cost of the awarded contract is affected by any applicable new
laws, ordinances, regulations, or other acts of the GOP, promulgated after the date
of bid opening, a contract price adjustment shall be made or appropriate relief shall
be applied on a no loss-no gain basis.

48. Certificates of Completion and Acceptance

48.1 The issuance of a Certificate of Completion shall be subject to the


provisions of DPWH DO 99, series of 2015.

a. Upon receipt of notice from the contractor that the project is


completed, the HOPE shall instruct its Inspectorate Team to conduct
an inspection of the project and to submit its Completion Inspection
Report within fifteen (15) days, indicating any construction
defects/deficiencies detected and the corresponding measures that
must be taken by the contractor to correct them. If no
defects/deficiencies are detected, the report is considered as the
Final Completion Inspection Report.

b. Based on the Inspection Report, the HOPE shall issue to the


Contractor a Notice of Defects/Deficiencies and Required Corrective
Repair Works, with the instructions for the Contractor to commence
the repair works within seven (7) days and to complete the works
within thirty (30) days.

c. Upon receipt of advice from the Contractor that the defects and
deficiencies indicated in the said Notice have been corrected, the
HOPE shall instruct the Inspectorate Team to conduct an inspection
of the project and to submit its Completion Inspection Report within
seven (7) days. If the report shows that the defects/deficiencies
have been satisfactorily corrected, the report is considered as the
Final Completion Inspection Report. Otherwise, the process is
repeated until the noted defects/deficiencies have been satisfactorily
corrected.

d. Upon the receipt of the Final Completion Inspection Report from the
Inspectorate Team, the HopE shall issue the Certificate of
Completion of the project, certifying that the Project has been
satisfactorily completed as of the date indicated in the Final
Inspection Report.

48.2 The Certificate of Acceptance shall be issued by the HoPE at the end of the
one-year Defects Liability period, after all defects/deficiencies, if any, shall
have been repaired by the Contractor to the satisfaction of the same
Inspectorate Team of the Procuring Entity mentioned above and upon
submission of the Warranty Certificate by the Contractor in accordance with

19ME0143
the provisions of GCC Clause 12.The issuance of a Certificate of Acceptance
shall be subject to the provisions of DPWH DO 99, series of 2015.

a. Upon receipt of notice from the Contractor that the project is ready
for inspection after the one-year Defects Liability Period from the
issuance of the Certificate of Completion, the HoPE shall instruct its
Inspectorate Team to conduct an inspection of the project and to
submit its Inspection Report within fifteen (15) calendar days,
indicating any construction defects/deficiencies detected and the
corresponding measures that must be taken by the Contractor to
correct them. If no defects/deficiencies are detected, the report is
considered as the Final Acceptance Inspection Report.

b. Based on the Inspection Report, the HoPE shall issue to the


Contractor a Notice of Defects/Deficiencies and Required Corrective
Repair Works, with the instructions for the Contractor to commence
the repair works within seven (7) calendar days and to complete the
works within ninety (90) days.

c. Upon receipt of advice from the contractor that the


defects/deficiencies in the said Notice have been corrected, the
HoPE shall instruct the Inspectorate Team to conduct an inspection
of the project and to submit its Acceptance Inspection Report within
seven (7) days. If the report shows that the defects/deficiencies
have been satisfactorily corrected, the report is considered as the
Final Acceptance Inspection Report. Otherwise, the process is
repeated until the noted defects/deficiencies have been satisfactorily
corrected.

d. Upon the receipt of the Final Acceptance Report, the Head of the I0
shall issue the Certificate of Acceptance.

49. Taking Over

The Procuring Entity shall take over the Site and the Works within seven (7) days
from the date the Procuring Entity’s Representative issues a Certificate of
Acceptance.

50. As-Built Drawings and Operating and Maintenance Manuals

50.1 If As-Built Drawings and/or Operating and Maintenance Manuals are


required, the Contractor shall supply them by the dates stated in the SCC.

If the Contractor does not supply the said Drawings by the date stated in the SCC, or if they
do not receive the approval of the Procuring Entity’s Representative, the Procuring Entity’s
Representative shall withhold the amount stated in the SCC from payments due to the
Contractor.

19ME0143
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
SARANGANI
DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE XII
Alabel, Sarangani Province

Contract ID No.: 19ME0143


Contract Name: Construction of Multi-Purpose Building Public
Market at Maitum;
Location: Maitum, Sarangani Province

SPECIAL CONDITIONS OF CONTRACT


GCC Clause

1.19 The Intended Completion Date is _______________.

1.24 The Procuring Entity is DPWH-Sarangani District Engineering Office.

1.25 The Procuring Entity’s Representative is JONATHAN G. BANTUG,


District Engineer.
1.26 The Site is located at Maitum, Sarangani Province and is defined in
drawings No. _____________.

List here locations of other Sites, if any.


1.30 The Start Date is seven (7) calendar days from the issuance of the Notice to
Proceed.
1.33 The Works consist of:

a. BICWOPLC – Buildings: Construction-without Piles-Low Rise-Concrete


(Frame) (1 to 5 Storeys)

b. BICWPHCCP – Buildings: Construction-with Piles-High Rise-Concrete


(Frame)-Cast-in-Place Piles

c. BICWPLCCP – Buildings: Construction-with Piles-Low Rise-Concrete


(Frame)-Cast-in-Place Piles

d. BICWPHCDP – Buildings: Construction-with Piles-High Rise-Concrete


(Frame)-Driven Piles

e. BICWPLCDP – Buildings: Construction-with Piles-Low Rise-Concrete


(Frame)-Driven Piles

f. BICWOPHC – Buildings: Construction-without Piles-High Rise-Concrete


(Frame)

g. BIH – Buildings: Industrial Plant – High Rise

19ME0143
h. BIL – Buildings: Industrial Plant – Low Rise

i. BIM – Buildings: Industrial Plant – Medium Rise

2.2 No Further Instructions.

5.1 The Procuring Entity shall give possession of all parts of the Site to the
Contractor upon the issuance of NTP.
6.5 The Contractor shall employ the following Key Personnel:

Project Manager: ___________________________________________

Project Engineer: ___________________________________________

Materials Engineer: _________________________________________

Foreman :_________________________________________________

(List key personnel by name and designation)


7.4 c No further instructions.

8.1 No further instructions.

8.3 No further instructions.

10. The Site Investigation Reports are: [if applicable]

12.3 No further instructions.

12.5 Permanent Structures: Fifteen (15) years

Buildings of types 4 (steel, iron, concrete, or masonry construction with walls,


ceilings, and permanent partitions of incombustible fire resistance) and 5
(steel, iron, concrete, or masonry construction), steel and concrete bridges,
flyovers, concrete aircraft movement areas, ports, dams, diversion tunnels,
causeways, wharves, piers, dikes, filtration and treatment plants, sewerage
systems, power plants, transmission and communication towers, railway
system, and other similar structures.

22.2 The Arbiter is: Construction Industry Arbitration Commission.


Makati, City
29.1 No dayworks are applicable to the contract.

31.1 The Contractor shall submit the Program of Work to the Procuring Entity’s
Representative within Seven (7) days of delivery of the Notice of Award.

31.3 The period between Program of Work updates is Thirty (30) days.

The amount to be withheld for late submission of an updated Program of


Work is [insert amount].

19ME0143
34.3 The Funding Source is the Government of the Philippines.

FY 2019 DPWH Local Infrastructure Program


39.1 The amount and schedule of the advance payment is 15% of the Contract
Price to be recouped every progress billing.
40.2 Materials and equipment delivered on the site but not completely put in place
shall be included for payment.
50.1 The date by which Operating and Maintenance Manuals are required is not
applicable.
The date by which “As-Built Drawings” are required is 30 days upon issuance
of the Certificate of Completion.

50.2 The amount to be withheld for failing to supply the As-Built Drawings and/or
Operating and Maintenance Manuals by the date required is 10% of the
Contract Price.

19ME0143
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
SARANGANI
DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE XII
Alabel, Sarangani Province

Contract ID No.: 19ME0143


Contract Name: Construction of Multi-Purpose Building Public
Market at Maitum;
Location: Maitum, Sarangani Province

Section VIII. Specifications

1. DPWH Standards

The DPWH Standard Specifications for Public Works and Highways (“Blue Book”) shall be
the main basis for the standards and codes to be met by the goods and materials to be
furnished and work performed or tested for the Contract. In particular, Volume II of the
Blue Book shall be used if the Contract pertains to Highways, Bridges and Airports.
Volume III of the Blue Book shall be used if the Contract pertains to Buildings, Flood
Control and Drainage, or Water Supply. The Blue Book incorporates standard of the
American Society for Testing and Materials (ASTM), and American Concrete Institute
(ACI), among others, pertaining to construction.

The Procuring Entity shall use the Standard Pay Items in the Project and Contract
Management Application (PCMA) in drawing up the Specifications.

2. Modifications of Standard

2.1 Modifications of and additions to standards and codes as stated in the DPWH
Standard Specifications for Public Works and Highways, if any, shall be included in
the enclosed Supplemental Specifications, which is part of these Bidding Documents.

2.2 Entries in the Supplemental Specifications are numbered to coincide with the
numbering of items in the DPWH Standard Specifications for Public Works and
Highways.

19ME0143
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
SARANGANI
DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE XII
Alabel, Sarangani Province

Contract ID No.: 19ME0143


Contract Name: Construction of Multi-Purpose Building Public
Market at Maitum;
Location: Maitum, Sarangani Province

Section VII. Drawings

Insert here a list of approved Drawings for the Contract. The actual Drawings, including Site
plans, shall be attached to this Section or annexed in a separate folder.

19ME0143
ANNEX II-1.1J
Section X. Bill of Quantities
1. The Bill of Quantities (BOQ) contains the following parts:
a. BOQ for each Part of the Contract, using Form DPWH-INFR-17.
b. Summary of Bid Prices for all Parts of the Contract, using Form DPWH-INFR-
18.

2. For the BOQ for each Part of the Contract, the Bidder shall not change the entries under
Pay Item No. (Column 1), Pay Item Description (Column 2), Unit (Column 3), and
Quantity (Column 4) in the Bill of Quantities, which are set by the Procuring Entity. For
each pay item in the BOQ, the Bidder shall indicate its unit bid price in words and in
figures (P) in Column 5, and its total bid price in Column 6 (Column 4 x Column 5)

3. For the Summary of Bid Prices, the Bidder shall not change the entries and Part No.
(Column 1) and Part Description (Column 2), which are provided by the Procuring Entity.
The Bidder shall indicate the Total Amount (Column 3) for each Part No. at the Total of
All Amounts at the bottom.

4. The Procuring Entity shall use the Standard Pay Items in the Project and Contract
Management Application (PCMA) in preparing the BOQ.

19ME0143
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
SARANGANI
DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE XII
Alabel, Sarangani Province

Contract ID No.: 19ME0143


Contract Name: Construction of Multi-Purpose Building Public
Market at Maitum;
Location: Maitum, Sarangani Province

BILL OF QUANTITIES
Part No. ___________ Part Description: ___________

Pay
Description Quantity Unit Unit Price (Pesos) Amount (Pesos)
Item
No.
B.3 Permits and Lumpsum Lumpsum In words: Pesos In figures: Php
Clearances _________________________ ____________________

_________________________ ____________________
In figures: Php
________________________

B.5 Project Billboard/ 1.00 Each In words: Pesos In figures: Php


Signboard _________________________ ____________________

_________________________ ____________________
In figures: Php
________________________

B.7 Occupational Lumpsum Lumpsum In words: Pesos In figures: Php


(2) Safety and Health _________________________ ____________________
Program
_________________________ ____________________
In figures: Php
________________________

Sub Total for this page In words: Pesos


____________________

____________________
In figures: Php
____________________

Page 1 of 6

19ME0143
Pay
Description Quantity Unit Unit Price (Pesos) Amount (Pesos)
Item
No.
B.9 Mobilization/ Lumpsum Lumpsum In words: Pesos In figures: Php
Demobilization ________________________ ____________________

________________________ ____________________
In figures: Php
________________________

801 Removal of Lumpsum Lumpsum In words: Pesos In figures: Php


(1) Structures and ________________________ ____________________
Obstruction
________________________ ____________________
In figures: Php
________________________

803 Structure 1,028.40 Cu.m. In words: Pesos In figures: Php


(1)a Excavation ________________________ ____________________

________________________ ____________________
In figures: Php
________________________

804 Embankment from 620.80 Cu.m. In words: Pesos In figures: Php


(1)a Structure ________________________ ____________________
Excavation
________________________ ____________________
In figures: Php
________________________

804 Gravel Fill 144.88 Cu.m. In words: Pesos In figures: Php


(4) ________________________ ____________________

________________________ ____________________
In figures: Php
________________________

Sub Total for this page In words: Pesos


____________________

____________________
In figures: Php
____________________

Page 2 of 6

19ME0143
Pay
Description Quantity Unit Unit Price (Pesos) Amount (Pesos)
Item
No.
900 Reinforced 699.99 Cu.m. In words: Pesos In figures: Php
(7) Concrete ________________________ ____________________

________________________ ____________________
In figures: Php
________________________

1000 Soil Poisoning 32.00 L. In words: Pesos In figures: Php


(1) ________________________ ____________________

________________________ ____________________
In figures: Php
________________________

1001 Sewer Line Works Lumpsum Lumpsum In words: Pesos In figures: Php
(8) ________________________ ____________________

________________________ ____________________
In figures: Php
________________________

1001 Septic Vault Lumpsum Lumpsum In words: Pesos In figures: Php


(11) (Concrete/CHB) ________________________ ____________________

________________________ ____________________
In figures: Php
________________________

1002 Plumbing Fixtures Lumpsum Lumpsum In words: Pesos In figures: Php


(4) ________________________ ____________________

________________________ ____________________
In figures: Php
________________________

Sub Total for this page In words: Pesos


____________________

____________________
In figures: Php
____________________

Page 3 of 6

19ME0143
Pay
Description Quantity Unit Unit Price (Pesos) Amount (Pesos)
Item
No.
1002 Cold Water Lines Lumpsum Lumpsum In words: Pesos In figures: Php
(24) ________________________ ____________________

________________________ ____________________
In figures: Php
________________________

1006 Flush Door 1.94 Sq.m. In words: Pesos In figures: Php


(2) ________________________ ____________________

________________________ ____________________
In figures: Php
________________________

1012 Glass and Glazing Lumpsum Lumpsum In words: Pesos In figures: Php
(6) ________________________ ____________________

________________________ ____________________
In figures: Php
________________________

1027 Cement Plaster 1,880.62 Sq.m. In words: Pesos In figures: Php


(1) Finish ________________________ ____________________

________________________ ____________________
In figures: Php
________________________

1043 PVC Doors and 12.04 Sq.m. In words: Pesos In figures: Php
(1) Frames ________________________ ____________________

________________________ ____________________
In figures: Php
________________________

Sub Total for this page In words: Pesos


____________________

____________________
In figures: Php
____________________

Page 4 of 6

19ME0143
Pay
Description Quantity Unit Unit Price (Pesos) Amount (Pesos)
Item
No.
1046 150mm CHB Non 369.05 Sq.m. In words: Pesos In figures: Php
(2) Loading (including ________________________ ____________________
a2 Reinforcing Steel)
________________________ ____________________
In figures: Php
________________________

1051 Railing Lumpsum Lumpsum In words: Pesos In figures: Php


(6) ________________________ ____________________

________________________ ____________________
In figures: Php
________________________

1100 Conduits, Boxes & Lumpsum Lumpsum In words: Pesos In figures: Php
(10) Fittings (Conduit ________________________ ____________________
Works/Conduit
Rough-In) ________________________ ____________________
In figures: Php
________________________

Sub Total for this page In words: Pesos


____________________

____________________
In figures: Php
____________________

Grand Total In words: Pesos


____________________

____________________
In figures: Php
____________________

Page 5 of 6

19ME0143
Contract ID No.: 19ME0143
Contract Name: Construction of Multi-Purpose Building Public
Market at Maitum;
Location: Maitum, Sarangani Province

Submitted by:

____________________________________________ Date: _____________


Name and Signature of Bidders, Representative
_____________________________________________
Position
_____________________________________________
Name of Bidder

Approved Budget Cost (ABC) Php 19,800,000.00


Calendar Days 180 Page 6 of 6

19ME0143
Contract ID No.: 19ME0143
Contract Name: Construction of Multi-Purpose Building Public
Market at Maitum;
Location: Maitum, Sarangani Province

SUMMARY OF BID PRICES


(All Parts of Bill of Quantities of BOQ)

Instruction for completing the Summary of Bid Prices:


1. Part No. – Enter the "Part No" for each section of the BOQ where unit prices are entered.
2. Part Description – Enter the "Part Description" corresponding to the "Part No".
3. Total Amount-Enter the "Total Amount" in Pesos for all pages having the same "Part
Description".
Part No. Part Description Total Amount

Total of Amounts

Total of All Amounts in Words:


Pesos ________________________________________________________
____________________________________________________________
and ______________________centavos.

Name ____________________________ in the capacity of _________________________


Signed ___________________________ Date ____________________________________
Duly authorized to sign the Bid for and on behalf of ______________________________
__________________________________________________________________________
Page 1 of 1

19ME0143
ANNEX II-1.1K
Section XI. Bidding Forms

The Bidder shall use the Bidding Forms (BFs) listed below in preparing its Bid and, in case it is
awarded the contract, in preparing the documents required to perfect the contract.

DPWH-INFR-05: Contractor’s Confidential Application Statement for Registration (CCASR)

DPWH-INFR-06: Contractor’s Registration Certificate (CRC)

DPWH-INFR-07: Contractor’s Information (CI)

DPWH-INFR-09: Bid Form

DPWH-INFR-10: Form of Bid Security: Bank Guarantee

DPWH-INFR-11: Form of Bid Security: Irrevocable Letter of Credit

DPWH-INFR-12: Form of Bid Securing Declaration

DPWH-INFR-13: Contractor’s Organizational Chart for the Contract

DPWH-INFR-14: List of Contractor’s Key Personnel to be Assigned to the Contract, with their
Qualification and Experience Data

DPWH-INFR-15: List of Contractor’s Equipment Units to be Assigned to the Contract,


Supported by Certificates of Availability

DPWH-INFR-16: Sworn Statement Required by IRR Section 25.2b)iv)

DPWH-INFR-17: Bill of Quantities (BOQ)

DPWH-INFR-18: Summary of Bid Prices

DPWH-INFR-19: Cash Flow by Quarter

DPWH-INFR-20: Bidder’s Checklist of Requirements for Its Bid, Including Technical and
Financial Proposals Requirement for Bidders

DPWH-INFR-43: Performance Security: Irrevocable Letter of Credit

DPWH-INFR-44: Performance Security: Bank Guarantee

DPWH-INFR-45: Construction Methods

Page 1 of 2

19ME0143
DPWH-INFR-46: Construction Schedule in the form of PERT/CPM or Precedence Diagram
and Bar Chart with S-Curve and Cash Flow

DPWH-INFR-47 Manpower Schedule

DPWH-INFR-48: Major Equipment Utilization Schedule

DPWH-INFR-49: Construction Safety and Health Program

DPWH-INFR-50: Checklist of Contract Documents and Supporting Documents

DPWH-INFR-51: Form of Contract Agreement

The content of each of these forms is given in the attached folder marked “ANNEX IIB –
Standard Bidding Forms.” The bidder may download these forms from the DPWH
website. The bidder may also obtain from the Procuring Entity hard copies of these forms as
part of the BDs for the contract.

Page 2 of 2

19ME0143
Contract ID No.: 19ME0143
Contract Name: Construction of Multi-Purpose Building Public
Market at Maitum;
Location: Maitum, Sarangani Province

Bidding Form
Date: _________________

To: DPWH- Sarangani District Engineering Office


Address: Kawas, Alabel, Sarangani Province

We, the undersigned, declare that:

(a) We have examined and have no reservation on the Bidding Documents (BDs), including
Supplemental Bid/Bulletins (Addenda), for the above stated contract;

(b) We offer to execute the Works for this Contract in accordance with the said BDs,
including Bid Data Sheet, General and Special Conditions of Contract, Specifications and
Drawings therein;

(c) We present our Bid to execute the Works, consisting of our Technical Proposal (Annex
“A”) and our Financial Proposal (“Annex B”);

(d) Our Technical Proposal includes the following required documents:

(1) Bid Security in the required form, amount and validity period, using Form DPWH-
INFR- 09, 10 or 11, as applicable (Annex “A-1”)
(2) Organizational Chart for the Contract, using DPWH-INFR-13 (Annex “A-3”)
(3) Contractor’s Certification on Key Personnel for the Contract, with the Key
Personnel’s Affidavits of Commitment to Work on the Contract, using Form DPWH-
INFR-14 (Annex “A-4”)
(4) List of Contractor’s Major Equipment Pledged for the Contract, using Form DPWH-
INFR-15 (Annex “A-5”)
(5) Omnibus Sworn Statement required under RA 9184-IRR Sec. 25.2b)iv), using Form
DPWH-INFR-15 (Annex “A-6”)

(e) Our Financial Proposal includes the following required documents:

(1) Bid Form (Annex “B-1”)


(2) Bid prices in the Bill of Quantities Form, using Forms DPWH-INFR-16 and 17
(Annex “B-2”)
(3) Detailed Estimates (Annex “B-3”)
(4) Cash Flow by quarter, using Form DPWH-INFR-18 (Annex “B-4”)

DPWH-INFR-09-2016 Page 1 of 2

19ME0143
(f) The total price of our Bid for this Contract based on the unit prices in the said Bill of
Quantities, excluding any discounts offered in item (g) below, is: total Bid price in words
and in figures;

(g) The discounts we offer and the methodology for their application for this Contract are:
__________________________.

(h) Our Bid shall be valid for a period of _____________________days after the date fixed
for the opening of bids in accordance with the Bidding Documents, and it shall remain
binding upon us and may be accepted by you at any time before the expiration of that
period;

(i) If our Bid is accepted and we receive from you a Notice of Award, we commit, within
ten (10) calendar days after our receipt of the said Notice, (1) submit to you the
required Performance Security and other documents prescribed in the Bidding
Documents, and (2) to sign the Contract Agreement;

(j) We understand that, if the contract is awarded to us, this Bid, together with your
written acceptance thereof through your Notice of Award, shall constitute a binding
contract between us, until a formal Contract Agreement is prepared and executed;

(k) We understand that you are not bound to accept the Lowest Calculated Bid or any other
Bid that you may receive; and

(l) We acknowledged that failure to sign each page of this Form of Bid and the
accomplished Bill of Quantities shall be ground for the rejection of our Bid.

(m) We likewise certify/confirm that the undersigned is the duly authorized representative of
the Bidder, and granted full power and authority to do, execute and perform any and all
acts necessary to participate, submit the Bid, and to sign and execute the appropriate
contract documents for the abovementioned Contract.

Name:
In the capacity of:
Signed:
Duly authorized to sign the Bid for and on behalf of:
Date: ________________________

DPWH-INFR-09-2016 Page 2 of 2

19ME0143
Contract ID No.: 19ME0143
Contract Name: Construction of Multi-Purpose Building Public
Market at Maitum;
Location: Maitum, Sarangani Province

PERFORMANCE SECURITY: BANK GUARANTEE


To : Name of Head of the Procuring Entity
Address

WHEREAS, _______Name and Address of Contractor_______, hereinafter called “the


Contractor,” has undertaken to enter into a contract with you to execute __Contract ID and
Name_, hereinafter called “the Contract;”

WHEREAS, you have stipulated in the said Contract that the Contractor shall furnish you
with a Bank Guarantee by a recognized bank for the sum specified therein as Performance
Security for compliance with his obligations in accordance with the Contract; and
WHEREAS, we have agreed to give the Contractor such a Bank Guarantee;

NOW THEREFORE, we hereby affirm that we are the Guarantor and responsible to you, on
behalf of the Contractor, up to a total of amount of guarantee, and we undertake to pay
you, upon your first written demand and without cavil or argument, any sum or sums within
the limits of amount of guarantee as aforesaid without your needing to prove or to show
grounds or reasons for your demand for the sum specified therein.

We hereby waive the necessity of your demanding the said debt from the Contractor before
presenting us with the demand.
We further agree that no change or addition to or other modification of the terms of the
Contract to be performed thereunder or of any of the Contract documents which may be
made between you and the Contractor shall in any way release us from any liability under
this guarantee, and we hereby waive notice of any such change, addition or modification.

The right to institute action on this guarantee pursuant to Act No. 3688 of any individual,
firm, partnership, corporation and association supplying the Contractor with labor and
materials for the prosecution of the works is hereby acknowledged and confirmed.

This guarantee shall be valid until the date of issuance to the Contractor of your Certificate
of Acceptance of the completed Contract works after the end of the one-year Defects
Liability Period of the Contract and upon the submission of the required Warranty Security.

SIGNATURE AND SEAL OF THE GUARANTOR _________________________________

NAME OF BANK _________________________________

ADDRESS _________________________________

DATE _____________________________

DPWH-INFR-44-2016 Page 1 of 1

19ME0143
Contract ID No.: 19ME0143
Contract Name: Construction of Multi-Purpose Building Public
Market at Maitum;
Location: Maitum, Sarangani Province

FORM OF BID SECURITY: BANK GUARANTEE

WHEREAS, Name of Bidder, hereinafter called “the bidder”, has submitted its bid dated
____________ for the Contract ID and Name, hereinafter called “the Bid”.

KNOW ALL MEN by these presents that We, Name of Bank of Name of Country, having our
registered office at __________________________, hereinafter called “the Bank”, are
bound unto Name of Procuring Entity, hereinafter called “the Entity”, the sum of amount in
words and figures for which payment well and truly to be made to the said Entity the Bank
binds itself, its successors and assigns by these presents.

SEALED with the Common Seal of the said Bank this _____ day of __________ 20________.

THE CONDITIONS of this obligation are that:

1) If the Bidder withdraws the Bid during the period of bid validity specified in
the Form of Bid; or

2) If the Bidder does not accept the correction of arithmetical errors of its bid
price in accordance with the Instructions to Bidder; or

3) If the Bidder having been notified of the acceptance of the Bid and award of
contract to it by the Entity during the period of bid validity:

a) Fails or refuses to submit the requirements for and to execute the Form
of Contract in accordance with the Instructions to Bidders, if required; or

b) Fails or refuses to furnish the Performance Security in accordance with


the Instruction to Bidders;

We undertake to pay to the Entity up to the above amount upon receipt of its first written
demand, without the Entity having to substantiate its demand, provided that in its demand,
provided that in its demand the Entity will note that the amount claimed by it is due to the
occurrence of any one or combination of the three (3) conditions stated above.

The Guarantee will remain in force up to a period of ___________________ days after the
opening of bids as stated in the Instructions to Bidders or as it may be extended by the
Entity, notice of which extension(s) to the Bank is hereby waived. Any demand in respect of
this Guarantee should reach the Bank within the said period.

Name and Signature of Bank’s Authorized Signatory Date: ____________


Position

DPWH-INFR-10-2016 Page 1 of 1

19ME0143
Contract ID No.: 19ME0143
Contract Name: Construction of Multi-Purpose Building Public
Market at Maitum;
Location: Maitum, Sarangani Province

FORM OF BID SECURITY: IRREVOCABLE LETTER OF CREDIT

Date: _____________

JONATHAN G. BANTUG
District Engineer
Department Public Works and Highways
Sarangani District Engineering Office
Kawas, Alabel, Sarangani Province
Tele Fax No. 083-554-2530

Irrevocable Letter of Credit No. _______________


For_____(Contract Number and Name)________________________________

WHEREAS, _____(Name of Bidder)_____, hereinafter called “Bidder” has undertaken to


submit to you a bid for the above stated Contract, and whereas you have stipulated in the
Instructions to Bidders for the said Contract that the Bidder shall furnish you with an
irrevocable standby Letter of Credit for a sum specified therein as Bid Security for the
faithful compliance of the obligations of the Bidder.

WHERAS, the Conditions of this obligation are that:

1) If the Bidder withdraws the Bid during the period of bid validity specified in the
Form of Bid; or

2) If the Bidder does not accept the correction of arithmetical errors of its bid price
in accordance with the Instructions to Bidder; or

3) If the Bidder having been notified of the acceptance of the Bids and award of
contract to it by the Entity during the period of bid validity.

a) Fails or refuses to submit the requirements for and to execute the Form
of Contract in accordance with the Instructions to Bidders; or
b) Fails or refuses to furnish the Performance Security in accordance with
the Instructions to Bidders;

We undertake to pay to the Entity up to the above amount upon receipt of its first written
demand, without the Entity having to substantiate its demand, provided that in its demand
the Entity will note that the amount claimed by it is due to the occurrence of any one or
combination of the three (3) conditions stated above.

DPWH-INFR-11-2016 Page 1 of 2

19ME0143
WHEREAS, we have agreed to guarantee this obligation of the Bidder.

THEREFORE, we hereby affirm that we are guarantors and responsible to you, on behalf of
the Bidder, up to the total amount of ___amount of guarantee_____ and we undertake to
pay you, upon first written demand declaring the Bidder to be in default under the
Instructions to Bidders and without cavil or argument, any sum or sums within the limits of
____amount of guarantee___ as foresaid, without you needing to prove or show grounds or
reasons for your demand for the sum specified therein.

This irrevocable guarantee is valid until one hundred twenty (120) calendar days after date
of opening of bids for the said Contract on ___date___.

This certification is being issued in favour of the said Contractor in connection with the
requirements of the bidding by DPWH Sarangani Engineering Office for the above-
mentioned contract. We are aware that any false statements issued by us make us liable to
perjury.

Name and Signature of Authorized


Financing Institution Officer : _________________________
Official Designation : _________________________

Concurred by:

Name and Signature of Contractor’s


Authorized Representative : _________________________
Official Designation : _________________________

Note:
The amount committed should be machine validated.

ACKNOWLEDGMENT

SUBSCRIBED and SWORN TO before me this_____ day of ____________, 20 ___,


affiant exhibited to me his/her Community Tax Certificate No. _______________ issued on
____________________ at ____________________, Philippines.

Notary Public
Until 31 December 2018
PTR No. ____________
Issued at:____________
Issued on: ___________
TIN No. ____________

Doc. No. ____________________


Page No. ____________________
Book No. ____________________
Series No. ___________________
DPWH-INFR-11-2016 Page 2 of 2

19ME0143
Contract ID No.: 19ME0143
Contract Name: Construction of Multi-Purpose Building Public
Market at Maitum;
Location: Maitum, Sarangani Province

REPUBLIC OF THE PHILIPPINES)


CITY/MUNICIPALITY OF _________________)S.S.
x------------------------------------------------------------------x

BID-SECURING DECLARATION

Invitation to Bid/Request for Expression of Interest No. ¹: [Insert reference number]


Contract ID:
Contract Name:

To: [Insert name and address of the Procuring Entity]

I/We, the undersigned, declare that:

1. I/We understand that, according to your conditions, bids must be supported by a


Bid Security, which may be in the form of a Bid-Securing Declaration.

2. I/We accept that: (a) I/we will be automatically disqualified from bidding for any
contract with any procuring entity for a period of two (2) years upon receipt of your
Blacklisting Order; and, (b) I/we will pay the acceptable fine provided under Section 6
of the Guidelines on the Use of Bid Securing Declaration, within (15) days from
receipt of the written demand by the Procuring Entity for the commission of acts
resulting to the enforcement of the bid securing declaration under Sections 23.1(b),
34.2, 40.1 and 69.1, except 69.1(f) of the IRR of RA 9184; without prejudice to other
legal action the government may undertake.

3. I/We understand that this Bid-Securing Declaration shall cease to be valid on the
following circumstances:

(a) Upon Expiration of the bid validity period, or any extension thereof pursuant
to your request;

(b) I am/we are declared ineligible or post-disqualified upon receipt of your


notice to such effect, and (i) I/we failed to timely file a request for
reconsideration or (ii) I/we filed a waiver to avail of said right;

(c) I am/we are declared as the bidder with Lowest Calculated and Responsive
Bid/Highest Rated and Responsive Bid, and I/we have furnished the
performance security and signed the Contract.

DPWH-INFR-12-2016 Page 1 of 2

19ME0143
IN WITNESS WHEROF, I/We have hereunto set my/our hand/s this ________day of
__[month]__[year]__ at [place of execution].

[Insert NAME OF BIDDER’S


AUTHORIZED REPRESENTATIVE]
[Insert signatory’s legal capacity]
Affiant

SUBSCRIBED AND SWORN to before me this_____ day of __[month]__[year]__ at


[place of execution], Philippines, Affiant/s is/are personally known to me and was/were
identified by me through competent evidence of identity as defined in the 2004 Rules on
Notarial Practice (A.M. No. 02-8-13-SC). Affiant/s exhibited to me his/her [Insert type of
government identification card used], with his/her photograph and signature appearing
thereon, with no. _____ and his/her Community Tax Certificate No. _____ issued on _____
at _____.

Witness my hand and seal this _____ day of __[month]__[year]__.

NAME OF NOTARY PUBLIC


Serial No. of Commission ________
Notary Public for _____ until _____
Roll of Attorneys No. _____
PTR No. ___, [date issued], [place issued]
IBP No. ___, [date issued], [place issued]

Doc. No. ____________________


Page No. ____________________
Book No. ____________________
Series of ___________________

Note: This must be dry-sealed.

DPWH-INFR-12-2016 Page 2 of 2

19ME0143
Contract ID No.: 19ME0143
Contract Name: Construction of Multi-Purpose Building Public
Market at Maitum;
Location: Maitum, Sarangani Province

CONTRACTOR’S ORGANIZATIONAL CHART FOR THE CONTRACT

Submit a copy of the Organizational Chart that the Contractor intends to use to execute the
Contract if awarded to it. Indicate in the chart the names of the Project Manager, Project
Engineer, Structural Engineer, Materials and Quality Control Engineer, Foremen, and other
Key Personnel, as required in the Instructions to Bidders (Bid Data Sheet). Include Sub-
Contractors, if any.

Attach the required Proposed Organizational Chart for the Contract as stated above.

Name and Signature of Bidder’s Representative Date: _____________


Position
Name of Bidder

DPWH-INFR-13-2016 Page 1 of 1

19ME0143
Contract ID No.: 19ME0143
Contract Name: Construction of Multi-Purpose Building Public
Market at Maitum;
Location: Maitum, Sarangani Province

LIST OF CONTRACTOR’S KEY PERSONNEL TO BE ASSIGNED TO THE


CONTRACT, WITH THEIR QUALIFICATION DATA

Date of Issuance

JONATHAN G. BANTUG
District Engineer
Sarangani District Engineering Office
Alabel, Sarangani Province

Dear Sir:

Supplementing our Organizational Chart for the above stated Contract, we submit, and
certify as true and correct, the following information:

1. We have engaged in the services of the following key personnel to perform the duties of
the positions indicated in the above stated Contract if it is awarded to us:

Proposed Years of Experience


Position Name Total (Similar
Similar Position
(as applicable) and Related
Project Manager

Project Engineer

Materials
Engineer
Construction
Safety Officer
Foreman
Electrical
Engineer/ Master
Electrician

2. We submit the enclosed Curriculum Vitae and Affidavit of Commitment to Work on the
Contract of these key personnel.

3. We ensure that the abovementioned personnel shall employ their best care, skill and
ability in performing the duties of their respective positions in accordance with the
provision of the Contract, including the Conditions of Contract, Specifications and
Drawings, and that they shall be personally present it the jobsite during the period of
their assignment in the Contract.

DPWH-INFR-14-2016 Page 1 of 2

19ME0143
4. In the event that we choose to replace any of the abovementioned key personnel, we
shall submit to you in writing at least fourteen (14) days before making the replacement,
for your approval, the name and bio data of the proposed replacement whose
qualification shall be equal to or better than that of the person to be replaced.

5. We understand that any violation of the above stated conditions shall be a sufficient
ground for us to be disqualified from this Contract and future biddings of the DPWH.

Very truly yours,

_________________________________________________
Name and Signature of Bidder’s Authorized Representative

DPWH-INFR-14-2016 Page 2 of 2

19ME0143
Contract ID No.: 19ME0143
Contract Name: Construction of Multi-Purpose Building Public
Market at Maitum;
Location: Maitum, Sarangani Province

LIST OF CONTRACTOR’S MAJOR CONSTRUCTION AND LABORATORY EQUIPMENT UNITS


TO BE ASSIGNED TO THE CONTRACT, SUPPORTED BY CERTIFICATION OF AVAILABILITY

Business Name : ____________________________________________


Business Address : ____________________________________________

Motor
Capacity/ Proof of/
Plate No./
Description Mode/Year Performance/ Location Condition Ownership/
No. Body
Size Lease/Purchase
No.
A. Owned
I.
II.
III.
IV.
V.
B. Leased
I.
II.
III.
IV.
V.
C. Leased Purchase
Agreements
I.
II.
III.
IV.
V.
1
Attached are copies of sales invoice/Registration Certificate from LTO.
2
Attached are the certifications from the lessors that the equipment units under B (Leased) shall be available for this contract.
3
Attached are the certifications from the vendors that the requirement units under C (Purchase Agreements) shall be available
for this contract.

Minimum major construction equipment Minimum major laboratory equipment


requirements as prescribed in Bid Data Sheet: requirement as prescribed in the Bid Data Sheet:

_____________________________ _____________________________
_____________________________ _____________________________
_____________________________ _____________________________
___________________________________________ _______________
Name and Signature of Bidder’s Authorized Representative Date
___________________________________________
Position
___________________________________________
Name of Bidder

DPWH-INFR-15-2016 Page 1 of 1

19ME0143
Contract ID No.: 19ME0143
Contract Name: Construction of Multi-Purpose Building Public
Market at Maitum;
Location: Maitum, Sarangani Province

OMNIBUS SWORN STATEMENT


AS REQUIRED BY RA 9184-IRR SECTION 25.2b)iv)

REPUBLIC OF THE PHILIPPINES)


CITY/MUNICIPALITY OF ______)S.S.

AFFIDAVIT

I, (Name of Affiant), of legal age, (Civil Status), (Nationality), and residing at (Address of
Affiant), after having been duly sworn in accordance with law, do hereby depose and state
that:
1. Select one, delete the other:
If a sole proprietorship: I am the sole proprietor or authorized representative of
[Name of Bidder] with office address at [address of Bidder];

If a partnership, corporation, cooperative, or joint venture: I am the duly authorized


and designated representative of [Name of Bidder] with office address at [address of
Bidder];
2. Select one, delete the other:
If a sole proprietorship: As the owner and sole proprietor or authorized
representative of [Name of Bidder], I have full power and authority to do, execute
and perform any and all acts necessary to participate, submit the bid, and to sign
and execute the ensuing contract for [Name of the Project] of the [Name of the
Procuring Entity] [insert “as shown in the attached duly notarized Special Power of
Attorney” for the authorized representative];
If a partnership, corporation, cooperative, or joint venture: I am granted full power
and authority to do, execute and perform any and all acts necessary to participate,
submit the bid, and to sign and execute the ensuing contract for the [Name of the
Project] of the [Name of the Procuring Entity] accompanied by the duly notarized
Special Power of Attorney, Board/Partnership Resolution, or Secretary’s Certificate,
whichever is applicable;
3. [Name of Bidder] is not “blacklisted” or barred from bidding by the Government of the
Philippines or any of its agencies, offices, corporations, or Local Government Units,
foreign government/foreign or international financing institution whose blacklisting rules
have been recognized by the Government Procurement Policy Board;
4. Each of the documents submitted in satisfaction of the bidding requirements is an
authentic copy of the original, complete, and all statements and information provided
therein are true and correct;

DPWH-INFR-16-2016 Page 1 of 3

19ME0143
5. [Name of Bidder] is authorizing the Head of the Procuring Entity or its duly notarized
representative(s) to verify all the documents submitted;

6. Select one, delete the rest:


If a sole proprietorship: The owner or sole proprietor is not related to the Head of
the Procuring Entity, members of the Bids and Awards Committee (BAC), the
Technical Working Group, and the BAC Secretariat, the head of the Project
Management Office/Implementing Unit, and the project consultants by consanguinity
or affinity up to the third civil degree;
If a partnership or cooperative: None of the officers and members of [Name of
Bidder] is related to the Head of the Procuring Entity, members of the Bids and
Awards Committee (BAC), the Technical Working Group, and the BAC Secretariat,
the head of the Project Management Office//Implementing Unit, and the project
consultants by consanguinity or affinity up to the third civil degree;
If a corporation or joint venture: None of the officers, directors, and controlling
stockholders of [Name of Bidder] is related to the Head of the Procuring Entity,
members of the Bids and Awards Committee (BAC), the Technical Working Group,
and the BAC Secretariat, the head of the Project Management Office/Implementing
Unit, and the project consultants by consanguinity or affinity up to the third civil
degree;
7. [Name of Bidder] complies with existing labor laws and standards;
8. [Name of Bidder] is aware of and has undertaken the following responsibilities as a
Bidder:

a) Carefully examine all of the Bidding Documents;

b) Acknowledge all conditions, local or otherwise, affecting the implementation of the


Contract;
c) Make an estimate of the facilities available and needed for the contract to be bid,
if any; and
d) Inquire or secure Supplemental/Bid Bulletin(s) issued for the [Name of the
Project]; and
9. [Name of Bidder] did not give or pay directly or indirectly, any commission, amount, fee,
or any form of consideration, pecuniary or otherwise, to any person or official, personnel
or representative of the government in relation to any procurement project or activity.

IN WITNESS WHEREOF, I have hereunto set my hand this _____ day of


_____,20____ at ____________, Philippines,

__________________________________
[Bidder’s Representative/ Authorized Signatory]

DPWH-INFR-16-2016 Page 2 of 3

19ME0143
SUBSCRIBED AND SWORN to before me this __ day of [month] [year] at [place of
execution], Philippines. Affiant/s is personally known to me and was identified by me
through competent evidence of identity as defined in the 2004 Rules on Notarial Practice
(A.M. No. 02-8-13-SC). Affiant exhibited to me his/her [insert type of government
identification card used], with his/her photograph and signature appearing thereon, with no.
______.

Witness my hand and seal this ___ day of [month] [year].

NAME OF NOTARY PUBLIC


Serial No. of Commission ______
Notary Public for ______ until _______
Roll of Attorneys No. _____
PTR No. __, [date issued], [place issued]
IBP No. __, [date issued], [place issued]

Doc. No. ___


Page No. ___
Book No. ___
Series of ____.

DPWH-INFR-16-2016 Page 3 of 3

19ME0143
Contract ID No.: 19ME0143
Contract Name: Construction of Multi-Purpose Building Public
Market at Maitum;
Location: Maitum, Sarangani Province

CASH FLOW BY QUARTER

Particular Total YEAR____ YEAR___


1 Q st
2 nd
Q 3 Q rd
4 Q th
1 ST
Q 2ND Q 3RD Q 4TH Q
ACCOMPLISHMENT, IN % 100.0%
CASH FLOW, IN PhP

CUMULATIVE 100.0%
ACCOMPLISHMENT, IN %
CUMULATIVE CASH FLOW,
IN PhP

Particular Total YEAR____ YEAR___


1 Q
st
2nd
Q 3 Q
rd
4 Q
th
1ST
Q 2ND Q 3RD Q 4TH Q
ACCOMPLISHMENT, IN %

CASH FLOW, IN PhP

CUMULATIVE
ACCOMPLISHMENT, IN %
CUMULATIVE CASH FLOW,
IN PhP

Submitted by:

Name and Signature of Bidder’s Representative Date: _______________


Position
Name of Bidder

DPWH-INFR-19-2016 Page 1 of 1

19ME0143
Contract ID No.: 19ME0143
Contract Name: Construction of Multi-Purpose Building Public
Market at Maitum;
Location: Maitum, Sarangani Province

PERFORMANCE SECURITY: IRREVOCABLE LETTER OF CREDIT

Date: _____________

JONATHAN G. BANTUG
District Engineer
Department Public Works and Highways
Sarangani District Engineering Office
Kawas, Alabel, Sarangani Province
Tele Fax No. 083-554-2530

Subject: Irrevocable Letter of Credit No. _______________


For _____(Contract Number and Name)_______

WHEREAS, _____(Name of Contractor)_____, hereinafter called “Contractor” has


undertaken to enter into a contract with you to execute ___(Contract ID and Name)___, and
whereas you stipulated in the said Contract that the Contractor shall furnish you with an
irrevocable standby Letter of Credit for a sum specified therein as performance Security for
the faithful compliance of the Contractor’s obligations in accordance with the Contract.

WHERAS, we have agreed to guarantee this obligation by the Contractor.

THERFORE, we hereby affirm that we are guarantors and responsible to you, on behalf of
the Contractor, up to the total amount of _____(amount of guarantee)_____ and we
undertake to pay you, upon first written demand declaring the Contractor to be in default
under the Contract and without cavil, or argument, any sum or sums within the limits of
_____(amount of guarantee)_____ as aforesaid, without you needing to prove or to show
grounds or reasons for your demand for the sum specified therein.

The right to institute action on this guarantee pursuant to Act No. 3688 of any individual,
firm, partnership, corporation and association supplying the Contractor with labor and
materials for the prosecution of the works is hereby acknowledge and confirmed.
This irrevocable guarantee is valid until the issuance by you of the Certificate of Acceptance
of the completed Contract works after the end of the one-year Defects Liability Period of the
Contract.

DPWH-INFR-43-2016 Page 1 of 2

19ME0143
This certification is being issued in favor of the said Contractor in connection with the
requirements of the bidding by DPWH Sarangani Engineering Office for the above-
mentioned contract. We are aware that any false statements issued by us make us liable to
perjury.

Name and Signature of Authorized


Financing Institution Officer : _________________________
Official Designation : _________________________

Concurred by:

Name and Signature of Contractor’s


Authorized Representative : _________________________
Official Designation : _________________________

Note:
The amount committed should be machine validated.

ACKNOWLEDGMENT

SUBSCRIBED AND SWORN to before me this_____ day of ____________, 20 ___, affiant


exhibited to me his/her Community Tax Certificate No. _______________ issued on
____________________ at ____________________, Philippines.

Notary Public
Until 31 December 20___
PTR No. ____________
Issued at:____________
Issued on: ___________
TIN No. ____________

Doc. No. _______


Page No. _______
Book No. _______
Series No. ______

DPWH-INFR-43-2016 Page 2 of 2

19ME0143
Contract ID No.: 19ME0143
Contract Name: Construction of Multi-Purpose Building Public
Market at Maitum;
Location: Maitum, Sarangani Province

PERFORMANCE SECURITY: BANK GUARANTEE


To : Name of Head of the Procuring Entity
Address

WHEREAS, _____(Name and Address of Contractor)_____, hereinafter called “the


Contractor” has undertaken to enter into a contract with you to execute ___(Contract ID
and Name)___, hereinafter called “the Contract”.

WHERAS, we have agreed to give the Contractor such a Bank Guarantee.

NOW THEREFORE, we hereby affirm that we are the Guarantor and responsible to you, on
behalf of the Contractor, up to a total amount of _____(amount of guarantee)_____ and we
undertake to pay you, upon your first written demand and without cavil or argument, any
sum or sums within the limits of _____(amount of guarantee)_____ as aforesaid, without
your needing to prove or to show grounds or reasons for your demand for the sum specified
therein.

We hereby waive the necessity of your demanding the said debt from the Contractor before
presenting us with the demand.

We further agree that no change or addition to or other modification of the terms of the
Contract to be performed thereunder or of any of the Contract documents which may be
made between you and the Contractor shall in any way release us from any liability under
this guarantee, and we hereby waive notice of any such change, addition or modification.

The right to institute action on this guarantee pursuant to Act No. 3688 of any individual,
firm, partnership, corporation and association supplying the Contractor with labor and
materials for the prosecution of the works is hereby acknowledge and confirmed.

This guarantee shall be valid until the date of issuance to the Contractor of your Certificate
of Acceptance of the completed Contract works after the end of the one-year Defects
Liability Period of the Contract.

SIGNATURE AND SEAL OF THE GUARANTOR


_____________________________________

NAME OF BANK _______________________

ADDRESS ____________________________

DATE _______________________________
DPWH-INFR-44-2016 Page 1 of 1

19ME0143

You might also like