PT Vs SOP 17 Tooling Repair
PT Vs SOP 17 Tooling Repair
PT Vs SOP 17 Tooling Repair
INDONESIA
1. Scope
2. Purpose
3. Responsibilities
4. Procedure
Internal Requisition
QC will determine if the mold repairing condition will have any impact
to product critical dimension.
(a) If yes - QC will inform customer.
(b) Otherwise, just proceed.
After confirmation from PPC, then mold can be down for repair based
on lead time and Tooling section shall ensure strict compliance to
agreed schedule.
After mold repairing, Tooling Sect. will update and inform Injection
Production, and PPC for re-scheduling Up Mold / Run production.
PPC will issue a Mold change list refer to schedule, and Injection
production will up the mold to test run. Injection Production and
Tooling Section, will monitor together the mold condition, with QC
check the parts for acceptance (esp. critical dimensions) before
continuing mass production.
Customer will request for mold modification / repair, esp. when found
products mot meeting customer requirements. Customer will then
request (email, discussion & etc.) for repair and specific points for
improvement to related dept., such as QC section.
Related section will submit the affected stock quantity to PPC, and
PPC will determine the cut off stock, for customer information. Refer
to delivery order from customer.
Tooling section determines modification area and lead time, then pass
this information to Sales/Marketing Dept. and Engineering Dept.
Sales/Marketing Dept. will then inform customer for cost and lead
time. After approval of the quotation from customer, the modification
of mold will start (with info rom Sales / Marketing Dept.)
Before start mass production, Engineering Dept. shall submit the part
after modification to customer. Customer will check the part/product
after modification. After getting confirmation & approval from
customer, mold can starting to mass production.
ECN
Engineering Dept. will raise ECN to all related Dept. cut off the old
stock before modification and discussion with customer for cut off
stock part.
5. Related Document
Tooling Repair
Tooling Modification
Alteration Modification Customer
ECN (Engineering Change Notice)
Reject
Tooling Sect. immediate
QC Check
action for improvement
Accept
Tooling Customer
Tooling Section will PPC issueswill confirm
schedule for lead time
judgeand stock cut off
QC
repair the Mold Tooling
Submission
Mold
Running period
Section
trial will start
repairrepair
Production
to
after
Customer
Check
PT VS TECHNOLOGY
INDONESIA
Reject
OK
Reject
OK
NG
Feedback and discussion
Eng.&
with Customer
Tooling Dept.
OK review
NG
Tooling Dept. takes
immediate action for
improvement
OK