Estimation - Construction Time Management
Estimation - Construction Time Management
Estimation - Construction Time Management
CONSTRUCTION TIME
MANAGEMENT
CONTENT:
I.THEORY OF ESTIMATING
II.ESTIMATING PRINCIPLES
III.BASIC ESTIMATING PROCESS AND
PROCEDURE
ABETRIA, JUANA L.
I. THEORY OF ESTIMATION
One of the major applications of statistics is to estimate the unknown population parameter. For
example, what is Estimation, a poll may seek to estimate the portion of adult residents of a city
who are unemployed. The process of providing numerical values to the unknown parameter of the
population is known as estimation. The theory of estimation was founded by Prof. R.A. Fisher in
a series of fundamental papers round about 1930 and includes some important characteristics and
Basic Terminologies
Population: A group of individuals under study is called population. The population may be finite
Sample: A finite subset of statistical individuals in a population. E.g. Selecting some voters from
Statistic: The statistical constants of the sample such as mean (X̄), variance (s2) etc. In other
words, any function of the random sample x1, x2, xn that are being observed say, Tn is called a
Estimate: A particular value of the estimator is called an estimate of an unknown parameter. Eg.
Mean income of selected voters is ₹25000 which represents mean income of all the registered
voters.
Sampling Distribution: When the total probability is distributed according to the value of statistic
then the distribution is said to be sampling distribution. Eg. If we want the average height of a
voter, we can randomly select some of them and use the sample mean to estimate the population
mean.
Standard Error: The standard deviation of the sampling distribution of a statistic is known as its
standard error and is denoted by ‘s.e.’ Eg. If we want to know the variability of the height of voters,
Now, before discussing about different methods of finding estimates of unknown population
parameter, it is important to know the characteristics of a good estimator. Here, “a good estimator”
is one which is close to the true value of the parameter as much as possible. The following are
1. Unbiasedness
2. Consistency
3. Efficiency
4. Sufficiency
Hence, now you have the basic understanding about the theory of estimation.
FROM: https://stepupanalytics.com/theory-of-estimation-or-what-is-estimation/
The introduction to cost management explored the importance of the differences between the
product and project life cycles. Understanding the total cost of the product life cycle is important
The project manager's main focus, however, is on developing estimates of project life cycle cost,
meaning all costs related to producing the product, service, or result of the project. Estimates
evolve and are refined as the project proceeds through its phases and stages.
Estimating is challenging, especially in the early stages of planning a project. As noted, cost
estimating, like all of the planning processes, is iterative. Initial estimates for some tasks may have
to suffice until later in the project, when more specific information becomes available.
This new information allows a more detailed estimate to be generated. The evolution of the
estimate as the project unfolds mirrors the refinement of the work breakdown structure (WBS);
initially, WBS components are listed at a relatively high level, and they are further decomposed as
It is important for project managers to manage senior management and stakeholder expectations
regarding estimates.
Far from commitments, early in the project estimates may be little more than approximations, but
these approximations will become more precise as the team learns more about the details of future
work from completing more elements of the definition of the project's product or service.
What is an estimate?
An estimate is not the same as a random guess or a bid, but is the derivation of an approximate
value based on one or more rational methods. An estimate uses available data for comparable
activities, components or events, and extrapolates or interpolates to the current situation being
In a limited number of instances, duration or resource requirement values may be a given. For
example, a test procedure may be defined as always running for a set number of hours. Another
example is that concrete takes a known amount of time to cure before construction can begin on
it, based on the environmental temperature and the mixture used. In these examples, the values are
resource effort will be. The project manager will not be able to account accurately for some factors,
such as large changes in requirements that were not factored into a project's original assumptions.
In some organizations, the project manager is not responsible for developing the cost estimates. A
qualified cost-estimating department may develop these instead. In other circumstances, the costs
of certain types of resources, for example, in-house staff labor, are not factored into the project
costs.
Within the general practice of project management, it remains the responsibility of the project
manager to understand and be able to justify the estimated project costs, whether or not he or she
Estimating range
It is the project manager's responsibility to communicate to the project sponsor the degree of
accuracy in the estimates. A single point number cannot provide sufficient understanding of the
uncertainties at the beginning stages of the project. The accuracy of estimates varies significantly
based on the information available at the time the estimating process is performed and the method
Preparing cost estimates is an iterative process, performed throughout the project life cycle. As
more information is discovered, the cost estimate should be revised to reflect the most current and
accurate cost data available. Each time a cost estimate is revised, the project manager should
review and evaluate the cost estimate to ensure that the proper technique was applied, based on
The information presented below suggests the characteristics of estimates as the project unfolds
and the appropriate accuracy at that point. The subsequent sections further map these
When done: Very early in the project life cycle, during initial planning
* The percentages of accuracy indicated for these types of estimates vary within industries and
application areas. The general theme is that the range of accuracy is quite broad for ROM
estimates, even up to -50% to +100% in the identification phase. The accuracy range is tightened
as one moves through the project to develop budgetary and definitive estimates.
Budgetary
When done: Early, during the project definition phase as scope is defined and agreed upon
Why done: Puts dollars in the budget plans and establishes a baseline commitment to the project
sponsor
Planning estimates
Planning estimates are normally created for a proposed project before the conceptual design is
completed. Planning estimates are used to set cost estimates for early project work involving scope
determination and feasibility study efforts and for a preliminary budget estimate of the total project
costs.
Planning estimates are based on drawing analogies from past cost experience with similar projects,
where available. Rough Order of Magnitude estimates are planning estimates used in the absence
Planning estimates are typically only approximations. It is imperative that the estimator fully
describe and document the basis of the estimate, including how the estimate was prepared and any
Ensuring that the project offers sufficient benefit for the estimated cost.
Developing a reliable project cost estimate consistent with the proposed schedule.
In a software engineering project, the conceptual design estimate tells the customer approximately
what it will cost to complete the project within the scope defined in the project scope statement.
The conceptual estimate will be based on any available conceptual design information, such as
The preliminary design and system design estimates are intermediate estimates created for two
purposes:
Verifying that the newly available design details still support the conclusion that the revised
Breaking down the cost budget to the work package level for the upcoming phase, to
Preliminary design estimates are based on the specifications that have just been developed.
Upon approval of system design and during subsequent delivery stages, system design estimates
become definitive estimates. They are updated during project monitoring and control to predict
Fundamentally, life cycle costing is important because it helps to ensure that the least expensive
alternative that will meet a project's functional requirements is selected. Initial design and
development costs may constitute only a fraction of a project's overall life cycle costs.
Estimating accuracy
The precision necessary for an estimate depends on its context. For example, the earliest estimate
for a project's cost at the concept evaluation stage may be a rough order of magnitude estimate,
which is good enough to determine whether the project should be pursued or not. Additional
accuracy would not affect the decision, so making the effort to obtain it is not cost-effective.
On the other hand, as an upcoming stage of a project is being planned, the stage’s activities are
defined at sufficient levels of detail to ensure that estimates of duration will have the necessary
accuracy. The resulting project baselines will be effective for measuring performance. Without
this level of detail, the project management team would not have the ability to detect and correct
As estimates are refined further and at increasing levels of detail, the effect of diminishing returns
comes into play. The project management team must determine when the estimate's accuracy is
Perhaps the most significant factor contributing to errors in estimates is the failure to encompass
the entire technical scope. This comes primarily from two sources: failure to elicit, analyze and
maintain the requirements properly, and incorrect decomposition of the work breakdown structure.
The first is the reason that poor requirements are cited so often as a cause for poor project
performance. The second leads to overlooked work, which often appears later as a scope change
request when it was actually an error, and the scope did not change.
The assumptions about the estimate must be documented. If significant assumptions are not tested,
the estimate may involve substantial error. For example, assumptions regarding productivity,
resource availability, vendor capabilities, and technical feasibility should be reflected in the
resource and duration estimates and spelled out in the basis of estimate (BOE) for the activity. The
BOE describes how the estimates were derived and the information on which they were based.
Influence of risk on estimating errors
When known risks are under- or overestimated, the amount of time or cost allocated to the estimate
will be wrong to some degree. Experience can reduce this kind of error, but it cannot eliminate it
completely.
Estimates must accommodate the budgeting and funding cycles of the performing organization.
When an estimate approaches or spans a boundary between two funding cycles, there is the
inherent risk that during the project the activity may slip at least partially out of the cycle in which
it was planned. This means the cost for the slipped portion will be incurred in the wrong cycle, and
the available funds in both cycles will no longer match the revised cost forecast.
Cost drivers
Cost drivers are project cost elements that heavily impact the overall project costs. They will either
inflate or moderate the base cost estimate that resulted from the measure of the project's scope.
Small changes in cost drivers result in large changes in the overall project costs.
Parametric cost estimating relies on an understanding of these cost drivers. They result in
additional estimating measures that must be used to adjust the cost estimates upward or downward
Project managers should be concerned about cost drivers because they represent specific elements
of the project that could potentially become budget busters. Cost drivers are the areas worth
spending extra time on when developing the estimate in order to get more accurate data on quantity
When reviewing a cost estimate, recognizing and focusing on cost drivers is more productive than
The cost estimating process requires the project management team to consider two environmental
factors:
Marketplace conditions - This involves the products, services, and results that are
available in the marketplace, their sources, and the terms and conditions of their use. These
conditions will affect the choice of resources, and their prices will then serve to establish
their cost estimates. In addition, if fluctuations in these conditions are expected, prices may
change during the project. These price changes will also affect the cost estimates.
Commercial databases - Resource cost rates are often available from commercial
databases that track skills and human resource costs and standard costs for material and
equipment. With adjustments for local variation, these may serve as the base prices for the
cost estimates.
Sources of information
Cost estimating policies - If the organization has established mandatory approaches for
cost estimating in various circumstances, the project management team must comply with
them;
Cost estimating templates - Often the finance function or previous project teams have
developed templates that are based on previous projects. These templates can be reused
information about work that has been performed in the past that was similar, or that used
the same resources planned for the current project. In this case, there may be available
historical information that the project management team can leverage in developing the
cost estimates;
Project files -Records from prior projects that have performed similar work can help with
Team knowledge - Frequently the team members will have been selected because of their
previous experience with similar work. This usually provides a base of knowledge about
Lessons learned - If previous cost estimates are available from a previous project that was
similar in scope and size, there will often be lessons learned about how to (and how not to)
generate and tailor the estimates to be even more accurate than those used on the previous
project.
• Quality Estimates
• Improve Accuracy/Confidence
• Reduce uncertainty
• Reduce Costs
• Save Time
Key Procedures:
• Documenting
ESTIMATE VALIDATION
Options :
• Benchmarking (IPA)
• Counter Estimate
• Verification deliverables
Structured Approach:
Estimating process
Estimating tools/data
Cost Check:
From:
theestimatingprocess-121228074538-phpapp01. Applied Cost Engineering Group. December
28,2012
ESTIMATION PROCESS (IN CONSTRUCTION)
Understanding cost estimation requires you to have a basic grasp of the construction process. (If
you’re interested in learning more about the construction process, Pearson’s Building
Construction: Principles, Materials, and Systems is an excellent resource.) Here are the nine basic
builder designs, constructs, and delivers a project according to the owner’s requirements. It begins
early in the construction process and can last until up to a year of occupancy or use. A
2. Determining Requirements: The first real step in constructing a project is a pre-design phase
or planning phase. The pre-design phase involves defining a project’s requirements: what its
function(s) will be, how much it should cost, where it will be located, and any legal requirements
3. Forming a Design Team: The project owner contracts with an architect who will then select
other specialized consultants to form a design team. Complex projects and projects which require
meeting specific design requirements — such as acoustics or housing hazardous materials — will
have more specialized consultants on board to ensure the design meets requirements. The architect
is generally responsible for overseeing and coordinating the design process, though for some
projects (such as industrial construction), an engineer may be one of the people overseeing design.
4. Designing the Structure: This step deals with the architect creating a series of designs. The
architect works first with the owner to decide on the broad strokes of the design and then
increasingly closely with the other members of the design team to flesh out the structure’s design
in accordance with requirements. Designing thus progresses from a schematic design phase, when
the architect presents a high-level design to the owner for approval, to a design development phase,
when the architect works with the design consultants to decide on specifics of the construction
design. The last step is the construction documents phase, i.e., creating construction drawings and
specifications from which the contractor will build. The specifications, which various participants
in the construction process read, appear in a standard format called the MasterFormat, which the
Construction Specifications Institute developed. Estimators produce and revise cost estimates for
5. Bidding Based on the Scope of Work: Once the construction documents are finalized, they
are released to contractors who wish to bid on the project. Along with these bidding documents,
they include instructions on how to submit bids, a sample of the contract agreement, and financial
and technical requirements for contractors. These documents, which effectively define the scope
of the work, are the basis on which contractors prepare their estimates. For more on how to develop
a statement of work, consult this guide. To ensure fair bidding, all contractors receive the same
information, and the project owner usually selects the lowest qualified bidder. This bid tabulation
6. Signing the Contract: Once the contractor has been selected, they execute a set of contract
documents with the owner. The contract documents encompass the bidding documents, which now
function as a legal contract between owner and contractor. Contracts can follow a number of
models, depending on how complete the construction design is and how the owner and contractor
bear risks. One of the basic models is a lump sum (also called a stipulated sum or turnkey) contract,
which involves the contractor bidding a fixed sum for the total project and agreeing upon it when
the project’s design is virtually complete. A unit price contract allows for more flexibility in design
by having the owner pay the contractor per number of units they build. A cost-plus contract, signed
when the design is incomplete, has the owner pay for all costs plus a predetermined fee for the
7. Construction: During the construction phase, the contractor oversees building in accordance
with the construction documents. A general contractor will hire specialized subcontractors for
different sets of construction tasks, such as plumbing or foundation work. Throughout the
construction process, the contractor engages in careful cost control, comparing actual expenditure
with forecasted expenditure at multiple points in the construction process. Cost control ensures
that the contractor is actually able to turn a profit. This budget template can help you compare
8. Close-Out: When the builder comes close to finishing a structure, the contractor requests the
architect perform a substantial completion inspection in which the architect verifies the near-
complete status of the project. At this stage, the contractor provides the architect with a document
called the punch list, which lists any incomplete work or needed corrections. After the architect
inspects the structure, they will add any additional incomplete items to the punch list.
9. Completion: After the contractor completes all the incomplete work detailed on the punch list,
the architect performs a final inspection. If the contractor has completed the structure according to
construction drawings and specifications, the architect will issue a certificate of final completion,
design and building construction. Instead of contracting first with a design team and then with a
contractor, the owner contracts with a design-build firm, which handles both functions. The main
strength of this approach is greater alignment and coordination between design and construction
and a reduction of construction missteps. Accountability rests with a single party, which owners
may appreciate. It can also save time and increase efficiency, and design-build processes are likely
to be significantly cheaper than conventional design-bid-construct processes like the one detailed
above.
From:
https://www.smartsheet.com/construction-cost-estimating