1-0 Introduction 1: Results of Investigation
1-0 Introduction 1: Results of Investigation
1-0 Introduction 1: Results of Investigation
1-0 INTRODUCTION................................................................................................................................................... 1
11 GENERAL......................................................................................................................................... 1
3.1 SEISMICITY..............................................................................................................................................2
3.2 SEISMIC SOIL PROFILE CHARACTERIZATION .............................................................................2
6.1 GENERAL.................................................................................................................................................5
APPENDIX “A”
BOREHOLE LOGS
APPENDIX “B”
APPENDIX “C”
SITE PHOTOGRAPHS
1.0 INTRODUCTION
1.1 GENERAL
This report presents the findings of Geotechnical Investigations for the Construction of Commercial
Building at Plot No. 6,7,8, Madina Town, Islamabad. The proposed building consists of Ground plus 9
storey structure with a basement (B+G+9). The purpose of investigations was to obtain geotechnical
parameters to design the foundations. The work was carried out for Ch. Tabassum Taj. Geotechnical
Investigations of proposed site were earned out by M/s AJK Engineers (Pvt.) Ltd., Islamabad. Field
investigations were carried out on 23rd August, 2019.
This report presents details of the geotechnical investigations carried out, provides evaluation of the
subsurface conditions encountered at the investigated locations, and recommendations for the
foundations of the proposed building. Recommendations given in this report are based on field and
laboratory test results, and on the state-of-the-art knowledge in geotechnical engineering, design and
construction.
Scope of work under this contract for geotechnical investigation consisted of the following major tasks.
1. Drilling and sampling of two (2) boreholes down to the max. Depth of 50ft or up
3. Performing laboratory tests to determine pertinent index and engineering properties of the strata
4. Analyze the Held and laboratory data and submit an engineering report
Islamabad. The area is mainly consists of layers of Silt with Sand to the maximum explored depth.
Location Plan of Site and boreholes are shown in Fig. 1 & 2 respectively.
zone indicates high degree of damage during the seismic loading. Keeping in view the seismotectonic set up of
the project site and the degree of importance of the structure of the proposed project, it is recommended that the
structures should be designed to withstand maximum horizontal peak ground acceleration (GPA) of 0.16- 0.24g.
in accordance with Table 16-J (UBC 97: Section 1636). It is recommended to use S D as soil profile type for this
4
(SPT),
The drilling of boreholes was carried out using heavy percussion method. Standard
Penetration Tests (SPTs) were performed at a depth interval of 3.0 - 5.0ft. These tests
were performed generally in accordance with ASTM D 1586. The samples recovered
from split spoon sampler were visually inspected and classified as per ASTM D 2488. A
description of soil samples recovered and the number of blows of the Standard hammer
used in SPTs for successive 6 inches of penetration was recorded on field borehole logs.
The boreholes were prepared in the field. These logs were finalized after laboratory
testing and are ptesented in Appendix “A” of this report.
5. LABORATORY TESTING
Samples retrieved from boreholes were examined in the field and then transported to
testing laboratory for relevant laboratory testing. The laboratory tests were conducted on
selected soil samples to determine the engineering characteristics of the subsurface strata.
Following laboratory test results are presented in Appendix “B” of this report:
The Atterberg limits are a basic measure of the critical water contents of a fine-grained
soil, such as itsfcrinkage limit, plastic limit, and liquid limit. As a dry, clayey soil takes
on increasing amounts of water, it undergoes dramatic and distinct changes in behavior
and consistency. Five (05) Atterberg limit tests were performed on the soil samples
including liquid limit, and plastic limit. The results indicate that the soils have liquid limit
(LL) ranging from 29% to 3^4% with a plasticity index (PI) ranging from 6 to 9.
Boreholes drilling, in-situ testing, and sampling were done in the field and
samples retrieved were tested in the laboratory. Results of the investigations
discussed in this report are based on the data obtained at the investigated
points, tests results and on the engineering interpretation of the data collected.
It is possible to have variations in the ground conditions; in case of any
significant variation revealed during execution of the construction work, the
matter should be referred back to AJK Engineers (Pvt.) Ltd. for further
clarifications.
6.2 SUBSURFACE STRATA
Based on the field and laboratory investigations, the site is found to be
underlain by similar type of strata to the maximum explored depth.
The subsurface stratum consists layers of Silt with Sand up to the maximum
explored depth.
In order to be safe, the load carrying strata must be competent to sustain the
imposed loading without undergoing shear failure,j and at the same time
settlements of the foundations must not exceed the tolerable limits. Therefore,
the load carrying characteristics of the strata must be evaluated keeping in
view these considerations.
7.1 BEARING CAPACITY ANALYSIS
7.1 The subsurface strata indicate that the load carrying strata mainly
consists of partially saturated strata. The bearing capacity calculation is
based on Meyerhof method for shear failure and Terzaghi’s Consolidation
Theory for settlement failure. Keeping in view, loading conditions and
subsurface strata, Raft foundations are recommended for main structure.
Recommended Allowable bearing capacities are given below in the table.
S. No.
Type of Footing Min. Depth of Allowable Bearing
E.G.L. (ft)
1. Raft 12.0 1.25
L_______________J
10.0 LIMITATIONS
AJK Engineers (Pvt.) Ltd. has prepared this report for this project, “ Construction of Commercial
Building at Taj Tower, Plot No. 6,7,8, Madina Town, Islamabad.” as per instruction’s received from the
client. This report is provided for the exclusive use of the proposed buildings and purpose as described
in the report. It should not be used for other projects or by a third party. In preparing this report, AJK
Engineers (Pvt.) Ltd. has necessarily relied upon information provided by the client.
AJK’s advice is based upon the conditions encountered during this investigation. The accuracy of the
advice provided by AJK in this report may be limited by undetected variations in ground conditions
between sampling locations.
This report must be read in conjunction with all of the attached notes and should be kept in its entirety
without separation of individual pages or sections. AJK
cannot be held responsible for interpretations or conclusions made by others unless
they are supported by an expressed statement, interpretation, outcome or conclusion
given in this report.
APPENDIX
“A”
B O R E H
O L EJL O
G
SAPPENDI
X “B”
L A B O R AT
ORY TEST
R E S U LT S
APPENDIX
“C” SITE
PHOTOGR
APHS