0% found this document useful (0 votes)
2K views1 page

Manpower Histogram

The document is a construction program detailing planned and actual manpower for building a water distribution network in Al Batinah region of Oman from March 2019 to October 2019. The program shows that actual manpower exceeded plans from March to June but fell below plans from July to October as the project progressed on schedule with planned reductions in workforce.

Uploaded by

Dilip Kumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
2K views1 page

Manpower Histogram

The document is a construction program detailing planned and actual manpower for building a water distribution network in Al Batinah region of Oman from March 2019 to October 2019. The program shows that actual manpower exceeded plans from March to June but fell below plans from July to October as the project progressed on schedule with planned reductions in workforce.

Uploaded by

Dilip Kumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Construction of Water Distribution Network for Nakhal,Awabi Wadi Al-Maawil Wilayats in Al-Batinah Region –Phase (1)

Tender No. 21/2015


CONSTRUCTION DETAILED PROGRAMME

MANPOWER HISTOGRAM
250

231

200
188 188

174
168 165
155
151
150

134

108 110 108


100
100
90
85 85

50

0
Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug Sep Oct

Description Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug Sep Oct

Planned Manpower(Nos) 168 165 155 151 134 110 100 90

Actual Manpower (Nos) 231 188 188 174 108 108 85 85