Method Statement

The document is a method statement form outlining the landscaping works for a construction project involving 6 buildings on lots 39918-39923. It details 4 tasks needed to complete the landscaping: 1) Excavating 1112 sqm of oversite which will take 17.5 days, 2) Compacting the excavated area which will take 12 days, 3) Applying a 200mm layer of hardcore which will take 17.5 days, and 4) Applying a 50mm sand blanket which will take 23 days to complete. Machinery and labor needs are specified for each task.

Uploaded by

Asyraf Hakeem
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
288 views

Method Statement

The document is a method statement form outlining the landscaping works for a construction project involving 6 buildings on lots 39918-39923. It details 4 tasks needed to complete the landscaping: 1) Excavating 1112 sqm of oversite which will take 17.5 days, 2) Compacting the excavated area which will take 12 days, 3) Applying a 200mm layer of hardcore which will take 17.5 days, and 4) Applying a 50mm sand blanket which will take 23 days to complete. Machinery and labor needs are specified for each task.

Uploaded by

Asyraf Hakeem
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 6

ONE EXCEL CONSTRUCTION SDN. BHD.

SURIA CITY, JALAN PJU 1/32, 47401


PETALING JAYA SELANGOR
NO TEL : +603 – 94621901 NO FAX: +603 - 94620055
[email protected]

Method Statement Form


PROJECT : MEMBANGUNKAN 6 LOT BANGUNAN KEDAI PEJABAT 5 TINGKAT YANG MENGANDUNGI 5 UNIT KEDAI PEJABAT DUA TINGKAT
DAN 1 UNIT HOTEL BUDGET 84 BILIK DI ATAS LOT 39918 – 39923
PREPARED BY : MUHAMMAD SYAZWAN BIN JAMALUDDIN DATE :
ELEMENT : LANDSCAPING WORKS PAGE NO :

MACHINERY / MANPOWER /
NO. TASK QUANTITY SEQUENTIAL DIAGRAM OUTPUT DURATION
TOOLS LABOUR

1 Excavate oversite to 1112 m2 2 Excavator 2 Operator Labour constant: 17 ½ days


formation level 0.25hrs (15min) /
commencing from 1 m2
reduce level, get out,
load, wheel, spread, 15min x 1112 m2
levelled and = 34day 6hrs for 1
consolidated directed excavator
on site.
35day / 2 excavator
= 17day 4hrs
ONE EXCEL CONSTRUCTION SDN. BHD.
SURIA CITY, JALAN PJU 1/32, 47401
PETALING JAYA SELANGOR
NO TEL : +603 – 94621901 NO FAX: +603 - 94620055
[email protected]

Method Statement Form


PROJECT : MEMBANGUNKAN 6 LOT BANGUNAN KEDAI PEJABAT 5 TINGKAT YANG MENGANDUNGI 5 UNIT KEDAI PEJABAT DUA TINGKAT
DAN 1 UNIT HOTEL BUDGET 84 BILIK DI ATAS LOT 39918 – 39923
PREPARED BY : MUHAMMAD SYAZWAN BIN JAMALUDDIN DATE :
ELEMENT : LANDSCAPING WORK PAGE NO :

MACHINERY / MANPOWER /
NO. TASK QUANTITY SEQUENTIAL DIAGRAM OUTPUT DURATION
TOOLS LABOUR

2 Compaction of all road 1112 m2 2 roller compactor 2 operator Labour constant: 12 days
formation levels as 0.17hr (10min) /
described before the 1 m2
commencement of any
construction thereon. 10min x 1112 m2
= 23day 1hr 22min
for 1 roller
compactor

23 ½ day / 2 roller
compactor
= 11.75 days
ONE EXCEL CONSTRUCTION SDN. BHD.
SURIA CITY, JALAN PJU 1/32, 47401
PETALING JAYA SELANGOR
NO TEL : +603 – 94621901 NO FAX: +603 - 94620055
[email protected]

Method Statement Form


PROJECT : MEMBANGUNKAN 6 LOT BANGUNAN KEDAI PEJABAT 5 TINGKAT YANG MENGANDUNGI 5 UNIT KEDAI PEJABAT DUA TINGKAT
DAN 1 UNIT HOTEL BUDGET 84 BILIK DI ATAS LOT 39918 – 39923
PREPARED BY : MUHAMMAD SYAZWAN BIN JAMALUDDIN DATE :
ELEMENT : LANDSCAPING WORK PAGE NO :

MACHINERY / MANPOWER /
NO. TASK QUANTITY SEQUENTIAL DIAGRAM OUTPUT DURATION
TOOLS LABOUR

3 Apply 200mm thick 1112 m2 2 Excavator 2 Operator Labour constant: 17 ½ days


(finished thickness) 0.25hrs (15min) /
bed of hardcore 1 m2
consolidated, watered
and blinded with sand 15min x 1112 m2
to receive concrete = 34day 6hrs for 1
paver excavator

35day / 2 excavator
= 17day 4hrs
ONE EXCEL CONSTRUCTION SDN. BHD.
SURIA CITY, JALAN PJU 1/32, 47401
PETALING JAYA SELANGOR
NO TEL : +603 – 94621901 NO FAX: +603 - 94620055
[email protected]

Method Statement Form


PROJECT : MEMBANGUNKAN 6 LOT BANGUNAN KEDAI PEJABAT 5 TINGKAT YANG MENGANDUNGI 5 UNIT KEDAI PEJABAT DUA TINGKAT
DAN 1 UNIT HOTEL BUDGET 84 BILIK DI ATAS LOT 39918 – 39923
PREPARED BY : MUHAMMAD SYAZWAN BIN JAMALUDDIN DATE :
ELEMENT : LANDSCAPING WORK PAGE NO :

MACHINERY / MANPOWER /
NO. TASK QUANTITY SEQUENTIAL DIAGRAM OUTPUT DURATION
TOOLS LABOUR

4 Apply 50mm layer of 1112 m2 1 Excavator 2 Operator Labour constant: 23 days


sand blanket well rolled 1 Roller compactor Excavator
and consolidated to 0.08hr (5min) /
falls and camber as 1 m2
described.
5min x 1112 m2
= 11day 4hr 39min
for 1 excavator

Labour constant:
Roller compactor
0.08hr (5min) /
1 m2

5min x 1112 m2
= 11day 4hr 39min
for 1 roller
compactor

Total = 23days
ONE EXCEL CONSTRUCTION SDN. BHD.
SURIA CITY, JALAN PJU 1/32, 47401
PETALING JAYA SELANGOR
NO TEL : +603 – 94621901 NO FAX: +603 - 94620055
[email protected]

Method Statement Form


PROJECT : MEMBANGUNKAN 6 LOT BANGUNAN KEDAI PEJABAT 5 TINGKAT YANG MENGANDUNGI 5 UNIT KEDAI PEJABAT DUA TINGKAT
DAN 1 UNIT HOTEL BUDGET 84 BILIK DI ATAS LOT 39918 – 39923
PREPARED BY : MUHAMMAD SYAZWAN BIN JAMALUDDIN DATE :
ELEMENT : LANDSCAPING WORK PAGE NO :

MACHINERY / MANPOWER /
NO. TASK QUANTITY SEQUENTIAL DIAGRAM OUTPUT DURATION
TOOLS LABOUR

5 Construct and complete 1112 m2 1 bucket 1 skill labour Labour constant: 12 days
115mm thick brickwall 1 shovel 4 general labour 0.08hr (5min) /
with concrete base 1 trowel 1 m2
including all necessary
excavation, formwork 5min x 1112 m2
and reinforcement. = 11day 4hr 39min
ONE EXCEL CONSTRUCTION SDN. BHD.
SURIA CITY, JALAN PJU 1/32, 47401
PETALING JAYA SELANGOR
NO TEL : +603 – 94621901 NO FAX: +603 - 94620055
[email protected]