Construction Project Reporting

The document provides a status update on the construction activities of a solar power plant project. It lists 18 main activities along with their unit of measurement, scope, percentage completed and current status. Most activities are still in progress with expected completion dates ranging from late October to late November. A few activities have yet to start. The transmission line installation work is also ongoing with pole erection 24% complete and other activities yet to commence.

Uploaded by

Ghanshyam Singh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
78 views6 pages

Construction Project Reporting

The document provides a status update on the construction activities of a solar power plant project. It lists 18 main activities along with their unit of measurement, scope, percentage completed and current status. Most activities are still in progress with expected completion dates ranging from late October to late November. A few activities have yet to start. The transmission line installation work is also ongoing with pole erection 24% complete and other activities yet to commence.

Uploaded by

Ghanshyam Singh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 6

Sr.NO.

Activities UOM Scope Completed

1 Boundary wall construction Mtrs 2770 2065


2 MMS piling work Nos 7450 6818
3 MMS superstructure installation Mtrs 764 701
4 Module installation Nos 44700 40440
MCR Room & Equipment foundation
5 Set 1 0.76
construction
6 DC/AC cable trench work Mtrs 9000 7500
7 DC cabling Mtrs 47289 37200
8 LVAC cabling Mtrs 11045 7734
9 HT cabling Mtrs 1129 0
10 String inverter Installation Nos 67 0
11 Equipment Foundation work Set 8 8
12 Equipment Erection Set 8 0
13 AC/DC Equipment testing Set 1 0
14 Transmission line laying Mtrs 4.8 0

15 PPS Bay construction & Equipment erection Set 1 0

16 Plant Charging & Commissioning (COD) Set 1 0


17 MCS system development Set 1 0
18 Monitoring system configuration Set 1 0
Schedule
% Progress Remarks
Start Finish
24-Jul-19 29-Jul-19 75% Work in progress
12-Aug-19 18-Oct-19 92% Work in progress
15-Sep-19 21-Oct-19 92% Work in progress
21-Sep-19 22-Oct-19 90% Work in progress

5-Sep-19 24-Oct-19 76% Work in progress

19-Sep-19 30-Oct-19 83% Work in progress


13-Oct-19 4-Nov-19 79% Work in progress
8-Oct-19 4-Nov-19 70% Work in progress
25-Oct-19 4-Nov-19 0% Yet to start
5-Oct-19 2-Nov-19 0% Work in progress
5-Oct-19 20-Oct-19 100% Completed
21-Oct-19 2-Nov-19 0% Yet to start
15-Nov-19 15-Nov-19 0% Yet to start
22-Oct-19 13-Nov-19 0% Yet to start

16-Oct-19 11-Nov-19 0% Yet to start

15-Nov-19 15-Nov-19 0%
4-Nov-19 26-Nov-19 0% Yet to start
6-Nov-19 12-Nov-19 0% Yet to start
Schedule
Activity Description UOM Scope Completed Balance
Start
Bay allocation approval Lot 1 1 0

GELO approval Lot 1 1 0 14-Oct-19

Permit for self execution Lot 1 1 0 26-Oct-19

Equipment foundation works Lot 1 0.05 0.95 23-Oct-19

Structure erection Lot 1 0 1 1-Nov-19

Equipment Installation Lot 1 0 1 5-Nov-19

Equipment Testing Lot 1 0 1 24-Nov-19


Schedule
% Progress Remarks
Finish
10-Oct-19 100% Approved

24-Oct-19 100% Approved

23-Oct-19 100% Approved

2-Nov-19 5% In Progress

10-Nov-19 0%

20-Nov-19 0%

24-Nov-19 0%
Schedule
Activity Description UOM Scope Completed Balance
Start

TL route profile approval Lot 1 1 0 12-Sep-19

Permit for self execution Lot 1 1 0 14-Oct-19

ROW for TL Lot 1 0.25 0.75 22-Oct-19

Excavation & Pole erection Nos 174 24 150 24-Oct-19

TL Hardware fitting Set 174 0 174 1-Nov-19

Conductor Stringing KM 4.8 0 4.8 15.11.2019


Schedule
% Progress Remarks
Finish

14-Oct-19 100% Approved

17-Oct-19 100% Approved

15-Nov-19 25% Work in progress

10-Nov-19 14% Work in progress

18.11.2019 0%

20.11.2019 0%