MK Structure User Guide
MK Structure User Guide
MK STRUCTURE
E03FFN
Construcción
IMPORTANT:
Neither all nor part of this document may be reproduced or transmitted in any way by any electronic or mechanical procedure,
including photocopy, magnetic recording or any other form of information storage or retrieval system without the permission of ULMA
Construcción.
Construcción
INDEX
DESCRIPTION .....................................
1. PRODUCT DESCRIPTION .....................................4 4.4. STRUCTURE CONNECTION WITH SHORING
SYSTEM ..................................................................39
1.1. MK TRUSS ....................................................... 5
4.5. STRUCTURE LEVELLING ....................................40
1.2. MK FORM CARRIERS ........................................ 7
4.6. FORWARD-MOVING OF STRUCTURES: ROLLING
2. SYSTEM COMPONENTS AND ACCESSORIES ...... 13 SYSTEM ..................................................................41
2.1. GRAPHIC DESCRIPTION ................................... 13 4.7. SAFETY AND ACCESS PLATFORMS ...................42
2.2. ITEMS DESCRIPTION ....................................... 17 5. SYSTEM PROPERTIES .......................................
....................................... 43
3. ASSEMBLY, USE AND DISMANTLING................. 25 5.1. MAIN ITEM PROPERTIES ...................................43
3.1. TECHNICHAL ASSEMBLY INSTRUCTIONS. 5.2. LIMITS FOR STANDARD STRUCTURES ................50
GENERAL ASSEMBLY .............................................. 25 CONDITIONS OF USE .................... 55
6. TERMS AND CONDITIONS
4. SOLUTIONS ......................................................
...................................................... 29 6.1. SAFE OPERATING GUIDELINES ..........................55
4.1. STRUCTURE TYPES .......................................... 32 6.2. TRANSPORT, HANDLING AND STORAGE ...........58
4.2. STRUCTURE LAYOUTS..................................... 34 6.3. INSPECTION AND MAINTENANCE .....................59
4.3. BRACING BETWEEN STRUCTURES .................... 38 7. LEGAL REFERENCES .........................................
......................................... 61
Construcción
3
MK STRUCTURE
1. PRODUCT DESCRIPTION
The MK System is a product designed for heavy-duty structures of high load-bearing capacity mainly used in civil
engineering.
Its main feature is its versatility to configure all types of structures such as gantry structures, formwork carriers and
tunnel structures, shoring structures, horizontal and vertical formwork, other structures for formwork support,
climbing brackets, slab perimeter protection structures and other applications.
The core item for all these solutions is the Waler MK. Its elaborated design and the combination with various
accessories, both unique of the MK system as well as shared with other ULMA products, enable to adapt it to all
those above mentioned applications.
With the MK Structure system, two or more load-bearing structures are formed in one direction, the so-called main
axis. These structures are braced to each other giving the required stability to the whole as well as absorbing wind
loads acting on the structure in perpendicular direction to the main axis.
Depending on their field of application, mainly two structure types are distinguished:
− MK Truss Structure
− MK Form Carrier Structure
Construcción
4
MK STRUCTURE
1.1. MK TRUSS
A truss structure, bi- or multi-supported, supports the formwork and absorbs the loads acting on the formwork.
The formwork systems commonly used with the MK Truss Structure are Enkoform VMK or Enkoform H-120.
The typical truss form of the structure is achieved with equilateral triangles consisting of Walers MK and Nodes MK
assembled in the same plane. These structures are braced to each other with joints and tubes. Depending on the
required load-bearing capacity of the truss, the main axis can be reinforced with push-pull props and tubes.
The Waler MK range allows assembling trusses of different load-bearing capacities. The most optimum load-
bearing capacity-weight ratio is the one given by a distance of 3 m between nodes axes and 2.6 m between waler
axes.
Construcción
5
MK STRUCTURE
If the span of the upper boom (or element that works at compression) is sought to be reduced or the bending
capacity to be increased, a vertical tube is used to make the structure bear higher loads.
The spans possible to cover with the MK Truss Structure change depending on the waler length used. Moreover,
the permissible working load changes depending on the layout of the truss structure.
The combination of the MK Truss Structure system with the MK Shoring system offers an even wider range of
solutions as shown in the following figures.
MK - 1250
MK - 1250
MK - 1250
MK - 1250
MK - 1250
MK - 1250
MK - 1250
MK - 1250
MK - 1250
MK - 1250
MK - 1250
MK - 1250
MK - 2625 MK - 2625 MK - 2625 M K - 2625 MK - 2625 MK - 2625
MK
MK
MK
MK
MK
MK
5
- 262
- 262
- 262
- 262
- 262
- 262
- 262
- 262
- 262
- 262
- 262
- 262
MK
MK
MK
MK
MK
MK
5
5
M K - 2625 MK - 2625 MK - 2625 M K - 2625 MK - 2625
MK - 1125
MK - 1125
MK - 1125
MK - 1125
M K - 2625 MK - 2625
M K - 2625 MK - 2625
MK -4625
MK -4625
MK -4625
MK -4625
M K - 2625 MK - 2625
M K - 1125
M K - 1125
M K - 1125
M K - 1125
625
- 2 625
MK
MK
MK
-2
-2
- 2 625
-2
-2
625
625
MK
MK
MK
MK - 2625 MK - 2625
MK - 1125
MK - 1125
MK -5625
MK -5625
MK - 4625
MK - 4625
MK -5625
MK - 1125
MK - 1125
Construcción
6
MK STRUCTURE
The following types of form carriers can be erected with the MK system:
− Deck flange form carrier
− Parapet form carrier
− Vertical formwork carrier
− Cut-and-cover tunnel form carrier
In the case of metallic bridges which are made up of pre-cast components or of a pre-cast centre part, it is
common to build the wings in a subsequent stage. This can be done with deck flange form carriers. These are
heavy-duty form carriers as the jacks are able to withstand a maximum load of approximately 360 kN. Due to the
load borne by the structure, the forward-moving of the form carrier is achieved by means of pull or push auxiliary
devices.
A deck flange form carrier with these properties usually consists of the following parts:
Construcción
7
MK STRUCTURE
A further distinction may be the requirement to cast both wings at the same time or one after the other.
In the first case, the rolling system rests on a guide rail to move the formwork to subsequent casting positions. It
can be applied in those cases where there is a solid base (pre-fabricated or pre-cast) to support the guide rail and
the levelling jacks on.
In the second case, it is the other way around. The bogie forms part of the secondary structure and the rolling
system is fixed to the bridge. This is rather common where there is no pre-cast structure (e.g. metallic bridges).
TF - 0121
TF - 0121
TF - 0121
Construcción
8
MK STRUCTURE
This form carrier is a lighter version of the previous one. It is used for applications with lower load-bearing and
forward-moving capacities. Unlike the one mentioned beforehand, the parapet form carrier can be moved manually
and requires a solid base where the guide rail rests on. The jacks of this form carrier type are able to withstand a
maximum load of approximately 150 kN.
The most common applications for parapet form carriers are the construction of protection parapets for bridges or
solutions that do not require high load-bearing capacity, mainly projects with formwork tables.
Construcción
9
MK STRUCTURE
The main feature that distinguishes the vertical formwork carrier from others is that the vertical loads acting on the
structure are exclusively caused by the self-weight of the structure. Its load-bearing and forward-moving capacities
are still lower than the ones of the above mentioned form carriers. The jacks of this form carrier type are able to
withstand a maximum load of approximately 60 kN.
As the parapet form carrier, the vertical formwork carrier can be moved manually and requires a solid base where
the guide rail rests on. It is mainly used in the construction of single-sided or double-sided concrete walls. In the
case of single-sided walls, there are considerable horizontal loads which must be taken into account when using
the vertical formwork carrier.
Construcción
10
MK STRUCTURE
1.2.4. CUT-
CUT-AND-
AND-COVER TUNNEL FORM CARRIER
The solution with the MK system for cut-and-cover tunnels can be regarded another type of form carrier adapted to
the particular requirements of tunnel construction where the structure must adapt to the vault shape of the tunnel.
This form carrier type also applies to applications where walls and slabs are cast at once as it is the case of
rectangular section tunnels.
Vaulted tunnels are usually not cast at once but in stages: first the gables then the top part of the vault. Cut-and-
cover tunnel form carriers are complemented with swivel parts to facilitate the stripping and forward-moving of the
structure.
An all-round solution for cut-and-cover tunnels combines the MK Structure system for the top part of the vault
with the MK Shoring system. A cut-and-cover tunnel form carrier usually consists of the following parts:
o Main structure: structure bearing the concrete load, both the vertical as well as the horizontal loads.
o Forward-moving structure: secondary structure which effects the movement and bears the forces
during such.
o Bracing: components that withstand wind effects and transverse movements.
o Formwork: part in touch with the concrete shaping it, allowing its adjustment and opening if this is
required for the movement of the structure.
o Rolling and levelling system: components that enable the rolling of the truss and its levelling at a
specific place, as well as its stripping.
o Safety items and access: walkway platforms, handrails etc., depending on the requirements of each
project.
Construcción
11
MK STRUCTURE
Cut-and-cover tunnel from carriers vary depending on aspects such as the load-bearing capacity and the area
where it is supported on and moved forward. Two types of cut-and-cover tunnel form carriers are distinguished
regarding a restricted or free support area. In all cases, the rolling system forms part of the form carrier, i.e. it is
integrated in the bogie.
C sn tr cu n
o ó
i
C
n s u
o rt c ó
in
Cut-
Cut-and-
and-cover tunnel form carrier with free support area
C
r ci ó
n st u
o n
Cut-
Cut-and-
and-cover tunnel form carrier with restricted support
support area Form carrier for slab and wall in rectangular section tunnel
Construcción
12
MK STRUCTURE
Construcción
13
MK STRUCTURE
Weight Weight
Item no. Item name Item no. Item name
(kg) (kg)
1990361 21.4 NODE 60 M MK 1990404 19.5 V BRACING TRUSS MK
1990300 15.0 AXIAL NODE M D40 MK 1990403 1.3 JOINT PUSH-PULL PROP E-NODE MK
1990301 23.0 AXIAL NODE 90º M D40 MK
PUSH-
PUSH-PULL PROPS E
Construcción
14
MK STRUCTURE
Weight Weight
Item no. Item name Item no. Item name
(kg) (kg)
0252070 0.28 PIN E20x70 1990401 3.6 NODE-WALER 90º JOINT MK
1990605 1.9 HORIZ. TUBE MK 0.75/ 550 1990515 37.7 JACK 150 MK
1990608 2.7 HORIZ. TUBE MK 1/ 800
1990613 4.5 HORIZ. TUBE MK 1.5/ 1300
1990618 6.2 HORIZ. TUBE MK 2/ 1800
1990623 7.9 HORIZ. TUBE MK 2,5/ 2800
1990619 10.1 DIAGONAL MK 1.5x1.5 / 1818 1990530 115.0 JACK WALER MK 0.5 / 1000
1990622 12.2 DIAGONAL MK 1.5x2 / 2201 1990551 161.0 JACK WALER MK 1 / 1500
1990626 17.9 DIAGONAL MK 1.5x2.5 / 2624 1990552 207.0 JACK WALER MK 1.5 / 2000
1990630 20.9 DIAGONAL MK 1.5x3 / 3071 1990553 253.0 JACK WALER MK 2 / 2500
Construcción
15
MK STRUCTURE
Weight Weight
Item no. Item name Item no. Item name
(kg) (kg)
0242460 0.30 BOLT M24x60 DIN-931-8.8 1990374 25.5 HEAD JOINT 74 MK
PROFILES MK-
MK-180
1990017 44,10 PROFILE MK-180/2,125
1990021 54,50 PROFILE MK-180/2,625
1990025 64,90 PROFILE MK-180/3,125
1990029 75,40 PROFILE MK-180/3,625
1990037 96,30 PROFILE MK-180/4,625
1990045 117,10 PROFILE MK-180/5,625
1990061 159,00 PROFILE MK-180/7,625
1990085 222,00 PROFILE MK-180/10,625
Construcción
16
MK STRUCTURE
The following connections with bolt and nut will of 45.5 mm. The spacing between the holes in the
be shortly describes as M16, M20 and M24 in this centre row is 125 mm.
document, meaning:
- M16: Bolt M16 DIN 931-8.8 + Nut M16 The centre rows always start and end with ∅20 mm
The waler consists of two UPN-120 profiles joined The Node 180 D40 MK differs from the previous one
back face-to-face. There are three rows of holes. The with respect to the connection of another (male)
holes of the outer rows have a diameter of ∅17 mm item to the node centre in a hinged way pointing
and the spacing between holes of the same row and downwards. The connection is fastened with pins
towards the other outer row is 62.5 mm. D40.
2 Tornillos M16
+
2 Tuercas
Autoblocantes
Agujero
In both cases, the D20 holes are mainly used for the
connection of secondary components, i.e., bracing
items.
Construcción
17
MK STRUCTURE
These nodes enable to connect up to 2 walers at 60º. They are male nodes connected to a female node of
The connections are fastened with 6 bolts M16 the structure with pins D40.
inserted into the D17 holes.
Construcción
18
MK STRUCTURE
The D20 holes are mainly used for the connection of The support plate provides D25 (25 mm diameter)
secondary components, i.e., bracing items. and D22 holes to connect other items and
accessories.
These nodes enable to connect up to 2 walers at 90º. The Orthogonal Joint MK connects up to 3 walers
The connections are fastened with 6 bolts M16 perpendicular to each other. The connection with the
inserted into the D17 holes. waler is fastened with 4 bolts M16 inserted into the
D17 holes.
The D20 holes are mainly used for the connection of
secondary components, i.e., bracing items. It can also connect 2 walers lengthwise. In this case,
each waler is fastened with 6 bolts M16 inserted into
the D17 holes .
It enables to connect up to 2 walers at 60º as the This node enables to connect one waler to another in
Node 60 MK does. The connections are fastened with a hinged way, always in the main plane. The waler
6 bolts M16 inserted into the D17 holes. and the node are fastened with 2 bolts M16 inserted
into the D17 holes. Unlike the Axial Node M D40,
this one does not have high load-bearing capacity.
Construcción
19
MK STRUCTURE
Push-
Push-Pull Prop E range up to 2.2
Construcción
20
MK STRUCTURE
Construcción
21
MK STRUCTURE
Construcción
22
MK STRUCTURE
2.2.25. WHEEL 15 MK
Construcción
23
MK STRUCTURE
Construcción
24
MK STRUCTURE
For further information on this section, it is advisable to read and follow the respective technical assembly
instructions for the different products offered by the MK System with regard to their erection, dismantling and
handling.
ITM_MK01-01 “ERECTION OF THE MK TRUSS SYSTEM WITH AND WITHOUT BOTTOM PLATFORMS IN HORIZONTAL
POSITION”
ITM_MK02-01 “DISMANTLING OF THE MK TRUSS SYSTEM WITH AND WITHOUT BOTTOM PLATFORMS IN
HORIZONTAL POSITION”
ITM_MK03-01 “ERECTION OF THE MK TRUSS SYSTEM WITH AND WITHOUT BOTTOM PLATFORMS IN VERTICAL
POSITION”
ITM_MK04-01 “DISMANTLING OF THE MK TRUSS SYSTEM WITH AND WITHOUT BOTTOM PLATFORMS IN VERTICAL
POSITION”
ITM_MK05-01 “ERECTION OF THE MK FORM CARRIER SYSTEM WITH AND WITHOUT BOTTOM PLATFORMS IN
HORIZONTAL POSITION”
ITM_MK06-01 “DISMANTLING OF THE MK FORM CARRIER SYSTEM WITH AND WITHOUT BOTTOM PLATFORMS IN
HORIZONTAL POSITION”
ITM_MK07-01 “ERECTION OF THE MK FORM CARRIER SYSTEM WITH AND WITHOUT BOTTOM PLATFORMS IN
VERTICAL POSITION”
ITM_MK08-01 “DISMANTLING OF THE MK FORM CARRIER SYSTEM WITH AND WITHOUT BOTTOM PLATFORMS IN
VERTICAL POSITION”
ITM_MK09-01 “ERECTION OF THE MK CUT-AND-COVER FORM CARRIER WITH BOTTOM PLATFORMS IN VERTICAL
POSITION”
ITM_MK10-01 “DISMANTLING OF THE MK CUT-AND-COVER FORM CARRIER WITH BOTTOM PLATFORMS IN
VERTICAL POSITION”
Construcción
25
MK STRUCTURE
- Place the U secondary axis joints on nodes and are connected to each other with bolts M24.
Construcción
26
MK STRUCTURE
- With BRIO
BRIO platforms placed onto the horizontal structures
braces: no need of extra components. - Attach auxiliary load lifting means to the modules
- With BRIO platforms placed on tubes D48: fix the assembled in section 3.1.3 and position the module
tube onto the Handrail Head MK and fasten with vertically by means of a mechanical load lifting
couplers 48. Insert the head into the gap device.
between the waler UPN profiles at the height
indicated in the assembly drawings and fasten
with bolts M16.
- With Beams VM20 and board: place another
waler with the Axial Node M D20 MK fastened
with bolt M16 additionally to the pin E20x70 at
the height indicated in the assembly drawings.
Construcción
27
MK STRUCTURE
Construcción
28
MK STRUCTURE
Construcción
29
MK STRUCTURE
Construcción
30
MK STRUCTURE
Construcción
31
MK STRUCTURE
2.125 m 2.5 m
This refers to truss structures resting on at least two
supports. These are mainly used for high load- 2.625 m 3m
MK - 2625 MK - 2625
Construcción
32
MK STRUCTURE
In general, they are tied directly to the main 4.1.3. Structure of form carriers
structures with pins D40 allowing of a fast and safe
Such structures must only bear their self-weight plus
on-site assembly.
the formwork they hold. They are medium load-
bearing capacity structures and light, in general.
TF - 0121
TF - 0121
TF - 0121
TF - 0121
Construcción
33
MK STRUCTURE
Forward-
Forward-moving structure in a MK deck flange form carrier 120º joint
Used at the ends which require a termination of the
structure at 120º. Moreover useful when a pre-
assembled structure (or tower) shall be quickly joined
to an already existing one.
Construcción
34
MK STRUCTURE
74º joint
Used at the ends which require an end joint at 74º.
This joint provides a single support in direction of the
main axis, as it is the case on bogies.
Construcción
35
MK STRUCTURE
Construcción
36
MK STRUCTURE
- The second waler joint is a joint only between The joint can be fixed at any point of the waler,
walers. The bracing of the secondary axis is made at aligned with a hole or slot every 62.5 mm, in both
another point. It enables either a butt joint fastened directions.
with 6 bolts each or a joint with a 125 mm gap
between walers fastened with 4 bolts. In the latter
case, walers can be crossed.
Construcción
37
MK STRUCTURE
Waler on V Bracing Truss MK joint used when actions in the secondary plane are
There is still another way to join two walers. That is certainly not important.
with the V Bracing Truss MK and without any
additional part. The V bracing can only be fixed to 4.3.1. Bracing on waler axis
the centre of a main truss waler, and only if tubes are
For this type of bracing, diagonals and horizontal
used in the application.
braces are used, joined to the walers with U
secondary axis joints fastened and with pins D20.
Hence these connections are all hinged which
requires them to be also braced diagonally at some
points to achieve an appropriate bracing for all the
structures.
There is another possibility to externally brace the carriers which are not supposed to be moved.
Construcción
38
MK STRUCTURE
4.4. STRUCTURE CONNECTION WITH These joints allow of the pre-assembly of towers.
Construcción
39
MK STRUCTURE
Construcción
40
MK STRUCTURE
4.5.2. Medium load-bearing capacity structure the next pouring stage is done with the aid of load
arrester devices (e.g. Tractels).
For lighter form carriers, the levelling is done using
the Jack MK 60. These solutions do not require a
Each form carrier or structure usually has 4 wheels
secondary structure for the forward-moving, and are
which allows of moving up to 40 tons. The wheels
usually made up of 2 or 3 main structures. Common
are also the support points for the secondary
applications are vertical formwork carriers or such
structure (bogie). In this case, the bogie bears the
applications where load requirements of the structure
total weight of the form carrier. Once the forward-
are not significant.
moving has finished, the form carrier gets blocked by
means of the jacks and the bogie gets not loaded any
more.
4.6. FORWARD-
FORWARD-MOVING OF STRUCTURES: Lighter form carriers are moved forward with the
Wheel MK 15 up to 60 kN. These are made up of
ROLLING SYSTEM
several main structures, and the wheels are attached
4.6.1. High load-bearing capacity structure
directly to the jack walers.
The forward-moving of this type of structures is done
with Wheels MK 100 attached directly onto the jack A lighter guide rail is used (UPN type) and the
walers which form the bogie. During the process of forward-moving of the structure is done manually.
forward-moving, the wheels run on a guide rail. The
guide rail rests directly on the ground and is
anchored to it.
Construcción
41
MK STRUCTURE
4.7. SAFETY AND ACCESS PLATFORMS Both options similarly serve to assemble platforms
inside the structure.
Safety platforms are assembled directly on the
structures. This can be done in two ways:
The safety handrail system can also be assembled in
two different ways:
Directly on two adjoining structures with the
available walers. Secondary beams and board
With Handrail Heads MK on secondary
rest on the walers. Depending on the beam used,
beamsusing the appropriate handrails for each
the corresponding fixing system is employed.
case as in any other system.
5.
Construcción
42
MK STRUCTURE
SYSTEM PROPERTIES
It is rather difficult to define limits for the manifold possible structure options which can be formed with the MK
system. As for their variety, each structure must be calculated on an individual basis. Nevertheless, this chapter
gives the necessary data to perform these calculations, and presents some limits for the most critical elements.
Some working load tables for particular applications are given below which may serve as orientation on the
obtainable load-bearing capacity of these structures.
52
120
y y
z
m = 27.5 [kg/m] weight/m
A = 27.5 10-4 [m2] net section area (without holes)
fy = 275 [MPa] yield strength
The technical properties of the WALER MK-120 are (for SLS loads):
MRdyy = 21.33 (kN m) Maximum permissible bending moment on axis y-y
VRdzz = 118,2 (kN) Maximum permissible shear force on axis y-y?
Construcción
43
MK STRUCTURE
1.5 m 360 kN **
2m 336 kN
2.5 m 287 kN
3m 240 kN
Values of pure buckling, not considering bending moment effects on any axis
PIN E20x70 77 kN
5.1.3. PIN E20X70 AND TUBE 50X6 JOINT (V BRACING TRUSS MK TUBE)
PIN E20x70 77 kN
PIN E20X70 30 kN **
** The strength limit of the diagonals is given by the tearing of the hole
Construcción
44
MK STRUCTURE
The working load of the pin D40 used in a joint of the structure:
The working load of a joint fixed with 6 bolts between Walers MK-120 and different nodes is:
The working load of a joint fixed with 4 bolts between Walers MK-120 and different nodes is:
The working load of a joint fixed with 2 bolts between Walers MK-120 and different nodes is:
These values refer to the maximum working load of the joint at pure tension and bending moment. They do
not refer to the load combination of both.
Construcción
45
MK STRUCTURE
It is NOT enough to verify the diagonals at buckling because diagonals submitted only to tension must be
verified with respect to the working load value NEVER exceeding 30 kN due to the tear of the ∅20 hole of the
diagonal. The maximum working load of the diagonals is given by the tearing of the hole.
Two limit values are given below for the horizontal braces. The first value does not consider any working platform
installed on the braces hence they are only submitted to compression loads. The second value considers apart from
compression, the generation of bending moments along the brace due to working platforms.
For the first case and for any length of horizontal braces:
It is NOT enough to verify the horizontal braces at buckling because braces submitted only to tension must be
verified with respect to the working load value NEVER exceeding 20kN due to the tear of the ∅20 hole of the
diagonal. The maximum working load of the braces is given by the tearing of the hole.
Construcción
46
MK STRUCTURE
R
C
** Due to the permissible load distribution, it is advisable not to install platforms on the horizontal braces of
2.5 m and 3 m. In any case, these braces require a previous verification.
Regarding the high variety of different board types on the market, a separate document collects all mechanical
properties of formwork boards. For more information, please refer to that document.
Construcción
47
MK STRUCTURE
The jack waler is studied for the stripping at a 250 mm distance from the supporting areas of the posts. These
areas have to be properly stiffened.
F = 360 kN (SLS)
The maximum permissible bending moment and shear force of the connection is:
8 bolts M24x60 8.8 Mmax yy (SLS) = 75 kNm ∼ 45 % waler strength Tmax yy (SLS) = 300 kN
8 bolts M24x60 10.9 Mmax yy (SLS) = 100 kNm ∼ 60 % waler strength Tmax yy (SLS) = 375 kN
Construcción
48
MK STRUCTURE
The working loads of the Jack MK 360 are indicated in the table below. The table shows the possible combinations
of axial (V) and horizontal (H) forces for the different jack extensions. In the same figure, two straight lines delimit
the values for which there might be a sliding of the nut with respect to the fixed base depending on some
estimated friction coefficients for a nut lubricated or non-lubricated on its base.
120,0
100,0
POSIBLE DESLIZAMIENTO TUERCA
RESPECTO AL PERFIL HUSILLO EN
E.L.S. (kN)
60,0
40,0
20,0
0,0
0 50 100 150 200 250 300 350 400
AXIL MAXIMO ADMISIBLE E.L.S.(kN)
Extension Husillo 50 Extension Husillo 100 Extension Husillo 200
BASE TUERCA LUBRICADA BASE TUERCA SIN LUBRICAR
150 kN 8 kN
Construcción
49
MK STRUCTURE
The following information and data may merely act as reference. Formulas included in different calculation
bases for truss beams are used. They are valid as a first approximation but it is advisable to always verify individually
any truss application.
There are no whatsoever limits for possible truss deformations included herein. Those must be verified with
the help of calculation software for structures.
This refers to a truss with supports at both ends as shown in the following figure. The spans possible to achieve
with this truss vary depending on the applied modulation. Three load application cases are analysed subsequently:
The tables show the maximum permissible load in SLS for each truss (qmax) (Pmax): maximum reaction on prop-
boom joint?, maximum bending moment the truss is able to absorb (M truss max), maximum bending moment in
the waler, maximum axial force in the waler and reactions on the supports depending on the distance between
nodes of the truss.
Construcción
50
MK STRUCTURE
LTruss 3 m
7.5 7.5 7.5 7.5 7.5 7.5 7.5 7.5
hTruss 2,60 m
Longitud Total qmax kN/m NTensor max MCercha max Mmax Riostra Axil Max kN R Apoyos kN
Tensor a utilizar
Truss (m) (ELS) kN (ELS) kNm (ELS) kNm (ELS) (ELS) (ELS)
LTruss 3 m
10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0
hTruss 2,60 m
Longitud Total qmax * kN/m Pmax kN NTensor max MCercha max Mmax Riostra Axil Max kN R Apoyos kN
Tensor a utilizar
Truss (m) (ELS) (ELS kN (ELS) kNm (ELS) kNm (ELS) (ELS) (ELS)
Longitud Total qmax * kN/m Pmax kN NTensor max MCercha max Mmax Riostra Axil Max kN R Apoyos kN
Tensor a utilizar
Truss (m) (ELS) (ELS kN (ELS) kNm (ELS) kNm (ELS) (ELS) (ELS)
Construcción
51
MK STRUCTURE
LTruss 2,5 m
7.5 7.5 7.5 7.5 7.5 7.5 7.5 7.5
hTruss 2,17 m
Longitud Total qmax kN/m NTensor max MCercha max Mmax Riostra Axil Max kN R Apoyos kN
Tensor a utilizar
Truss (m) (ELS) kN (ELS) kNm (ELS) kNm (ELS) (ELS) (ELS)
LTruss 2,5 m
10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0
hTruss 2,17 m
Longitud Total qmax * kN/m Pmax kN NTensor max MCercha max Mmax Riostra Axil Max kN R Apoyos kN
Tensor a utilizar
Truss (m) (ELS) (ELS kN (ELS) kNm (ELS) kNm (ELS) (ELS) (ELS)
Longitud Total qmax * kN/m Pmax kN NTensor max MCercha max Mmax Riostra Axil Max kN R Apoyos kN
Tensor a utilizar
Truss (m) (ELS) (ELS kN (ELS) kNm (ELS) kNm (ELS) (ELS) (ELS)
Construcción
52
MK STRUCTURE
LTruss 2 m
7.5 7.5 7.5 7.5 7.5 7.5 7.5 7.5
hTruss 1,73 m
Longitud Total qmax kN/m NTensor max MCercha max Mmax Riostra Axil Max kN R Apoyos kN
Tensor a utilizar
Truss (m) (ELS) kN (ELS) kNm (ELS) kNm (ELS) (ELS) (ELS)
LTruss 2 m
10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0
hTruss 1,73 m
Longitud Total qmax * kN/m Pmax kN NTensor max MCercha max Mmax Riostra Axil Max kN R Apoyos kN
Tensor a utilizar
Truss (m) (ELS) (ELS kN (ELS) kNm (ELS) kNm (ELS) (ELS) (ELS)
Longitud Total qmax * kN/m Pmax kN NTensor max MCercha max Mmax Riostra Axil Max kN R Apoyos kN
Tensor a utilizar
Truss (m) (ELS) (ELS kN (ELS) kNm (ELS) kNm (ELS) (ELS) (ELS)
Construcción
53
MK STRUCTURE
LTruss 1,5 m
7.5 7.5 7.5 7.5 7.5 7.5 7.5 7.5
hTruss 1,30 m
Longitud Total qmax kN/m NTensor max MCercha max Mmax Riostra Axil Max kN R Apoyos kN
Tensor a utilizar
Truss (m) (ELS) kN (ELS) kNm (ELS) kNm (ELS) (ELS) (ELS)
LTruss 1,5 m
10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0
hTruss 1,30 m
Longitud Total qmax * kN/m Pmax kN NTensor max MCercha max Mmax Riostra Axil Max kN R Apoyos kN
Tensor a utilizar
Truss (m) (ELS) (ELS kN (ELS) kNm (ELS) kNm (ELS) (ELS) (ELS)
Longitud Total qmax * kN/m Pmax kN NTensor max MCercha max Mmax Riostra Axil Max kN R Apoyos kN
Tensor a utilizar
Truss (m) (ELS) (ELS kN (ELS) kNm (ELS) kNm (ELS) (ELS) (ELS)
Construcción
54
MK STRUCTURE
Construcción
55
MK STRUCTURE
6.1.2. Guidelines for structures • Ensure that there are no loose elements on top
of the structure if the dismantling is done by
6.1.2.1. Structure assembly
means of crane.
• Mark and bound an area for the assembly so that
• Ensure that there are no workers in the vertical of
anyone outside the assembly will enter the area.
the removed gang or nearby.
• Ensure the correct fastening of bolts and nuts
• Take special care to ensure structure stability
between different elements, and the correct
when dismantling process.
positioning and tightening of push-pull props.
• Do not accumulate material on the platforms
• Ensure the fastening of ties, nuts, plate nuts, and
while dismantling, it must be lowered while
lots anchors and in general the correct anchorage
dismantling process is making.
of those additional items to be tied to the
ground.
• Ensure the correct anchorage of the previous set,
6.1.3. Guidelines for structures
before placing the next.
• Do not leave any part half-assembled or half- 6.1.3.1. Formwork
dismantled.
• Place some sort of support to store or move the
• Ensure ground resistance to withstand the loads,
formwork panels which prevent their damage
in terms of use, to which it will be subject, and
and ease the building site order, the panel
weather conditions, taking the necessary
cleaning and the transport to their area of
measures (surface cleaning, foundation, …).
operation.
• In the event that loads are important, make a
• Ensure the fastening of plate nuts, and the
geotechnical report and dimension the necessary
correct positioning and anchorage of push-pull
foundation by the contractor.
props to the ground.
• When special foundations are needed, make a
• Ensure the correct anchorage of the previous
foundation project with drawings and
formwork set, before placing the next.
calculations.
• Do not leave any part half-assembled or half-
• Ensure structure stability, making the remarked
dismantled.
anchors according to the project or/and standard
• It is forbidden to climb on formwork except in
configurations.
extraordinary cases duly studied and with
• If any product is spilled on the platforms, it will
appropriate protection systems in place.
be cleaned immediately.
• Before concrete pouring, make sure the
• Do not accumulate material on the platforms,
formwork surfaces are clean.
only have the necessary equipment at all times.
• Clean panels after each use. Wire brushes are not
suitable for cleaning as they are damaging the
6.1.2.2. Dismantling of structures phenolic film of the plywood.
• It is important to state that the phenolic coating
• Inspect the condition of the structure before
rarely suffers from the chemical and abrasive
dismantling, in order to check if any items or
action of the concrete. But where it is already
anchor is missing.
damaged, e.g. at holes and deteriorated areas, it
Construcción
56
MK STRUCTURE
must be thoroughly sealed to prevent any further • Place the concrete in uniform layers of 30 to 45
damage to the plywood. cm.
• Any cut edge of the plywood should be sealed as • For vertical concrete placement, cast the concrete
soon as possible, because cut edges soak up from the least height above the formwork
water from the concrete and swell, thus possible. Do never exceed 2 m height unless a
increasing in thickness. pipe or tube or any similar accessory is used to
• In general, it is not recommended to use nails or channel the concrete. Deposit the concrete as
screws on the plywood. near as possible to the formwork base, centring
• For storage, the panels should be stacked one on on one point without casting directly against the
top of the other, placing wood runners between formwork.
them. Use some sort of support to separate them • When casting with bucket, take special care of
from the ground, and provide shelter. Prolonged not hitting the formwork, and of complying with
sun and rain exposure damages the panels. the maximum load-bearing capacity of the crane.
• Avoid concrete splashes on the plywood as these
will reflect on the finished surface.
6.1.3.2. Release agent
• Use the appropriate method for concrete
• Release agent helps separating the formwork
consolidation and compaction depending on the
from the concrete, and thus increases the
concrete consistency and its workability.
number of uses and the life span of the panel in
• The preferred consolidation and compaction
general.
method for wet cast-in-place concrete are poker
• It plays an important role for the quality of the
vibrators. Use external vibrators only when the
concrete finishing because it prevents holes from
concrete cannot be accessed with poker vibrators
air bubbles on the concrete surface and provides
and for parts moulded already in the workshop.
a uniform colour.
External vibration requires a specific analysis.
• Apply the release agent uniformly and in thin
• Completely immerse the poker 10 to 15 cm into
layers onto the panel, bearing in mind at all times
the concrete, and put it into each area of
the instructions for correct use.
concrete, only once. When concrete is poured in
• Thoroughly clean the panel surface before
layers, place the vibrator into the previous layer
applying the release agent on it. to meld the two layers together.
• Clean the metal frame and the panel off the • Never allow the vibrator to touch the formwork
release agent after every 4 to 5 uses. to prevent exceeding the considered loads.
• Immerse vertically or slightly inclined and quickly,
6.1.3.3. Concrete placement and compaction but withdraw slowly.
Construcción
57
MK STRUCTURE
• Increase the curing time of the concrete when • The material is packed for transport in
facing fast drying and shrinkage due to appropriate containers such as wood or steel
evaporation from wind or low temperatures. pallets, boxes, or strapped in bundles with stable
• The time span between casting and stripping base.
shall be the same for all parts of the concrete • Strap the bundles sufficiently stable to prevent
structure. This is justified when a high finishing them from moving and getting damaged. If
quality is aimed for because the tone of the necessary, protect the items with some sort of
concrete surface depends on how long the buffer.
concrete surface is isolated from the outside. • Cut the metal strap, standing on the side, using
• Ensure the absence of unauthorised people in the gloves and goggles to prevent getting cut by the
vicinity where stripping takes place. bouncing strap or caught in the strap.
• Once stripping is finished, place the formwork on
a sort of support and proceed with its cleaning
6.2.2. Transport
and dismantling, if it is not going to be used for
further casts. • Ensure the stable loading of the material,
complying with the instructions of the driver
(equilibrated distribution on the lorry bed,
fastening of auxiliary items, etc.).
6.2. TRANSPORT, HANDLING AND • Keep your distance when opening the containers
STORAGE after transport to prevent injuries from falling
objects.
6.2.1. General guidelines
Construcción
58
MK STRUCTURE
6.2.3.2. Mechanical handling of loads • Ensure the stability of any piles, bearing in mind
the following aspects:
• Only statutory mechanical lifting devices,
- Load-bearing capacity of the ground
appropriate for the operation are allowed for
- Varying ground levels
use.
- Levelling of the packages
• Check the condition of the lifting gear such as
- Package or container support
slings or cables before each use and report any
- Package stability
defects.
- State of the strap
• Place lifting accessories and step back to a secure
- State and capacity of the containers used
distance from the load and other materials which
- Do not stack full containers on top of empty
could get affected.
or half-empty containers
• Comply with all instructions given by the team
- External conditions (wind, risk of another
chef who is specifically trained for this.
object hitting the pile, etc.)
• Cause no sudden acceleration or deceleration of
the moving load.
• When conducting difficult or dangerous lifting
operations, or in the case that the crane operator
has no obstruction free visual control of the 6.3. INSPECTION AND MAINTENANCE
entire trajectory of the load, the crane operations
6.3.1. General guidelines
are directed by a banksman who is in constant
communication with the crane operator by • ULMA is responsible for the delivery of the
means of a previously agreed sign code. products, for sale or rent, in good working
from distance. Keep hands clear of suspended • From the moment of delivery, the responsibility
load if hands could get caught between the load for correct use, inspection and product
and another object. Swinging and/or unforeseen maintenance passes on to the purchaser or
movements with the load can cause serious lessee. All damaged and broken parts, parts with
accidents. missing components, i.e. all parts in no proper
working condition must be removed from
service.
6.2.4. Storage
• For use, inspection and maintenance of the
• Proper storage of the parts is fundamental to product, special attention should be paid to the
keep them in good working condition. following points:
• Wherever possible, store the material in a place - Items aimed to ensure people´s safety
protected from atmospheric impact to avoid - Items made of aluminium, as they are more
wear. vulnerable to damages of the welded joints
• It is recommended to place parts of the same and deformation
type and dimensions in its respective container
(boxes, steel pallets, etc.).
Construcción
59
MK STRUCTURE
6.3.2. Inspection instructions of elements appliances 6.3.3. Inspection instructions with CE marking of
with CE marking of ULMA Construcción equipment marketed by ULMA Construcción
Before each use, the condition of element appliances Equipment with CE marking marketed by ULMA
with CE marking must be checked. In case that it Constucción is checked following the instructions
does not fulfil all defined requirements, it must be stipulated in the User´s Guide of the respective
removed from service. product.
Construcción
60
MK STRUCTURE
7. LEGAL REFERENCES
• Council Directive 89/391/EEC of 12 June 1989 on the introduction of measures to encourage improvements in
the safety and health of workers at work.
• Council Directive 89/654/EEC of 30 November 1989 concerning the minimum safety and health requirements
for the workplace.
• Council Directive 89/656/EEC of 30 November 1989 on the minimum health and safety requirements for the
use by workers of personal protective equipment at the workplace.
• Council Directive 90/269/EEC of 29 May 1990 on the minimum health and safety requirements for the manual
handling of loads where there is a risk particularly of back injury to workers.
• Council Directive 92/57/EEC of 24 June 1992 on the implementation of minimum safety and health
requirements at temporary or mobile construction sites.
• Council Directive 92/58/EEC of 24 June 1992 on the minimum requirements for the provision of safety and/or
health signs at work.
• Council Directive 89/655/EEC - Council Directive 95/63/EEC - Directive 2001/45/EC of the European Parliament
and of the Council of 27 June 2001 amending Council Directive 89/655/EEC concerning the minimum safety
and health requirements for the use of work equipment by workers at work.
• Directive 2002/44/EC of the European Parliament and of the Council of 25 June 2002 on the minimum health
and safety requirements regarding the exposure of workers to the risks arising from physical agents (vibration).
• Directive 2003/10/EC of the European Parliament and of the Council of 6 February 2003 on the minimum
health and safety requirements regarding the exposure of workers to the risks arising from physical agents
(noise).
• Directive 2006/42/EC of the European Parliament and of the Council of 17 May 2006 on machinery, and
amending Directive 95/16/EC (recast).
Standards:
• EN 12812:2008 Falsework. Performance requirements and general design
• EN 12811-1 Temporary works equipment. Part 1: Scaffolds. Performance requirements and general design
• EN 12811-2 Temporary works equipment. Part 2: Information on materials
• EN 12811-3 Temporary works equipment. Part 3: Load testing
• EN 13374 Temporary edge protection systems. Product specifications, test methods
• EN 74-1 Couplers, spigot pins and baseplates for use in falsework and scaffolds. Part 1: Couplers for tubes.
Requirements and test procedures
• EN 74-2_Couplers, spigot pins and baseplates for use in falsework and scaffolds. Part 2: Special couplers.
Requirements and test procedures
• EN 74-3_Couplers, spigot pins and baseplates for use in falsework and scaffolds. Part 3: Plain base plates and
spigot pins. Requirements and test procedures.
Construcción
61
ULMA Construcción around the world
www.ulma-c.com
LUBLIN Branch
LUBLIN Office
BIAŁYSTOK Office
EUROPE
ZACHÓD REGION
Germany POZNAŃ Branch
ULMA Betonschalungen POZNAŃ Office
und Gerüste GmbH BYDGOSZCZ Office
RÖDERMARK
www.ulma-c.de GDAŃSK Branch
GDAŃSK Office
Nordwest Branch SZCZECIN Office
NEUSS
WROCŁAW Branch
Südwest Branch WROCŁAW Office
GÖPPINGEN NOWA SÓL Office
POŁUDNIE REGION
France
JAWORZNO Branch
ULMA, S.A.R.L.
JAWORZNO Office
BONDOUFLE
ŁÓDŹ Office
www.ulma-c.fr
IDF Branch
Portugal
BONDOUFLE
ULMA Portugal Lda.
Eguilles Branch São João da Talha - LISBON
EGUILLES www.ulma-c.pt
Lille Branch
LA CHAPELLE D’ARMENTIÈRES Czech Republic
ULMA Construcción CZ, s.r.o.
Lescar Branch BENÁTKY NAD JIZEROU
LESCAR www.ulma-c.cz
Evénements Branch
LONS Slovac Republic
ULMA Construccion SK, s.r.o.
Tarnos Branch BRATISLAVA
TARNOS www.ulma-c.sk
Italy Romania
ALPI, S.P.A. ULMA Cofraje s.r.l.
MONGUELFO (BZ) BUCHAREST
www.alpionline.net www.ulma-c.ro
Kazakhstan Ukraine
ULMA Kazakhstan ULMA Formwork Ukraine Ltd.
ASTANA KIEV
www.ulma-c.kz www.ulma-c.com
Construcción
USA
ULMA Form Works, Inc.
Hawthorne - NEW JERSEY
www.ulma-c.us
Mid-Atlantic Branch
(Baltimore)
Jessup - MARYLAND
Spain
Mexico ULMA C y E, S. Coop.
ULMA Cimbras y Andamios de www.ulma-c.es
AMERICA
México S.A. de C.V.
TLALNEPANTLA ANDALUCÍA Branch
Argentina ALCALÁ DE GUADAIRA (Sevilla)
(Mexico State)
ULMA Andamios y Encofrados PELIGROS (Granada)
www.ulma-c.com.mx
Argentina, S.A.
CAPITAL FEDERAL ARAGÓN Branch
www.ulma-c.com.ar PEDROLA (Zaragoza)
Peru
ULMA Encofrados Perú, S.A.
CANARIAS Branch
Brazil LIMA
INGENIO (Las Palmas)
ULMA Brasil - Fôrmas e www.ulma-c.com.pe
GÜIMAR (Tenerife)
Escoramentos Ltda.
Itapevi - SP Norte Branch
CASTILLA Branch
www.ulma-c.com.br Chiclayo - LAMBAYEQUE
CIGALES (Valladolid)
GIJÓN (Asturias)
Rio de Janeiro Branch
Ramos - Rio de Janeiro - RJ CATALUÑA Branch
POLINYA (Barcelona)
Centro-Oeste Branch LLUCMAJOR (Illes Balears)
Gama - Brasilia DF
CENTRO Branch
Salvador Branch COBEÑA (Madrid)
Centro - Lauro de Freitas - BA AJOFRÍN (Toledo)
Sur Branch
CONCEPCIÓN India
ULMA FORMWORK SYSTEMS
INDIA PVT. LTD.
GURGAON - Haryana
www.ulma-c.in
Singapore
ULMA Formwork Singapore PTE. LTD.
SINGAPUR
www.ulma-c.sg
Construcción