Flow Chart Beton Instan
Flow Chart Beton Instan
Flow Chart Beton Instan
COST ( RUPIAH )
NO ELEMENT COST UNIT QTY
Rp / Unit Amount (Rp)
1 2 3 4 5 6 = 4+5
A. LABOUR COST
1. Supervisor hr 0.0670 150,000.00 10,050.00
2. Foreman hr 0.1334 140,000.00 18,676.00
3. Laborat hr 0.2668 140,000.00 37,352.00
4. Laborat Helper hr 0.5336 125,000.00 66,700.00
5. Skilled Labour hr 0.2668 125,000.00 33,350.00
6. Unskilled Labour hr 0.5336 120,000.00 64,032.00
Sub Total (A) 230,160.00
B. HEAVY EQUIPMENT
1. Dry Aggregat Mechine hr 0.025 350,000.00 8,750.00
2. Wheel Loader hr 0.025 250,000.00 6,250.00
3. Solar ltr 20 12,500.00 250,000.00
4. Aqitator Mixer Dry hr 0.285 325,000.00 92,625.00
5. Tools ls 1.000 150,000.00 150,000.00
Sub Total (B) 507,625.00
C. MATERIALS
1. Portland Cement (PPC) kg 400 1,000.00 400,000.00
2. Coarse Aggregate (1-2 cm) Cu.m 0.68 300,000.00 204,000.00
3. Coarse Aggregate (2-3 cm) Cu.m - 200,000.00 -
4. Sand Cu.m 0.524 300,000.00 157,200.00
5. Bag pc 48 10,000.00 480,000.00
6. Additive kg 10.00 115,000.00 1,150,000.00
0.12 Sub Total (C) 2,391,200.00
Sub Total ( A + B + C ) 3,128,985.00
Profit 20 % 625,797.00
DRY MIX K.300 Total Unit Of Work 3,754,782.00
Rounded 78,229.17
Flow Proses Produksi Beton Instan
Mulai
Dryer Dryer
Silo Silo
Timbangan
Silo
Mesin Packing
Selesai