Step Activity Rules What can cause Result of cause Preventative measures Controls (test, checks)
No injury/damage (injury/damage) (tools, PPE, equipment)
Safety Health Finan.
Scaffold may only be Scaffold can collapse; Injuries to all parts of the Always use scaffold safe or Weekly inspections to be
erected, altered or scaffold planks/boards body, damage to property unsafe for use signs; done and a register to be
dismantled under the may break or give way; employees must wear safety kept up to date.
supervision of a employees may fall off belts. Kick boards must be Inspections must also be
competent person scaffold placed on all scaffolds to done after bad weather
appointed in writing prevent items falling off; only (rain, strong wind) or after
use scaffold if competent any part of the scaffold
person has inspected the has been altered and a
scaffold and a safe to use sign safe to use sign displayed
displayed
2 Scaffold built on gravel Lose or weekly braced Injuries to all parts of the Report unsafe scaffolds to Charge hand, supervisor
or sand must have sole scaffolds will collapse. body and damage to supervisor immediately; Do not to do inspections
plates. Base jacks must Jacks extended too far property work on an unsafe scaffold.
not extend more than do not make sufficient Only use scaffolds if a safe to
400mm. Scaffold contact with standards use sign is displayed.
standards must be and therefore cannot
secure and braced. All hold the weight.
scaffold components Damaged scaffold
must be in good components can break /
condition, free of collapse.
corrosion and not
damaged
3 Scaffolding shall be Employees may be Injury to all parts of body Safe and convenient access for Supervisor must plan
erected in such a way so injured when attempting all employees to their place of access to site areas before
as not to obstruct any to gain access work must remain a priority erecting scaffolding
through way or access
ladder
4 Dangerous protruding Sharp edges and Head eyes and leg injuries Try to eliminate protruding Supervisor to be aware of
ends of scaffold must be protruding edges. edges – if not possible warning the problem and control it
identified clearly to warn signs and banners must be put
employees of the in place to warn employees
danger.
5 Do not allow material Can get entangled with Injury to employees and Crane operator and Banksman Supervisor to control
closer than 2m from scaffold structure and damage to property. to control all lifting procedures
94009
RISK ASSESSMENT: SCAFFOLDING
2003/06
94009