ID ID Task Name Duration Start Finish Qtr 2, 2020 Qtr 3, 2020 Qtr 4, 2020

Mar Apr May Jun Jul Aug Sep Oct Nov


1 1 Phase 1 (Planning and Design LoRawan Gateway) 30 days Mon 02-03-20 Fri 10-04-20
2 2 Kick-Off Meeting 1 day Mon 02-03-20 Mon 02-03-20
3 3 Technical specifications determined 5 days Tue 03-03-20 Mon 09-03-20 Administrative Assistant ;Project Manager ;Senior Writers ;System Analysts ;Systems Consultant ;Vice Presid
4 4 Design plan developed 23 days Tue 10-03-20 Thu 09-04-20
8 8 Administrative Preparation 22 days Tue 10-03-20 Wed 08-04-20
12 12 Phase 2 (Preparation for installation) 60 days Mon 13-04-20 Fri 03-07-20
13 13 Preliminary Preparation 7 days Mon 13-04-20 Tue 21-04-20
14 14 Preliminary Design Review 5 days Mon 13-04-20 Fri 17-04-20
15 15 Preliminary Design Approval 2 days Mon 20-04-20 Tue 21-04-20
16 16 Equipment ordering 3 days Wed 22-04-20 Fri 24-04-20 Administrative Assistant
17 17 System Prototype 15 days Mon 27-04-20 Fri 15-05-20
22 22 Prototype Configuration 5 days Mon 18-05-20 Fri 22-05-20 Programmers ;Senior Testers ;System Analysts ;Tester
23 23 Prototype Testing 2 days Mon 25-05-20 Tue 26-05-20 Senior Testers ;Tester
24 24 Prototype Analysis 5 days Wed 27-05-20 Tue 02-06-20
28 28 System Software Configuration 23 days Wed 03-06-20 Fri 03-07-20
30 30 Phase 3 (Installation) 30 days Mon 06-07-20 Fri 14-08-20
31 31 Site Installation : Kota Jayapura 25 days Mon 06-07-20 Fri 07-08-20
48 48 Site Installation : Kabupaten Jayapura 25 days Mon 06-07-20 Fri 07-08-20
64 64 Site Installation : Kabupaten Keerom 25 days Mon 06-07-20 Fri 07-08-20
75 75 Documentation set-up for all sites 5 days Mon 10-08-20 Fri 14-08-20 Site Engineer;Chief Editor ;Senior Writers ;W
76 76 Phase 4 ( Installation follow - up) 15 days Mon 10-08-20 Fri 28-08-20
77 77 Testing and Commissioning di Kota Jayapura 5 days Mon 10-08-20 Fri 14-08-20 Programmers ;Site Engineer;Tester
78 78 Testing and Commissioning di Kabupaten Jayapura 5 days Mon 10-08-20 Fri 14-08-20 Programmers ;Site Engineer;Tester
79 79 Testing and Commissioning di Kabupaten Keerom 5 days Mon 10-08-20 Fri 14-08-20 Programmers ;Site Engineer;Tester
80 80 User Orientation 7 days Mon 17-08-20 Tue 25-08-20
85 85 Post-installation Review 4 days Wed 26-08-20 Mon 31-08-20 Project Manager ;System Analysts ;Sys
86 86 System Acceptance 1 day Tue 01-09-20 Tue 01-09-20 Project Manager ;Vice President - Man
87 87 Phase 5 (Masa Garansi) 60 days Wed 02-09-20 Tue 24-11-20
88 88 Maintenance 60 days Wed 02-09-20 Tue 24-11-20 Adm