0% found this document useful (0 votes)
334 views1 page

Pipeline - Team Wise Productivity PDF

The document provides a summary of pipeline construction progress across multiple zones. It shows the total pipe length, average productivity in meters per day, number of construction teams, and estimated duration in days to complete the work for each zone. The longest pipeline is in Zone-2E at 14,076.95 meters, which will be completed by 4 teams over 56 days. The shortest pipeline is in Zone-1 at 1,204 meters, which will be completed by 1 team over 17 days.

Uploaded by

Dilip Kumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
334 views1 page

Pipeline - Team Wise Productivity PDF

The document provides a summary of pipeline construction progress across multiple zones. It shows the total pipe length, average productivity in meters per day, number of construction teams, and estimated duration in days to complete the work for each zone. The longest pipeline is in Zone-2E at 14,076.95 meters, which will be completed by 4 teams over 56 days. The shortest pipeline is in Zone-1 at 1,204 meters, which will be completed by 1 team over 17 days.

Uploaded by

Dilip Kumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

 SUMMARY OF PIPELINE

Total Pipe Length  Avg 
SL No. Zones No of Teams Duration
(m.) Productivity

Productivity/LM 
1 Zone‐1 1204.000 70 1 17

2 Zone‐2A 10733.900 66 3 54

Zone‐2B 12909.300 70 3 61

Zone‐2C 10761.250 70 2 77

Zone‐2D 7823.600 63 2 62

Zone‐2E 14076.950 63 4 56