9078 - 13!02!02 - Pull-Out Testmethod Statement Lot 2 Rev 01
9078 - 13!02!02 - Pull-Out Testmethod Statement Lot 2 Rev 01
9078 - 13!02!02 - Pull-Out Testmethod Statement Lot 2 Rev 01
FOR
9078/13/02-02 - 400KV
FOR THE
Siseko W Mdlokolo
Name Avinash Lal Ramesh Subbiah
R S Batcha
Date 16.06.2019
Signature
Page 2 of 12
1
TABLE OF CONTENTS
8.0 INSPECTION.................................................................................................................. 9
10.0 RECORDS...................................................................................................................... 10
Page 3 of 12
1
1.0 PURPOSE
This Method statement details the procedure of installation & Pull out testing of anchor foundation.
2.0 REFERENCES
BPC Technical Specification
Applicable codes & standards as per contract
Accepted Design Drawings
Baseline Risk Assessment
Approved Technical Data Sheet Approved PQP
Approved SHE Plan
EC Engineering Consultants
SC Subcontractor
Page 4 of 12
1
SHE File
The subcontractor shall be required to comply with all Project SHE aspects in line with the L&T SHEQ
policy, BPC Safety requirements, EIA and EMP recommendations and Project Quality Plan. The
subcontractor shall accede to the mandatory agreement as prescribed by L&T and the following shall
be submitted for review and approval prior to commencement of work;
Workmen cover/insurance
Employee competencies
Employee Identities
Employee medical certificates
Project Specific Induction
PPE issue
Risk Assessment & Hazard identification
Risk Assessments & Hazard Identification shall be prepared including mitigation measures, and
responsibility for implementation. This shall be coordinated with site Safety In-charge and attach to
this method statement.
Hazard Identification, Risk Assessment plan showing activity, risk, mitigation measures,
responsibility are prepared to ensure safe working. Activity based HIRA plan is attached in this
method statement.
Before commencing any work, all permits shall be checked and ensured that they are valid until
completion of activity.
All works shall be referred to the Drawings and specifications.
All materials shall be approved, sampled, tested, & accepted (as applicable) by client prior to
incorporation to the work.
All staff and workmen shall wear Personnel Protective Equipment (PPE).
Toolbox talks shall be conducted every day before commencement of work.
All personnel shall be cautioned while working near live lines and other services.
Prior to commencement of activities/works, the entire area shall be barricaded.
Adequate sign boards shall be kept to forewarn all.
Accumulated debris shall be cleared from the work site on daily basis.
It will be ensured that all men working in high-level are wearing necessary safety harness complying
with the safety requirements and following precautionary measures on safety aspects.
All plant and equipment shall be calibrated and accompanied by the competent operators prior to
commencement of any works.
Page 5 of 12
1
to be kept on file.
The L&T Site Manager will ensure that the internal resources are available to carry out the works as
scheduled. The L&T Engineer and Subcontractor is responsible for conducting pull out testing as per
method statement/approved drawings and as per Contract Specifications and report completed works
to the Site Manager on a daily basis.
Ensure latest approved drawing available at site prior to start work. Conduct training and awareness
programs for all personnel deployed for the activity.
Follow up & Co-ordinate with design engineering team for preparation and approval of drawings.
Ensure method statement is prepared, established and control measures taken before starting the
work and guiding team for implementation.
Obtain necessary approval as per contract requirement.
Page 6 of 12
1
PPE & Equipment as per the BPC SHE Specification and L&T SHE Plan
6.3 Earthing Testing (Ref: Botswana Power Corporation Specification for 420 kV single circuit overhead
transmission line Letlhakane to Mawana Substation and Associated Works item 46 “EARTHING OF
TOWERS”)
Page 8 of 12
1
Measurement of the electrical resistance to earth of each tower before the earth conductor/s
are installed.
Where counterpoise is installed an electrical resistance reading to earth shall also be taken
after the counterpoise is installed.
The three-point method is the most thorough and reliable test method; used for measuring
resistance to earth of an installed grounding electrode.
With a four terminal tester, P1 and C1 terminals on the instrument are jumpered and connected
to the earth electrode under test while the C2 reference rod is driven into the earth straight out as
far from the electrode under test as possible. Potential reference P2 is then driven into the earth, at
a set number of points, roughly on a straight line between C1 and C2. Resistance readings are
logged for each P2 point.
Correct earth resistance is read from the curve for the distance that is roughly 62% of the total
distance between C1 and C2.
General prevailing ground conditions (e.g. dry, wet etc.) shall also be recorded when
measuring tower electrical resistances.
6.4 Backfilling
Excavated soil suitable for backfill will be returned to the excavation by backfilling with the
subsoil first and the top soil last.
The distribution of material shall be such that the compacted material will be homogenous to
secure the best practicable degree of compaction, impermeability, stability and no water
deposition.
Material removed from the excavation, which is either not suitable or not required for backfill,
shall be spread evenly over or adjacent to the site.
Page 9 of 12
1
Soil Resistivity is most necessary when determining the design of the grounding system for
new installations to meet ground resistance requirements. Ideally to find a location with the
lowest possible resistance. As poor soil conditions can be overcome with more elaborate
grounding systems. The soil composition, moisture content, and temperature all impact the
soil resistivity. Soil is rarely homogenous and the resistivity of the soil will vary geographically
and at different soil depths. Moisture content changes seasonally, varies according to the
nature of the sub layers of earth, and the depth of the permanent water table. Since soil and
water are generally more stable at deeper strata, it is recommended that the ground rods be
placed as deep as possible into the earth, at the water table if possible. Also, ground rods
should be installed where there is a stable temperature, i.e. below the frost line. For a
grounding system to be effective, it should be designed to withstand the worst possible
conditions.
Calculate soil resistivity: The measuring procedure described below uses the universally
accepted Wenner method. The formula is as follows: ρ = 2 p A R (ρ = the average soil resistivity
to depth A in ohm—cm) p = 3.1416 A = the distance between the electrodes in cm R = the
measured resistance value in ohms from the test instrument.
Procedure to measure soil resistance: To test soil resistivity, connect the ground tester as
shown below. Four earth ground stakes are positioned in the soil in a straight line, equidistant
from one another. The distance between earth ground stakes should be at least three times
greater than the stake depth. So if the depth of each ground stake is one foot (30 meters), make
sure the distance between stakes is greater than three feet (.91 meters).
Principle: The Soil resistivity tester generates a known current through the two outer ground
stakes and the drop in voltage potential is measured between the two inner ground stakes.
Using Ohm’s Law (V=IR), the Soil resistivity tester automatically calculates the soil resistance.
By changing the depth and distance several times, a profile is produced that can determine a
suitable ground resistance system.
Page 10 of 12
1
FIRE 997
998
AMBULANCE
POLICE 999
77780973 / 77138257
PROJECT MANAGER
Page 11 of 12
1
Malatswai 4639561
Dimajwe 4620346
10.0 RECORDS
Document TFR Checking report
Document Soil resistivity report
Page 12 of 12