HITUNGAN VOLUME KANTOR IAIN WALISONGO DAKULTAS USHULUDIN SEMARANG

No URAIAN PEKERJAAN / PERHITUNGAN VOLUME SATUAN

I PEKERJAAN PERSIAPAN
1 Pemebersihan Lapangan

Vol = 34.00 x 18.75 637.500 m2

2 Pagar sementara
Vol = (34 x 2)+(18.75 x 2) 105.500 m'

3 Bowplang dan pengukuran


Vol = (12 x 4)+(5 x 2)+(6 x 2)+(9 x 2)+(1 x 8)+(0.75 x 2) 97.500 m'

4 Direksi Kit 1.000 ls


5 Bedeng / Gudang 1.000 ls
6 Air kerja / Listrik 1.000 ls
7 Mobilisasi Tenaga Alat 1.000 ls

II PEKERJAAN TANAH DAN PASIR


1 Galian Pondasi
- Galian pondasi batu kali

Panjang galian :
(9 x 7)+(12 x 6)+(6 x 4)+(3 x 4)+(3,5 x 3)+(1,75 x 2)+(5,25)
No URAIAN PEKERJAAN / PERHITUNGAN VOLUME SATUAN
=190,25 m'
Volume Galian = (1+1.3) x 1.2 x 0.5 x 190,25 262.545 m3

-Pondasi Footplat

Jumlah = 38 Buah
Vol.Galian = 1.2 x 1.2 x 2.2 x 38 120.384 m3

Total Galian Tanah 382.929 m3


-pondasi bt kali = 262.545 m3
- Footplat = 120.384 m3
382.929 m3

2 Urugan Tanah Kembali


Vol. Urg Kembli = galian tanah - pondasi footplat
Total galian tanah = 382.929

Volume = 382,929 - 120,384


262.545 262.545 m3

3 Urugan Pasir
-pondasi bt. kali
Panjang Pondasi = 190.25 m'
Volume = 0.1 x 1 x 190,25
= 19.025 m3

-Footplat
No URAIAN PEKERJAAN / PERHITUNGAN VOLUME SATUAN
Jumlah = 38 bh
Volume = 0.1 x 1.2 x 1.2 x 38
5.472 m3
Total Urugan Pasir
-pondasi bt. Kali = 19.025 m3
= 5.472 m3
24.497 m3 24.497 m3

III. PEKERJAAN BETON


1 Sloof beton 20x30

Panjang = 231.75 m'


Volume = 231,75 x 0.2 x 0.3
= 13.905 m3
Bekisting = 0.3 x 231,75 x 2
139.05 m2

penulangan untuk tumpuan dan lapangan

tulangan Pokok 6-Æ 12


= 6 x 231,75 = 1390.5 m'
=1390,5 x 0.888 = 1234.764 kg
sengkang Æ 8 - 100
=(231,75/0.125)x1 = 1854 m'
=1854 x 0.395 = 732.33 kg
No URAIAN PEKERJAAN / PERHITUNGAN VOLUME SATUAN

Jumlah = 1234,764 + 723,33 1958.094 kg

2 Balok Lantai beton 40x20

Panjang = 218.25 m'


Volume = 0.2 x 0.4 x 218.25
= 17.46 m3
Bekisting = (0,4 + 0,2) x 2 x 218,25
= 261.9 m3

Penulangan untuk tumpuan dan lapangan

Tulangan pokok 2-Æ 12


=2 x 218,25 = 436.5 m'
=436,5*0.888 = 387.612 Kg
Tulangan pokok 5-Æ 16
=5 x 218,25 = 1091.25 m'
=1091,25*1,578 = 1721.9925 Kg
Sengkang Æ 8-100
=(218.25/0.125) x 1,2 = 18856.8 m'
=18856,8*0.395 = 7448.436 kg

Jumlah = 387,612 + 1721,993 + 7448,436 9558.041 kg

3 Balok lantai beton 15x35


No URAIAN PEKERJAAN / PERHITUNGAN VOLUME SATUAN

Panjang = 131.5 m'


Volume = 0.35 x 0.15 x 131,5
= 6.9 m3
Bekesting = (0,15+0,35) x 2 x 131,5
= 131.5 m2

Penulangan tumpuan dan lapangan

Tulangan pokok 2-Æ 12


=2 x 131,5 = 263 m'
=263 x 0.888 = 233.544 Kg
Tulangan pokok 5-Æ 16
=8 x 131,5 = 1052 m'
=1052 x 1,578 = 934.176 Kg
Sengkang Æ 8-100
=(131,5/0.125) x 1 = 1052 m'
=1052 x 0.395 = 415.54 kg

Jumlah = 233,544 + 934,176 + 415,54 1583.260 kg

4 Balok lantai beton 15x30

Panjang = 109.25 m'


Volume = 0.30 x 0.15 x 109,25
= 4.91625 m3
Bekesting = (0,3 + 0,15) x 2 x 109,25
= 98.325 m2

Penulangan Tumpuan dan lapangan


No URAIAN PEKERJAAN / PERHITUNGAN VOLUME SATUAN

Tulangan pokok 5-Æ 12


=5 x 109,25 = 546.25 m'
=546 x 1,578 = 861.588 Kg
Sengkang Æ 8-100
=(109,25/0.125) x 9 = 7866 m'
=7866 x 0.395 = 3067.74 kg

Jumlah = 861,588 + 3067,74 3929.328 kg

5 Kolom Struktur 30x30

Jumlah kolom
Lt. 1 = 38 bh
Lt.2 = 38 bh
Tinggi
Lt. 1 = 4 m
Lt. 2 = 4 m
Panjang = 304 m'
Volume = 304 x 0.3 x 0.3
27.36 m3
Bekisting = 38 x 0,3 x 4 x 8
364.8 m2

Penulangan Tumpuan dan Lapangan

Tulangan pokok 8-Æ 16


=8 x 304 = 2432 m'
No URAIAN PEKERJAAN / PERHITUNGAN VOLUME SATUAN
=2432 x 1.578 = 3837.696 Kg
Sengkang Æ 8-100
=(304/0.1) x 1.2 = 3648 m'
=3648 x 0.395 = 1440.96 kg

Jumlah = 3837,696 + 1440,96 5278.656 kg

6 Kolom Struktur 20x20

Jumlah kolom
Lt. 1 = 16 bh
Lt.2 = 16 bh
Tinggi
Lt. 1 = 4 m
Lt. 2 = 4 m
Panjang = 128 m'
Volume = 128 x 0.2 x 0.2
5.12 m3
Bekisting = 4 x 0.2 x 128
102.4 m2

Penulangan Tumpuan dan Lapangan

Tulangan pokok 8-Æ 16


=8 x 128 = 1024 m'
=1024 x 1.578 = 1615.872 Kg
Sengkang Æ 8-100
=(128/0.1) x 0.8 = 1024 m'
=1024 x 0.395 = 404.48 kg

Jumlah = 1615,872 + 404,48 2020.352 kg

7 Plat Lantai tebal 12 cm


No URAIAN PEKERJAAN / PERHITUNGAN VOLUME SATUAN

Luas I
Tebal = 12 cm
Luas = 6 x 11.75
= 70.5 m2
Volume Beton = 0.12 x 6 x 11.75
= 8.28 m3
Pembesian
Arah X
Æ10-400 = ( 6/0,4) x 11.75 x 0.617
= 108.75 Kg
Arah Y
Æ10-400 = (11,75/0,4) x 6 x 0.617
= 108.75 Kg

Luas 2
Tebal = 12 cm
Luas = 2 x 9 x 13
= 234 m2
Volume Beton = 0.12 x 234
= 28.08 m3
Pembesian
Arah X
Æ10-400 = (9/0,4) x 13 x 0.617 x 2
= 360.95 Kg
Arah Y
Æ10-400 = (13/0,4) x 9 x 0.617 x 2
= 360.65 Kg
No URAIAN PEKERJAAN / PERHITUNGAN VOLUME SATUAN

Luas 3
Tebal = 12 cm
Luas = 6x5
= 30 m2
Volume Beton = 0.12 x 30
= 3.6 m3
Pembesian
Arah X
Æ10-400 = (6/0,4) x 5 x 0.617
= 46.28 Kg
Arah Y
Æ10-400 = (5/0,4) x 6 x 0.617
= 46.28 Kg

Luas 4
Tebal = 12 cm
Luas = 4*1*12
= 48 m2
Volume Beton = 0.12*48
= 5.76 m3
Pembesian
Arah X
Æ10-400 = (12/0,4) x 1 x 0.617 x 4
= 74.04 Kg
Arah Y
Æ10-400 = (1/0,4) x 12 x 0.617 x 4
= 73.98 Kg

Jumlah
Luas = 70,5 + 234 + 30 + 48
= 382.5 m2 382.5 m2
Volume = 8,28 + 28,08 + 3,6 + 5,76
= 45.72 m3 45.72 m3
Pembesian = 108,75 + 108,75 + 360,95
+ 360,95 + 46,28 + 46,28
= 1179.66 kg 1,179.66 kg
No URAIAN PEKERJAAN / PERHITUNGAN VOLUME SATUAN

Pekerjaan Tangga

Jumlah anak tangga = 20 bh


Uk. Optrade = 18 cm
Uk. Antrade = 28 cm
Plat Bordes = 1 bh
Balok Bordes = 2 bh
Tebal selimut = 2.5 cm

Balok Bordes 2 buah


Volume = 0.2 x 0.3 x 3 x 2
= 0.36 m3
Pembesian
6 - D 14 = 6 x 3 x 1.208
21.744 Kg
Æ 8 - 100 = (3/0.1) x 0.9 x 0.395
10.665 Kg

Jumlah = (21,744 + 10,665) x 2


= 64.818 Kg

Plat Bordes
Vol. Beton = 0.15 x 1 x 3
No URAIAN PEKERJAAN / PERHITUNGAN VOLUME SATUAN
0.45 m3
Pembesian
Arah X
Æ 10- 150(atas) = (3/0.15) x 3.1 x 0.616
38.192 Kg
Æ 10- 150(bawah) = (3/0.15) x 3.025 x 0.616
37.268 Kg
Arah Y
Æ 10- 150(atas) = (1/0.15) x 1.1 x 0.616
4.517 Kg
Æ 10- 150(bawah) = (1/0.15) x 1.025 x 0.616
4.209 Kg
Bekisting balok dan plat bordes

LUAS =(2 x 1 x 0.15)+(2 x 0.2 x 0.3)+(0.3 x 3)


+ (0.15 x 3) + (1 x 3)
4.77 m2

Bagian I
Volume Beton = 0.12 x 1.5 x (3.6 + 3.6)
1.296 m3

Pembesian
Æ 10- 150 = (1.5/0.15) x 7.2 x 0.616
= 44.352 Kg

Æ 10- 150 = (7.2/0.15) x 1.5 x 0.616


= 44.352 Kg

Bagian II
Volume beton = 0.18 x 0.28 x 0.5 x 1.5 x 20
= 0.756 m3

Pembesian
Æ 10- 150 = (1.5/0.15) x 0.46 x 0.616
= 2.8336 x 20 bh
= 56.672 kg
No URAIAN PEKERJAAN / PERHITUNGAN VOLUME SATUAN
Æ 10- 150 = ((0.28/0.18)+1) x 1.5 x 0.616
= 2.361 x 20 bh
= 47.227 kg

Bekisting = (2(0.12x6.8))+(2x0.18x0.28x20)
+(1x x6.8)+(0.18 x 1.5x 20)
= 15.848 m2

Kapasitas
Volume Beton = 0.36 + 0.45 + 1.296 + 0.756
= 2.862 m3 2.862 m3

Pembesian = 64,818 + 38,192 + 37,268 + 4,517


+ 4,209 + (44,352 x 2)
+ (44,352 x 2) + 56,672 + 47,227
= 430.311 kg 430.311 kg

Bekisting = 4,77 + 15,848


= 20.618 m2 20.618 m2

11 Ring Balk 15x30

Panjang = 90 m'
Volume = 0.15 x 0.30 x 90
4.05 m3

bekisting = 0.3 x 2 x 90
54 m2

Penulangan Tumpan dan lapangan


No URAIAN PEKERJAAN / PERHITUNGAN VOLUME SATUAN

Tulangan pokok 4-Æ 16


= 4 x 90 = 360 m'
= 360 x 1.58 = 568.8 Kg

Sengkang Æ 8-100
= (90/0.1) x 0.82 = 738 m'
= 738 x 0.39 = 287.82 kg

Jumlah = 856.62 Kg 856.62 Kg

12 Ring Balk 15x12

Panjang = 76 m'
Volume = 0.15 x 0.12 x 76
1.368 m3

bekisting = 0.15 x 2 x 76
22.8 m2

Penulangan Tumpuan dan Lapangan

Tulangan pokok 4-Æ 16


= 4 x 76 = 296 m'
= 296*1.58 = 467.68 Kg

Sengkang Æ 8-100
= 76/0.1*0.46 = 349.6 m'
= 349.6*0.39 = 136.344 kg
No URAIAN PEKERJAAN / PERHITUNGAN VOLUME SATUAN

Jumlah = 467,68 + 136,344


= 604.024 kg 604.024 kg

13 Footplat

Vol 1
Tebal selimut = 2.5
Jumlah = 38

Volume Beton = 1.2 x 1.2 x 0.3 x 38


16.416 m3
Pembesian
Tul.Atas = 38 x 20 x 1.25 x 1.578
1499.1 Kg

Tul. Bawah = 38 x 20 x 1.75 x 1.578


2098.74 Kg

Total = 3597.84 Kg

bekisting = 38 x 4 x (1.2 x 0.3)


54.72 m2

Vol 2
Volume Beton = 38 x 1.5 x (0.3 x 0.3)
5.13 m3

Pembesian
8 d14 = 38 x 2.05 x 8 x 1.208
752.8256 Kg
No URAIAN PEKERJAAN / PERHITUNGAN VOLUME SATUAN

Æ 10- 100 = (1.5x 38/0.1) x 1.1 x 0.616


386.232 Kg

Total = 1139.058 Kg

Bekisting = 38 x 4 x (1.5 x 0.3)


68.4 m2

Vol 1 + vol 2 = 16.416 + 5.13


21.546 m3
123.12
Bekisting Footplat = 123.12/21.546
5.7143 m2/m3

Kapasitas 4736.898
Pembesian = 4736.898/21.546
219.850 kg/m3

14 Lantai Kerja 10 cm

Jumlah Footplat = 38 bh
Volume = 38 x 1.2 x 1.2 x 0.1
5.472 m3

15 Dag Atap
Luas L1 1 x 12 x 4 = 48
L2 1x6x2 = 12
L3 1x9x2 = 18
L4 1 x 6 x 1.75 = 10.5
total = 88.5

Volume = 0.1 x 88.5


= 8.85 m3
HITUNGAN VOLUME KANTOR IAIN WALISONGO DAKULTAS USHULUDIN SEMARANG

No URAIAN PEKERJAAN / PERHITUNGAN

PEKERJAAN PASANGAN

1 Pasangan batu kosong (Aanstamping)

Panjang = 202.25 m'


Volume = 0.15 x 0.9 x 202.25
27.304 m3
2
Pasangan Pondasi Batu Kali 1 pc : 3 pp

Panjang = 202.25 m'


Volume = ((0.25 + 0.70)/2) x 0.7 x 202.25
= 67.248 m3

3
Pasangan Trasram

Lantai 1 setinggi 50 cm =0.50 x 172.25


86.125

Kamar Mandi
Lt .1 (2.83 m) = 2.83 x 37.25 = 105.4175 m2
Lt .1 (2.83 m) = 2.83 x 29.5 = 83.485 m2
4 188.9025 m2
Pasangan Batu Bata merah 1pc : 5 pp
Luas Bukaan Kusen
L. PJ 1 = 6,125 x 1 = 6.125 m2
L. PJ 2 = 7.489 x 1 = 7.489 m2
L. P1 = 3.792 x 5 = 18.96 m2
L. P2 = 2.136 x 11 = 23.496 m2
L. P3 = 1.848 x 14 = 25.872 m2
L. J1 = 5.104 x 30 = 153.12 m2
L. J2 = 2.266 x 6 = 13.596 m2
L. J3 = 2.42 x 4 = 9.68 m2
258.338 m2
No URAIAN PEKERJAAN / PERHITUNGAN
Panjang Lt 1 = 172.25
Lt 2 = 178.75
Total 351

Volume = 3.96 x 351


= 1389.96 m3

Luas Pekerjaan Dinding pasang batu bata


= 1389,96-258,338-188,9025 942.7195 m2

5 Pekerjaan Pasangan Roster


Uk. 25 x 25 Jumlah = 22 buah
= 0.25 x 0.25 x 22
= 1.375 m2

6 Granite Tile
60 x 60 Lantai 1
Luasan = 44544.1701388889
= 283.5 m2

Lantai 2
Luasan = 350.5 - 12 - 16.5
= 322 m2

L. Total = 283.5 + 322 m2


605.5 m2

7 Keramik Kamar Mandi (Lt.1&Lt.2)


30 x 30
Lantai 1 = 21 m2
Lantai 2 = 16.5 m2
Total = 37.5 m2

8 Pasangan Border Keramik dinding KM/WC 10x20


Lt.1 Panjang = 52 m
Luas = 52 x 10
= 5.2 m2
Lt.2 Panjang = 40 m
Luas = 40 x 0.1
= 4 m2
Total = 9.2 m2

9 Pasangan Dinding Keramik


Lt. 1
No URAIAN PEKERJAAN / PERHITUNGAN
Luas = 52 x 2.83
147.16 m2
Lt. 2
Luas = 40 x 2.83
113.2 m2

Total = 147.16 + 113.2 - 9.2


251.16 m2

PEKERJAAN PLESTERAN
- Plesteran dinding tembok ( 1pc : 5 pp )
tebal = 20 mm
Volume = 2(L.dinding Pas. Batu bata )
= 2(942.7195)
= 1885.439 m2

- Plesteran Trasram ( 1pc:2pp)


tebal = 20 mm
Volume = 2 x (188.9025)
= 377.805 m2

PEKERJAAN KUSEN, PINTU DAN JENDELA


1 Pek. Kusen pintu, jendela dan boven (digunakan kayu 4/15)
Type P. J1 (1 buah )

Volume = 0.04 x 0.15 x 12.86 x 1


= 0.07716 m3

Type P. J2 (1 buah)

Volume = 0.04 x 0.15 x 17.84 x 1


= 0.10704 m3

Type P.1 (5 buah )


No URAIAN PEKERJAAN / PERHITUNGAN

Volume = 0.04 x 0.15 x 6.38 x 5


= 0.1914 m3
Type P.2 (11 buah )

Volume = 0.04 x 0.15 x 5.69 x 11


= 0.3755 m3

Type P.3 (14 buah )

Volume = 0.04 x 0.15 x 5.57 x 14


= 0.4679 m3

Type J1 (22 buah )


No URAIAN PEKERJAAN / PERHITUNGAN

Volume = 0.04 x 0.15 x 13.44 x 30


= 2.4192 m3

Type J2 (6 buah )

Volume = 0.04 x 0.15 x 6.4 x 6


= 0.2304 m3

Type J3 (4 buah )

Volume = 0.04x 0.15 x 6.6 x 4


= 0.1584 m3

Type BV (6 buah )
No URAIAN PEKERJAAN / PERHITUNGAN

Volume = 0.04 x 0.15 x 3.52 x 8


= 0.1690 m3

2 Pek. Daun Pintu Panel


Type P2
Volume = 0.79 x 2.35 x 11
= 20.4215 m2

Type P3
Volume = 0.67 x 2.35 x 14
= 22.043 m2

Total = 42.465 m2

3 Pek. Daun Pintu dan Ram


Type P. J1
Volume = 1 x 1.48 x 2.40
= 3.552 m2

Type J.1
Volume = 30 x 2 x 0.5 x 2.1
= 63 m2

Total = 66.552 m2

4 Pek. Daun Jendela Kaca mat


Type J.1
Luas = ((0.55 x 2.20 x 2)) x 30
= 72.6 m2

5 Pasang Kaca Pintu dan Jendela


Type PJ.1 ( 1 Unit )
Luas Kaca Pintu = 2 x (2.03 x 0.50)
= 2.03 m2

Luas Kaca Jendela = 2*(0.48*2.10)


= 2.016 m2

Total = 4.046 m2
No URAIAN PEKERJAAN / PERHITUNGAN

Type PJ.2 ( 1 Unit )


Luas Jendela 1 = 0.48 x 2.10
1.008 m2

Luas Jendela 2 = 2 x (1.29 x 0.87)


= 2.2446 m2

Luas Kaca Pintu = 2 x (2.03 x 0.50)


= 2.05 m2

Total = 5.3026 m2

Type P.1 ( 5 Unit )


Luas Kaca Pintu = (2 x 2.03 x 0.50) x 5
= 10.15 m2

Type J.1 (30 Unit)


Luas Kaca Pintu = 30 x ((0.45 x 2.00 x 2)+(1 x 2.2)
= 120 m2

Type J.2 (6 Unit)


Luas Kaca Pintu = 6 x (1 x 1.2)
= 7.2 m2

Type J.2 (4 Unit)


Luas Kaca Pintu = 4 x (1 x 1.2)
= 4.8 m2

Type BV.1 (8 Unit) (Kaca Es)


Luas Kaca Pintu = 8 x (0.5 x 0.45)
= 1.8 m2

6 Engsel Pintu 102x76 mm ( 4" x 3" )


7 Engsel Jendela 76 x 64 mm (3" x 2")
8 Handel Pintu Depan
9 Handel Pintu Biasa
10 Handel Pintu Servis
11 Kait Angin
12 Door Stop
13 Magnet Pintu
TAS USHULUDIN SEMARANG

VOLUME SAT

27.304 m3

67.248 m3

942.720 m2
VOLUME SAT

1.375 m2

605.500 m2

37.500 m2

9.200 m2

251.160 m2
VOLUME SAT

1885.439 m2

377.805 m2
VOLUME SAT
VOLUME SAT
VOLUME SAT
VOLUME SAT

114.000 bh
120.000 bh
2.000 bh
16.000 bh
13.000 bh
60.000 bh
16.000 bh
16.000 bh
HITUNGAN VOLUME KANTOR IAIN WALISONGO DAKULTAS USHULUDIN SEMARANG

No URAIAN PEKERJAAN / PERHITUNGAN VOLUME SAT

PEKERJAAN SANITASI
1 Closet duduk C 150 E/S 151 ( lengkap ) warna spesial ex Toto 7.00 bh

2 Washtafel ex Toto type LW 524 7.00 bh

3 Floor drain TX 1 B ex Toto 7.00 bh

4 Floor drain H 508 ex San Ei 7.00 bh

5 Kran cebok ex Toto type TB 19 CS V9N5 7.00 bh

6 Stop kran cebok ex Toto type TX 403 SV1 7.00 bh

7 Kran air bersih ex San Ei 1/2 " 14.00 bh

8 Bak kontrol air kotor 15.00 LS

9 Septic tank dan peresapan 1.00 LS

10 Ground water tank 1.00 LS

11 Tandon air kapasitas 1 m³ 1.00 LS

12 Pompa air National otomatis 1.00 bh

13 Pipa air bersih ( pipa PVC Rucika Ø 3/4" ) 2.00 btg

14 Pipa air bersih ( pipa PVC Rucika Ø 1" ) 2.00 btg

15 Saluran air kotor PVC klas D ex vinilon Ø 3" 2.00 btg

16 Saluran air kotor PVC klas D ex vinilon Ø 4" 3.00 btg

PEKERJAAN FINISHING CAT


1 Cat dinding dalam 1885.44 m2

2 Cat Plafond gypsum 655.00 m2

3 Cat Melamik Kosen 4.20 m2

4 Cat Melamik daun Jendela 72.60 m2

5 Cat Melamik daun Pintu 66.55 m2

PEKERJAAN UTILITAS / INSTALASI


1 Lampu TL 2 x 20 watt 65.00 bh
2 Lampu Down light 20 watt 96.00 bh
3 Lampu SL 20 watt 29.00 bh
4 Stop kontak t = 120 18.00 bh
5 Stop kontak t = 30 25.00 bh
6 Saklar ganda 18.00 bh
7 Saklar tunggal 7.00 bh
8 Sparing telephon 17.00 LS
9 Sparing AC 22.00 LS
No URAIAN PEKERJAAN / PERHITUNGAN VOLUME SAT

10 KWH meter 1.00 LS


11 Box zekering MCB 12 group 1.00 bh
12 Kabel jaringan 3 x 6 mm² 390.00 m
13 Kabel jaringan 3 x 4 mm² 170.00 m
14 Arde 1.00 bh
15 Penangkal petir 2 titik 2.00 titik

PEKERJAAN LAIN-LAIN
Penyambungan daya 3500 VA 1.00 LS

Penyambungan PDAM 1.00 LS


No URAIAN PEKERJAAN / PERHITUNGAN VOLUME SAT
No URAIAN PEKERJAAN / PERHITUNGAN VOLUME

Pekerjaan Atap
1 Metal light steel Galvallum
Type T1 ( 22 Unit )

Baja _II_ 70.70.7 mm


Panjang = 79.34 m'
Berat = 7.83 Kg/m
Volume = 10.133 Kg

Baja _II_ 50.50.5 mm


Panjang = 33.46 m'
Berat = 3.77 Kg/m

Volume = 8.875 Kg

Total Vol. 1 Unit = 19.008 Kg

Total Volume = 22 x 19.008


= 418.179 Kg

Type T2 ( 2 Unit )

Baja _II_ 70.70.7 mm


Panjang = 84.5 m'
Berat = 7.83 Kg/m

Volume = 10.792 Kg
No URAIAN PEKERJAAN / PERHITUNGAN VOLUME
Baja _II_ 50.50.5 mm
Panjang = 41.14 m'
Berat = 3.77 Kg/m

Volume = 10.912 Kg

Total Vol. 1 Unit = 21.704 Kg


Total Volume = 2 x 21.704
= 43.409 Kg

Type T3 ( 2 Unit )

Baja _II_ 70.70.7 mm


Panjang = 81.22 m'
Berat = 7.83 Kg/m

Volume = 10.373 Kg

Baja _II_ 50.50.5 mm


Panjang = 38.72 m'
Berat = 3.77 Kg/m

Volume = 10.271 Kg

Total Vol. 1 Unit = 20.643 Kg

Total Volume = 2 x 20.643


= 41.287 Kg

Type T4 ( 2 Unit )
No URAIAN PEKERJAAN / PERHITUNGAN VOLUME

Baja _II_ 70.70.7 mm


Panjang = 76.66 m'
Berat = 7.83 Kg/m

Volume = 9.791 Kg

Baja _II_ 50.50.5 mm


Panjang = 34.68 m'
Berat = 3.77 Kg/m

Volume = 9.199 Kg

Total Vol. 1 Unit = 18.989 Kg

Total Volume = 2 x 18.989


= 37.979 Kg

Type T5 ( 2 Unit )

Baja _II_ 70.70.7 mm


Panjang = 65.1 m'
Berat = 7.83 Kg/m

Volume = 8.314 Kg

Baja _II_ 50.50.5 mm


Panjang = 23.04 m'
Berat = 3.77 Kg/m

Volume = 6.111 Kg

Total Vol. 1 Unit = 14.426 Kg

Total Volume = 2 x 14.426


= 28.851 Kg

Type T6 ( 2 Unit )
No URAIAN PEKERJAAN / PERHITUNGAN VOLUME

Baja _II_ 70.70.7 mm


Panjang = 62.26 m'
Berat = 7.83 Kg/m

Volume = 7.951 Kg

Baja _II_ 50.50.5 mm


Panjang = 20.52 m'
Berat = 3.77 Kg/m

Volume = 5.443 Kg

Total Vol. 1 Unit = 13.394 Kg

Total Volume = 2 x 13.394


= 26.789 Kg

Type 7 ( 2 Unit )

Baja _II_ 70.70.7 mm


Panjang = 84.18 m'
Berat = 7.83 Kg/m

Volume = 10.751 Kg

Baja _II_ 50.50.5 mm


Panjang = 42.42 m'
Berat = 3.77 Kg/m
No URAIAN PEKERJAAN / PERHITUNGAN VOLUME

Volume = 11.252 Kg

Total Vol. 1 Unit = 22.003 Kg

Total Volume = 2 x 21.998


= 44.006 Kg

Type 8 ( 2 Unit )

Baja _II_ 70.70.7 mm


Panjang = 83.04 m'
Berat = 7.83 Kg/m

Volume = 10.605 Kg

Baja _II_ 50.50.5 mm


Panjang = 39.88 m'
Berat = 3.77 Kg/m

Volume = 10.578 Kg

Total Vol. 1 Unit = 21.184 Kg

Total Volume = 2 x 21.178


= 42.367 Kg

Type 9 ( 2 Unit )
No URAIAN PEKERJAAN / PERHITUNGAN VOLUME
Baja _II_ 70.70.7 mm
Panjang = 82.26 m'
Berat = 7.83 Kg/m

Volume = 10.506 Kg

Baja _II_ 50.50.5 mm


Panjang = 37.76 m'
Berat = 3.77 Kg/m

Volume = 10.016 Kg

Total Vol. 1 Unit = 20.522 Kg

Total Volume = 2 x 20.522


= 41.043 Kg

Type 10 ( 8 Unit )

Baja _II_ 70.70.7 mm


Panjang = 49.94 m'
Berat = 7.83 Kg/m

Volume = 6.378 Kg

Baja _II_ 50.50.5 mm


Panjang = 20.1 m'
Berat = 3.77 Kg/m

Volume = 5.332 Kg

Total Vol. 1 Unit = 11.710 Kg

Total Volume = 8 x 11.710


= 93.677 Kg

Type R.1 ( 2 Unit )


No URAIAN PEKERJAAN / PERHITUNGAN VOLUME

Baja _II_ 70.70.7 mm


Panjang = 10.3 m'
Berat = 7.83 Kg/m

Volume = 1.315 Kg

Baja _II_ 50.50.5 mm


Panjang = 1.44 m'
Berat = 3.77 Kg/m

Volume = 0.382 Kg

Total Vol. 1 Unit = 1.697 Kg

Total Volume = 2 x 1.697


= 3.395 Kg

Type R.2 ( 4 Unit )

Baja _II_ 70.70.7 mm


Panjang = 8.4 m'
Berat = 7.83 Kg/m

Volume = 1.073 Kg

Baja _II_ 50.50.5 mm


Panjang = 1.44 m'
Berat = 3.77 Kg/m

Volume = 0.382 Kg
No URAIAN PEKERJAAN / PERHITUNGAN VOLUME

Total Vol. 1 Unit = 1.455 Kg

Total Volume = 4 x 1.697


= 5.819 Kg

Type R.3 ( 4 Unit )

Baja _II_ 70.70.7 mm


Panjang = 6.6 m'
Berat = 7.83 Kg/m

Volume = 0.843 Kg

Baja _II_ 50.50.5 mm


Panjang = 1.44 m'
Berat = 3.77 Kg/m

Volume = 0.382 Kg

Total Vol. 1 Unit = 1.225 Kg

Total Volume = 4 x 1.225


= 4.899 Kg

Type R.4 ( 4 Unit )

Baja _II_ 70.70.7 mm


Panjang = 4.74 m'
No URAIAN PEKERJAAN / PERHITUNGAN VOLUME
Berat = 7.83 Kg/m

Volume = 0.605 Kg

Baja _II_ 50.50.5 mm


Panjang = 1.44 m'
Berat = 3.77 Kg/m

Volume = 0.382 Kg

Total Vol. 1 Unit = 0.987 Kg

Total Volume = 4 x 0.987


= 3.949 Kg

Type R.5 ( 4 Unit )

Baja _II_ 70.70.7 mm


Panjang = 2.9 m'
Berat = 7.83 Kg/m

Volume = 0.370 Kg

Baja _II_ 50.50.5 mm


Panjang = 1.44 m'
Berat = 3.77 Kg/m

Volume = 0.382 Kg

Total Vol. 1 Unit = 0.752 Kg

Total Volume = 4 x 0.752


= 3.009 Kg

Type R.6 ( 4 Unit )


No URAIAN PEKERJAAN / PERHITUNGAN VOLUME

Baja _II_ 70.70.7 mm


Panjang = 1.04 m'
Berat = 7.83 Kg/m

Volume = 0.133 Kg

Baja _II_ 50.50.5 mm


Panjang = 1.44 m'
Berat = 3.77 Kg/m

Volume = 0.382 Kg

Total Vol. 1 Unit = 0.515 Kg

Total Volume = 4 x 0.515


= 2.059 Kg

Type R.7 ( 1 Unit )

Baja _II_ 70.70.7 mm


Panjang = 11.16 m'
Berat = 7.83 Kg/m

Volume = 1.425 Kg

Type R.8 ( 1 Unit )


No URAIAN PEKERJAAN / PERHITUNGAN VOLUME

Baja _II_ 70.70.7 mm


Panjang = 7.48 m'
Berat = 7.83 Kg/m

Volume = 0.955 Kg

Type R.9 ( 1 Unit )

Baja _II_ 70.70.7 mm


Panjang = 3.72 m'
Berat = 7.83 Kg/m

Volume = 0.475 Kg

Type H.1 ( 4 Unit )

Baja _II_ 70.70.7 mm


Panjang = 12.86 m'
Berat = 7.83 Kg/m

Volume = 1.642 Kg
No URAIAN PEKERJAAN / PERHITUNGAN VOLUME

Baja _II_ 50.50.5 mm


Panjang = 1.44 m'
Berat = 3.77 Kg/m

Volume = 0.382 Kg

Total Vol. 1 Unit = 2.024 Kg

Total Volume = 4 x 2.024


= 8.097 Kg

I
I I I

II
I

I I
V V

2 Pemasangan Listplank Kayu Bengkirai 0.504


Panjang = 84 m'
Uk. 3/20 = 0.20 x 0.03 x 84
= 0.504 m3

3 Pemasangan Genteng Beton 358.873


Luas I ( 2 Unit ) = (9 x 5.59/2) x 2
50.31 m2

Luas II = (30+21)/2 x 5.59


= 142.545 m2

Luas III = Luas II - (3.82 x 6/2)


= 131.085 m2

Luas IV(2 Unit) = (8.98+6)/2 x 3.83) x 2


57.373 m2

Total Luasan Atap = 381.313 m2

4 Pemasangan NOK Genteng Beton 29.980

Panjang = 21+8.98
No URAIAN PEKERJAAN / PERHITUNGAN VOLUME
= 29.98 m'

5 Gording Baja ( C 125.50.20.2,3 )


C 125.50.20.2,3 = 108.274
Keliling = 125+(2 x 50)+(2 x 20) 1842.696
= 265 mm 0.265 m
Berat = 4.51 Kg/m

Panjang I = 1.53+3.13+4.72+6.32+7.91
= 23.61 m

Panjang II = 21+22.53+24.13+25.72+27.32+28.91
= 149.61 m

Panjang II = 8.98+8.16+7.36+6.57
= 31.07 m

Total Panjang = 2x(23,61+149,61+31,07)


408.58 m

Volume (m2) = Total Panjang x Keliling


408,58x0,265
108.2737 m3

Volume (Kg) = 408,58x4,51


1842.696 kg

6 Rangka Kayu
- Usuk(5/7) 494.880
Jumlah =
T1 ( 22 Unit ) = 22 x 5.59 x 2 m
= 245.96 m

T2 ( 2 Unit ) = 2 x 4.65 x 2 m
= 18.6 m

T3 ( 2 Unit ) = 2 x 3.74 x 2 m
= 14.96 m

T4 ( 2 Unit ) = 2 x 2.81 x 2 m
= 11.24 m

T5 ( 2 Unit ) = 2 x 1.89 x 2 m
= 7.56 m

T6 ( 2 Unit ) = 2 x 0.96 x 2 m
= 3.84 m
No URAIAN PEKERJAAN / PERHITUNGAN VOLUME

T7 ( 2 Unit ) = 2 x 7.88 m
= 15.76 m

T8 ( 2 Unit ) = 2 x 8.79 m
= 17.58 m

T9 ( 2 Unit ) = 2 x 9.69 m
= 19.38 m

T10 ( 8 Unit ) = 8 x 3.8 x 2 m


= 60.8 m

R1 ( 2 Unit ) = 2 x 5.62 m
= 11.24 m

R2 ( 4 Unit ) = 4 x 4.67 m
= 18.68 m

R3 ( 4 Unit ) = 4 x 3.77 m
= 15.08 m

R4 ( 4 Unit ) = 4 x 2.87 m
= 11.48 m

R5 ( 4 Unit ) = 4 x 1.92 m
= 7.68 m

R6 ( 4 Unit ) = 4 x 0.99 m
= 3.96 m

R7 ( 2 Unit ) = 2 x 2.76 m
= 5.52 m

R8 ( 2 Unit ) = 2 x 1.85 m
= 3.7 m

R9 ( 2 Unit ) = 2 x 0.93 m
= 1.86 m

TOTAL = 494.88 m'

2 PEKERJAAN PLAFOND 655.00


Plafond Gypsum rangka plafond metal furing
Luas Lt.1 = 316.5 - Void
= 316.5 - 12
= 304.5 m2
No URAIAN PEKERJAAN / PERHITUNGAN VOLUME
Luas Lt. 2 = 350.5 m2

Luas Total = 655 m2

Pek. List Plafond 509.00


Panjang Lt.1 = 247 m'
Panjang Lt.2 = 262 m'
509 m'
SAT
SAT
SAT
SAT
SAT
SAT
SAT
SAT
SAT
SAT
SAT
SAT

m3

m2

m'
SAT

m3
kg

m'
SAT

m2
SAT

m'
No Perhitungan Rangka Atap Baja Ringan dan luas genteng volume satuan

Luas I
( luas sisi sejajar ) / 2 * tinggi
( 21 + 30 ) / 2 * 3,21 81.855 m²

Luas II
( luas sisi sejajar ) / 2 * tinggi
( 21 + 30 ) / 2 * 3,21 81.855 m²

Luas III
( alas * tinggi ) / 2
( 9 * 3,21 ) / 2 14.445 m²

Luas IV
( alas * tinggi ) / 2
( 9 * 3,21 ) / 2 14.445 m²

Luas V
( alas * tinggi )
( 5 * 2,33 ) 11.65 m²

Luas VI
( alas * tinggi )
( 5 * 2,33 ) 11.65 m²

Luas VII
( alas * tinggi ) / 2
( 6 * 2,33 ) / 2 6.99 m²

total jumlah 222.89 m²